CN206505440U - Test assignment dispatching system - Google Patents
Test assignment dispatching system Download PDFInfo
- Publication number
- CN206505440U CN206505440U CN201620954800.1U CN201620954800U CN206505440U CN 206505440 U CN206505440 U CN 206505440U CN 201620954800 U CN201620954800 U CN 201620954800U CN 206505440 U CN206505440 U CN 206505440U
- Authority
- CN
- China
- Prior art keywords
- information
- test
- server
- unit
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The test assignment dispatching system that the utility model is provided, including information collecting device, server, transmitting device and for receiving send the terminal device of work information, described information harvester includes being used for the personnel information acquisition module of collecting test personal information and the equipment information collection module for gathering exemplar information and facility information;Test assignment dispatching system in the utility model, pass through information collecting device collecting test personal information, exemplar information and facility information, and carry out sending work by server, experimental duties are assigned and carry out standardized management, establish digital experiment digitization management platform, it ensure that the security of experimental data, authenticity, integrality, uniformity and trackability, realize the unified management of experimental data, the task of improving sends work efficiency rate, improve the total quality of experiment, reduce repetition experiment, greatly reduce the experiment development cost of enterprise, realize restrictive scheduling.
Description
Technical field
The utility model is related to the communications field, more particularly to a kind of test assignment dispatching system.
Background technology
Any product is required for doing substantial amounts of experiment during research and development, and can be produced in experimentation a large amount of
Data, but come the process and data of management misconduct without special technological means for a long time, and the management for passing through science
Method carries out assigned tasks, and this brings huge challenge to management.Lack effective experimental data management in the prior art
The support of system, the work related to experiment also rests on manual work state, and data statistics is difficult, and it is difficult real-time to make manager
Know which experiment currently done, how is the state that experiment is carried out, and which experimental project who take part in, and experimental duties are such as
What specific assignment, it is impossible to realize the multistage project management of test center, project process module solidification management, it is impossible to by test equipment
Tester is organically associated with the auxiliary material information used in test process, and is unable to the maintenance criterion testing time, refer to
Lead understand when working out plan daily workload whether saturation, it is impossible to exact p-value center, which is paid special attention to, tests real per sub-project
Existing standard time, personnel account for the standard time, it is impossible to tester can be carried out into multinomial test experiments, tester marks daily simultaneously
The quasi- working time connects with daily order ticket and is managed.
Experiment have mostly it is very strong professional, according to the difference of product, professional difference, the regulatory requirement of experimental data
There is very big difference with application, it is necessary to which the professional and diversity for experiment carries out the management of differentiation.Experimental data is existing
Structural data, also there is unstructured data, and with the difference of collecting device, the form of unstructured data is also thousand poor
Ten thousand are not, and it is a problem to manage these data, and the data that experimentation is produced include initial data, the pretreatment number that equipment is gathered
All it is very important data according to, analysis report etc., because the support without experimental data management system, these data often dissipate
It is placed on experimenter's personal computer, it is easy to lose, its main cause is that data are not left concentratedly and managed, and makes custodian
Member, designer and experimenter can not inquire about experimental data, laboratory report, also cause the Experiment Result before reusing to become very
Difficulty, is more unfavorable for the assignment of experiment test task, causes experimentation inefficiency, and effect is not good, have impact on overall reality
The progress and result tested, therefore, need a kind of new technological means badly, to solve the above problems.
Utility model content
In view of this, the utility model provides a kind of test assignment dispatching system, to solve the above problems.
A kind of test assignment dispatching system that the utility model is provided, including information collecting device, server, transmitting device
With the terminal device that work information is sent for receiving, described information harvester includes believing for the personnel of collecting test personal information
Cease acquisition module and the equipment information collection module for gathering exemplar information and facility information;
The output end of described information harvester is connected by the input of transmitting device and server, the server with
Terminal device is connected.
Further, the personnel information acquisition module includes fingerprint collecting unit, fingerprint identification unit and fingerprint attendance list
Member, the output end of the fingerprint collecting unit and the input of fingerprint identification unit are connected, the output of the fingerprint identification unit
End is connected with the input of fingerprint attendance unit.
Further, the equipment information collection module include being arranged at being used in exemplar and/or equipment represent exemplar and/
Or the electronic tag and reading unit for recognizing the electronic tag of the identity information of equipment, the output of the reading unit
End is connected by transmitting device with server.
Further, the terminal device is provided with test result logging modle, and the server is provided with test result and sentenced
Other module and automatic job distribution module, the test result discrimination module is connected with automatic job distribution module, for according to test result
Work is sent in progress.
Further, the transmitting device is wireless transport module, and the wireless transport module includes GPRS module, 3G module
Or 4G modules.
Further, the terminal device is mobile terminal, and the mobile terminal includes micro-control unit, input block and shown
Show unit, the input block and display unit are connected with micro-control unit respectively, it is described to be connected for control unit with server.
Further, the terminal device also includes entering when finally completing the time more than the project plan for the test assignment time
The alarm unit of row alarm, the alarm unit is connected with for control unit.
Further, the server also includes the authentication server for being used to carry out rights management.
The beneficial effects of the utility model:Test assignment dispatching system in the utility model, passes through information collecting device
Collecting test personal information, exemplar information and facility information, and work is sent by server progress, experimental duties are assigned into professional etiquette
Generalized is managed, and establishes digital experiment digitization management platform, it is ensured that the security of experimental data, authenticity, integrality,
Uniformity and trackability, realize the unified management of experimental data, and the task of improving sends work efficiency rate, improves the entirety of experiment
Quality, reduces repetition experiment, greatly reduces the experiment development cost of enterprise, realize restrictive scheduling.
Brief description of the drawings
The utility model is further described with reference to the accompanying drawings and examples:
Fig. 1 is principle schematic of the present utility model.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples:Fig. 1 is that principle of the present utility model is shown
It is intended to.
As shown in figure 1, the test assignment dispatching system in the present embodiment, including information collecting device, server, transmission dress
The terminal device of work information is put and is sent for receiving, described information harvester includes the personnel for collecting test personal information
Information acquisition module and the equipment information collection module for gathering exemplar information and facility information;Described information harvester
Output end is connected by the input of transmitting device and server, and the server is connected with terminal device.
In the present embodiment, experimental project planning management and manufacturing process management have been carried out effective to conjunction, establishment item
During mesh plan can clear wash rice equipment service condition, personal information, by information collecting device, system server according to the project plan,
The list that assigns a task of facility information, personal information, exemplar information, auxiliary material information on time, passes through each tester of terminal device
Experiment test task without any confusion can be carried out according to job order, overall experimentation is finally completed.By in the application
Method can assign rational task in the rational time, sensible substantial amounts of test experiments summarize modification determine the standard time, it is complete
Kind experiment flow, formation test database, knowledge base, system write laboratory report automatically.
In the present embodiment, personnel information acquisition module includes fingerprint collecting unit, fingerprint identification unit and fingerprint attendance
The input of unit, the output end of the fingerprint collecting unit and fingerprint identification unit is connected, the fingerprint identification unit it is defeated
Go out end to be connected with the input of fingerprint attendance unit, personnel information acquisition module can use fingerprint attendance machine, by fingerprint attendance
Machine is connected with each other with server, obtains the information of tester, and tester's information includes identity information, finger print information and arranged an order according to class and grade
Information, passes through the fingerprint attendance situation and the workload of experiment of tester, dynamic assignment experiment test task;The equipment letter
Breath includes whether device identifying information, equipment account for inspection information and plant maintenance information.The identity information of tester can be to institute
Have employee carry out unified organizational system employee's coding, by system typing employee coding, employee's title, department, educational background, enter factory's date,
The information such as identity card, home address, employee's fingerprint is gathered by attendance record terminal equipment, stores attendance record terminal, and administrative staff can be with
One section of date situation on duty (day shift or night shift) of employee is arranged according to test job amount is unified;Pass through fingerprint before employee's working daily
The daily reality of work situation of attendance recorder automatic data collection employee, attendance recorder and test center's Management System Data storehouse are direct-connected, and employee is every
When making a call to a fingerprint, automatically write in test center's Management System Data storehouse.By above method, employee is actual examines for statistics daily
Diligent situation, is that personnel's dimension beam provides foundation when project task assigns offer.
In the present embodiment, equipment information collection module includes being arranged at being used in exemplar and/or equipment and represents exemplar
And/or the electronic tag and reading unit for recognizing the electronic tag of the identity information of equipment, the reading unit
Output end is connected by transmitting device with server, and by being encoded accordingly to equipment, facility information enters factory including equipment
Examine, paste bar code, whether bar code content accounts for inspection comprising the information such as equipment serial number, model, purchase date, producer, and equipment,
Plant maintenance information includes whether to exceed defects liability period, verifies the information such as whether pass through, will be above-mentioned by electronic tag and read write line
All information unifications register storage in test and management system.
In the present embodiment, terminal device is provided with test result logging modle, and the server is provided with test result
Discrimination module and automatic job distribution module, test result discrimination module and automatic job distribution module can use CPU, FPGA or other can
To realize the chip of above-mentioned functions, test result logging modle can be inputted by input block, or by other means
Recorded, by the unified preservation of all test results into test record module, be easy to the whole process in the future to experiment to enter
Row control, test result discrimination module is connected with automatic job distribution module, and for being carried out sending work according to test result, transmitting device is
Wireless transport module, the wireless transport module includes GPRS module, 3G module or 4G modules, and terminal device is mobile terminal,
The mobile terminal includes micro-control unit, input block and display unit, and input block can use single input equipment,
Such as keyboard, it would however also be possible to employ the touch-screen for being combined display module with logging modle, the input block and display unit
It is connected respectively with micro-control unit, the micro-control unit is connected with server, when terminal device also includes being used for test assignment
Between finally complete the alarm unit alarmed during the time more than the project plan, the alarm unit is connected with for control unit
Connect, in the present embodiment, server is simulated resolving by test assignment and identified project the test deadline, it is preferable that test is appointed
Business simulation resolving can include order resolving and inverted order is resolved, and the order, which is resolved, to be included test assignment being divided into some height
Project, statistics can concurrent testing sub-project, the initial time of test assignment is determined, during according to the standard testing of every sub-project
Between and the full test duration that allows daily, obtain the deadline of test assignment;The inverted order, which is resolved, to be included appointing test
Business is divided into some sub-projects, statistics can concurrent testing sub-project, the deadline of test assignment is determined, according to every height
The testing time of project and the full test duration allowed daily, it is counter to push away the initial time for obtaining test assignment.For example, it is assumed that
Totally 7 test sub-projects, sub-project 2, sub-project 3 can concurrent testing, other sub-projects can only test serially, daily test job
Time is 7 hours, total to test 14 hours, it is necessary to which 2 days survey.Order solution process includes:Such as Start Date is 2016
The morning 8 on June 1,:00 starts, and the test of sub-project 1 completes to be 11 points (tests 3 hours), and sub-project 2, sub-project 3 are parallel, can
Simultaneously since 11 points, the maximum testing time is the beginning testDate of sub-project 4, and Ruo Dangkai arranges sub-project 4 then to surpass
7 hours are spent, needs to start for second day;The morning 8 on June 2nd, second day:00 beginning sub-project 4 is tested, 11 points of end time;
11 points of 5 time started of sub-project, 12 points of end time;The time started 13 of sub-project 6:00 (nooning 1 hour), 16:00 knot
Beam;The time started 16 of sub-project 7:00, end time 17:00;Resolving of seizing back confiscated property includes:June 2 2016 last day is before leaving offices
Complete sub-project 7 to test, retrodict sub-project 6, sub-project 5, sub-project 4, sub-project 3, sub-project 1 and start over the time.At this
In embodiment, free time short equipment is added up according to facility information prioritizing selection history and tested, while by tester
Sort by priority, according to test assignment according to priority sequential selection test man, if exemplar has been put in storage, work is sent in progress, if sample
Part is not put in storage, then stops to carry out sending work, and sends alarm, and such as task delegation 1, commission 2 respectively need 3 hour testing time, by item
Mesh task priority resolves principle, it is assumed that first resolve order ticket 1:
Committal charge 1 resolves principle:1. available devices A B C, judge device A B C whether can use, if available, take and set
(the equipment component daily working time is 7 hours to the standby accumulative idle how many equipment of history, only arranges day shift test;Equipment component
Work 24 hours, can arrange night shift to test), device A B C it is idle be all 7 hours, appoint and take a device A to meet test request;
2. tester A B C D E F can be used, the same day attendance information of personnel are judged, wherein personnel E F ask for leave, desired is met
There are tester A B C D, it is 7 hours to take A B C D each personnel's free time, according to priority takes personnel A B to test;3. judge
Whether exemplar is put in storage, if being put in storage the condition of satisfaction, is not put in storage, and this order ticket is invalid, it is impossible to which system automatic job distribution, system sends report
It is alert, point out related personnel processing, and point out that the plan of extension can be caused.
Equipment, personnel, exemplar all meet condition, the automatic job distribution of committal charge 1, tester A B respectively account for 3 hours, device A
Consume 3 hours.
Committal charge 2 resolves principle:1. available devices A B C, judge device A B C whether can use, if available, take and set
(the equipment component daily working time is 7 hours to the standby accumulative idle how many equipment of history, only arranges day shift test;Equipment component
Work 24 hours, can arrange night shift to test), device A (idle 4 hours) B (idle 4 hours) C (idle 7 hours), appoint to take and set
Standby B meets test request;2. tester A B C D E F can be used, the same day attendance information of personnel, wherein personnel E F is judged
Ask for leave, meet desired only tester A (idle 4 hours) B (idle 4 hours) C (idle 7 hours) D (free time 7 is small
When), according to priority take personnel C to test;3. judge whether exemplar is put in storage, if being put in storage the condition of satisfaction, be not put in storage, this order ticket without
Effect, it is impossible to system automatic job distribution, system sends alarm, points out related personnel processing, and points out that the plan of extension can be caused, and also may be used
Judged with will determine that exemplar is placed on the first step.
Equipment, personnel, exemplar all meet condition, and the automatic job distribution of committal charge 2, tester C is accounted for 3 hours, and equipment B consumes
3 hours.
Other committal charges the like, tester no more than works as no more than testing standard time on the same day, equipment
It testing time, exemplar must be put in storage as most basic principle, otherwise system alarm prompting need manual intervention processing (or overtime work,
Or delay), one-state according to the urgency level of the project plan or is promptly inserted, test assignment priority is changed, if during test assignment
Between finally complete the time more than the project plan, then automatic alarm, the above method simply to illustrate that the present embodiment and enumerate one
Kind preferred mode, it is also not improvement to its method that the utility model is claimed, plays specific structure and its connection
Relation is only core content of the present utility model.
In the present embodiment, in addition to equipment point inspection is carried out, spot-checking plan table is obtained according to an overhaul period automatically, and lead to
Mobile terminal is crossed to check staff's progress spot-checking plan prompting, the threshold value pre-set to the point inspection item time basis that can quantify is certainly
It is dynamic to judge whether equipment is qualified;Use artificial judgment whether qualified not energetic point inspection item time, if item is examined in equipment arbitrfary point
It is secondary unqualified, then trigger maintenance flow and freeze equipment, until it meets standard, according to work generation test order ticket is sent, survey
Examination personnel send test assignment start information by testing order ticket described in mobile scanning terminal, by moving after end to be tested
Dynamic terminal record test result, if test result is unqualified, work is sent in triggering again automatically, and carries out repeatedly experiment survey repeatedly
Examination, records and uploads test initial data and all previous test data of experiment.It is automatic raw according to the performance of test sub-project
Into test report, the service efficiency, the operating efficiency of each tester and item of every equipment are analyzed by the test report
The completion efficiency of mesh overall progress.
In the present embodiment, mobile terminal can use the smart mobile phone equipped with corresponding APP programs, by smart mobile phone
APP prompting inspector on the day of verify plan;According to the plan of verifying, temporary freezing equipment, inspector's typing or equipment collection
Point inspection item, whether energetic item subsystem automatic decision is qualified, it is impossible to which whether the item time artificial judgment of quantization is qualified;If core
Look into equipment any one time unqualified, then system trigger maintenance flow, this equipment is frozen, could used until meeting standard;
If all qualified, the automatic thawing equipment of system, is that task sends work most basic condition.Defective item system triggers quality announcement automatically
Ticket, user fills in correlated quality information, uploads maintenance daily record.Often test group director checks test plan, the survey of current group
Try equipment situation, personal information situation, assigned a task performance;According to the emergency of the project plan or urgent slotting single feelings
Condition, changes test assignment priority, arranges the test assignment time, finally completes the date no more than the project plan in principle, no
Then system automatic alarm, points out to cause other project delay information.The accepted survey of task, history on the day of group group leader receiving
The information such as whether trial business completes, performance;According to the standard testing time of sub-project, (whether the same day by test qualification personnel
Work attendance is gone to work), whether facility information, exemplar is put in storage, the whether enough information of auxiliary material stock, system automatic job distribution, in the present embodiment
In, according to test order ticket, it can start to test by corresponding APP program scannings using smart mobile phone, test is swept after terminating
Bar code typing test result is retouched, if unqualified, gap filling macadam writ information is needed;For test failure sub-project, system is automatic
Work job order is sent in triggering again, needs tester repeatedly to test repeatedly;Tester uploads test initial data or and test equipment
Network automatic read test initial data, according to test sub-project test performance, return the performance of falling the project plan, experiment
Target performance;According to object of experiment reporting requirement, system reads partial data and writes test report automatically;Thus can be with
Realize that analysis every equipment service efficiency, the operating efficiency of each tester, and project process complete efficiency.
In the present embodiment, server also includes the authentication server for being used to carry out rights management, and tester is carried out
Rights management, controls different functional testers to check relative test assignment by rights management, and leader's group can be looked into
All items node data is seen, project process instrument board is shown, project report.Shown and can successively deployed by abnormal alarm, chased after
Trace back to original test data.For example:All personnel project plan group, task be can be divided into according to function and group, test assigned
The different groups such as group, quality group, equipment group, exemplar management group, disbursement and sattlement group and information management group, project plan group can root
Plan is worked out according to project superclass, examination & approval are submitted.Task, which assigns group, can only check this group of project plan, arrange the test number of this group
According to.Test group can only check my test assignment, upload this test record.Quality group is accused according to test result typing quality
Ticket.Equipment group can only manage the equipment registration authorized, point inspection, maintenance, verification.Exemplar management group can only manage exemplar receive,
Storage, neck material, cancelling stocks, all data of return.Disbursement and sattlement group is according to test process management, and system calculates clearing form automatically.
Information management group handles the authority of each group, and the intersection authority of one or two people can set different authorities according to employee post's difference, make
The personnel in respective post can only be checked, operate this post number evidence, and unified Role Management is realized by rights management.
Finally illustrate, above example is only unrestricted to illustrate the technical solution of the utility model, although ginseng
The utility model is described in detail according to preferred embodiment, it will be understood by those within the art that, can be to this
The technical scheme of utility model is modified or equivalent substitution, without departing from the objective and model of technical solutions of the utility model
Enclose, it all should cover among right of the present utility model.
Claims (7)
1. a kind of test assignment dispatching system, it is characterised in that:Including information collecting device, server, transmitting device and it is used for
The terminal device for sending work information is received, described information harvester includes the personnel information acquisition for collecting test personal information
Module and the equipment information collection module for gathering exemplar information and facility information;
The output end of described information harvester is connected by the input of transmitting device and server, the server and terminal
Equipment is connected;
The personnel information acquisition module includes fingerprint collecting unit, fingerprint identification unit and fingerprint attendance unit, the fingerprint
The output end of collecting unit and the input of fingerprint identification unit are connected, the output end and fingerprint attendance of the fingerprint identification unit
The input connection of unit.
2. test assignment dispatching system according to claim 1, it is characterised in that:The equipment information collection module includes
Being arranged at being used in exemplar and/or equipment represents the electronic tag of exemplar and/or the identity information of equipment and for recognizing
The reading unit of electronic tag is stated, the output end of the reading unit is connected by transmitting device with server.
3. test assignment dispatching system according to claim 1, it is characterised in that:The terminal device is provided with test knot
Fruit logging modle, the server is provided with test result discrimination module and automatic job distribution module, and the test result differentiates mould
Block is connected with automatic job distribution module, for being carried out sending work according to test result.
4. test assignment dispatching system according to claim 2, it is characterised in that:The transmitting device is to be wirelessly transferred mould
Block, the wireless transport module includes GPRS module, 3G module or 4G modules.
5. test assignment dispatching system according to claim 1, it is characterised in that:The terminal device is mobile terminal,
The mobile terminal include micro-control unit, input block and display unit, the input block and display unit respectively with it is micro-
Control unit is connected, and the micro-control unit is connected with server.
6. test assignment dispatching system according to claim 5, it is characterised in that:The terminal device also includes being used to survey
Examination task time finally completes the alarm unit alarmed during the time more than the project plan, and the alarm unit is with being that control is single
Member connection connection.
7. test assignment dispatching system according to claim 1, it is characterised in that:The server also includes being used to carry out
The authentication server of rights management.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620954800.1U CN206505440U (en) | 2016-08-26 | 2016-08-26 | Test assignment dispatching system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620954800.1U CN206505440U (en) | 2016-08-26 | 2016-08-26 | Test assignment dispatching system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206505440U true CN206505440U (en) | 2017-09-19 |
Family
ID=59843163
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620954800.1U Expired - Fee Related CN206505440U (en) | 2016-08-26 | 2016-08-26 | Test assignment dispatching system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206505440U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112055069A (en) * | 2020-08-31 | 2020-12-08 | 深圳供电局有限公司 | Electric power automation equipment testing method and system |
-
2016
- 2016-08-26 CN CN201620954800.1U patent/CN206505440U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112055069A (en) * | 2020-08-31 | 2020-12-08 | 深圳供电局有限公司 | Electric power automation equipment testing method and system |
CN112055069B (en) * | 2020-08-31 | 2023-12-05 | 深圳供电局有限公司 | Electric power automation equipment testing method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106327087A (en) | Test task assignment method | |
CN206921161U (en) | It is a kind of to include inspection management and defect processing and the intelligent inspection system of examination | |
CN106447156A (en) | Attendance management method and system | |
US10116165B2 (en) | Powergrid operation and supervision system | |
CN103824340B (en) | Unmanned plane power transmission line intelligent cruising inspection system and method for inspecting | |
CN104809597B (en) | Data resource management platform based on data fusion | |
CN106846530A (en) | A kind of property movement cruising inspection system and method based on NFC technique | |
CN104361445B (en) | Labour's real-time management system and management method | |
CN105260841B (en) | A kind of distribution network failure repairing receipt auditing system | |
CN105574593B (en) | Track state static detection and control system and method based on cloud computing and big data | |
CN106296038A (en) | Test assignment triggering method | |
CN109359900A (en) | A kind of inspection management platform | |
CN111369208A (en) | Intelligent auxiliary case handling system for criminal penalty change execution inspection | |
CN104881006A (en) | Fire coal sampling, preparation and testing management method and apparatus | |
CN108154340A (en) | Prefabricated component informationization management system based on BIM cloud platforms | |
CN109447286A (en) | A kind of power transformation O&M Intelligent mobile job platform based on Internet of Things | |
CN111488999A (en) | Be applied to wind-powered electricity generation field safety production information-based management system | |
CN114841662A (en) | Infrastructure construction project management and control method and device, computer equipment and storage medium | |
CN106447157A (en) | Product testing and supervision method and monitoring system thereof | |
CN107693997B (en) | Fire fighting equipment detection and maintenance management system and management method | |
CN107169627A (en) | A kind of electric energy meter quality management-control method and system based on augmented reality | |
CN206505440U (en) | Test assignment dispatching system | |
CN112184072B (en) | Machine room equipment management method and device | |
CN114091944A (en) | Cloud-end-coordinated distribution network engineering field operation analysis decision system | |
CN105718602A (en) | Cloud system for work safety standardization of rural hydropower station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180604 Address after: 211200 road 19, zhe Tang new town, Lishui Economic Development Zone, Nanjing, Jiangsu Patentee after: Nanjing longni Pml Precision Mechanism Ltd Address before: 400052 No. 99 Hualong Avenue, Kowloon Park, Kowloon Po, Chongqing. Patentee before: Loncin General Dynamics Co., Ltd. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170919 Termination date: 20180826 |
|
CF01 | Termination of patent right due to non-payment of annual fee |