CN206590414U - The lifting Gua Tong mechanisms of side loading type garbage truck - Google Patents

The lifting Gua Tong mechanisms of side loading type garbage truck Download PDF

Info

Publication number
CN206590414U
CN206590414U CN201720198398.3U CN201720198398U CN206590414U CN 206590414 U CN206590414 U CN 206590414U CN 201720198398 U CN201720198398 U CN 201720198398U CN 206590414 U CN206590414 U CN 206590414U
Authority
CN
China
Prior art keywords
lifting
bucket
support
garbage truck
loading type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720198398.3U
Other languages
Chinese (zh)
Inventor
计京宝
文杰
王鸿举
张国强
向科
徐加强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Kairui Special Vehicle Co Ltd
China Automotive Engineering Research Institute Co Ltd
Original Assignee
Chongqing Kairui Special Vehicle Co Ltd
China Automotive Engineering Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Kairui Special Vehicle Co Ltd, China Automotive Engineering Research Institute Co Ltd filed Critical Chongqing Kairui Special Vehicle Co Ltd
Priority to CN201720198398.3U priority Critical patent/CN206590414U/en
Application granted granted Critical
Publication of CN206590414U publication Critical patent/CN206590414U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

A kind of lifting Gua Tong mechanisms of side loading type garbage truck are claimed in the utility model; including extension bucket support, bucket support is hung provided with bucket tooth is hung, bucket tooth is hung in a symmetrical arrangement in extension bucket support; hang bucket support both sides and be arranged with lift shaft, lift shaft is hinged with the raising rod of both sides respectively;Bucket support is hung to be connected with the lift carriage axis of guide by the axle sleeve on support;Hang and connecting spring is provided between bucket support and lift carriage;Lift carriage both sides are arranged with two groups of rollers, internal trolley group and outer roller group, and it is distributed in inside and outside track runner.The utility model lifting hangs bucket mechanism structure simply, occupies little space, and is adapted to a kind of side-mounted lifting Gua Tong mechanisms of compact car repacking, realizes that bucket body function is hung in the lifting of side loading type garbage truck.

Description

The lifting Gua Tong mechanisms of side loading type garbage truck
Technical field
The utility model is related to engineering field lifting Gua Tong mechanisms, is carried more particularly, to the automatic charging of garbage reclamation Rise the equipment of mechanism.
Background technology
At present, the fast-developing and social environmental consciousness of urbanization is improved, and environmental sanitation garbage collecting and transferring pattern is proposed Higher requirement;Therefore, good airproof performance, the receipts fortune mode of the self-loading and unloading type garbage collecting and transferring car of receipts fortune efficiency high, which is able to promote, answers With.Side loading type garbage truck is a kind of shipment mode of self-loading and unloading type garbage collecting and transferring car, the lifting Gua Tong mechanisms position of side loading type garbage truck In the right front position that fortune carriage body is received on automobile chassis, compression set is coordinated to match somebody with somebody before such structure arrangement is transported in carriage body with receipts Close, by lifted by front side hang that bucket collect pours into expand, loose rubbish is to efficiently compressed to receive fortune carriage body rear portion, increase is single Car rubbish useful load, improves bicycle conevying efficiency.
The lifting of side loading type garbage truck is hung bucket linkage and is widely popularized, at present, and bucket mechanism type is hung in the lifting used Formula is also more;General oil cylinder+chain mode drawback is to take rubbish car body side spaces greatly, with garbage inlet closure Linkage can not be constituted between plate, need to separately increase hydraulic control device control seal cover board and open and close, therefore, cause deployment cost to increase; The utility model can realize with garbage inlet seal cover board link form, relatively general oil cylinder+chain mode, which can be reduced, matches somebody with somebody It is set to this;Similar structures hoisting way is compared, the utility model structure garbage truck carriage body layout is more compact, reasonable, takes rubbish Car body side spaces are smaller, therefore, and the utility model is adapted to a kind of side-mounted lifting Gua Tong mechanisms of compact car repacking.
The content of the invention
The utility model aims to solve the problem that above problem of the prior art.Propose one kind simple in construction, occupy little space The lifting Gua Tong mechanisms method of side loading type garbage truck.The technical solution of the utility model is as follows:
A kind of lifting Gua Tong mechanisms of side loading type garbage truck, including:For fixing the extension bucket support of dustbin and for carrying Rise the lift carriage of dustbin, extension bucket support be connected between lift carriage by buffer gear, it is characterised in that in institute State extension bucket support and be provided with the alternate setting extension bucket tooth of the row for being used for mutually fixing with dustbin hangers, the extension bucket tooth hangs bucket branch Into being symmetrically arranged on frame, and the bucket support both sides that hang are arranged with the lift shaft that bucket support is hung for being lifted, described to carry Lifting shaft is articulated and connected with the raising rod of both sides respectively, and the bucket support of hanging passes through the axle sleeve for being used to be oriented on support and lifting The axis of guide connection of frame;The lift carriage both sides are arranged with the sliding equipment slided for lift carriage.
Further, the buffer gear is spring, and its one end is fixed on extension bucket support, and the other end is fixed on elevator On frame.
Further, the sliding equipment includes internal trolley group, outer roller group and track runner, the internal trolley group, outer Roller group is respectively distributed to the inner and outer of track runner.
Further, the lift carriage is additionally provided with the oil cylinder for providing lifting power.
Further, the support bottom of lift carriage is provided with extension bucket arc location-plate, arc location-plate radian and pail phase Answer position radian roughly the same.
Further, the lift carriage both sides are symmetrically provided with bar hole, and lift shaft can be realized in bar hole and moved down It is dynamic.
Advantage of the present utility model and have the beneficial effect that:
Advantage of the present utility model is as follows, and oil cylinder+chain mode drawback general at present is to take rubbish car side Portion space is big, and linkage can not be constituted between garbage inlet seal cover board, need to separately increase hydraulic control device control seal cover board and open Close, therefore, cause deployment cost to increase;The utility model can realize with garbage inlet seal cover board link form, it is relatively general Oil cylinder+chain mode can reduce deployment cost;Compare similar structures hoisting way, the utility model structure garbage truck carriage body Layout is more compact, reasonable, and occupancy rubbish car body side spaces are smaller, therefore, and the utility model is adapted to the one of compact car repacking Plant side-mounted lifting Gua Tong mechanisms.
Brief description of the drawings
Fig. 1 is that the utility model provides preferred embodiment schematic front view;
Fig. 2 is that Fig. 1 axles regard structural representation;
Fig. 3 is Fig. 1 lift carriages, hangs bucket holder combination schematic diagram;
In figure:1- hangs bucket support;2- hangs bucket tooth;3- lift shafts;4- raising rods;The 5- axis of guides;6- lift carriages;7- bullets Spring;8- internal trolley groups;The outer roller groups of 9-;10- track runners;11- axle sleeves;12- sides wall.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out It is clear, describe in detail.Described embodiment is only a part of embodiment of the present utility model.
The utility model solve above-mentioned technical problem technical scheme be,
Reference picture 1- Fig. 3 show a kind of lifting Gua Tong mechanisms of side loading type garbage truck, including:For fixing dustbin Bucket support 1 and the lift carriage 6 for lifting dustbin are hung, buffer gear phase is passed through between the extension bucket support 1 and lift carriage 6 Connection, it is characterised in that 1 alternate set of a row being provided with for mutually being fixed with dustbin hangers hangs bucket on the extension bucket support Tooth 2, the extension bucket tooth 2 is hung on bucket support 1 into being symmetrically arranged, and the both sides of extension bucket support 1 are arranged with for carrying The lift shaft 3 of extension bucket support is risen, the lift shaft 3 is articulated and connected with the raising rod 4 of both sides respectively, the extension bucket support 1 leads to The axle sleeve 11 for being used to be oriented to crossed on support is connected with the axis of guide 5 of lift carriage;The both sides of lift carriage 6 are arranged with use The sliding equipment slided in lift carriage 6.
It is preferred that, in order to during decline, make lift carriage tend to synchronous whereabouts, the buffer gear with hanging bucket support For spring 7, its one end is fixed on extension bucket support 1, and the other end is fixed in lift carriage 6.
It is preferred that, the sliding equipment include internal trolley group 8, outer roller group 9 and track runner 10, the internal trolley group 8, Outer roller group 9 is respectively distributed to the inner and outer of track runner 10.
It is preferred that, the lift carriage 6 is additionally provided with the oil cylinder for providing lifting power.
It is preferred that, it is suspended in order that dustbin is stable in lifting Gua Tong mechanisms, the support bottom of lift carriage 6 is provided with Bucket arc location-plate is hung, arc location-plate radian is roughly the same with pail relevant position radian.
It is preferred that, the both sides of lift carriage 6 are symmetrically provided with bar hole, and lift shaft 3 can be realized in bar hole and moved down It is dynamic.
The utility model lifting hangs bucket mechanism structure simply, occupies little space, and is adapted to a kind of side-mounted of compact car repacking Gua Tong mechanisms are lifted, realize that bucket body function is hung in the lifting of side loading type garbage truck.
Utility model works process description:
The utility model side loading type garbage truck lifting Gua Tong mechanisms, are to constitute side-mounted garbage collecting and transferring car part; During garbage reclamation operation, the feeding function that bucket is hung in lifting is realized.
Side loading type garbage truck lifts Gua Tong mechanisms main working process:When reclaiming charging operation, Gua Tong mechanisms are lifted Both sides are hung over the hangers of dustbin by hanging on the raising rod that the lift shaft on bucket support is hinged on outside the wall of garbage truck side On the extension bucket tooth of bucket support correspondence position, in the presence of oil cylinder, raising rod drives extension bucket support to be oriented to along along lift carriage Axle is moved up, and is suspended on the dustbin hung on bucket support while being lifted up, until after being contacted with lift carriage upper head plate, Lift carriage is driven integrally to be moved up along track runner, internal trolley group roller is oriented to along track runner inwall and rolled, outer roller Group roller is oriented to along track runner outer wall and rolled.Finally, to track runner top stop bit, hoisting mechanism is around internal trolley group roller Axle rotates respective angles, realizes Tilting, completes charging operation.
The above embodiment is interpreted as being merely to illustrate the utility model rather than limits of the present utility model protect Protect scope.After the content of record of the present utility model has been read, technical staff can make various changes to the utility model Or modification, these equivalence changes and modification equally fall into the utility model claim limited range.

Claims (6)

1. a kind of lifting Gua Tong mechanisms of side loading type garbage truck, including:For fixing the extension bucket support (1) of dustbin and for carrying The lift carriage (6) of dustbin is risen, described to hang bucket support (1) and be connected between lift carriage (6) by buffer gear, its feature It is, alternate set of the row for being used for mutually fixing with dustbin hangers is provided with the extension bucket support (1) and hangs bucket tooth (2), institute Extension bucket tooth (2) is stated to hang on bucket support (1) into being symmetrically arranged, and described extension bucket support (1) both sides are arranged with for carrying The lift shaft (3) of extension bucket support is risen, the lift shaft (3) is articulated and connected with the raising rod (4) of both sides respectively, the extension bucket branch Frame (1) is connected by the axle sleeve (11) for being used to be oriented on support with the axis of guide (5) of lift carriage;The lift carriage (6) Both sides are arranged with the sliding equipment slided for lift carriage (6).
2. the lifting Gua Tong mechanisms of side loading type garbage truck according to claim 1, it is characterised in that the buffer gear is Spring (7), its one end is fixed on extension bucket support (1), and the other end is fixed in lift carriage (6).
3. the lifting Gua Tong mechanisms of side loading type garbage truck according to claim 1 or 2, it is characterised in that the skate machine Structure includes internal trolley group (8), outer roller group (9) and track runner (10), and the internal trolley group (8), outer roller group (9) are divided respectively Inner and outer of the cloth in track runner (10).
4. the lifting Gua Tong mechanisms of side loading type garbage truck according to claim 1 or 2, it is characterised in that the elevator Frame (6) is additionally provided with the oil cylinder for providing lifting power.
5. the lifting Gua Tong mechanisms of side loading type garbage truck according to claim 1 or 2, it is characterised in that lift carriage (6) Support bottom provided with bucket arc location-plate is hung, arc location-plate radian is roughly the same with pail relevant position radian.
6. the lifting Gua Tong mechanisms of side loading type garbage truck according to claim 5, it is characterised in that the lift carriage (6) both sides are symmetrically provided with bar hole, and lift shaft (3) can be realized in bar hole and moved up and down.
CN201720198398.3U 2017-03-02 2017-03-02 The lifting Gua Tong mechanisms of side loading type garbage truck Active CN206590414U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720198398.3U CN206590414U (en) 2017-03-02 2017-03-02 The lifting Gua Tong mechanisms of side loading type garbage truck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720198398.3U CN206590414U (en) 2017-03-02 2017-03-02 The lifting Gua Tong mechanisms of side loading type garbage truck

Publications (1)

Publication Number Publication Date
CN206590414U true CN206590414U (en) 2017-10-27

Family

ID=60126405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720198398.3U Active CN206590414U (en) 2017-03-02 2017-03-02 The lifting Gua Tong mechanisms of side loading type garbage truck

Country Status (1)

Country Link
CN (1) CN206590414U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108640060A (en) * 2018-06-29 2018-10-12 朱志祥 Hang bucket elevator
CN115593823A (en) * 2022-11-18 2023-01-13 徐州德高电动车科技有限公司(Cn) Garbage bin promotes turning device for electronic sanitation car

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108640060A (en) * 2018-06-29 2018-10-12 朱志祥 Hang bucket elevator
CN115593823A (en) * 2022-11-18 2023-01-13 徐州德高电动车科技有限公司(Cn) Garbage bin promotes turning device for electronic sanitation car
CN115593823B (en) * 2022-11-18 2023-09-05 徐州德高电动车科技有限公司 Garbage bin promotes turning device for electronic sanitation

Similar Documents

Publication Publication Date Title
CN101927908B (en) Slag soil transfer system
CN106004609B (en) The handling method of Self-loading-unloading boxcar
CN209442061U (en) A kind of automobile-used fluid pressure type extension bucket raising tilting device of rubbish
CN208716059U (en) Dustbin hangs bucket and overturns structure
CN206590414U (en) The lifting Gua Tong mechanisms of side loading type garbage truck
CN106742980A (en) Garbage truck docking system
CN109625691A (en) A kind of underground dustbin and move case method
CN110329685B (en) New energy electric hanging barrel device for classified cleaning of garbage
CN203568720U (en) Integrally loading/unloading vehicle based on slippage arm-changing mechanism
CN201525703U (en) Loading/unloading device for vehicle-mounted large-scale equipment
CN205061401U (en) Single track hangs heavy crane beam
CN203877301U (en) Side-mounting compression type refuse collector
CN206278544U (en) Garbage truck docking system
CN205873007U (en) Immerse formula rubbish compression station
CN105775777B (en) A kind of dustbin lifting tipping mechanism
CN206203170U (en) A kind of universal self-discharging garbage vehicle Ce Zhuanguatong mechanisms
CN201534691U (en) Swing arm device of garbage truck
CN205932037U (en) A tilting mechanism that is used for split type side material loading rubbish equipment
CN108116471B (en) A skip for material transportation circulation
CN205240456U (en) Multi -functional closed arm railway carriage that colludes
CN206278542U (en) Small-sized rubbish car for carrying out slitless connection with bulky refuse car
CN206520962U (en) A kind of refuse depot row hanging casing suspension bracket
CN204998399U (en) Full -automatic tipping bucket bonnet is fluffy
CN209442055U (en) A kind of underground dustbin
CN112340322A (en) Automatic hook arm type garbage truck

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant