CN206652683U - Blowning installation and point gum machine - Google Patents

Blowning installation and point gum machine Download PDF

Info

Publication number
CN206652683U
CN206652683U CN201720167102.1U CN201720167102U CN206652683U CN 206652683 U CN206652683 U CN 206652683U CN 201720167102 U CN201720167102 U CN 201720167102U CN 206652683 U CN206652683 U CN 206652683U
Authority
CN
China
Prior art keywords
air
blowning installation
plate
gas
bottom wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720167102.1U
Other languages
Chinese (zh)
Inventor
杨勇
胡明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zowee Technology Co Ltd
Original Assignee
Shenzhen Zowee Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Zowee Technology Co Ltd filed Critical Shenzhen Zowee Technology Co Ltd
Priority to CN201720167102.1U priority Critical patent/CN206652683U/en
Application granted granted Critical
Publication of CN206652683U publication Critical patent/CN206652683U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Coating Apparatus (AREA)

Abstract

A kind of blowning installation and point gum machine are the utility model is related to, it includes:Substrate has air drain mounting hole and heating component mounting hole, and the heating component mounting hole is arranged at two ends of substrate;Air drain includes side wall, bottom wall and cover plate, the side wall and bottom wall are connected with each other and form the box like structure of a upper shed, are fixed in the box like structure formed with cavity, the cover plate in the side wall, the bottom wall is provided with step with side wall junction, and air-vent is provided with the step;Heating component includes heating tube, heating plate and fixed column.Air blowing plate above the air drain, helps uniformly from the gas hole for being distributed in regional on air blowing plate to disperse during air drain outlet, reaches the effect uniformly supplied gas in tile horizontally.

Description

Blowning installation and point gum machine
Technical field
It the utility model is related to the point gum machine of a kind of blowning installation and the application device.
Background technology
Point gum machine is common injection-moulding device, is widely used.Point gum machine during dispensing, to glue glue by environment temperature The influence of degree and flow velocity is very big, the too low phenomenon that wire drawing occurs of temperature, and glue flow velocity is slow, easily causes electronic component bottom Portion can not be filled and not have the effect of safeguard protection;Temperature is too high to make glue premature cure, can not flow and plugging point Needle head, and then it is bad to directly result in dispensing, influences production procedure and product quality.Commonly use and blow on automatic dispensing machine at present Wind after device conveying heating is controlled to environment temperature, and blowning installation typically uses traditional fan, but traditional fan Air quantity and wind speed be difficult to control, on automatic dispensing machine, it is also necessary to blown using uniform, and require that tolerance can be controlled arbitrarily System, the exhaust of common fan air-supply obviously fail the demand for meeting product.
Therefore, based on drawbacks described above, in the market is badly in need of providing a kind of blowning installation of uniformly outlet.
The content of the invention
Based on this, the defects of the utility model is to overcome prior art, there is provided a kind of blowning installation and apply the device Point gum machine, it assembles simple, and outlet is uniform.
Its technical scheme is as follows:A kind of blowning installation, including substrate, air drain and heating component.
Substrate has air drain mounting hole and heating component mounting hole, and the heating component mounting hole is arranged at two of substrate End.
Air drain, including side wall, bottom wall and cover plate, the side wall and bottom wall are connected with each other and form the box-like of upper shed Structure, the box like structure is interior formed with cavity, and the cover plate is fixed in the side wall to close the cavity, the bottom wall Side wall junction is provided with step, the air-vent for connecting the cavity is provided with the step, the bottom wall is arranged on gas In groove mounting hole and air drain mounting hole is sealed, the step and air-vent are located at surface.
Heating component includes heating tube, heating plate and fixed column, and the heating plate is fixed on the top of the heating tube, institute Stating heating plate includes heat emission hole, relative upper and lower surface, and the heat emission hole runs through the upper and lower surface, described The both ends of heating tube are individually fixed in the fixed column, and the fixed column interfixes with the heating component mounting hole.
Gas-tpe fitting is fixed on below the bottom wall of air drain, and the gas-tpe fitting is interconnected with the cavity.
In one of the embodiments, be provided with air blowing plate above the air drain, the air blowing plate include gas hole, Relative air blowing plate upper surface and air blowing plate lower surface, the gas hole run through the air blowing plate upper surface and air blowing plate following table Face.The air blowing plate above the air drain, contributes to uniformly each from being distributed on air blowing plate during air drain outlet in tile horizontally The gas hole in individual region disperses.Reach the effect uniformly supplied gas.Heated barrier is provided with above the air blowing plate.The heating Dividing plate includes through hole, relative heated barrier upper surface and heated barrier lower surface, and the through hole is in the heated barrier Surface and heated barrier lower surface.Heated barrier mainly plays heat-insulated and thermal resistance, prevents heat transmission from being blown to following influence The accelerated ageing of device of air, while heat energy is further also gathered in top and up distributed, reach heat-insulated and cumulative effect.
In one of the embodiments, two ends of the air blowing plate contact with each other with the fixed column.Air blowing plate Two ends contact with each other with the fixed column and mutually supported, and are easy to the fixation of air blowing plate.
In one of the embodiments, the heated barrier contacts with each other with the fixed column.Two ends of heated barrier Portion contacts with each other with the fixed column and mutually supported, and is easy to the fixation of heated barrier.
In one of the embodiments, it is fixedly connected between the gas-tpe fitting and the bottom wall by way of spiral. Sealing ring can also be set between gas-tpe fitting and the bottom wall to prevent the gas of conveying from leaking.
A kind of point gum machine, including support, the exercise group frame on support, the front side of described support are provided with control Panel, is provided with workbench between the support and exercise group frame, exercise group frame is provided with multigroup Glue dripping head and scanner, institute State and blowning installation is provided with workbench, the blowning installation cooperates with the Glue dripping head, above-mentioned of the blowning installation Blowning installation described in one embodiment.
Principle of the present utility model, effect are further illustrated with reference to above-mentioned technical proposal:
1st, air drain includes side wall, bottom wall and cover plate, and the side wall and bottom wall are connected with each other and form the box of a upper shed Shape structure, the box like structure is interior to be fixed in the side wall formed with cavity, the cover plate, the bottom wall and side wall junction Step is provided with, air-vent is provided with the step.The circumferential seal of air drain, air can only be ventilative on step from being arranged on Discharge in hole.Air channel is made to change, realization is uniformly supplied gas..
2nd, air blowing plate contributes to during air drain outlet uniformly from being distributed on air blowing plate in tile horizontally above the air drain The gas hole of regional disperses.Reach the effect uniformly supplied gas.
3rd, hot dividing plate mainly plays heat-insulated and thermal resistance, prevents that the acceleration of heat transmission to following influence blowning installation is old Change, while heat energy is further also gathered in top and up distributed, reach heat-insulated and cumulative effect.Gas-tpe fitting and the bottom Sealing ring can also be set between wall to prevent the gas of conveying from leaking.
Brief description of the drawings
Fig. 1 is the structural representation one of blowning installation described in the utility model embodiment.
Fig. 2 is the structural representation two of blowning installation described in the utility model embodiment.
Fig. 3 is the structural representation of the air drain of blowning installation described in the utility model embodiment.
Description of reference numerals:
1st, substrate, 11, heating component mounting hole, 12, air drain mounting hole, 2, air drain, 21, side wall, 22, bottom wall, 23, lid Plate, 24, step, 25, air-vent, 31, heating tube, 32, heating plate, 33, fixed column, 4, gas-tpe fitting, 5, air blowing plate, 6, heating Dividing plate.
Embodiment
Embodiment of the present utility model is described in detail below:
As shown in Figure 1 and Figure 2, blowning installation described in the utility model, including substrate 1, air drain 2 and heating component.
Substrate 1 has air drain mounting hole 12 and heating component mounting hole 11, and the heating component mounting hole 11 is arranged at base Two ends of plate 1, the air drain mounting hole 12 is arranged on the medium position of substrate 1, and the air drain mounting hole 12 is compared with base The frontal projected area of plate 1 is small.Air drain mounting hole 12 is depending on the installation number of air drain 2, in the utility model, the air drain Mounting hole 12 is specially two.
Air drain 2 is installed in the air drain mounting hole 12, a single air drain 2 and a single air drain mounting hole 12 Cooperate, air drain 2 is fixed on the substrate 1 after coordinating with the air drain mounting hole 12, in envelope between air drain 2 and substrate 1 Closed state.During installation, the part of air drain 2 is fixed in the air drain mounting hole 12 of substrate 1, and air drain 2 is partially disposed in the upper of substrate 1 Side.With reference to Fig. 2 and Fig. 3, air drain 2 includes side wall 21, bottom wall 22 and cover plate 23, and the side wall 21 and bottom wall 22 are connected with each other And the box like structure of a upper shed is formed, formed with cavity in the box like structure.The lower section of bottom wall 22 passes through spiral Mode is fixed with gas-tpe fitting 4, and one end of the gas-tpe fitting 4 is connected with the bottom wall 22 and is interconnected with the cavity, The tracheae of the other end connection conveying gas of the gas-tpe fitting 4.Sealing is provided between gas-tpe fitting 4 and the bottom wall 22 Part, the seal are sealing ring.The cover plate 23 is fixed in the side wall 21 by screw, the cover plate 23, side wall 21 With bottom wall 22 jointly by the cavities seals.Bottom wall 22 is consistent with the profile of the air drain mounting hole 12.The bottom wall 22 and side The junction of wall 21 is provided with step 24, and specifically, the step 24 sets at right angles and has a downward plane.Step 24 Several air-vents 25 are provided with downward plane, the effect of air-vent 25 is to make the cavity with the external world by described Air-vent 25 realizes connection, and the step 24 and air-vent 25 are in the top of substrate 1.Air-vent 25 is arranged on step Under multiple regions, for equably the gas in cavity to be discharged by the air-vent 25.The top of the air drain 2 is set There is air blowing plate 5, the air blowing plate 5 is provided with gas hole, and the gas hole runs through the air blowing plate upper surface and air blowing plate lower surface. The top of the air blowing plate 5 is additionally provided with heated barrier 6, and the heated barrier 6 includes relative heated barrier upper surface and added Hot dividing plate lower surface, the heated barrier 6 are provided with the through hole through the heated barrier upper surface and heated barrier lower surface. It is relation stacked on top of one another between the air blowing plate 5, heated barrier 6, part or full when the gas hole is laminated with the through hole Portion is mutually corresponding.
Heating component includes heating tube 31, heating plate 32 and fixed column 33, and the heating plate 32 is fixed on the heating tube 31 top, the heating plate 32 include relative upper and lower surface, and the heating plate 32, which is provided with, runs through the heating The heat emission hole of the upper and lower surface of plate 32.The both ends of the heating tube 31 are individually fixed in the fixed column 33, institute Fixed column 33 is stated to install again at the heating component mounting hole 11 being fixed on substrate 1.Heating tube 31, fixed column 33 and heating component Fixed form between mounting hole 11 can be plugged and fixed or be that spiral is fixed.When fixed, the air blowing plate 5, heating The both ends of dividing plate 6 contact with fixed column 33 and are fixed on the inner side of the fixed column 33.
At work, extraneous gas enters air drain 2 to above-mentioned blowning installation by gas-tpe fitting 4, because air drain 2 is circumferential seal State, gas can't blow out directly up, but several air-vents 25 set at step 24 below air drain that turn back Uniformly discharge.Because the frontal projected area of air drain 2 is small compared with substrate 1, and opposing seal between air drain and substrate 1.Gas is from saturating The barrier of substrate 1 is run into after being discharged at stomata 25, turns back and flows to air blowing plate 5;Because air blowing plate 5 is provided with the air blowing run through up and down Hole, gas can now be blown out upwards from the gas hole in air blowing plate 5.Because heating tube 31 produces heat at work, and by heat Amount is delivered to the region between heating plate 32 and heated barrier 6 so that produces hot-air between heating plate 32 and heated barrier 6. The gas blown out upwards from the gas hole in air blowing plate 5, the hot-air between heating plate 32 and heated barrier 6 is up transmitted; Now, hot-air is discharged.Similarly, because heated barrier 6 is provided with the through hole run through up and down, blown out upwards from gas hole Gas is uniformly reached between heating plate 32 and heated barrier 6 by through hole again, continues to be heated pipe 31 working caused heat Realize that heat exchange becomes hot-air, the gas blowout then newly entered again.So as to which the gas for ensureing to be blown is heating all the time Hot-air afterwards, and the gas for ensureing to be sent between heating plate 32 and heated barrier 6 is even into, the shape uniformly discharged State, avoid phenomena such as subregion gas flowing is too fast, gas temperature is too low.Said structure of the present utility model breaks traditions The mode that fan blade is blown so that air flow direction bending is tortuous, is finally uniformly outflowed from heating plate.
In the present embodiment, the air blowing plate 5 in tile horizontally above the air drain 2, it is equal when contributing to 2 outlet of air drain It is even to disperse from the gas hole for being distributed in regional on air blowing plate 5, reach the effect uniformly supplied gas.It is main to increase heated barrier 6 Play heat-insulated and thermal resistance, prevent accelerated ageing of the heat transmission to following influence blowning installation, while also further by heat Top can be gathered in up to distribute, reach heat-insulated and cumulative effect.It can also be set between gas-tpe fitting 4 and the bottom wall 22 Sealing ring with prevent conveying gas leak.
The utility model also provides a kind of point gum machine (not shown), and the point gum machine includes support, installed in support On exercise group frame, the front side of described support is provided with control panel, work is provided between the support and exercise group frame Platform (not shown), exercise group frame are provided with multigroup Glue dripping head and scanner, blowning installation are provided with the workbench, The blowning installation cooperates with the Glue dripping head, the blowning installation described in any of the above-described embodiment of blowning installation.Work When making, it will treat that product for dispensing glue is right against the heating plate 32 of the heating component of above-mentioned blowning installation, or in heating plate 32 A face is set to treat the flushing air outlet of product for dispensing glue.During work, heating tube 31 passes through heat caused by electrical heating The gas in region is hot-air between heating plate 32 and heated barrier 6, and extraneous gas enters air drain 2 by gas-tpe fitting 4, then passes through Several air-vents 25 set by the step 24 of lower section are uniformly discharged, and are realized and are uniformly supplied gas for the first time;Uniformly send for the first time The gas gone out is up transmitted by gas hole again, and realization is uniformly supplied gas for the second time;Ensure to enter between hot plate 32 and heated barrier 6 Gas be even into state, the gas after up discharges original hot-air, and hot-air face, which blows to, treats dispensing Product.After balanced ventilation by above-mentioned blowning installation so that hot air flowrate is more uniform, so that treating product for dispensing glue It is uniformly heated, while to just playing insulation effect in product for dispensing glue, improves quality for dispensing glue.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply each technical characteristic in example it is all possible combination all holes be described, as long as however, the combination of these technical characteristics not Contradiction be present, be all considered to be the scope of this specification record.
Embodiment described above only expresses several embodiments of the present utility model, and its description is more specific and detailed, But therefore it can not be interpreted as the limitation to utility model patent scope.It should be pointed out that the common skill for this area For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to The scope of protection of the utility model.Therefore, the protection domain of the utility model patent should be determined by the appended claims.

Claims (9)

  1. A kind of 1. blowning installation, it is characterised in that including:
    Substrate, there is air drain mounting hole;
    Air drain, including side wall, bottom wall and cover plate, the side wall and bottom wall are connected with each other and form the box-like knot of a upper shed Structure, formed with cavity in the box like structure, the cover plate is fixed in the side wall to close the cavity, the bottom wall with Side wall junction is provided with step, and the air-vent for connecting the cavity is provided with the step, and the bottom wall is arranged on air drain In mounting hole and air drain mounting hole is sealed, the step and air-vent are located at surface;
    Heating component, it is installed on substrate and covers the air drain, the heating component includes heating tube and is fixed on described add The heating plate of the top of heat pipe, the heating plate are provided with the heat emission hole of the upper and lower surface through the heating plate;
    Gas-tpe fitting, wear the substrate and be sealingly fastened in below the bottom wall of air drain and be interconnected with the cavity.
  2. 2. blowning installation according to claim 1, it is characterised in that:Air blowing plate is provided with above the air drain, it is described Air blowing plate is provided with the gas hole of the upper and lower surface through the air blowing plate.
  3. 3. blowning installation according to claim 2, it is characterised in that:Heated barrier is provided with above the air blowing plate, The heated barrier is provided with the through hole of the upper and lower surface through the air blowing plate.
  4. 4. blowning installation according to claim 3, it is characterised in that:The heating component also includes being arranged on heating tube two The fixed column at end, the fixed column are fixedly connected with the substrate, the air blowing plate, heating plate, heated barrier and the fixation Post contacts with each other.
  5. 5. blowning installation according to claim 4, it is characterised in that:The both ends of the substrate set heating component to install Hole, fixed column of fearing are fixedly connected at heating component mounting hole.
  6. 6. blowning installation according to claim 3, it is characterised in that:The gas hole is part or all of with the through hole It is mutually corresponding.
  7. 7. blowning installation according to claim 1, it is characterised in that:The gas-tpe fitting is fixed on by way of spiral The lower section of the bottom wall.
  8. 8. blowning installation according to claim 7, it is characterised in that:It is provided between the gas-tpe fitting and the bottom wall Sealing ring.
  9. 9. a kind of point gum machine, including support, the exercise group frame on support, it is characterised in that before described support Side is provided with control panel, and workbench is provided between the support and exercise group frame, and exercise group frame is provided with multigroup Glue dripping head And scanner, blowning installation is provided with the workbench, the blowning installation cooperates with the Glue dripping head, the air blowing Device is any described blowning installations of claim 1-8.
CN201720167102.1U 2017-02-23 2017-02-23 Blowning installation and point gum machine Expired - Fee Related CN206652683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720167102.1U CN206652683U (en) 2017-02-23 2017-02-23 Blowning installation and point gum machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720167102.1U CN206652683U (en) 2017-02-23 2017-02-23 Blowning installation and point gum machine

Publications (1)

Publication Number Publication Date
CN206652683U true CN206652683U (en) 2017-11-21

Family

ID=60314201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720167102.1U Expired - Fee Related CN206652683U (en) 2017-02-23 2017-02-23 Blowning installation and point gum machine

Country Status (1)

Country Link
CN (1) CN206652683U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109571236A (en) * 2019-01-08 2019-04-05 京东方科技集团股份有限公司 A kind of grinding and cleaning apparatus
CN110722753A (en) * 2019-10-25 2020-01-24 芜湖市智睿包装制品有限公司 Disposable box processing injection molding machine of plastics
CN112221898A (en) * 2020-09-28 2021-01-15 苏州天准科技股份有限公司 Heating equipment and dispensing system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109571236A (en) * 2019-01-08 2019-04-05 京东方科技集团股份有限公司 A kind of grinding and cleaning apparatus
CN110722753A (en) * 2019-10-25 2020-01-24 芜湖市智睿包装制品有限公司 Disposable box processing injection molding machine of plastics
CN112221898A (en) * 2020-09-28 2021-01-15 苏州天准科技股份有限公司 Heating equipment and dispensing system

Similar Documents

Publication Publication Date Title
CN206652683U (en) Blowning installation and point gum machine
CN102628562A (en) Light-emitting diode lamp bar with fully waterproof glue pouring structure and manufacturing method thereof
CN101347775A (en) Heating devcie of glue-dropping machine
CN106786052A (en) A kind of easy heat radiation damp-proof transformation cabinet
CN206516929U (en) A kind of good distribution box of waterproof cooling
CN204122132U (en) One makes climatic environmental testing equipment wind speed stablize and uniform device
CN104931679B (en) A kind of aging test device for asphaltic binder
CN205259512U (en) Decoration hanging plate for outer wall of building
CN104801463A (en) Dispensing device and dispensing method
CN104190605B (en) IR bake and the infrared heating device with hot blast nozzle
CN203094549U (en) Labeling equipment and heat-shrinkable device thereof
CN206348322U (en) A kind of accelerating aging test case
CN102673159B (en) Recording equipment
CN206046056U (en) A kind of constant temperature and moisture test machine
CN209523108U (en) A kind of bituminous pavement maintenance heating device
CN203934199U (en) A kind of outdoor cabinet with moistureproof ventilating opening
CN209109509U (en) A kind of sealing device of Reactive hot melt adhesive
CN207487225U (en) A kind of air duct sealing structure and its wind cooling refrigerator
CN208296500U (en) Electric drying oven with forced convection
CN207351097U (en) A kind of organic pigment production drying unit
CN206976881U (en) A kind of distribution box of high efficiency and heat radiation
CN205738248U (en) A kind of reaction type polyurethane hot-melt adhesive packaging device
CN204243598U (en) Tank body and use arc control device, the closed type switch of this tank body
CN204243600U (en) Closed type switch and arc control device, tank body
CN205175170U (en) Heat exchanger is used in cooling tower water conservation fog dispersal

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171121