CN206607505U - Cement placing installation for bridge construction - Google Patents

Cement placing installation for bridge construction Download PDF

Info

Publication number
CN206607505U
CN206607505U CN201720217417.2U CN201720217417U CN206607505U CN 206607505 U CN206607505 U CN 206607505U CN 201720217417 U CN201720217417 U CN 201720217417U CN 206607505 U CN206607505 U CN 206607505U
Authority
CN
China
Prior art keywords
inner template
outer snare
sheet metal
interlayer
bridge construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720217417.2U
Other languages
Chinese (zh)
Inventor
密长征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720217417.2U priority Critical patent/CN206607505U/en
Application granted granted Critical
Publication of CN206607505U publication Critical patent/CN206607505U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

Cement placing installation for bridge construction, it is related to bridge engineering construction apparatus field, including outer snare and inner template, the outer snare is circular configuration, inner template is installed in the inside of outer snare, the inner template is hollow regular polygon structure, outer snare is circumscribed outside inner template, hollow interlayer is installed with the centre of inner template, corrugated sheet metal is provided with interlayer, the sheet metal surrounds the surrounding for being arranged on inner template, and hollow cavity is formed between sheet metal and the interlayer of inner template.The utility model structure is novel, using simple, efficiently quick, conveniently it is applied in combination, solidness after bridge pier is poured can be increased by sheet metal and using cooperatively for inner template, increase the hardness of bridge pier, the firmness that the speed poured and increase are poured can be effectively improved.

Description

Cement placing installation for bridge construction
Technical field:
The utility model is related to bridge engineering construction apparatus field, and in particular to a kind of cement for bridge construction is poured Equipment.
Background technology:
Science of bridge building refers to the course of work of bridge exploration, design, construction, maintenance and calibrating etc., and studies this process Science and engineering technology, it is a branch of civil engineering.The development of bridge engineering depends primarily on communications and transportation pair The need for it.Ancient Bridges are based on current people, animal, and less, deck profile grade can be steeper, it might even be possible to lays step for load-carrying, Construction through too busy to get away bridge pier in the construction of bridge;
And bridge pier is propped up in addition to the abutment that two ends and embankment are connected in the middle of remaining in bridge more than holes and holes Support structure, bridge pier is mainly made up of top cap, pier shaft, and abutment is mainly made up of top cap, abutment body, and bridge pier is divided into solid pier, column pier With framed bent pier etc..It can be divided into rectangle pier, sophisticated shape pier, circular pier etc. by flat shape.The material of building bridge pier can use timber, stone Material, concrete, armored concrete, steel etc..
It is general many using the method poured progress in the building course of bridge pier, and be all to use mould during pouring Tool is shaped, and the technical scheme that this patent is provided is exactly a kind of cement placing installation for bridge construction, and the equipment can The firmness that the speed and increase poured with effectively improving is poured, facilitates and is used, and efficiency is fast at high speed, facilitates building for bridge pier And if carrying.
Utility model content:
Technical problem to be solved in the utility model be to provide a kind of structure it is novel, using simple, efficiently quick, side Just it is applied in combination, the cement for bridge construction that can effectively improve the firmness that the speed poured and increase are poured is poured and set It is standby.
Technical problem to be solved in the utility model is realized using following technical scheme:
For the cement placing installation of bridge construction, including outer snare and inner template, the outer snare is circular configuration, The inside of outer snare is provided with inner template, and the inner template is hollow regular polygon structure, and outer snare is circumscribed in outside inner template Portion, hollow interlayer is installed with the centre of inner template, and corrugated sheet metal is provided with interlayer, and the sheet metal is surrounded and set The surrounding in inner template is put, hollow cavity is formed between sheet metal and the interlayer of inner template;
Outer ring set can use rectangular configuration in different environments, and inner template in different situations then can be with Use circular configuration;
The depth of the sheet metal is identical with the depth of outer snare with inner template, and sheet metal is uniformly arranged and mounted on inner template In the interlayer of surrounding;
The thickness of the outer snare is twice of internal model plate thickness;
Outer snare is taken out after the completion of pouring and then inner template of arranging in pairs or groups proceeds to reuse;
The outer snare is solid construction;
After installing outer snare and inner template in the place for needing to pour when use, cement mortar is circulated into outer Inside snare, after after the inside cavity between the completely outer snare of grout filling and inner template and inner template and sheet metal, by outside Snare is withdrawn, and such cement bridge pier, which is poured, to be finished, and outer snare then is moved into next objective, and install supporting Inner template can be poured next time;
The beneficial effects of the utility model are:Structure is novel, using simple, efficiently quick, is conveniently applied in combination, passes through gold Category piece and using cooperatively for inner template can increase the solidness after bridge pier is poured, and increase the hardness of bridge pier, can effectively improve The firmness that the speed and increase poured is poured.
Brief description of the drawings:
Fig. 1 is structural representation of the present utility model;
Wherein:The outer snares of 1-;2- inner templates;3- sheet metals.
Embodiment:
In order that technological means, creation characteristic, reached purpose and effect that the utility model is realized are easy to understand, under Face combines and is specifically illustrating, and the utility model is expanded on further.
As shown in Figure 1:For the cement placing installation of bridge construction, including outer snare 1 and inner template 2, the outer snare 1 For circular configuration, inner template 2 is installed in the inside of outer snare 1, the inner template 2 is hollow regular polygon structure, outer ring It is cut in outside set 1 outside inner template 2, is installed with hollow interlayer in the centre of inner template 2, corrugated metal is provided with interlayer Piece 3, the sheet metal 3 surrounds the surrounding for being arranged on inner template 2, and hollow cavity is formed between sheet metal 3 and the interlayer of inner template 2 Body;
The outer snare 1 can use rectangular configuration in different environments, and inner template then may be used in different situations To use circular configuration;
The depth of the sheet metal 3 is identical with the depth of outer snare 1 with inner template 2, and sheet metal 3 is uniformly arranged and mounted on interior In the interlayer of the surrounding of template 2;
The thickness of the outer snare 1 is twice of the thickness of inner template 2;
Outer snare 1 is taken out after the completion of pouring and then inner template 2 of arranging in pairs or groups proceeds to reuse;
The outer snare 1 is solid construction;
After installing outer snare 1 and inner template 2 in the place for needing to pour when use, cement mortar is circulated into Inside outer snare 1, the inside cavity between the completely outer snare 1 of grout filling and inner template 2 and inner template 2 and sheet metal 3 is treated Afterwards, outer snare 1 is withdrawn, such cement bridge pier, which is poured, to be finished, and outer snare 1 then is moved into next objective, and pacify Loading onto supporting inner template 2 can be poured next time;
General principle of the present utility model and principal character and advantage of the present utility model has been shown and described above.One's own profession The technical staff of industry is it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification Simply illustrate principle of the present utility model, on the premise of the utility model spirit and scope are not departed from, the utility model is also Various changes and modifications are had, these changes and improvements are both fallen within the range of claimed the utility model.The utility model Claimed scope is by appended claims and its equivalent thereof.

Claims (5)

1. the cement placing installation for bridge construction, it is characterised in that:Including outer snare and inner template, the outer snare is circle Shape structure, is provided with inner template in the inside of outer snare, and the inner template is hollow regular polygon structure, outer snare it is circumscribed in Outside inner template, hollow interlayer is installed with the centre of inner template, corrugated sheet metal, the metal are provided with interlayer Piece surrounds the surrounding for being arranged on inner template, and hollow cavity is formed between sheet metal and the interlayer of inner template.
2. the cement placing installation according to claim 1 for bridge construction, it is characterised in that:The depth of the sheet metal Degree is identical with the depth of outer snare with inner template, and sheet metal is uniformly arranged and mounted in the interlayer of inner template surrounding.
3. the cement placing installation according to claim 1 for bridge construction, it is characterised in that:The thickness of the outer snare Spend for twice of internal model plate thickness.
4. the cement placing installation according to claim 1 for bridge construction, it is characterised in that:The outer snare is real Core structure.
5. the cement placing installation according to claim 1 for bridge construction, it is characterised in that:The outer snare can be used Rectangular configuration is substituted.
CN201720217417.2U 2017-03-07 2017-03-07 Cement placing installation for bridge construction Expired - Fee Related CN206607505U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720217417.2U CN206607505U (en) 2017-03-07 2017-03-07 Cement placing installation for bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720217417.2U CN206607505U (en) 2017-03-07 2017-03-07 Cement placing installation for bridge construction

Publications (1)

Publication Number Publication Date
CN206607505U true CN206607505U (en) 2017-11-03

Family

ID=60165828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720217417.2U Expired - Fee Related CN206607505U (en) 2017-03-07 2017-03-07 Cement placing installation for bridge construction

Country Status (1)

Country Link
CN (1) CN206607505U (en)

Similar Documents

Publication Publication Date Title
CN103088844B (en) Reinforced concrete inspection well whole prefabricated hoisting construction method
CN105350777A (en) Device and method for one-time pouring molding of ultra-high concrete column
CN102828468B (en) Construction method for controlling prefabricated crack of high-strength thin-walled box girder under high-temperature dry condition
CN103485370B (en) A kind of concrete construction control method preventing wallboard harmful cracks
CN106113230B (en) The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need
CN103556819A (en) Construction method for reserving constructional column holes in beam plate
CN103741949B (en) Treatment of juncture between vertical structure and horizontal structure
CN206607505U (en) Cement placing installation for bridge construction
CN206800800U (en) Horizontal reinforcement distance piece
CN103741944B (en) Fixation kit, template system containing this fixation kit and body of wall casting method
CN108179754A (en) The construction method of long and narrow Extra-Deep Foundation Pit system
CN114657940B (en) Formwork supporting system for cement slab formwork cast-in-situ gravity type embankment retaining wall concrete and construction method
CN206034946U (en) Structure is handled to large -scale pressure vertical shaft concrete defect based on slipform technology
CN207526118U (en) For pre-buried and closure unwrapping wire hole unwrapping wire punch die
CN105908883A (en) Construction method for preventing upward floating of composite floor system lightweight core formwork
CN104499481B (en) A kind of prestressing force screw stake and preparation method thereof
CN216076481U (en) Concrete side wall hole shutoff construction equipment
CN205329714U (en) Compound retaining wall structure of highway precast concrete piece
CN201835524U (en) Pouring device for concrete beam with top embedded part
CN108612121A (en) A kind of formwork structure and its construction method of the pile framing of large area shallow waters
CN104100091A (en) Construction method and cylinder fixing device for pouring concrete to obtain cylinders by aid of paper forms
CN204418666U (en) A kind of building site is with there being side wall stair template
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN109291208B (en) Large-span prestressed concrete double-T-plate construction method
CN203782715U (en) Self-floating type inner mold system for under water pouring of hollow pipe column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171103

Termination date: 20180307