CN206667259U - A kind of final grouting pressure control device - Google Patents

A kind of final grouting pressure control device Download PDF

Info

Publication number
CN206667259U
CN206667259U CN201720272049.1U CN201720272049U CN206667259U CN 206667259 U CN206667259 U CN 206667259U CN 201720272049 U CN201720272049 U CN 201720272049U CN 206667259 U CN206667259 U CN 206667259U
Authority
CN
China
Prior art keywords
pressure
grouting
grouting pressure
slip casting
control device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720272049.1U
Other languages
Chinese (zh)
Inventor
张蕊
王志伟
王卫斌
李洪岗
高立
杨子龙
邱绍富
任庆慧
聂文峰
唐本升
陈琼
芶文锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Kunming Survey Design and Research Co Ltd
Original Assignee
CREEC Kunming Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Kunming Survey Design and Research Co Ltd filed Critical CREEC Kunming Survey Design and Research Co Ltd
Priority to CN201720272049.1U priority Critical patent/CN206667259U/en
Application granted granted Critical
Publication of CN206667259U publication Critical patent/CN206667259U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of final grouting pressure control device, including the stock inlet and grout outlet being arranged on energy storage equipment, and the relief valve and pressure sensor being arranged on energy storage equipment.The utility model can guarantee that slurries smoothly pass in and out energy storage equipment;Stable grouting pressure can be provided for slip casting process to a certain extent when grouting pressure gathers during slip casting;After grouting pressure exceedes setting value, by relief valve releasing pressure automatically, the purpose for controlling maximum grouting pressure is realized;Pressure sensor is connected with data collection and analysis device, in order to monitors the grouting pressure during slip casting.The utility model not only saves injecting paste material using final grouting pressure control device, also solve to cause the problem of the upward lifting of high-speed railway rail level because final grouting pressure exceedes design pressure simultaneously, it can effectively block and cover karst water under high-speed railway existing line roadbed, increase the stability of roadbed base plate, solve subgrade deformation destabilization problems.

Description

A kind of final grouting pressure control device
Technical field
The utility model belongs to high-speed railway existing line roadbed karstic water flooding Prevention Technique field, more particularly to a kind of note Starch final pressure control device.
Background technology
Solution cavity is covered under the high-speed railway existing line of karst area and solutional cavity is more, karst cave(Solutional cavity)In charges with The activity for underground water is pulled away, and the roadbed easily caused thereon collapses, sinks or ftractureed.
For this kind of karst area high-speed railway existing line subgrade defect problem, grouting filling solution cavity(Solutional cavity)It is most normal With one of, maximally effective reinforcing means.But during actual mortar depositing construction, when grouting pressure is close to design final pressure, due to Acted on by grouting pump temporary impact pressure, easily cause final grouting pressure and exceed design pressure, then cause high-speed railway rail level Upward lifting, the lighter can impact to the normal operation of high-speed railway, and severe one can cause heavy economic losses or even personnel to hinder Die.
Therefore, a kind of device how is designed, is this area field technician in karst area height to solve the above problems Faced during the safe operation of fast Existing Railway Line road.
Utility model content
The purpose of this utility model is to overcome above-mentioned the deficiencies in the prior art, there is provided a kind of final grouting pressure control device, The present apparatus is realized both wired to high-speed railway by energy storage equipment, relief valve, pressure sensor and equipment data acquisition analyzing The control of Karst grouting final pressure is covered under the roadbed of road.
To achieve these goals, the utility model adopts the following technical scheme that:A kind of final grouting pressure control device, including The stock inlet and grout outlet being arranged on energy storage equipment, and the relief valve and pressure sensor being arranged on energy storage equipment.
High pressure valve is respectively equipped with the stock inlet and grout outlet.
The pressure sensor is connected with data collection and analysis device.
The stock inlet is connected by high-pressure slip-casting pipe with grouting pump.
The grout outlet is connected by pressure duct with slip casting orifice tube.
The grouting pump is connected with slurry pool.
The slurry pool is at least one.
When the slurry pool is two or more, slurry pool is connected by grouting pump and slip casting pipe of eating dishes without rice or wine respectively.
The relief valve is connected by pressure duct with slurry pool.
The grouting pump and slip casting are eated dishes without rice or wine between pipe, and pressure gauge is equipped between grouting pump and stock inlet.
The energy storage equipment is cylinder, is processed by thick 10mm steel plate, can under the conditions of 2MPa test pressure Ensure sealing;Vertical in use to place, bottom sets stock inlet, and top sets grout outlet.
The relief valve uses blowdown relief valve, and it is 0.6 that can ensure the ratio of mud:1~1:The slurries of 1 scope can pass through.
The pressure sensor measurement range is 0 ~ 1MPa, measurement accuracy≤± 0.5%.
The data collection and analysis device, for continual gathered data and image and data analysis is carried out, monitoring note The change of grouting pressure during slurry, early warning is provided for the grouting pressure control during slip casting.
When the final grouting pressure control device works, maximum pressure on relief valve need to be pre-adjusted and, to design load, pressure is passed Sensor is connected with data collection and analysis device, and the maximum pressure value of data collection and analysis device is adjusted to design load.Slurry pool passes through Pressure duct, grouting pump carry out the charging of energy storage equipment into stock inlet, and slurry enters injected hole mouth pipe after grout outlet, to brill Hole slip casting;After grouting pressure exceedes the grouting pressure design load of relief valve, relief valve automatically opens up carry out pressure release, data acquisition Analyzer is alarmed automatically.If slurry pool is two or more, other slurry pools by pressure duct, grouting pump to Slip casting orifice tube carries out slip casting.After slip casting terminates, relief valve, pressure sensor and pressure duct etc. are cleaned in time.
The utility model has the advantage of:The utility model can guarantee that slurries smoothly pass in and out energy storage equipment;Relief valve is gone out Mouth is connected in slurry pool by pressure duct, in order to avoid cause slurries unrestrained after exceeding setting pressure due to pressure during slip casting Take.Stable grouting pressure can be provided for slip casting process to a certain extent when grouting pressure gathers during slip casting;When slip casting pressure After power exceedes setting value, by relief valve releasing pressure automatically, the purpose for controlling maximum grouting pressure is realized;Pressure sensor and data Collection analysis device is connected, in order to monitors the grouting pressure during slip casting.The utility model is controlled using final grouting pressure Device not only saves injecting paste material, while also solves to cause high-speed railway rail level upward because final grouting pressure exceedes design pressure The problem of lifting, it can effectively block and cover karst water under high-speed railway existing line roadbed, increase the stability of roadbed base plate, solve Certainly subgrade deformation destabilization problems.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model final grouting pressure control device;
Fig. 2 uses connection diagram to be of the present utility model.
Wherein, first slurry pool 1, second slurry pool 2, pressure duct 3, grouting pump 4, pressure gauge 5, high pressure valve 6, stock inlet 7, go out Starch mouth 8, energy storage equipment 9, relief valve 10, pressure sensor 11, data collection and analysis device 12, three-way pipe 13, slip casting orifice tube 15.
Embodiment
The utility model is described further with reference to embodiment.
Embodiment 1
As shown in Figure 1, 2, final grouting pressure control device includes the stock inlet 7 and grout outlet 8 being arranged on energy storage equipment 9, And it is arranged on relief valve 10 and pressure sensor 11 on energy storage equipment 9;It is respectively equipped with the stock inlet 7 and grout outlet 8 High pressure valve 6;Pressure sensor 11 is connected with data collection and analysis device 12;Stock inlet 7 is connected by high-pressure slip-casting pipe 3 and grouting pump 4 Connect;Grout outlet 8 is connected by pressure duct 3 with slip casting orifice tube 15;The grouting pump 4 respectively with first slurry pool 1 and second slurry Pond 2 is connected, and grouting pump 4 and slip casting pipe 15 of eating dishes without rice or wine are connected;Relief valve 10 is connected by pressure duct 3 with first slurry pool 1;The note Stock pump 4 and slip casting are eated dishes without rice or wine between pipe 15, and pressure gauge 5 is equipped between grouting pump 4 and stock inlet 7.
The energy storage equipment 9 is cylinder, is processed by thick 10mm steel plate, can under the conditions of 2MPa test pressure Ensure sealing;Vertical in use to place, bottom sets stock inlet 7, and top sets grout outlet 8.The relief valve 10 is using row Dirty relief valve, it is 0.6 that can ensure the ratio of mud:1~1:The slurries of 1 scope can pass through;The measurement range of pressure sensor 11 be 0 ~ 1MPa, measurement accuracy≤± 0.5%;The data collection and analysis device 12, for continual gathered data and image and progress Data analysis, the change of grouting pressure during slip casting is monitored, early warning is provided for the grouting pressure control during slip casting.
When the final grouting pressure control device works, it need to be pre-adjusted on relief valve 10 that maximum pressure is to design load, by pressure Sensor 11 is connected with data collection and analysis device 12, and the maximum pressure value of data collection and analysis device 12 is adjusted to design load.First Slurry pool 1 carries out the charging of energy storage equipment 9 by pressure duct 3, grouting pump 4 into stock inlet 7, and slurry is laggard through grout outlet 8 Enter slip casting orifice tube 15, to bored grouting;After grouting pressure exceedes the grouting pressure design load of relief valve 10, relief valve 10 is certainly Dynamic open carries out pressure release, and data collection and analysis device 12 is alarmed automatically;Second slurry pool 2 is also by pressure duct 3, grouting pump 4 Slip casting is carried out to slip casting orifice tube 15, the top of slip casting orifice tube 15 sets three-way pipe 13.After slip casting terminates, in time to relief valve 10, Pressure sensor 11 and pressure duct 3 etc. are cleaned.

Claims (4)

  1. A kind of 1. final grouting pressure control device, it is characterised in that:Including the stock inlet and grout outlet being arranged on energy storage equipment, with And it is arranged on relief valve and pressure sensor on energy storage equipment;High pressure valve is respectively equipped with the stock inlet and grout outlet, institute Pressure sensor is stated to be connected with data collection and analysis device, the stock inlet is connected by high-pressure slip-casting pipe with grouting pump, it is described go out Slurry mouth is connected by pressure duct with slip casting orifice tube, and the grouting pump is connected with slurry pool, and the relief valve passes through high-voltage tube Road is connected with slurry pool.
  2. 2. final grouting pressure control device according to claim 1, it is characterised in that:The slurry pool is at least one.
  3. 3. final grouting pressure control device according to claim 1, it is characterised in that:The slurry pool be two or two with When upper, slurry pool is connected by grouting pump and slip casting pipe of eating dishes without rice or wine respectively.
  4. 4. final grouting pressure control device according to claim 3, it is characterised in that:The grouting pump and slip casting eat dishes without rice or wine pipe it Between, and pressure gauge is equipped between grouting pump and stock inlet.
CN201720272049.1U 2017-03-20 2017-03-20 A kind of final grouting pressure control device Active CN206667259U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720272049.1U CN206667259U (en) 2017-03-20 2017-03-20 A kind of final grouting pressure control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720272049.1U CN206667259U (en) 2017-03-20 2017-03-20 A kind of final grouting pressure control device

Publications (1)

Publication Number Publication Date
CN206667259U true CN206667259U (en) 2017-11-24

Family

ID=60377820

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720272049.1U Active CN206667259U (en) 2017-03-20 2017-03-20 A kind of final grouting pressure control device

Country Status (1)

Country Link
CN (1) CN206667259U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952760A (en) * 2018-06-27 2018-12-07 中国矿业大学 A kind of intelligent circulation increasing-pressure-releasing type dynamic grouting system and method
CN109882115A (en) * 2019-04-08 2019-06-14 贵州盘江精煤股份有限公司 A kind of level pressure grouting device
CN110976125A (en) * 2019-12-14 2020-04-10 山东里能鲁西矿业有限公司 Pneumatic roadway whitening device and whitening method using same
CN112252088A (en) * 2020-10-13 2021-01-22 中铁四院集团工程建设有限责任公司 Method for remedying track settlement disease

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952760A (en) * 2018-06-27 2018-12-07 中国矿业大学 A kind of intelligent circulation increasing-pressure-releasing type dynamic grouting system and method
CN108952760B (en) * 2018-06-27 2020-02-07 中国矿业大学 Intelligent circulating pressure increasing-discharging type dynamic grouting system and method
CN109882115A (en) * 2019-04-08 2019-06-14 贵州盘江精煤股份有限公司 A kind of level pressure grouting device
CN109882115B (en) * 2019-04-08 2023-11-21 贵州盘江精煤股份有限公司 Constant-pressure grouting device
CN110976125A (en) * 2019-12-14 2020-04-10 山东里能鲁西矿业有限公司 Pneumatic roadway whitening device and whitening method using same
CN112252088A (en) * 2020-10-13 2021-01-22 中铁四院集团工程建设有限责任公司 Method for remedying track settlement disease

Similar Documents

Publication Publication Date Title
CN206667259U (en) A kind of final grouting pressure control device
CN202450537U (en) Composite dewatering device of vacuum tube well
CN106180083B (en) A kind of petroleum pipeline segmented cleaning equipment
CN206873457U (en) The concrete elevation measurement device of catheterized reperfusion underwater concrete
CN208415968U (en) Hydraulic climbing formwork/slding form operation shaft of high pier intelligence curing system
CN109610920A (en) Transmission line of electricity single-column steel tube column construction method for hanging
CN106847048B (en) Simulate the emulation Boundary Test system of artesian groundwater recharge
CN202870056U (en) Test device of grouting reinforcement model for weak dam
CN208039062U (en) A kind of automatic mud jacking system of bridge prestress pipeline
CN208455622U (en) A kind of quick pile driving equipment of architectural engineering
CN109322310B (en) Control device and control method for concrete pumping quantity of pile machine
CN110292796A (en) A kind of concentrator and dense method
CN105587053B (en) A kind of industrialization house wall bottom grouting construction method
CN206129597U (en) Spiral shell sucker -rod pumping is prevented burning with preventing buggy by coal seam gas well
CN206956513U (en) A kind of pavement construction disintegrating apparatus
CN207047829U (en) Modified vibrosinking pile construction equipment
CN102287193A (en) Special hanging scaffold for sleeve-building inner shaft wall in shaft sinking of vertical shaft
CN206069243U (en) A kind of crane span self-checking device
CN205776417U (en) A kind of novel unit for single-pile vertical anti-pulling static loading experiment device
CN212110728U (en) Pile hole bottom mud sampling device
CN207295777U (en) A kind of storage battery well
CN210621642U (en) Drainage structure for high-speed flow area of stilling pool
CN103452125B (en) Rock gap water blocking structure and construction method on geologic condition of weathered rocks
CN207749611U (en) Device for dragging dregs and the abandoned stream equipped with device for dragging dregs or shunting well
CN208378287U (en) A kind of simple vertical transport equipment of architecture construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant