CN206654661U CN201720386758.2U CN201720386758U CN206654661U CN 206654661 U CN206654661 U CN 206654661U CN 201720386758 U CN201720386758 U CN 201720386758U CN 206654661 U CN206654661 U CN 206654661U
Authority
CN
China
Prior art keywords
wire rope
steel wire
upper plate
shaped frame
jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720386758.2U
Other languages
Chinese (zh)
Inventor
白光宇
刘跃强
张耀东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HBIS Co Ltd Chengde Branch
Original Assignee
HBIS Co Ltd Chengde Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HBIS Co Ltd Chengde Branch filed Critical HBIS Co Ltd Chengde Branch
Priority to CN201720386758.2U priority Critical patent/CN206654661U/en
Application granted granted Critical
Publication of CN206654661U publication Critical patent/CN206654661U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

A kind of device for adjusting bridge crane steel wire rope counter-jib is the utility model is related to, belongs to bridge crane auxiliary apparatus for repairing technical field.Technical scheme is:Include upper plate(1), riser(2), lower plate(3), brace(4), bolt hole and steel wire rope one(6), upper plate(1)And lower plate(3)Parallel arrangement, upper plate(1)And lower plate(3)Between pass through riser(2)It is fixedly connected, forms U-shaped frame, the upper plate of U-shaped frame(1)It is provided with bolt hole and wire rope hole, steel wire rope one(6)One end through wire rope hole and being fixed in U-shaped frame, the upper plate in U-shaped frame(1)And riser(2)Between be provided with brace(4).The beneficial effects of the utility model are:Bridge crane steel wire rope counter-jib can be quickly adjusted, improves operating efficiency, reduces the labor intensity of worker.

Description

A kind of device for adjusting bridge crane steel wire rope counter-jib
Technical field
A kind of device for adjusting bridge crane steel wire rope counter-jib is the utility model is related to, especially large-tonnage bridge-type rises Heavy-duty machine, belong to bridge crane auxiliary apparatus for repairing technical field.
Background technology
When changing bridge crane steel wire rope, especially large-tonnage bridge crane steel wire rope, master file steel wire rope are all Acted on and formed simultaneously by four steel wire ropes.At present, well known steel rope replacing method is all to drive new steel wire rope with old steel wire rope, Change when, the wire rope wedge form joint installed on old steel wire rope counter-jib is dismantled, by the steel wire rope head at wedge joint with New steel wire rope connection, while the pressing plate of old steel wire rope other end is disassembled, the new steel wire rope into disk is placed on steel wire rope pallet, Pallet can rotate, and the steel wire rope so newly changed is not in just the phenomenon tightened.Start master file motor, old steel wire rope is immediately By on new rope belt to reel, after the completion of four steel wire ropes are all changed, then fixation and the steel wire rope wedge shape of pressing plate are carried out The installment work of joint, after whole installations, it is necessary to be adjusted to steel wire rope counter-jib, ensure that four steel wire ropes are same When uniform stressed.Found in real work, if steel wire rope counter-jib is uneven, plate hook is landed must again and be laid flat, will After the bearing pin and steel cable clamp of wire rope wedge form joint are all removed, then readjust installation, so since, steel of adjustment Cord counter-jib needs a hour at the soonest, wastes time and energy, and influences to produce.
Utility model content
The utility model purpose is to provide a kind of device for adjusting bridge crane steel wire rope counter-jib, can quickly adjust Bridge crane steel wire rope counter-jib, operating efficiency is improved, solve problem present in background technology.
The technical solution of the utility model is:
A kind of device for adjusting bridge crane steel wire rope counter-jib, includes upper plate, riser, lower plate, brace, bolt hole With steel wire rope one, upper plate and lower plate parallel arrangement, it is fixedly connected between upper plate and lower plate by riser, forms U-shaped frame, U-shaped frame Interior upper plate is provided with bolt hole and wire rope hole, and one end of steel wire rope one through wire rope hole and is fixed in U-shaped frame, U-shaped Brace is provided between upper plate and riser in frame.
The other end of the steel wire rope one is connected with one end of steel wire rope two, the other end and the overhead traveling crane main drum of steel wire rope two Connection, that one end that steel wire rope two is connected with steel wire rope one are provided with wedge joint, and U-shaped frame is stuck in overhead traveling crane plate hook by fixing bolt On crossbeam.
The lower plate upper surface is in broached-tooth design.
One end of the brace and upper plate weld, the other end and the riser of brace weld.
Using the utility model, in steel wire rope counter-jib pre-adjustment, one is accomplished fluently in wedge joint one end of steel wire rope two After individual steel cable clamp, wedge joint one end of steel wire rope two is connected on steel wire rope one, at the same four U-shaped framves are symmetrical Be stuck on overhead traveling crane plate hook crossbeam, start overhead traveling crane master file, progressively stretch the wedge joint of steel wire rope two tightly, stretch next, see steel wire Rope two wedge joint relative to overhead traveling crane plate hook bottom distance, it is possible to measure the length of steel wire rope two, and then be adjusted.
The beneficial effects of the utility model are:Bridge crane steel wire rope counter-jib can be quickly adjusted, improves work Efficiency, reduce the labor intensity of worker.
Brief description of the drawings
Fig. 1 is the utility model front view;
Fig. 2 is the utility model top view;
Fig. 3 is the utility model use state diagram;
In figure:Upper plate 1, riser 2, lower plate 3, brace 4, fixing bolt 5, steel wire rope 1, overhead traveling crane plate hook crossbeam 7.
Embodiment
Below in conjunction with accompanying drawing, by example, the utility model is described in further detail.
Referring to the drawings 1,2, a kind of device for adjusting bridge crane steel wire rope counter-jib, upper plate 1, riser 2, lower plate are included 3rd, brace 4, bolt hole and steel wire rope 1, upper plate 1 and lower plate 3 are arranged in parallel, solid by riser 2 between upper plate 1 and lower plate 3 Fixed connection, forms U-shaped frame, and the upper plate 1 in U-shaped frame is provided with bolt hole and wire rope hole, and one end of steel wire rope 1 passes through steel wire Cord hole is simultaneously fixed in U-shaped frame, and brace 4 is provided between the upper plate 1 and riser 2 in U-shaped frame.
In the present embodiment, the length of steel wire rope 1 is one meter, a diameter of 15mm, and fixing bolt 5 is M24 high-strength bolts, on Plate 1, riser 2 and lower plate 3 are 20mm steel plates, and upper plate 1, riser 2 and lower plate 3 are welded into U-shaped frame, and the upper surface of lower plate 3 is saw Tooth-shape structure, to increase its end-face friction, one end of steel wire rope 1 is penetrated in U-shaped frame by wire rope hole, and make a call to one Wire line hitch, then by one piece of sheet metal welding, prevent steel wire rope from coming off.
In steel wire rope counter-jib pre-adjustment, beaten in wedge joint one end of steel wire rope two what a steel cable clamp it Afterwards, wedge joint one end of steel wire rope two is connected on steel wire rope 1, while four U-shaped framves is symmetrically stuck in a day sweep On hook crossbeam 7, start overhead traveling crane master file, progressively stretch the wedge joint of steel wire rope two tightly, stretch next, see that the wedge shape of steel wire rope two connects Head need not adjust counter-jib relative to the distance of overhead traveling crane plate hook bottom if being of the required size.If size difference is super Bid alignment request, it is possible to according to corresponding size, readjust the steel cable clamp position of fastening steel wire rope two.Adjustment is completed Afterwards, the steel cable clamp of steel wire rope two is stuck on steel wire rope 1.

Claims (4)

1. a kind of device for adjusting bridge crane steel wire rope counter-jib, it is characterised in that include upper plate(1), riser(2), lower plate (3), brace(4), bolt hole and steel wire rope one(6), upper plate(1)And lower plate(3)Parallel arrangement, upper plate(1)And lower plate(3)It Between pass through riser(2)It is fixedly connected, forms U-shaped frame, the upper plate in U-shaped frame(1)It is provided with bolt hole and wire rope hole, steel wire rope One(6)One end through wire rope hole and being fixed in U-shaped frame, the upper plate in U-shaped frame(1)And riser(2)Between be provided with oblique pull Muscle(4).
2. a kind of device for adjusting bridge crane steel wire rope counter-jib according to claim 1, it is characterised in that described Steel wire rope one(6)The other end be connected with one end of steel wire rope two, the other end of steel wire rope two is connected with overhead traveling crane main drum, steel wire Rope two and steel wire rope one(6)That one end of connection is provided with wedge joint, and U-shaped frame passes through fixing bolt(5)It is stuck in overhead traveling crane plate hook horizontal stroke Beam(7)On.
3. a kind of device for adjusting bridge crane steel wire rope counter-jib according to claim 1, it is characterised in that described Lower plate(3)Upper surface is in broached-tooth design.
4. a kind of device for adjusting bridge crane steel wire rope counter-jib according to claim 1, it is characterised in that described Brace(4)One end and upper plate(1)Welding, brace(4)The other end and riser(2)Welding.
CN201720386758.2U 2017-04-13 2017-04-13 A kind of device for adjusting bridge crane steel wire rope counter-jib Expired - Fee Related CN206654661U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720386758.2U CN206654661U (en) 2017-04-13 2017-04-13 A kind of device for adjusting bridge crane steel wire rope counter-jib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720386758.2U CN206654661U (en) 2017-04-13 2017-04-13 A kind of device for adjusting bridge crane steel wire rope counter-jib

Publications (1)

Publication Number Publication Date
CN206654661U true CN206654661U (en) 2017-11-21

Family

ID=60317523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720386758.2U Expired - Fee Related CN206654661U (en) 2017-04-13 2017-04-13 A kind of device for adjusting bridge crane steel wire rope counter-jib

Country Status (1)

Country Link
CN (1) CN206654661U (en)

Similar Documents

Publication Publication Date Title
CN203209852U (en) Stirring friction welding tool for longitudinal joint of cylinder section
CN104060607B (en) Prestress steel pipe pile and production method of prestress steel pipe pile
CN106758882A (en) For the hood type automatic leveling anchor and its method for suspender replacement of CFST Arch Bridge suspender replacement
CN206591449U (en) Hood type automatic leveling anchor for CFST Arch Bridge suspender replacement
CN105173379B (en) The band special Auxiliary support bar assembly of door opening prefabricated panel
CN206654661U (en) A kind of device for adjusting bridge crane steel wire rope counter-jib
CN208613612U (en) A kind of device for straightening pile crown reinforcing bar
CN102182150A (en) Installation method of externally hung steel template for anti-collision guardrail construction outside viaduct
CN102267046B (en) Device for separated assembling of dry-quenching hoister frame
CN102275829B (en) Frame high-altitude piece mounting method of dry quenching lifter device
CN106012834B (en) A kind of spatial warping curve abnormal shape antisymmetry steel king-tower inner support and tensioning system
CN208516837U (en) One kind is for borehole filling pile cage of reinforcement overlapped hanging apparatus
CN206172803U (en) Clamp type ear plate
CN203821865U (en) Adjusting device for installing gap of H-shaped steel beam
CN108943379A (en) Long-line pedestal compressor wire and steel strand wires exchange integral tension and put a device
CN104495644B (en) A kind of crane and crane gooseneck boom thereof
CN103835516A (en) H-type steel beam installation gap adjusting device and use method thereof
CN201155150Y (en) Steel cable connection device for construction steel structure
CN104310241A (en) Standard knot of tower crane
CN108222503A (en) A kind of combined large pier stud steel form
CN209721363U (en) A kind of lifting pipeline auxiliary device
CN209686924U (en) A kind of large volume arc concrete steel lattice supporting framework
CN201405004Y (en) Tension station for steel wire rope conveyer belt production line
CN202271145U (en) Wheel fixing device for installing frame of coke dry quenching hoister in fragmentation mode
CN205772901U (en) A kind of conduction rack

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171121

CF01 Termination of patent right due to non-payment of annual fee