- CN206655468U CN206655468U CN201720419757.3U CN201720419757U CN206655468U CN 206655468 U CN206655468 U CN 206655468U CN 201720419757 U CN201720419757 U CN 201720419757U CN 206655468 U CN206655468 U CN 206655468U
- Authority
- CN
- China
- Prior art keywords
- line box
- once mounting
- box frame
- box
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of wall pre-embedded line box once mounting mould, including mold box, module, the mold box include the framework of upper and lower opening, and framework is interior to be provided with line box frame by end face, and line box frame is adapted with pre-buried line box size;It is provided with perforation hole on line box frame, plug-in-sleeve in perforation hole, the module is coagulation block, coagulation block pouring molding in framework.A kind of wall pre-embedded line box once mounting mould provided by the utility model, by setting mold box, module, line box can be installed while during building a wall, improve the steadiness of pre-buried line box and the accuracy of position.
Description
Technical field
Mould is the utility model is related to, especially a kind of wall pre-embedded line box once mounting mould.
Background technology
Traditional wall pre-embedded line box installation is mainly the installation that holes in the later stage, not only very big to wall injury, and the later stage
Hole irregular, and it is regular and closely knit should to fill up mortar when installing by electrician, it is also necessary to line box absolute altitude is adjusted to design attitude,
Take a lot of work material, and installation accuracy and line box steadiness cannot ensure.In addition, in masonry bottom and surrounding position be not beaten it is close
Real, empty existence rate is higher, and line box bottom has part masonry disintegrating slag, has had a strong impact on steadiness and the position of the installation of wall line box
The accuracy put.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of wall pre-embedded line box once mounting mould, can keep away
Exempting from the later stage holes installation, ensures the steadiness of pre-buried line box and the accuracy of position.
In order to solve the above technical problems, technical scheme is used by the utility model:
A kind of wall pre-embedded line box once mounting mould, including mold box, module, the mold box include upper and lower opening
Framework, framework is interior to be provided with line box frame by end face, and line box frame is adapted with pre-buried line box size;Perforation hole is provided with line box frame, is worn
Plug-in-sleeve in pore, the module are coagulation block, coagulation block pouring molding in framework.
The wide * of the long * of mold box two kinds of specifications of a height of 390*190*190mm or 190*190*190mm, corresponding line box
Frame is respectively double line box frame, single line box frame.
The Outside Dimensions of the line box frame are more major 5mm than corresponding line box base external diameter.
Described sleeve pipe is DN20PVC sleeve pipes, and sleeve pipe one end is provided with the direct joints of DN20 of port sealing, and the joint with
Upper end flushes, and the sleeve pipe other end extend into line box inframe.
The mold box both ends are provided with handle.
A kind of wall pre-embedded line box once mounting mould of the utility model, by setting the framework with line box frame, common structure
Into mold box, module can be molded using the mold box, so as to obtain with building block line box mounting seat of the same size, such phase can
The line box mounting seat is built a wall together with other building blocks, does not influence metope building block entirety typesetting, and pre-buried line box can be carried out simultaneously
Installation, holed without the later stage.Further, since the module is to mix concrete clout by the damaged small-sized masonry block in job site to pour
Build and form, waste material can be made to obtain secondary use, it is cost-effective.It is convenient to position and beat because the apparatus structure is more upright in itself
Slurry, be advantageous to keep steadiness and accuracy.
Brief description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and examples:
Fig. 1 is the schematic diagram of mold box in the utility model(Plug-in-sleeve).
Fig. 2 is the schematic diagram of mold box in the utility model.
Fig. 3 is the schematic diagram of module in the utility model(It is single).
Fig. 4 is the schematic diagram of module in the utility model(It is double).
In figure:Mold box 1, module 2, framework 3, line box frame 4, perforation hole 5, sleeve pipe 6, handle 7.
Embodiment
As Figure 1-4, a kind of wall pre-embedded line box once mounting mould, including mold box 1, module 2.The mold box
1 is made from 3mm steel plates, and mold box 1 includes the framework 3 of upper and lower opening, and the internal diameter of framework 3 has two kinds of specifications, respectively with wall
Light aggregate concrete hollow block is in the same size, specially 390*190*190mm and 190*190*190mm.End face is leaned in framework 3
Provided with line box frame 4, line box frame 4 has two kinds of double line box frame, single line box frame specifications.Line box frame 4 leans on end face one end open, remote
End face one end is closed state.Line box frame 4 is adapted with pre-buried line box size, and Outside Dimensions are more each than corresponding line box base external diameter
Big 5mm, line box installation and building wall are so may insure in finishing operations while is carried out.So, line box can letter
Single firm installation, reduce secondary hole in similar traditional construction and this process and the infringement to wall material are installed, really
Play and subtract this synergy.It is provided with perforation hole 5 on line box frame 4, plug-in-sleeve 6 in perforation hole 5, double line box inframe is 4, single
Line box inframe is 2.Sleeve pipe 6 is DN20PVC sleeve pipes, and sleeve pipe one end is provided with the direct joints of DN20 of port sealing, and this connects
Head flushes with upper end, and the sleeve pipe other end, which extend into line box frame 4 and stretches out the sole length of line box frame 4, reaches 10mm.By mould
Box 1 is placed on bottom surface with the end face of the opening of line box frame 4 side, mixes concrete clout using the damaged small-sized masonry block in job site
Mold box 1 is poured, is poured out before treating the final set of module 2, examination water is conserved formation model as Figure 2-3.Later stage can be by the module 2
Built a wall together with other building blocks, do not influence metope building block entirety typesetting, and the installation of pre-buried line box can be carried out simultaneously, without the later stage
Hole.
Pre-buried line box installation process and principle:Bricklayer is built a wall together in masonry panel, by module 2 with other building blocks, electricity
Work team's group is installed to wall surface line box base simultaneously, using the M10 masonry mortars pair of a grade higher than building wall during installation
Line box base and its surrounding are beaten;Before installation, spool threading pad is removed, then back box is penetrated in prominent spool, according to
There is gap mashing to surrounding and fill up closely knit in design drawings explanation adjustment back box position and perpendicularity, right to precise location
Line box is consolidated and is accurately positioned to correspondence position;The pre-buried end of back box, will by drawing when entering line box installation procedure
Installation line box is sought, and checks the steadiness of back box and line box installation.
Claims (5)
- A kind of 1. wall pre-embedded line box once mounting mould, it is characterised in that:Including mold box(1), module(2), the mould Box(1)Framework including upper and lower opening(3), framework(3)It is interior to be provided with line box frame by end face(4), line box frame(4)It is big with pre-buried line box It is small to be adapted;Line box frame(4)On be provided with perforation hole(5), perforation hole(5)Interior plug-in-sleeve(6), the module(2)For coagulation block, Coagulation block is in framework(3)Interior pouring molding.
- A kind of 2. wall pre-embedded line box once mounting mould according to claim 1, it is characterised in that:The mold box (1)The a height of 390*190*190mm of long wide * of * or two kinds of specifications of 190*190*190mm, corresponding line box frame(4)It is respectively double Line box frame, single line box frame.
- A kind of 3. wall pre-embedded line box once mounting mould according to claim 1, it is characterised in that:The line box frame (4)Outside Dimensions it is more major 5mm than corresponding line box base external diameter.
- A kind of 4. wall pre-embedded line box once mounting mould according to claim 1, it is characterised in that:Described sleeve pipe(6) For DN20PVC sleeve pipes, sleeve pipe one end is provided with the direct joints of DN20 of port sealing, and the joint flushes with upper end, and sleeve pipe is another One end extend into line box frame(4)It is interior.
- A kind of 5. wall pre-embedded line box once mounting mould according to claim 1, it is characterised in that:The mold box (1)Both ends are provided with handle(7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720419757.3U CN206655468U (en) | 2017-04-20 | 2017-04-20 | A kind of wall pre-embedded line box once mounting mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720419757.3U CN206655468U (en) | 2017-04-20 | 2017-04-20 | A kind of wall pre-embedded line box once mounting mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206655468U true CN206655468U (en) | 2017-11-21 |
Family
ID=60319126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720419757.3U Active CN206655468U (en) | 2017-04-20 | 2017-04-20 | A kind of wall pre-embedded line box once mounting mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206655468U (en) |
-
2017
- 2017-04-20 CN CN201720419757.3U patent/CN206655468U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101225909B (en) | Locating preburied sleeve for electrical installation project | |
CN104264676A (en) | Construction method of mass concrete of high-rise building foundations | |
CN206971732U (en) | A kind of doubly-linked beam forms pouring structure | |
CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
CN206655468U (en) | A kind of wall pre-embedded line box once mounting mould | |
CN206319620U (en) | A kind of floor concrete casting controls scale | |
CN108729669A (en) | A kind of wall pre-embedded wire box once mounting mold | |
CN206986727U (en) | A kind of device to be vibrated for bridge skew web plate | |
CN207633342U (en) | A kind of bridge pile foundation pile crown abolishes device | |
CN205577430U (en) | Concrete placement structure is managed to big scale of construction composite steel concrete column body swift current ball formula pipe cluster in ground | |
CN107762135A (en) | The construction method of skin scaffold wall connecting piece | |
CN201406834Y (en) | Reserved opening die for top plate | |
CN205976503U (en) | Vertical concrete structure's template lacing device | |
CN204551173U (en) | Pull bar locating support | |
CN208267362U (en) | A kind of constructing device of deformation joint concrete wall formwork | |
CN206942140U (en) | A kind of shear wall formwork support meanss | |
CN206189449U (en) | Soleplate with lead integrated plank sheathing system of wall | |
CN105952002B (en) | A kind of terrace heavy steel plate pre-embedded device and construction method | |
CN114704293A (en) | Tunnel secondary lining vault anti-run-out multi-angle slip casting device | |
CN205875714U (en) | A consolidate fixture for retainer plate beam mold board | |
CN209538669U (en) | A kind of architectural engineering seismic hardening plate | |
CN104912209B (en) | Bars In Poured Concrete Slab reserved holes of pipes plugging device and processing and plugging construction method | |
CN108678377A (en) | Constructional column concrete pouring construction method | |
CN105780815B (en) | The constructing device and method of diaphragm wall leakproof | |
CN208329613U (en) | Mouth structure is poured at the top of constructional column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |