CN206617182U - Constructing tunnel Terrace prevention device - Google Patents

Constructing tunnel Terrace prevention device Download PDF

Info

Publication number
CN206617182U
CN206617182U CN201720318757.4U CN201720318757U CN206617182U CN 206617182 U CN206617182 U CN 206617182U CN 201720318757 U CN201720318757 U CN 201720318757U CN 206617182 U CN206617182 U CN 206617182U
Authority
CN
China
Prior art keywords
operating platform
prevention device
constructing tunnel
terrace prevention
longeron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720318757.4U
Other languages
Chinese (zh)
Inventor
胡仲春
任高峰
王焕
张挺军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201720318757.4U priority Critical patent/CN206617182U/en
Application granted granted Critical
Publication of CN206617182U publication Critical patent/CN206617182U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of constructing tunnel Terrace prevention device, including:Stand, stand has operating platform;Ceiling is protected, protection canopy cover is on the top of stand.The rock that the utility model solves Tunnel top in the prior art drops the problem of causing potential safety hazard.

Description

Constructing tunnel Terrace prevention device
Technical field
The utility model is related to technical field of construction, in particular to a kind of constructing tunnel Terrace prevention device.
Background technology
Chinese transportation net is quickly grown, and increasing road and rail tunnel needs to excavate.In constructing tunnel, the palm is excavated Sub- face removes float stone, punches the tunnel cross-section of linked network operation to having completed to have between two lining tunnels one section to need to repair top.Carry out tunnel During road end face construction, workmen needs to carry out inverted arch construction, and in this section of construction operation, the loosening country rock pushed up due to hole It may drop at any time, this causes great potential safety hazard to the workmen in tunnel and equipment.
Utility model content
Main purpose of the present utility model is to provide a kind of constructing tunnel Terrace prevention device, to solve in the prior art The rock on hole top drops the problem of causing potential safety hazard.
To achieve these goals, according to one side of the present utility model, there is provided a kind of constructing tunnel Terrace prevention Device, including:Stand, stand has operating platform;Ceiling is protected, protection canopy cover is on the top of stand.
Further, protection ceiling is spliced by polylith arc, arcuately the bending direction of plate, adjacent two pieces of arcs Plate is connected by bearing pin.
Further, arc is transparent panel and has operation perforate.
Further, constructing tunnel Terrace prevention device also includes support beam, and the bottom of support beam is connected with stand, supports The apical support protection ceiling of beam.
Further, protection ceiling and stand are detachably connected;And/or protection ceiling can folding storage to stand The side on top.
Further, constructing tunnel Terrace prevention device also includes:Support adjustment mechanism, the top branch of support adjustment mechanism Operating platform is supportted, the height of support adjustment mechanism can adjust to change position of the operating platform on stand;Walking mechanism, OK Walk the bottom that mechanism is arranged on support adjustment mechanism.
Further, support adjustment mechanism includes:Installation base plate;Lifting support, the bottom of lifting support and installation base plate Connection, the apical support operating platform of lifting support;First hydraulic cylinder, first hydraulic cylinder adjusts the height of lifting support.
Further, lifting support is scissor lift support.
Further, constructing tunnel Terrace prevention device also includes:Limit switch, limit switch is arranged on stand, when After operating platform triggering limit switch, limit switch sends limit signal;Controller, controller is adjusted with limit switch and support Mechanism is connected, and controller receives limit signal and controls support adjustment mechanism stopping to act.
Further, stand includes:Many longerons;Many crossbeams, the two ends of each crossbeam respectively with least one longeron Top is connected;Operating platform, operating platform is adjustably disposed on longeron along the length direction of longeron, operating platform relative to Longeron can be overturn, and operating platform has deployed condition and folded state;When operating platform is in deployed condition, operating platform Vertical with longeron, when operating platform is in folded state, operating platform laminating longeron is in perpendicular.
Further, constructing tunnel Terrace prevention device also includes:Electric hoist, electric hoist is movably disposed at crossbeam On;And/or multiple hydraulic legs, hydraulic leg is arranged on the bottom of longeron;And/or cat ladder, cat ladder is connected with operating platform.
Further, longeron has guide rail along its length, and operating platform is slided along guide rail.
Further, many longerons surround construction area, and operating platform is multiple, when operating platform is in deployed condition When, multiple operating platforms are located in construction area.
Further, operating platform includes:Platform body, the first end of platform body is connected with longeron;Connector, connection Second end of the two ends of part respectively with longeron and platform body is connected, so that operating platform is maintained at deployed condition;It is at least one set of Backplate, the first end of platform body and/or the second end are provided with backplate, and backplate is arranged on platform body turnablely.
Further, connector is drag-line.
Using the technical solution of the utility model, by setting protection ceiling on the top of stand, workmen can be The lower section of ceiling is protected to carry out construction operation, protection ceiling can stop that the rock on hole top falls down the constructor injured by a crashing object in hole Member, so that the rock for eliminating hole top drops and injures the potential safety hazard of personnel by a crashing object.
Brief description of the drawings
The Figure of description for constituting the part of the application is used for providing further understanding to of the present utility model, this practicality New schematic description and description is used to explain the utility model, does not constitute to improper restriction of the present utility model. In the accompanying drawings:
Fig. 1 shows the structural representation of constructing tunnel Terrace prevention device in an alternative embodiment of the present utility model Figure;And
Fig. 2 shows the right view of the constructing tunnel Terrace prevention device in Fig. 1;
Fig. 3 shows the structural representation of the arc in Fig. 1.
Wherein, above-mentioned accompanying drawing is marked including the following drawings:
10th, stand;11st, operating platform;111st, body;112nd, connector;113rd, backplate;12nd, longeron;121st, guide rail; 122nd, construction area;13rd, crossbeam;20th, ceiling is protected;21st, arc;22nd, bearing pin;23rd, perforate is operated;30th, support beam;40、 Support adjustment mechanism;41st, installation base plate;42nd, lifting support;43rd, first hydraulic cylinder;50th, walking mechanism;60th, limit switch; 70th, controller;80th, electric hoist;90th, hydraulic leg;91st, cat ladder.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Describe the utility model in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
It is pointed out that unless otherwise specified, all technologies used in this application and scientific terminology have and the application The identical meanings that person of an ordinary skill in the technical field is generally understood that.
In the utility model, in the case where not making opposite explanation, the noun of locality used such as " upper and lower, top, bottom " is generally Be for direction shown in the drawings, or for part in itself on vertical, vertical or gravity direction for;Together Sample, for ease of understanding and describing, " inside and outside " refers to the inside and outside of the profile relative to each part in itself, but the above-mentioned noun of locality is simultaneously It is not used in limitation the utility model.
In order to which the rock for solving hole top in the prior art drops the problem of causing potential safety hazard, the utility model provides one Plant constructing tunnel Terrace prevention device.
As shown in figure 1, the constructing tunnel Terrace prevention device, including stand 10 and protection ceiling 20.Wherein, stand 10 has There is operating platform 11;Protection ceiling 20 is covered on the top of stand 10.By setting protection ceiling 20 on the top of stand 10, apply Workman person can carry out construction operation in the lower section of protection ceiling 20, and protection ceiling 20 can stop that the rock on hole top is fallen down Injure the workmen in hole by a crashing object, may injure personnel by a crashing object so that the rock for eliminating hole top drops or smash the potential safety hazard of equipment.
As shown in figure 1, protection ceiling 20 is spliced by polylith arc 21, arcuately the bending direction of plate 21, adjacent Two pieces of arcs 21 are connected by bearing pin 22.In constructing tunnel is carried out, the width and height in tunnel can produce certain change.Phase Connected between adjacent two arcs 21 by bearing pin 22, the angle between adjacent two pieces of arcs 21 can be adjusted, so as to With the change of construction environment, the width and height of regulation protection ceiling 20.
When the side wall to tunnel is constructed, workmen can trust operation under the protection of protection ceiling 20.And When needing to construct to tunnel top, protection ceiling 20 can block the sight of workmen, cause workmen not obtain Know the situation of tunnel top, so, workmen has to move away protection ceiling 20 and be absorbed in once more may be at any time by top The predicament that the rock dropped injures by a crashing object.
In view of this problem, in the present embodiment, as shown in figure 3, the arc 21 for constituting protection ceiling 20 is transparent Plate and with operation perforate 23.It is preferred that, arc 21 is manufactured using transparent safety glass, and open up on safety glass one Section rectangular notch.By it is transparent and with operation perforate 23 protection ceiling 20, workmen can see tunnel top Situation, the position constructed in order to determine tunnel top to need.When needing to construct to tunnel top, workmen Under the protection of arc 21 through operating perforate 23 directly to be constructed to tunnel top protection can be moved away so as to avoid The risk that ceiling 20 may be injured by a crashing object.
As shown in figure 1, constructing tunnel Terrace prevention device also includes support beam 30, bottom and the stand 10 of support beam 30 connect Connect, the apical support protection ceiling 20 of support beam 30.Support beam 30 plays a part of support protection ceiling 20, in the present embodiment In, support beam 30 is many, and the top of each support beam 30 is connected with bearing pin, it is preferred that support beam 30 is aluminium alloy rod.
Alternatively, protection ceiling 20 and stand 10 are detachably connected;And/or protection ceiling 20 can folding storage to platform The side on the top of frame 10.During without using constructing tunnel Terrace prevention device, protection ceiling 20 is disassembled from stand 10, And/or side of the folding storage of ceiling 20 to the top of stand 10 will be protected, so, constructing tunnel Terrace prevention dress can be saved The parking space put.
As shown in figure 1, constructing tunnel Terrace prevention device also includes support adjustment mechanism 40 and walking mechanism 50.Support is adjusted The apical support operating platform 11 of mechanism 40 is saved, the height of support adjustment mechanism 40 can adjust to change operating platform 11 in platform Position on frame 10;Walking mechanism 50 is arranged on the bottom of support adjustment mechanism 40.By the height for adjusting support adjustment mechanism 40 Degree can change position of the operating platform 11 on stand 10, be easy to different height of the workmen in tunnel to be constructed. Walking mechanism 50 can then change position of the constructing tunnel Terrace prevention device in tunnel with convenient construction personnel, eliminate construction Personnel move the trouble of constructing tunnel Terrace prevention device.In the present embodiment, walking mechanism 50 uses electric walking wheel, passes through The movement of driven by power constructing tunnel Terrace prevention device, further eliminates workmen's push-and-pull constructing tunnel Terrace prevention dress Put.
Specifically, support adjustment mechanism 40 includes installation base plate 41, lifting support 42 and first hydraulic cylinder 43.Lifting branch The bottom of frame 42 is connected with installation base plate 41, the apical support operating platform 11 of lifting support 42.Deviating from for installation base plate 41 rises The side of descending branch frame 42 is connected with walking mechanism 50.First hydraulic cylinder 43 adjusts the height of lifting support 42.Pass through the first hydraulic pressure The stretching motion of cylinder 43 is to adjust rising or falling for lifting support 42, so as to adjust height of the operating platform 11 on stand 10 Position.Optionally, first hydraulic cylinder 43 can be substituted by cylinder.
Optionally, lifting support 42 is scissor lift support, to improve the stability and security of support adjustment mechanism 40.
As shown in Fig. 2 constructing tunnel Terrace prevention device also includes limit switch 60 and controller 70, limit switch 60 is set Put on stand 10, after operating platform 11 triggers limit switch 60, limit switch 60 sends limit signal;Controller 70 and limit Bit switch 60 and support adjustment mechanism 40 are connected, and controller 70 receives limit signal and controls support adjustment mechanism 40 to stop moving Make.Coordinate control support adjustment mechanism 40 persistently to rise by limit switch 60 and controller 70, on the one hand ensure the first hydraulic pressure Cylinder 43 carries out stretching motion in its stroke range, on the other hand avoids operating platform 11 too high and causes the constructor thereon Member bumps against the protection ceiling 20 at top, i.e., first hydraulic cylinder 43, workmen and protection ceiling 20 are played a protective role.
Fig. 1 and Fig. 2 are refer to, stand 10 includes many longerons 12, many crossbeams 13 and operating platform 11.In the present embodiment In, longeron 12 and crossbeam 13 are 4, and the top of the two ends of each crossbeam 13 respectively with least one longeron 12 is connected;Operation is flat Length direction of the platform 11 along longeron 12 is adjustably disposed on longeron 12, and operating platform 11 can be overturn relative to longeron 12, Operating platform 11 has deployed condition and folded state;When operating platform 11 is in deployed condition, operating platform 11 and longeron 12 is vertical, when operating platform 11 is in folded state, and the laminating longeron 12 of operating platform 11 is in perpendicular.By many The quality inspection of root longeron 12 sets up crossbeam 13, to improve the stability of constructing tunnel Terrace prevention device.
When the lower position in tunnel is constructed, operating platform 11 can be made to be rotated towards longeron 12, by it Fold, can so be come and gone and walked about and haulage equipment in tunnel with convenient construction personnel.
In the present embodiment, as shown in Fig. 2 constructing tunnel Terrace prevention device also includes:Electric hoist 80, electric hoist 80 can It is movably arranged on crossbeam 13;Multiple hydraulic legs 90, hydraulic leg 90 is arranged on the bottom of longeron 12;Cat ladder 91, cat ladder 91 are connected with operating platform 11.
Specifically, hook is provided with electric hoist 80, by linking up with lifting means and material.Such as when needing stretching material When, electric hoist 80 is moved to the surface of material on crossbeam 13, then transfers hook, and hook hook is got after material, electric hoist 80 Lift again and link up with and drive the material on linking up with and linking up with to be moved to along crossbeam 13 at workmen, both save the time, drop again The low labor intensity of workmen.
As depicted in figs. 1 and 2, the bottom of longeron 12 sets hydraulic leg 90 to be to prevent that ground injustice causes in tunnel Constructing tunnel Terrace prevention device can not be placed steadily, the height of the bottom of longeron 12 be adjusted by hydraulic leg 90, so that respectively Longeron 12 it is highly consistent, it is ensured that the stationarity of operating platform 11, beneficial to safe construction.Cat ladder 91 is connected on operating platform 11 Can be with convenient construction personnel's down operation platform 11.Optionally, it is provided with hydraulic leg 90 for examining whether it places Stable level detector.
Longeron 12 in the utility model has guide rail 121 along its length, and operating platform 11 is slided along guide rail 121 It is dynamic, it is easy to the position on longeron 12 according to the height adjustment operation platform 11 of construction.
As shown in figure 1, many longerons 12 surround construction area 122, operating platform 11 is multiple, when operating platform 11 is in During deployed condition, multiple operating platforms 11 are located in construction area 122.In the present embodiment, the both sides in construction area 122 Operating platform 11 is provided with, personnel are independently constructed with convenient construction.
As shown in figure 1, operating platform 11 includes platform body 111 and connector 112.Wherein, the first of platform body 111 End is connected with longeron 12;Second end of the two ends of connector 112 respectively with longeron 12 and platform body 111 is connected, so that operation Platform 11 is maintained at deployed condition;At least one set of backplate 113, the first end of platform body 111 and/or the second end are provided with backplate 113, backplate 113 is arranged on platform body 111 turnablely.
In the present embodiment, connector 112 is drag-line, and its one end is connected with longeron 12, the other end and platform body 111 Connection away from one end of longeron 12, when platform body 111 is in deployed condition, drag-line, longeron 12 enclose with platform body 111 Into a right angled triangle.The two ends of platform body 111 are both provided with backplate 113, with to the constructor on platform body 111 Member plays protective action.When without using constructing tunnel Terrace prevention device, the backplate 113 away from one end of longeron 12 may be used also Packed up with folding.
As can be seen from the above description, the utility model the above embodiments realize following technique effect:
And constructing tunnel Terrace prevention device of the present utility model is easily installed, the protection top with safety protection function Canopy, can not disturb carry out tunnel top on the premise of other working procedures to repair top, punching, linked network operation, also without prejudice to other Construction equipment and personnel pass through, while the safety of the equipment personnel by this section of tunnel can be protected effectively, prevent from being dropped rock The danger pounded.
Obviously, above-mentioned described embodiment is only the embodiment of the utility model part, rather than whole realities Apply example.Based on the embodiment in the utility model, those of ordinary skill in the art institute under the premise of creative work is not made The every other embodiment obtained, should all belong to the scope of the utility model protection.
It should be noted that term used herein above is merely to describe embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in this manual using term "comprising" and/or " bag Include " when, it indicates existing characteristics, step, work, device, component and/or combinations thereof.
It should be noted that term " first " in the description and claims of this application and above-mentioned accompanying drawing, " Two " etc. be for distinguishing similar object, without for describing specific order or precedence.It should be appreciated that so using Data can exchange in the appropriate case, so that presently filed embodiment described herein can be with except illustrating herein Or the order beyond those of description is implemented.In addition, term " comprising " and " having " and their any deformation, it is intended that Covering is non-exclusive to be included, for example, containing process, method, system, product or the equipment of series of steps or unit need not limit In those steps or unit for clearly listing, but may include not list clearly or for these processes, method, production Product or the intrinsic other steps of equipment or unit.
Preferred embodiment of the present utility model is the foregoing is only, the utility model is not limited to, for this For the technical staff in field, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle Within, any modification, equivalent substitution and improvements made etc. should be included within protection domain of the present utility model.

Claims (15)

1. a kind of constructing tunnel Terrace prevention device, it is characterised in that including:
Stand (10), the stand (10) has operating platform (11);
Ceiling (20) is protected, the protection ceiling (20) is covered on the top of the stand (10).
2. constructing tunnel Terrace prevention device according to claim 1, it is characterised in that the protection ceiling (20) is by more Block arc (21) is spliced, along the bending direction of the arc (21), and adjacent two pieces of arcs (21) pass through pin Axle (22) is connected.
3. constructing tunnel Terrace prevention device according to claim 2, it is characterised in that the arc (21) is transparent Plate and with operation perforate (23).
4. constructing tunnel Terrace prevention device according to claim 1, it is characterised in that the constructing tunnel Terrace prevention Device also includes support beam (30), and the bottom of the support beam (30) is connected with the stand (10), the support beam (30) Ceiling (20) is protected described in apical support.
5. constructing tunnel Terrace prevention device according to claim 1, it is characterised in that
The protection ceiling (20) and the stand (10) are detachably connected;And/or
The protection ceiling (20) is capable of the side on top of the folding storage to the stand (10).
6. constructing tunnel Terrace prevention device according to claim 1, it is characterised in that the constructing tunnel Terrace prevention Device also includes:
Support adjustment mechanism (40), operating platform (11) described in the apical support of the support adjustment mechanism (40), the support The height of governor motion (40) can adjust to change position of the operating platform (11) on the stand (10);
Walking mechanism (50), the walking mechanism (50) is arranged on the bottom of the support adjustment mechanism (40).
7. constructing tunnel Terrace prevention device according to claim 6, it is characterised in that the support adjustment mechanism (40) Including:
Installation base plate (41);
Lifting support (42), the bottom of the lifting support (42) is connected with the installation base plate (41), the lifting support (42) operating platform (11) described in apical support;
First hydraulic cylinder (43), the first hydraulic cylinder (43) adjusts the height of the lifting support (42).
8. constructing tunnel Terrace prevention device according to claim 7, it is characterised in that the lifting support (42) is to cut Formula lifting support.
9. constructing tunnel Terrace prevention device according to claim 7, it is characterised in that the constructing tunnel Terrace prevention Device also includes:
Limit switch (60), the limit switch (60) is arranged on the stand (10), when the operating platform (11) triggering After the limit switch (60), the limit switch (60) sends limit signal;
Controller (70), the controller (70) is connected with the limit switch (60) and the support adjustment mechanism (40), institute Controller (70) is stated to receive the limit signal and control the support adjustment mechanism (40) stopping to act.
10. constructing tunnel Terrace prevention device according to any one of claim 1 to 9, it is characterised in that the stand (10) include:
Many longerons (12);
Many crossbeams (13), the top of the two ends of each crossbeam (13) respectively with least one longeron (12) is connected;
The operating platform (11), length direction of the operating platform (11) along the longeron (12) is adjustably disposed in institute State on longeron (12), the operating platform (11) can overturn relative to the longeron (12), the operating platform (11) has Deployed condition and folded state;When the operating platform (11) is in the deployed condition, the operating platform (11) and institute State longeron (12) vertically, when the operating platform (11) is in the folded state, operating platform (11) laminating is described Longeron (12) is in perpendicular.
11. constructing tunnel Terrace prevention device according to claim 10, it is characterised in that the constructing tunnel platform is prevented Protection unit also includes:
Electric hoist (80), the electric hoist (80) is movably disposed on the crossbeam (13);And/or
Multiple hydraulic legs (90), the hydraulic leg (90) is arranged on the bottom of the longeron (12);And/or
Cat ladder (91), the cat ladder (91) is connected with the operating platform (11).
12. constructing tunnel Terrace prevention device according to claim 10, it is characterised in that the longeron (12) has edge The guide rail (121) of its length direction, the operating platform (11) is slided along the guide rail (121).
13. constructing tunnel Terrace prevention device according to claim 10, it is characterised in that many longerons (12) are enclosed Into construction area (122), the operating platform (11) is multiple, when the operating platform (11) is in the deployed condition, Multiple operating platforms (11) are located in the construction area (122).
14. constructing tunnel Terrace prevention device according to claim 10, it is characterised in that operating platform (11) bag Include:
Platform body (111), the first end of the platform body (111) is connected with the longeron (12);
Connector (112), the two ends of the connector (112) respectively with the longeron (12) and the platform body (111) Second end is connected, so that the operating platform (11) is maintained at the deployed condition;
At least one set of backplate (113), the first end of the platform body (111) and/or the second end are provided with the backplate (113), the backplate (113) is arranged on the platform body (111) turnablely.
15. constructing tunnel Terrace prevention device according to claim 14, it is characterised in that the connector (112) is Drag-line.
CN201720318757.4U 2017-03-29 2017-03-29 Constructing tunnel Terrace prevention device Active CN206617182U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720318757.4U CN206617182U (en) 2017-03-29 2017-03-29 Constructing tunnel Terrace prevention device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720318757.4U CN206617182U (en) 2017-03-29 2017-03-29 Constructing tunnel Terrace prevention device

Publications (1)

Publication Number Publication Date
CN206617182U true CN206617182U (en) 2017-11-07

Family

ID=60234695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720318757.4U Active CN206617182U (en) 2017-03-29 2017-03-29 Constructing tunnel Terrace prevention device

Country Status (1)

Country Link
CN (1) CN206617182U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302679A (en) * 2020-10-26 2021-02-02 中国电建集团成都勘测设计研究院有限公司 Visual support structure of exploration footrill covering layer hole section and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302679A (en) * 2020-10-26 2021-02-02 中国电建集团成都勘测设计研究院有限公司 Visual support structure of exploration footrill covering layer hole section and construction method thereof

Similar Documents

Publication Publication Date Title
CN205590191U (en) Prevent overload formula building tower crane
CN106481061A (en) Climbing frame
CN206617182U (en) Constructing tunnel Terrace prevention device
CN211202019U (en) Excavation working face roof protective structure
CN204738226U (en) Arched bridge main arch bottom plate rail formula tool car
CN114645614A (en) Rapid moving aerial work platform based on rail device
CN207194419U (en) It may span across the aerial work platform of landing beam
CN209242622U (en) A kind of architectural electricity construction lifting device
CN209703967U (en) A kind of Multifunctional decoration construction bracket
CN106744404A (en) Using the method for portable pylon hoisting rolling mill housings
CN205654063U (en) Tower crane concrete cap's safety protection platform is demolishd in high altitude
CN208605120U (en) It is a kind of to use stable aerial ladder
CN211775606U (en) Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway
CN106892379A (en) A kind of high altitude rescue and job safety slow descending device
CN106337652A (en) Electric power maintenance ladder
CN114044474A (en) Safety protection type power maintenance device
CN207377568U (en) The low vcehicular tunnel maintenance and reinforcement platform and device for influencing traffic
CN206359163U (en) mobile network base station antenna hoisting device
CN207121404U (en) A kind of aerial platform
CN201303221Y (en) Distribution transformer overhauling platform device on 10KV column
CN207142783U (en) A kind of chute type aerial ladder
CN117703454B (en) Safety protection equipment in coal mine
CN220080920U (en) Large-span steel structure beam unloading device
CN105155862B (en) Portable outdoor operation protection frame for aluminum and plastic window decoration
CN211992944U (en) Movable large mining height hydraulic support maintenance platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant