Prior art keywords
wall
slabstone
dam body
stone
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620705499.0U
Other languages
Chinese (zh)
Inventor
王泽飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620705499.0U priority Critical patent/CN206554324U/en
Application granted granted Critical
Publication of CN206554324U publication Critical patent/CN206554324U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Finishing Walls (AREA)

Abstract

The structure of wall, dam body, including the T-shaped component that stone material makes are assembled into the utility model discloses a kind of Stone brick component for realizing comprehensive fixation, tongue and groove is provided with the middle slabstone side of T-shaped component, the two ends slabstone of T-shaped component is provided with tongue and groove;The two ends slabstone male and female feather joint of the side tongue and groove of slabstone respectively with other T-shaped component in the middle of T-shaped component, it is continuous assembled, constitute wall, dam body, the tongue and groove end of the two ends slabstone of the T-shaped component and middle slabstone are respectively provided with spacing hole, adjacent T-shaped component two ends slabstone is corresponding with the spacing groove location of middle slabstone, wherein pre-installing limiting plate in the stopper slot that Open Side Down.T-shaped component of the present utility model, can the machine-shaping in factory, then carried out in building site assembled, reduce construction process, small is influenceed on site environment, it is simple in construction, stably, firmly, and save material.

Description

Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body
Technical field
The utility model is related to a kind of Stone brick component for realizing comprehensive fixation and is assembled into the structure of wall, dam body, category In masonry work technical field.
Background technology
In the prior art, the build of the wall, dam body of stone material be typically using processing of stone into stone, then with cement, Stone is piled into wall, dam body by mortar.It has the disadvantage that feed consumption is more, and load weight, the construction period is long, and cost is high, in the prior art Have and obtained to each other by male and female feather joint using T-shaped stone material, but the cavity or dam body of structure formation can only ensure individual event Connection is uncertain, i.e., can only realize and be fixed with the position in tongue and groove vertical direction, and a nothing is fixed in the position put identical with tongue and groove Method realizes that during the wall or dam body that are made in the later stage, full method position is fixed if can not realize, made wall or dam Body security cannot ensure very well.
The content of the invention
The purpose of this utility model is:Comprehensive position is consolidated between providing the stone component of a kind of made wall or dam body Fixed and simple in construction, stably, short Stone brick component of easy to operate, engineering time is assembled into the structure of wall, dam body, with gram Take the deficiencies in the prior art.
What technical solutions of the utility model were formed by:
A kind of Stone brick component for realizing comprehensive fixation of the present utility model is assembled into the structure of wall, dam body, including The T-shaped component that stone material makes, tongue and groove is provided with the middle slabstone side of T-shaped component, and the two ends slabstone of T-shaped component is provided with male and female Tenon;The two ends slabstone male and female feather joint of the side tongue and groove of slabstone respectively with other T-shaped component in the middle of T-shaped component, continuous assembled, group Into wall, dam body, the tongue and groove end of the two ends slabstone of the T-shaped component and middle slabstone are respectively provided with spacing hole, adjacent T-shaped component two Hold slabstone corresponding with the spacing groove location of middle slabstone, wherein pre-installing limiting plate in the stopper slot that Open Side Down.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, stone component it Between form cavity, the stone column or metallic support of reinforcing are provided with cavity.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, provided with guarantor in cavity Adiabator.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, the wall, dam Body is provided with water injector.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, the wall, dam The stone component of body is provided with embossment, mural painting or word, to preserve for a long time.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, the insulation material For foam concrete, haydite, polystyrene, polyurethane or phenolic foam body.
The foregoing Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, in, the limiting plate Base cross section is arc structure.
The stone material that the utility model is used, is low energy building product generally acknowledged in the world, the T-shaped component and a type of design Component, can the machine-shaping in factory, then carried out in building site assembled, reduce construction process, no dust, sewage, Noise, solid waste, influence small to site environment, have accomplished the form of construction work of environmental protection.Stone component by tongue and groove with It is simple in construction, stably, firmly and glue is attached, and material is saved, deadweight is alleviated, cost is reduced, shortened The site operation duration.Wall of the present utility model, dam body, can on stone component direct engraving embossment, mural painting or word, collection Structural ornament is integrated, and revolutionizes traditional metope wet combining or dry-hang stone decorates the multiple construction method of panel, contract significantly Short construction period.Wall, the dam body constituted using stone component, fire prevention, hydrophobic, weather resisteant are good, simple generous, attractive in appearance, also The visual effect and artistic value of building can be improved by polishing, scuoptor processing.Cavity in stone component Structure, can also play the effect of insulation, energy-conservation, emission reduction, while by setting stopper slot and limiting plate, realizing adjacent T-shaped The comprehensive fixation of position between component, compared with the existing technology, the utility model has simple in construction, firm, overall cost is low, Construction period is short, the advantages of good appearance is generous.
Brief description of the drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is the structural representation of T-shaped component in the utility model.
Embodiment
Embodiment of the present utility model:A kind of Stone brick component for realizing comprehensive fixation is assembled into the knot of wall, dam body Structure, as shown in figure 1 and 2, construction include the T-shaped component of stone material making, and tongue and groove, T are provided with the middle slabstone side of T-shaped component The two ends slabstone of type component is provided with tongue and groove;The two ends of the side tongue and groove of slabstone respectively with other T-shaped component in the middle of T-shaped component Slabstone male and female feather joint, continuous assembled, composition wall, dam body, the tongue and groove end of the two ends slabstone of the T-shaped component and middle slabstone Spacing hole is respectively provided with, adjacent T-shaped component two ends slabstone is corresponding with the spacing groove location of middle slabstone, wherein in the limit that Open Side Down Prepackage limiting plate in the groove of position.
Wherein formed in cavity, cavity and be provided with the stone column or metallic support of reinforcing, the cavity between stone component Provided with insulation material, the wall, dam body be provided with water injector, wall, dam body stone component provided with embossment, mural painting or Word, to preserve for a long time, the insulation material is foam concrete, haydite, polystyrene, polyurethane or phenolic foam body, institute The base cross section for stating limiting plate is arc structure.
During specific making, as shown in figure 1 and 2, T-shaped component 1 is made using stone material, stone material can use existing various Stone material.Wherein, tongue and groove 3 is made in the middle slabstone side of T-shaped component 1, public affairs is also produced on the two ends slabstone of T-shaped component 1 During 3 practical operation of female tenon, middle slabstone is made as male tenon, then two ends slabstone is made as female tenon, and vice versa, while in two ends stone Stopper slot 2 is set at the male tenon or female tenon of plate, set on middle slabstone with setting the position of stopper slot 2 to position at male tenon or female tenon Stopper slot 2, and base cross section for arc-shaped the pre-placing of limiting plate 5 stopper slot that Open Side Down 2 in, the limiting plate 5 is grown Degree is more than the depth of stopper slot 2 of opening upwards, and less than the depth of stopper slot 2 that Open Side Down, T-shaped component 1 can add in factory Work, then transports to scene and carries out assembly, when assembled, first head into limiting plate in the stopper slot that Open Side Down, then by adjacent T Type component is inserted along correspondence tongue and groove position, now unclamps limiting plate and the following of the limiting plate is moved on T-shaped component, directly The stopper slot fallen into the limiting plate on adjacent T-shaped component, then complete wall or dam stabilization after assembled and assembly, adjacent T-shaped component realize comprehensive fixation.The structure of tongue and groove 3 can make the male and female tenon structure such as triangularity, circular arc, stairstepping Shape, T-shaped component 1 can also use variety classes, the stone material of color, realize the different outward appearance of inner-outer wall.
During build, the two ends slabstone by the side tongue and groove 3 of the middle slabstone of T-shaped component 1 respectively with other T-shaped component at the scene Male and female feather joint, so alternately continuous assembled, composition wall, dam body.It is continuous assembled in a manner described, composition wall, dam body.Adopt With the wall of all T-shaped components 1, structure is more firm.
For stone component, its height is preferably within 200~3000 millimeters, 20~600 millimeters of thickness of slab.Convenient processing, It can be connected between transport, every layer of component above and below by binding agent.Can also be according to prior art, in stone material internal layer glue The intensity and shock resistance of stick and fibre-reinforced components.
Wall, the dam body constructed, cavity 4 can be formed between T-shaped component 1, and the stone column of reinforcing is installed in cavity Or metallic support 6,, can be without installing for the wall less than 10 square metres according to the metope size of design, 10~20 squares The wall of rice, installs stone column 5, and the wall more than 20 square metres installs metallic support 6.
Wall, the dam body of heat insulating effect are needed, insulation material 7 can be filled in cavity 4, insulation material is using existing Various insulating products, such as foam concrete, haydite, polystyrene, polyurethane or phenolic aldehyde.
Water injector can also be installed on wall, dam body, due to stone component anti-corrosion, hydrophobic, can directly be sprayed, water drenching Cooled.
Direct engraving goes out embossment, mural painting or word on wall, the stone component of dam body, to preserve for a long time.
Stone component can also select different cultivars, quality, the processing of stone of color, realize that inner-outer wall, dam body are different Outward appearance.

Claims (7)

1. a kind of Stone brick component for realizing comprehensive fixation is assembled into the structure of wall, dam body, including the T-shaped structure that stone material makes Part, it is characterised in that:Tongue and groove is provided with the middle slabstone side of T-shaped component, the two ends slabstone of T-shaped component is provided with tongue and groove;T The two ends slabstone male and female feather joint of the side tongue and groove of slabstone respectively with other T-shaped component in the middle of type component, it is continuous assembled, constitute wall Body, dam body, the tongue and groove end of the two ends slabstone of the T-shaped component and middle slabstone are respectively provided with spacing hole, adjacent T-shaped component two ends stone Plate is corresponding with the spacing groove location of middle slabstone, wherein pre-installing limiting plate in the stopper slot that Open Side Down.
2. the Stone brick component according to claim 1 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:Formed between stone component in cavity, cavity and be provided with the stone column or metallic support of reinforcing.
3. the Stone brick component according to claim 2 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:Insulation material is provided with cavity.
4. the Stone brick component according to claim 3 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:The insulation material is foam concrete, haydite, polystyrene, polyurethane or phenolic foam body.
5. the Stone brick component according to claim 1 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:The wall, dam body are provided with water injector.
6. the Stone brick component according to claim 1 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:The wall, the stone component of dam body are provided with embossment, mural painting or word, to preserve for a long time.
7. the Stone brick component according to claim 1 for realizing comprehensive fixation is assembled into the structure of wall, dam body, it is special Levy and be:The base cross section of the limiting plate is arc structure.
CN201620705499.0U 2016-07-06 2016-07-06 Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body Expired - Fee Related CN206554324U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620705499.0U CN206554324U (en) 2016-07-06 2016-07-06 Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620705499.0U CN206554324U (en) 2016-07-06 2016-07-06 Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body

Publications (1)

Publication Number Publication Date
CN206554324U true CN206554324U (en) 2017-10-13

Family

ID=60368758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620705499.0U Expired - Fee Related CN206554324U (en) 2016-07-06 2016-07-06 Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body

Country Status (1)

Country Link
CN (1) CN206554324U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI669435B (en) * 2018-02-23 2019-08-21 沈德祿 Insulating brick
CN111794894A (en) * 2020-07-24 2020-10-20 孔令西 Fast-assembling tank type river power generation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI669435B (en) * 2018-02-23 2019-08-21 沈德祿 Insulating brick
CN111794894A (en) * 2020-07-24 2020-10-20 孔令西 Fast-assembling tank type river power generation

Similar Documents

Publication Publication Date Title
CN206554324U (en) Realize that the Stone brick component of comprehensive fixation is assembled into the structure of wall, dam body
CN203257040U (en) Building board dry-hanging method structure
CN205329965U (en) Decorative plate
CN204551763U (en) Assembled architecture bottom waterproof device
CN203921758U (en) A kind of coloured glaze stone rubbish container
CN203795695U (en) Trapezoidal grout-free interlocking brick
CN209194809U (en) A kind of one fossilized wood sparkling lattice composite exterior wall
CN202483123U (en) Composite decorative board with built-in insert
CN201843294U (en) Tile with low falling possibility
CN202969686U (en) Fire-proof clay brick
CN205088851U (en) Plug -in type partition block
CN206144019U (en) Frameless frame industrialization wall body can be built fast to light
CN206468186U (en) A kind of GRC window casing board lines of green assembled architecture
CN205025039U (en) Modular exterior wall cladding
CN201704847U (en) Concrete arc-shaped building block
CN204040297U (en) Ground, building wall and architectural decoration face ornamental blocks
CN201512875U (en) Structure using stone bricks to assemble wall body and dam body
CN204370665U (en) A kind of light-weight thermal-insulating and sound-insulating brick
CN210827930U (en) Hui style building heat preservation wallboard structure
CN202577752U (en) Novel wall slab for light steel nesting integrated house
CN101660329A (en) Method and structure of wall body or dam body assembled by stone and brick members
CN210086708U (en) Composite integrated board for heat preservation and decoration of metal facing of outer wall
CN203393900U (en) Light foam concrete hanging beam
CN210342280U (en) Expansion joint structure of parapet on window side
CN202324317U (en) Brick used for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171013

Termination date: 20200706