CN206625215U CN201720244931.5U CN201720244931U CN206625215U CN 206625215 U CN206625215 U CN 206625215U CN 201720244931 U CN201720244931 U CN 201720244931U CN 206625215 U CN206625215 U CN 206625215U
Authority
CN
China
Prior art keywords
pedestal
spandrel girder
reinforcing cage
lowering device
drilled pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720244931.5U
Other languages
Chinese (zh)
Inventor
曾宪柳
潘文铭
徐洲
汪勇
邓安华
许哲
吴培浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201720244931.5U priority Critical patent/CN206625215U/en
Application granted granted Critical
Publication of CN206625215U publication Critical patent/CN206625215U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The assembled decentralization field of tool of steel reinforcement cage is the utility model is related to, in particular to a kind of lowering device for reinforcing cage of drilled pile.Including pedestal;Described pedestal is the frame structure for being fixed on steel pile casting upper end, it is characterised in that:At least two groups of supporting constructions are installed, every group of supporting construction is positioned opposite in the spandrel girder on pedestal centered on steel pile casting axis including two on described pedestal;Described spandrel girder is shelved on pedestal upper surface, and one end is rotatably articulated and connected on the outside of pedestal, and the other end can turn inside out the cantilevered structure to be formed in the horizontal direction to pedestal.Whole system of the present utility model is simple in construction, easy to operate, reasonable stress, and the drilled pile reinforcing cage especially big to diameter, weight is big is smoothly installed, and efficiency of construction is high, and construction safety is reliable.

Description

A kind of lowering device for reinforcing cage of drilled pile
Technical field
The assembled decentralization field of tool of steel reinforcement cage is the utility model is related to, transfers and fills in particular to a kind of drilled pile reinforcing cage Put.
Background technology
Drilled pile construction is very common, and when installing drilled pile reinforcing cage, method is different, common are and makees pad using shaped steel, To wearing shaped steel load-bearing installation steel reinforcement cage;Have and pad is made using sleeper, to wearing shaped steel load-bearing installation steel reinforcement cage.These methods usually can Gene basis is bad, cause steel reinforcement cage tilt can not install, or because steel reinforcement cage weight greatly caused by wear load-bearing shaped steel bending.
Prior art has carries out steel reinforcement cage decentralization assembly, such as Patent No. using girder structures The Chinese invention patent of entitled " reinforcement cage quick-assembling positioning system " of " CN200810021685.2 ", the patent describe one Kind special load-bearing beam type splicing structure, including an operating platform, be provided with platform it is multiple can insert in the horizontal direction and The spandrel girder of extraction, spandrel girder can be fixed on the operational platform by bearing pin when steel reinforcement cage is transferred, steel reinforcement cage is fixed on eight On individual spandrel girder, then it is welded, prepares decentralization steel reinforcement cage using hanging device after the completion of welding, eight spandrel girders is taken out Go out, then transfer the steel reinforcement cage being welded, carry out successively until all steel reinforcement cages are transferred in steel pile casting.Under load-bearing beam type Put simple in construction, construction technology is more convenient, but because spandrel girder and platform be on-fixed structure, it is impossible to formed overall, transported Difficulty, the extraction of spandrel girder and insertion are comparatively laborious in addition, influence the quick progress of construction.Particularly diameter is big, weight is big In drilled pile reinforcing cage decentralization process, if without special, easy to operate steel reinforcement cage erecting device, low construction efficiency, installation Difficulty is very big, and certain security risk be present.
The content of the invention
The purpose of this utility model seeks to the deficiency for solving above-mentioned background technology, there is provided a kind of drilled pile reinforcing cage decentralization Device.
The technical solution of the utility model is:A kind of lowering device for reinforcing cage of drilled pile, including pedestal;Described pedestal is It is fixed on the frame structure of steel pile casting upper end, it is characterised in that:At least two groups of supporting constructions are installed on described pedestal, Every group of supporting construction is positioned opposite in the spandrel girder on pedestal centered on steel pile casting axis including two;Described spandrel girder is The rod-like structure of pedestal upper surface is shelved on, spandrel girder one end is rotatably articulated and connected on the outside of pedestal, and the other end can be to platform Seat turns inside out the cantilevered structure to be formed in the horizontal direction.
Further described supporting construction also includes the otic placode for being fixed on pedestal upper surface;Described otic placode includes two pieces Riser positioned at spandrel girder both sides;Described riser one end is fixed on pedestal upper surface, and the other end is in the horizontal direction on the outside of pedestal Extension forms cantilevered structure, and riser extends on the part on the outside of pedestal and is equipped with bearing pin;Described spandrel girder one end is extend into Rotatably it is articulated and connected on otic placode by the bearing pin being arranged on riser and spandrel girder between two pieces of risers.
Further described riser, which is extended on the part on the outside of pedestal, is provided with floor;Described floor upper end is fixed In riser lower end, floor sidepiece is welded in pedestal end face outside.
Further described pedestal is the frame structure that at least three crossbeam head and the tail welding are formed.
Further described cross rail inner end face is provided with support bracket;Described spandrel girder to cross rail inner rotate to Its lower surface is supported in the upper surface of support bracket during horizontal direction.
Supporting steel plate is provided between further two adjacent crossbeams;Described supporting steel plate is located at adjacent two horizontal strokes Beam junction, its both ends, which is respectively welded, to be fixed on adjacent two crossbeams.
Whole system of the present utility model is simple in construction, easy to operate, reasonable stress, and especially big to diameter, weight is big Drilled pile reinforcing cage is smoothly installed, and efficiency of construction is high, and construction safety is reliable.
Brief description of the drawings
Fig. 1:Top view of the present utility model;
Fig. 2:Front view of the present utility model;
Fig. 3:Spandrel girder of the present utility model is overturn to structural representation during horizontal direction;
Fig. 4:Spandrel girder of the present utility model is overturn to structural representation during vertical direction;
Wherein:1-steel pile casting;2-spandrel girder;3-riser;4-bearing pin;5-floor;6-crossbeam;7-support bracket; 8-supporting steel plate;9-steel reinforcement cage.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Such as Fig. 1~4, a kind of lowering device for reinforcing cage of drilled pile, including pedestal, the pedestal of the present embodiment protect to be fixed on steel The frame structure of 1 upper end of cylinder, joins end to end the frame structure to be formed as shown in figure 1, pedestal is at least three crossbeams 6, this implementation The square frame that the pedestal of example is formed for four crossbeams.In order to increase the structural strength of pedestal, the present embodiment is between adjacent crossbeam 6 Supporting steel plate 8 is installed, supporting steel plate 8 is located at the adjacent junction of crossbeam 6, and its both sides is separately fixed at two adjacent crossbeams On 6.
At least two groups of supporting constructions are installed, every group of supporting construction includes two centered on the axis of steel pile casting 1 on pedestal It is positioned opposite in the spandrel girder 2 on pedestal, spandrel girder 2 is the rod-like structure for being shelved on pedestal upper surface, and the one end of spandrel girder 2 can revolve It is articulated and connected on the outside of pedestal with turning, the other end can turn inside out the cantilevered structure to be formed in the horizontal direction to pedestal.Steel reinforcement cage 9 Supported by the spandrel girder 2 rotated to horizontal direction, disengaged when spandrel girder 2 is flipped up with steel reinforcement cage 9.
It is four spandrel girders 2 as shown in figure 1, the present embodiment is provided with two groups of supporting constructions, four spandrel girders, 2 liang of two-phases To arrangement, positioned at the four direction of steel reinforcement cage 9, such structure stress is stable, facilitates the decentralization and installation of steel reinforcement cage 9.
The rotation articulated structure of the end of spandrel girder 2 is realized by otic placode, and as shown in figures 1-4, otic placode includes two pieces of positions Riser 3 in the both sides of spandrel girder 2, the one end of riser 3 are fixed on pedestal upper surface, and the other end extends shape in the horizontal direction on the outside of pedestal Into cantilevered structure, riser 3, which is extended on the part on the outside of pedestal, is equipped with bearing pin 4, and the one end of spandrel girder 2 extend into two pieces of risers 3 Between be rotatably articulated and connected on otic placode by the bearing pin 4 being arranged on riser 3 and spandrel girder 2, wherein, riser 3 extends Floor 5 is provided with part on the outside of to pedestal, the upper end of floor 5 is fixed on the lower end of riser 3, and the sidepiece of floor 5 is welded on outside pedestal On side end face.The part of spandrel girder 2 is shelved forms stable supporting construction on the cross beam 6.
In order to increase the contact area of crossbeam 6 and spandrel girder 2, the present embodiment is provided with support ox in the inner side end of crossbeam 6 Leg 7, spandrel girder 2 are supported in the upper surface of support bracket 7 to the rotation of the inner side of crossbeam 6 to its lower surface during horizontal direction.
In use, by correct position on hanging device handling steel reinforcement cage 9 to steel pile casting 1, spandrel girder 2 is rotated, makes load-bearing Beam 2 is extend into steel reinforcement cage 9, and decentralization steel reinforcement cage 9 makes its weight be transferred on spandrel girder 2, releases hanging device and the section reinforcing bar The connection of cage 9, next section steel reinforcement cage 9 is lifted, by the section steel reinforcement cage 9 of branch sleeve connection two, then using hanging device handling Two section steel reinforcement cages 9 rise 30~40cm, outwards rotate spandrel girder 2, spandrel girder 2 is disengaged with steel reinforcement cage 9, transfer steel reinforcement cage 9 to Correct position, make its spacer bar cage 9 to internal rotation spandrel girder 2 again, then handling it is next section steel reinforcement cage 9, circulate successively into OK, until all connections of steel reinforcement cage 9 are completed.Pedestal is removed, in case next time uses.
The advantages of general principle of the present utility model, principal character and the utility model has been shown and described above.One's own profession The technical staff of industry is it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification Simply illustrate principle of the present utility model, the utility model can also on the premise of the spirit and scope of the utility model is not departed from There are various changes and modifications, these changes and improvements are both fallen within claimed the scope of the utility model.The utility model will Protection domain is asked to be defined by appended claims and its equivalent.

Claims (6)

1. a kind of lowering device for reinforcing cage of drilled pile, including pedestal;Described pedestal is to be fixed on steel pile casting (1) upper end Frame structure, it is characterised in that:At least two groups of supporting constructions are installed on described pedestal, every group of supporting construction include two with It is positioned opposite in the spandrel girder (2) on pedestal centered on steel pile casting (1) axis;Described spandrel girder (2) is to be shelved on pedestal The rod-like structure of end face, spandrel girder (2) one end are rotatably articulated and connected on the outside of pedestal, and the other end can turn inside out to pedestal Form cantilevered structure in the horizontal direction.
A kind of 2. lowering device for reinforcing cage of drilled pile as claimed in claim 1, it is characterised in that:Described supporting construction is also wrapped Include the otic placode for being fixed on pedestal upper surface;Described otic placode includes two pieces of risers (3) for being located at spandrel girder (2) both sides;Described Riser (3) one end is fixed on pedestal upper surface, and extension forms cantilevered structure, riser (3) to the other end on the outside of pedestal in the horizontal direction Extend on the part on the outside of pedestal and be equipped with bearing pin (4);Described spandrel girder (2) one end is extend between two pieces of risers (3) Rotatably it is articulated and connected on otic placode by the bearing pin (4) being arranged on riser (3) and spandrel girder (2).
A kind of 3. lowering device for reinforcing cage of drilled pile as claimed in claim 2, it is characterised in that:Described riser (3) extension Floor (5) is provided with part on the outside of to pedestal;Described floor (5) upper end is fixed on riser (3) lower end, floor (5) side Portion is welded in pedestal end face outside.
A kind of 4. lowering device for reinforcing cage of drilled pile as described in claim 1,2 or 3, it is characterised in that:Described pedestal is The frame structure that at least three crossbeam (6) head and the tail welding are formed.
A kind of 5. lowering device for reinforcing cage of drilled pile as claimed in claim 4, it is characterised in that:On the inside of described crossbeam (6) End face is provided with support bracket (7);Described spandrel girder (2) is rotated to its lower surface branch during horizontal direction to crossbeam (6) inner side Support in the upper surface of support bracket (7).
A kind of 6. lowering device for reinforcing cage of drilled pile as claimed in claim 5, it is characterised in that:Two adjacent crossbeams (6) Between be provided with supporting steel plate (8);Described supporting steel plate (8) is located at adjacent two crossbeams (6) junction, and its both ends is welded respectively Connect and be fixed on adjacent two crossbeams (6).
CN201720244931.5U 2017-03-14 2017-03-14 A kind of lowering device for reinforcing cage of drilled pile Expired - Fee Related CN206625215U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720244931.5U CN206625215U (en) 2017-03-14 2017-03-14 A kind of lowering device for reinforcing cage of drilled pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720244931.5U CN206625215U (en) 2017-03-14 2017-03-14 A kind of lowering device for reinforcing cage of drilled pile

Publications (1)

Publication Number Publication Date
CN206625215U true CN206625215U (en) 2017-11-10

Family

ID=60211639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720244931.5U Expired - Fee Related CN206625215U (en) 2017-03-14 2017-03-14 A kind of lowering device for reinforcing cage of drilled pile

Country Status (1)

Country Link
CN (1) CN206625215U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485412A (en) * 2019-09-20 2019-11-22 五冶集团上海有限公司 The bracket system and its application method of pile foundation more piece steel reinforcement cage connection construction
CN114837205A (en) * 2022-05-31 2022-08-02 保利长大工程有限公司 Cofferdam method for bearing platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485412A (en) * 2019-09-20 2019-11-22 五冶集团上海有限公司 The bracket system and its application method of pile foundation more piece steel reinforcement cage connection construction
CN110485412B (en) * 2019-09-20 2022-09-02 五冶集团上海有限公司 Bracket device for pile foundation multi-section reinforcement cage connection construction and use method thereof
CN114837205A (en) * 2022-05-31 2022-08-02 保利长大工程有限公司 Cofferdam method for bearing platform

Similar Documents

Publication Publication Date Title
CN202080812U (en) Dedicated sling system for large-scaled reinforcing cage
CN103243930B (en) System and method for modularized construction of super high-rise steel structures
CN103556627B (en) A kind of hanging cage structure for large diameter bored pile reinforcing bar cage hoisting
CN107191676A (en) Buried pipeline construction method
CN207714310U (en) A kind of lowering device for reinforcing cage
CN206625215U (en) A kind of lowering device for reinforcing cage of drilled pile
US7337738B2 (en) Gate type vertical elevated mast
CN105484164B (en) Spanning type bailey beam bracket and construction method thereof
CN106276577A (en) The suspension bracket of a kind of framework isolated footing and operational approach
CN203625889U (en) Hanging cage structure for large-diameter hole drilling cast pile reinforcement cage hanging
CN106150057B (en) A kind of split blade type hydraulic pressure lift climbing frame
CN109235424A (en) Pile foundation steel bar cage is segmented installation method
CN102587643A (en) Large-tonnage long-stroke cylinder jacking formwork
CN202881858U (en) Jig frame used for vertical assembly construction of truss arc bridge
CN110745683A (en) Hoisting device and method for reinforcement cage of underground continuous wall
CN206570700U (en) The continuous lowering system of steel jacket box
CN106276630A (en) A kind of internal-climbing tower crane supporting construction of band shearing frame
CN105951683A (en) Construction method for corbel steel reinforcements of gate pier
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN205242891U (en) Prefabricated hollow staircase
CN104790300A (en) Flexible pier-side girder erecting platform and construction method thereof
CN210885075U (en) Equipment secondary transportation and hoist and mount frame of taking one's place
CN201128882Y (en) Lifting and supporting brackets integrated construction device for bridge arch rib
CN211285682U (en) Deepwater cantilever type tower crane foundation structure
CN204435359U (en) Reinforcing cage suspension bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171110