CN206574384U - Factory Logistics analogue experiment installation - Google Patents
Factory Logistics analogue experiment installation Download PDFInfo
- Publication number
- CN206574384U CN206574384U CN201720211576.1U CN201720211576U CN206574384U CN 206574384 U CN206574384 U CN 206574384U CN 201720211576 U CN201720211576 U CN 201720211576U CN 206574384 U CN206574384 U CN 206574384U
- Authority
- CN
- China
- Prior art keywords
- raw material
- contact
- intermediate bin
- bin
- exhaust
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Casting Devices For Molds (AREA)
Abstract
The utility model is related to a kind of Factory Logistics analogue experiment installation, the supplement of raw material cabin analog raw material in the way of inflating, the output of first row air valve and analog raw material is opened in the way of raw material dolly triggers exhaust contact, analog raw material dolly the replenishing to intermediate bin in the way of raw material dolly rubs the driving wheel for driving intermediate bin, rubbed the output for driving the counter-rotational mode of driving wheel to simulate finished product in intermediate bin with finished product dolly, the opening of charging valve is controlled in the way of second piston triggering inflation contact in intermediate bin and simulates the deposit finished product to finished bin, the lasting output of finished product is simulated in the way of the second row air valve of finished bin is persistently vented simultaneously, in these analog informations, can be by valve opening, the control of the output speed of source of the gas and the speed of dolly, realize the simulation to real-time logisticses information, thus the experimental provision has degree of verisimilitude high, the good advantage of experiment effect.
Description
Technical field
The utility model is related to a kind of Factory Logistics analogue experiment installation.
Background technology
During Factory Logistics are the physical flow process of material or raw material from supply workshop to reception workshop, according to actual need
Ask, the functions such as transport, storage, buying, handling, packaging, circulation and process, dispatching, information processing are combined reality
The process that existing user requires.In the research and design of logistics major, the understanding to the process is one of main research direction.It is existing
It is typically the writing on the blackboard combination figure of explanation person to the research meanses during this in the research and design of stage logistics major, or
Further, a manually operated model sand table is set up, allows audience to have an intuitively experience understanding.But this research mode
The shortcoming of presence has:1, although say that solution preocess is directly perceived, but all processes are manual, entirely say that solution preocess expends the time
It is long;2, explanation person should operate sand table, also explain, influence explanation effect;3, the interactive difference of explanation person and audience, Zhi Nengjing
State is shown, it is impossible to be illustrated in logistics transportation system complicated under different key elements.
Chinese patent literature CN201620298709.9 discloses a kind of logistics major teaching simulation sand table, including installs
Logistic storage model, a number of Logistics Transportation vehicle model in sand table surface and the Logistics Transportation vehicle model is controlled with one
Determine the trajectory control system of orbital direction traveling.The sand table make use of the combination of appropriate mechanical structure and magnetic block, form one
Plant the effect of logistics trolley model automatically walk;Also, each mechanical mechanism can control its rotating speed by control device control again,
Whether dally, turn to and rotation time.
But in above-mentioned sand table, simply demonstrate merely in running of the traffic car between storage arrangement, it is impossible to
Combined, also can not be just delayed relevant with logistics with the information such as the storage information, the speed of special bus, the loading capacity of special bus of warehouse
Flow situation of the information after changing, thus the sand table has presentation information not comprehensively and the poor defect of degree of verisimilitude.
Utility model content
The utility model aims to provide a kind of Factory Logistics analogue experiment installation, to solve logistics sand table in the prior art
The problem of degree of verisimilitude is poor.
In order to solve the above technical problems, the technical scheme of Factory Logistics analogue experiment installation is as follows in the utility model:
Be disposed with from front to back on Factory Logistics analogue experiment installation, including sand table, the surface of sand table raw material cabin, in
Between storehouse and finished bin,
Provided with the first piston that can slide up and down in raw material cabin, it is connected with above first piston for pushing down on the first work
The first source of the gas for persistently supplying is connected with first return spring of plug, the plunger shaft below first piston and for controlling
The first row air valve of exhaust, first row air valve is magnetic valve, the automatically controlled end of first row air valve be connected with turn the first controller and
Contact is vented, on triggering, delay switch control first row air valve is opened and raw material cabin is arranged in the first controller for exhaust contact
Gas;
The raw material track of closed curve-shaped is provided between raw material cabin and intermediate bin and thereon along the original of raw material track travel
Trolley, raw material dolly is electric self-propelled, and is vented contact on raw material track;
Axis in intermediate bin around extension up and down is rotatably equipped with worm drive on leading screw, leading screw and is connected with guiding dress up and down
Fit on the second piston in intermediate bin, leading screw also rotation stop and be connected with the driving wheel positioned at bottom, the wheel side of driving wheel is from centre
Storehouse front and rear sides are exposed, and the inflation contact that can be triggered by second piston is provided with the inwall of intermediate bin;
Be provided between intermediate bin and finished bin closed curve-shaped finished product track and thereon along finished product track travel into
Product dolly, finished product dolly is electric self-propelled, and finished product track and raw material track are on symmetrical before and after intermediate bin, finished product dolly
Steering with raw material dolly is in the same direction, and the partial frictional that finished product dolly and raw material dolly each can expose with driving wheel coordinates;
Provided with the 3rd piston that can slide up and down in finished bin, it is connected with above the 3rd piston for pushing down on the 3rd work
It is connected with plunger shaft below 3rd return spring of plug, the 3rd piston for the second row air valve of control exhaust and for controlling
The charging valve of air inlet processed, charging valve is magnetic valve, and is connected with the import of charging valve the second source of the gas, and is filled
The automatically controlled end of air valve passes through second controller connection inflation contact, after the triggering of inflation contact, second controller control inflation
Valve is opened and inflated into finished bin.
Intermediate bin has two, two intermediate bins between left and right every the first intermediate bin and the second intermediate bin, the first middle position in storehouse
In the left of the second intermediate bin;
The steering of raw material dolly is counterclockwise;
Raw material track has the first orbital segment of closing corresponding with the first intermediate bin, and the left side of the first orbital segment is provided with head
Auxiliary Track that tail two ends connect with the first orbital segment section, the right side of the first orbital segment provided with head and the tail two ends with the first track
The second orbital segment that section connects, the second orbital segment is corresponding with the second intermediate bin, and in the initiating terminal and first of Auxiliary Track section
Orbital segment connecting position is provided with the first switch mechanism, is set in the initiating terminal of the second orbital segment and the first orbital segment connecting position
There is the second switch mechanism, the first switch mechanism and the second switch mechanism are in the firing state by raw material dolly from the first orbital segment
In guide;
Exhaust contact has two, and two exhaust contacts are respectively first exhaust contact and second exhaust contact, and first exhaust is touched
Point is located at the position between the initiating terminal of the clearing end of the second orbital segment on the first orbital segment and Auxiliary Track section, second exhaust
Contact is located in Auxiliary Track section, and first exhaust contact connects the first switch mechanism and the second track switch machine by reversing switch
At least one in structure, reversing switch have by the first switch mechanism and the second switch mechanism simultaneously with first exhaust contacting
First state, reversing switch also has disconnect the first switch mechanism and the second switch mechanism with first exhaust contact simultaneously the
Two-state;
First controller has the counting list for being used for counting when first exhaust contact and second exhaust contact are successively triggered
Member and the computing unit for setting delay length according to the counting of counting unit.
The steering of finished product dolly is counterclockwise;
Inflation contact has two, and two inflation contacts are respectively the first inflation contact for being located in the first intermediate bin and positioned at the
The second inflation contact in two intermediate bins;
Second controller has the counting list for being used for counting when the first inflation contact and the second inflation contact are successively triggered
Member and the computing unit for setting delay length according to the counting of counting unit.
It is provided with the top of raw material cabin, intermediate bin and finished bin for being touched above the arrival of corresponding piston during limit position
The inductor of hair and the alarm being connected electrically on inductor.
Alarm is the warning lamp above raw material cabin or intermediate bin or finished bin.
Be additionally provided with sand table for control the first source of the gas aeration speed the first control handle, for controlling the second gas
Second control handle of the aeration speed in source and for the 3rd control handle of the aperture for controlling second row air valve.
Raw material track and finished product track are the track of waist-hole type.
The supplement of raw material cabin analog raw material in the way of inflating in the utility model, is triggered with raw material dolly and is vented contact
Mode opens the output of first row air valve and analog raw material, is simulated in the way of raw material dolly rubs the driving wheel for driving intermediate bin
Raw material dolly replenishes to intermediate bin, drives the counter-rotational mode of driving wheel to simulate finished product in intermediate bin with the friction of finished product dolly
Output, control the opening of charging valve in the way of second piston triggering inflation contact in intermediate bin and simulate to finished bin
Finished product is stored in, while the lasting output of finished product is simulated in the way of the second row air valve of finished bin is persistently vented, in these simulations
In information, it can be realized by the control of the speed to valve opening, the output speed of source of the gas and dolly to real-time logisticses information
Simulation so that the problem of degree of verisimilitude for solving logistics sand table in the prior art is poor, thus the experimental provision have degree of verisimilitude it is high,
The good advantage of experiment effect.
Brief description of the drawings
Fig. 1 is the structural representation of experimental provision in the utility model;
Fig. 2 is the structural representation of raw material cabin in Fig. 1;
Fig. 3 is the structural representation of intermediate bin in Fig. 1;
Fig. 4 is the structural representation of finished bin in Fig. 1.
Embodiment
Describe the utility model in detail below with reference to accompanying drawing and in conjunction with the embodiments.It should be noted that not rushing
In the case of prominent, the feature in embodiment and embodiment in the utility model can be mutually combined.
The embodiment of Factory Logistics analogue experiment installation in the utility model:As shown in Figure 1 to Figure 3, the experimental provision bag
Include and be disposed with a raw material cabin 2, two intermediate bins and a finished bin 10 on sand table 1, the surface of sand table 1 from front to back.
Provided with the first piston 21 that can slide up and down in raw material cabin 2, the top of first piston 21 is connected with for pushing down on
The first gas for persistently supplying is connected with first return spring 22 of first piston 21, the plunger shaft of the lower section of first piston 21
Source 23 and the first row air valve 24 for controlling exhaust, first row air valve 24 is magnetic valve, the automatically controlled end of first row air valve 24 according to
It is secondary to be connected with the first controller 25 and exhaust contact, exhaust contact on triggering, delay switch control the in the first controller 25
One air bleeding valve 24 is opened and raw material cabin 2 is vented.Exhaust contact has two, and two exhaust contacts are respectively the He of first exhaust contact 26
Second exhaust contact 27, first exhaust contact 26 is located at the clearing end and auxiliary rail of the second orbital segment 53 on the first orbital segment 51
Position between the initiating terminal of road section 52, second exhaust contact 27 is located in Auxiliary Track section 52, and first exhaust contact 26
At least one in first switch mechanism 61 and the second switch mechanism 62 is connected by reversing switch 114, reversing switch 114 has will
The first state that first switch mechanism 61 and the second switch mechanism 62 are connected with first exhaust contact 26 simultaneously, reversing switch 114
Also there is the second state for disconnecting the first switch mechanism 61 and the second switch mechanism 62 with first exhaust contact 26 simultaneously.
The raw material track 5 of closed curve-shaped is provided between raw material cabin 2 and intermediate bin and thereon along the walking of raw material track 5
Raw material dolly 4, raw material dolly 4 is electric self-propelled, and is vented contact on raw material track 5.Raw material track 5 has and the
First orbital segment 51 of the corresponding closing of one intermediate bin 31, the left side of the first orbital segment 51 provided with head and the tail two ends with the first track
The Auxiliary Tracks section 52 that section 51 connects, the right side of the first orbital segment 51 connect provided with head and the tail two ends with the first orbital segment 51 the
Two orbital segments 53, the second orbital segment 53 is corresponding with the second intermediate bin 32, and in the initiating terminal and the first rail of Auxiliary Track section 52
Road 51 connecting positions of section are provided with the first switch mechanism 61, connect position in the initiating terminal and the first orbital segment 51 of the second orbital segment 53
Install and be equipped with the second switch mechanism 62, the first switch mechanism 61 and the second switch mechanism 62 are in the firing state by raw material dolly
4 guide from the first orbital segment 51.
Axis in intermediate bin around extension up and down is rotatably equipped with worm drive on leading screw 33, leading screw 33 and is connected with leads up and down
To the second piston 34 being assemblied in intermediate bin, also rotation stop is connected with the driving wheel 35 positioned at bottom, driving wheel 35 on leading screw 33
Wheel side expose from intermediate bin front and rear sides, and the inflation that can be triggered by second piston 34 is provided with the inwall of intermediate bin
Contact.Intermediate bin has two, two intermediate bins between left and right every structure identical the first intermediate bin 31 and the second intermediate bin 32, the
One intermediate bin 31 is located at the left of the second intermediate bin 32.Inflation contact has two, and two inflation contacts are respectively to be located in the middle of first
The first inflation contact 36 in storehouse 31 and the second inflation contact 37 in the second intermediate bin 32.
The finished product track 8 of closed curve-shaped is provided between intermediate bin and finished bin 10 and is walked thereon along finished product track 8
Finished product dolly 9, finished product dolly 9 is electric self-propelled, and finished product track 8 and raw material track 5 are on symmetrical before and after intermediate bin,
In the same direction, and finished product dolly 9 and raw material dolly 4 each can expose with driving wheel 35 for the steering of finished product dolly 9 and raw material dolly 4
Partial frictional coordinates.The steering of raw material dolly 4 is counterclockwise.
Provided with the 3rd piston 101 that can slide up and down in finished bin 10, the top of the 3rd piston 101 is connected with for pushing down on
It is connected with 3rd return spring 102 of dynamic 3rd piston 101, the plunger shaft of the lower section of the 3rd piston 101 for controlling exhaust
Second row air valve 103 and the charging valve 104 for controlling air inlet, charging valve 104 are magnetic valve, and in charging valve
The second source of the gas 105 is connected with 104 import, and the automatically controlled end of charging valve 104 connects inflation by second controller 106
Contact, after the triggering of inflation contact, the control charging valve 104 of second controller 106 is opened and inflated into finished bin 10.
First controller 25, which has, is used for what is counted when first exhaust contact 26 and second exhaust contact 27 are successively triggered
Counting unit and the computing unit for setting delay length according to the counting of counting unit.Second controller 106, which has, to be used for
The counting unit that counts and for according to counting unit when the first inflation contact 36 and second inflation contact 37 is successively triggered
Count the computing unit of setting delay length.
The top of raw material cabin 2, intermediate bin and finished bin 10 is provided with for the limit position above the arrival of corresponding piston
When the inductor that the triggers and alarm being connected electrically on inductor.Alarm is to be located at raw material cabin 2 or intermediate bin or finished bin
The warning lamp of 10 tops.
Be additionally provided with sand table 1 for control the first source of the gas 23 aeration speed the first control handle 111, for controlling
Second control handle 112 of the aeration speed of the second source of the gas 105 and for the 3rd control of the aperture for controlling second row air valve 103
Knob 113.
Raw material track 5 and finished product track 8 are the track of waist-hole type.
The working method of experimental provision is in the present embodiment:The supplement of the analog raw material in the way of inflation of raw material cabin 2, with original
The mode of the triggering exhaust of trolley 4 contact opens the output of first row air valve 24 and analog raw material, is rubbed and driven with raw material dolly 4
The replenishing to intermediate bin of mode analog raw material dolly 4 of the driving wheel 35 of intermediate bin, driving wheel 35 is driven with the friction of finished product dolly 9
Counter-rotational mode simulates the output of finished product in intermediate bin, the control in the way of the triggering inflation of second piston in intermediate bin 34 contact
The opening of charging valve 104 processed and simulate the deposit finished product to finished bin 10, while being held with the second row air valve 103 of finished bin 10
The mode of continuous exhaust simulates the lasting output of finished product, in these analog informations, can be by valve opening, the output speed of source of the gas
The control of the speed of degree and dolly, realizes the simulation to real-time logisticses information, thus the experimental provision has degree of verisimilitude height, experiment
The good advantage of effect.
Finally it should be noted that:Above example is only to illustrate the technical solution of the utility model, rather than its limitations;
Although the utility model is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:
It can still modify to the technical scheme described in foregoing embodiments, or which part technical characteristic is carried out etc.
With replacement;And these modifications or replacement, the essence of appropriate technical solution is departed from each embodiment technology of the utility model
The spirit and scope of scheme.
Claims (7)
1. Factory Logistics analogue experiment installation, including sand table, it is characterised in that be disposed with from front to back on the surface of sand table
Provided with the first piston that can slide up and down in raw material cabin, intermediate bin and finished bin, raw material cabin, being connected with above first piston is used for
Push down on be connected with the plunger shaft below the first return spring of first piston, first piston for persistently supply first
Source of the gas and the first row air valve for controlling exhaust, first row air valve is magnetic valve, and the automatically controlled end of first row air valve is sequentially connected
There are the first controller and exhaust contact, on triggering, delay switch control first row air valve is beaten in the first controller for exhaust contact
Open and raw material cabin is vented;
The raw material track of closed curve-shaped is provided between raw material cabin and intermediate bin and raw material thereon along raw material track travel is small
Car, raw material dolly is electric self-propelled, and is vented contact on raw material track;
Axis in intermediate bin around extension up and down, which is rotatably equipped with worm drive on leading screw, leading screw and is connected with to be oriented to up and down, to be assemblied in
Also rotation stop is connected with the driving wheel positioned at bottom on second piston in intermediate bin, leading screw, and the wheel side of driving wheel is before intermediate bin
Both sides are exposed afterwards, and the inflation contact that can be triggered by second piston is provided with the inwall of intermediate bin;
The finished product track of closed curve-shaped is provided between intermediate bin and finished bin and finished product thereon along finished product track travel is small
Car, finished product dolly is electric self-propelled, and finished product track and raw material track are on symmetrical before and after intermediate bin, finished product dolly and original
The steering of trolley is in the same direction, and the partial frictional that finished product dolly and raw material dolly each can expose with driving wheel coordinates;
Provided with the 3rd piston that can slide up and down in finished bin, it is connected with above the 3rd piston for pushing down on the 3rd piston
Be connected with plunger shaft below 3rd return spring, the 3rd piston for control exhaust second row air valve and for control into
The charging valve of gas, charging valve is magnetic valve, and is connected with the import of charging valve the second source of the gas, and charge valve
The automatically controlled end of door passes through second controller connection inflation contact, after the triggering of inflation contact, second controller control charging valve
Open and inflated into finished bin.
2. Factory Logistics analogue experiment installation according to claim 1, it is characterised in that intermediate bin has two, in the middle of two
Storehouse between left and right every the first intermediate bin and the second intermediate bin, the first intermediate bin be located at the second intermediate bin left;
The steering of raw material dolly is counterclockwise;
Raw material track has the first orbital segment of closing corresponding with the first intermediate bin, and the left side of the first orbital segment is provided with head and the tail two
Hold the Auxiliary Track section connected with the first orbital segment, the right side of the first orbital segment provided with head and the tail two ends with the first orbital segment phase
The second orbital segment connect, the second orbital segment is corresponding with the second intermediate bin, and in the initiating terminal and the first track of Auxiliary Track section
Section connecting position is provided with the first switch mechanism, and the initiating terminal and the first orbital segment connecting position of the second orbital segment are provided with the
Two switch mechanisms, the first switch mechanism and the second switch mechanism in the firing state draw raw material dolly from the first orbital segment
Export comes;
Exhaust contact has two, and two exhaust contacts are respectively first exhaust contact and second exhaust contact, first exhaust contact position
Position between the initiating terminal of clearing end and the Auxiliary Track section of the second orbital segment on the first orbital segment, second exhaust contact
In Auxiliary Track section, and first exhaust contact is connected in the first switch mechanism and the second switch mechanism by reversing switch
At least one, reversing switch have the first switch mechanism and the second switch mechanism simultaneously with first exhaust contacting first
State, reversing switch also has the second shape for disconnecting the first switch mechanism and the second switch mechanism with first exhaust contact simultaneously
State;
First controller have the counting unit that is used for counting when first exhaust contact and second exhaust contact are successively triggered and
Computing unit for setting delay length according to the counting of counting unit.
3. Factory Logistics analogue experiment installation according to claim 2, it is characterised in that inflation contact has two, and two fill
Gas contact is respectively the first inflation contact and the second inflation contact in the second intermediate bin being located in the first intermediate bin;
Second controller have be used for when the first inflation contact and the second inflation contact are successively triggered the counting unit that counts and
Computing unit for setting delay length according to the counting of counting unit.
4. the Factory Logistics analogue experiment installation according to claim 1 or 2 or 3, it is characterised in that raw material cabin, intermediate bin
Be provided with the top of finished bin for the inductor that triggers and being connected electrically in during limit position above the arrival of corresponding piston
Alarm on inductor.
5. Factory Logistics analogue experiment installation according to claim 4, it is characterised in that alarm be positioned at raw material cabin or
Warning lamp above intermediate bin or finished bin.
6. the Factory Logistics analogue experiment installation according to claim 1 or 2 or 3, it is characterised in that be additionally provided with sand table
Second control of the first control handle for the aeration speed of the first source of the gas of control, the aeration speed for controlling the second source of the gas
Knob and for the 3rd control handle of the aperture for controlling second row air valve.
7. the Factory Logistics analogue experiment installation according to claim 1 or 2 or 3, it is characterised in that raw material track and finished product
Track is the track of waist-hole type.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720211576.1U CN206574384U (en) | 2017-03-07 | 2017-03-07 | Factory Logistics analogue experiment installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720211576.1U CN206574384U (en) | 2017-03-07 | 2017-03-07 | Factory Logistics analogue experiment installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206574384U true CN206574384U (en) | 2017-10-20 |
Family
ID=60057491
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720211576.1U Expired - Fee Related CN206574384U (en) | 2017-03-07 | 2017-03-07 | Factory Logistics analogue experiment installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206574384U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106652753A (en) * | 2017-03-07 | 2017-05-10 | 郑州大学 | Factory logistics simulation experimental apparatus |
-
2017
- 2017-03-07 CN CN201720211576.1U patent/CN206574384U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106652753A (en) * | 2017-03-07 | 2017-05-10 | 郑州大学 | Factory logistics simulation experimental apparatus |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3169733A (en) | Battery charging system for vehicles | |
CN206574384U (en) | Factory Logistics analogue experiment installation | |
CN106192708B (en) | A kind of highway repairs quick pressuring flat device with small crack | |
CN209597677U (en) | A kind of crossed belt type goods sorting system | |
CN110369301A (en) | Goods sorting system and method for sorting | |
CN211035109U (en) | Platform attitude adjusting and controlling device | |
CN205809696U (en) | Cross-country heavy duty AGV | |
CN103615130B (en) | Dynamic rotary type intelligent carrier | |
CN106652753A (en) | Factory logistics simulation experimental apparatus | |
CN204095866U (en) | A kind of intelligent shopping guide boosted vehicle | |
CN206405072U (en) | One kind is based on pilotless automobile camera wiping arrangement | |
CN109094445A (en) | A kind of item dispenser vehicle | |
CN203545658U (en) | Double-row-in and double-row-out negative pressure type nail polish filling machine | |
CN103273641B (en) | Bottle blank conveying device of bottle blowing machine | |
CN209581264U (en) | A kind of item dispenser vehicle | |
CN206219156U (en) | Las er-guidance order-picking trucks | |
CN206590005U (en) | Automatical pilot transportation vehicle | |
CN204472787U (en) | Guideway vehicle platform order apparatus for getting on/down | |
CN209210375U (en) | One kind is with function fuel charger of selling goods | |
CN108382441A (en) | Logistics handling device | |
CN107628090A (en) | A kind of automatic unloading stroller of logistics transportation | |
CN105730417A (en) | Multifunctional lifting positioning device for repairing vehicle | |
CN207511303U (en) | Electric business sorting plant | |
CN203545102U (en) | Control device for tire sequential distribution | |
CN105417199B (en) | A kind of automatic skeleton loader |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |