CN206503164U - Contrary sequence method fetches earth outspoken fast closure construction connecting node - Google Patents

Contrary sequence method fetches earth outspoken fast closure construction connecting node Download PDF

Info

Publication number
CN206503164U
CN206503164U CN201720103218.9U CN201720103218U CN206503164U CN 206503164 U CN206503164 U CN 206503164U CN 201720103218 U CN201720103218 U CN 201720103218U CN 206503164 U CN206503164 U CN 206503164U
Authority
CN
China
Prior art keywords
reinforcing bar
precast beam
fetches earth
closure construction
connecting node
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720103218.9U
Other languages
Chinese (zh)
Inventor
龙莉波
张瑞
仲成伟
王喜伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201720103218.9U priority Critical patent/CN206503164U/en
Application granted granted Critical
Publication of CN206503164U publication Critical patent/CN206503164U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model is related to a kind of contrary sequence method and fetched earth outspoken fast closure construction connecting node, belongs to technical field of construction.Contrary sequence method disclosed in the utility model fetches earth outspoken fast closure construction connecting node, including ring beam, precast beam, after pour beam and prefabricated board, splice by using precast beam and the ring beam poured, splice point is poured beam after using and is combined, and the closure construction for the mouth that fetched earth using prefabricated board progress, scene only carries out concreting to precast beam and ring beam stitching portion, and precast beam, prefabricated board is prefabrication, only need on-site hoisting, so as to reach raising efficiency of construction, shorten the purpose of construction period, simultaneously, prefabrication uses normal process, precast beam, the quality of prefabricated board is also ensured.

Description

Contrary sequence method fetches earth outspoken fast closure construction connecting node
Technical field
The utility model is related to a kind of contrary sequence method and fetched earth outspoken fast closure construction connecting node, belongs to technical field of construction.
Background technology
Reverse construction, is that skyscraper underground structure is successively constructed from top to down, with prevent setting of ground around, Environmental protection, many advantages, such as save social resources, shorten the construction period, therefore it is able in deep foundation pit support extensive use.
In reverse construction, underground cubic metre of earth needs to take out by the mouth that fetches earth, and therefore, every layer is provided with the mouth that fetches earth.Such as Fig. 1 Shown, mouthful surrounding that fetches earth is provided with ring beam 110, and ring beam 110 is arranged on column 120;With reference to shown in Fig. 1 and Fig. 2, by cast-in-place Concrete constitutes and is provided with the mouth 100 that fetches earth on the top plate or bottom plate of underground structure, each layer of top plate or bottom plate.Phase after construction, Need to close the mouth that fetches earth.The existing mouthful later stage closure construction that fetches earth mainly is constructed using cast-in-place method, including:(1) formwork Cast-in-place closure construction;(2) hanging module and cast-in-situ closure construction;(3) the cast-in-place closure construction of reinforcement bar truss mould plate.
Branch module and cast-in-situ closure construction is the most frequently used mouthful closure construction method that fetches earth in contrary working method engineering.This method is to take Bent formwork installation is set up below native mouth, and by design requirement assembling reinforcement, casting concrete, cast-in-situ floor is made through maintenance, form removal, So as to the closure construction for the mouth that completes to fetch earth.Branch module and cast-in-situ closure construction have good integrity, shock resistance it is strong, suitable for irregular The advantages of fetching earth mouthful of shape.But when using branch module and cast-in-situ closure construction, every layer fetch earth mouthful at be required for setting up and remove and prop up Support and template, and upper strata fetch earth mouth construction need to fetch earth after a mouthful closure construction reaches design strength and could carry out in lower floor, construction work Phase is longer.
If it is to be fetched earth in dried layer at the top of mouth using hanging girder steel while multiple template component is suspended in midair, every to hang mould closure construction Assembling reinforcement and casting concrete in layer template assembly, complete floor closure construction.This method has operating efficiency height, saves pin The advantages of setting up expense, reduction engineering cost of hand cradle.
Reinforcement bar truss mould plate is the minor diameter reinforcing bar by the upper and lower layer longitudinal reinforcement of cast-in-situ floor and bending shaping, composition tool There is the jack truss of certain altitude and energy bearing load, then weld profiled sheet.The cast-in-place closure construction of reinforcement bar truss mould plate can be significantly Live reinforcing bar binding work amount is reduced, site operation progress can be accelerated.
However, closing the mouth that fetches earth using cast-in-place method, it is necessary to be required to carry out template splicing, reinforcing bar to each layer of the mouth that fetches earth The steps such as colligation, concreting, concrete curing, form removal, engineering time length, quality can not be fully guaranteed, and this can not Meet current construction it is high-quality, it is allegro require.Accordingly, it would be desirable to be entered using the new technical scheme mouth that fetched earth to contrary sequence method Row quick closure is constructed.
Utility model content
Engineering time length, the quality for closing mouth presence of fetching earth by the construction of cast-in-place method for prior art can not be guaranteed The problems such as, the utility model fetches earth outspoken fast closure construction connecting node there is provided a kind of contrary sequence method, using precast beam with having poured The ring beam splicing built, then hoisting prefabricated plate realize the closure construction for the mouth that fetches earth, and scene is only carried out to precast beam and ring beam stitching portion Concreting, and precast beam, prefabricated board are prefabrication, only need on-site hoisting, thus reach raising efficiency of construction, Shorten the purpose of construction period, meanwhile, prefabrication uses normal process, and precast beam, the quality of prefabricated board are also ensured.
To solve above technical problem, the utility model includes following technical scheme:
A kind of contrary sequence method fetches earth outspoken fast closure construction connecting node, including:
Ring beam, the ring beam is arranged on mouthful surrounding that fetches earth, and is supported by column fixation, is provided with and stretches on the ring beam The connection reinforcing bar one of the mouth that fetches earth;
Precast beam, the precast beam is provided at both ends with connection reinforcing bar two, and the precast beam is across the mouth that fetches earth, the company Connect and be welded and fixed between reinforcing bar two and the connection reinforcing bar one;
After pour beam, it is described after pour beam and be located between the ring beam and the precast beam, wrap up the ring beam and described prefabricated Connection reinforcing bar one between beam and the connection reinforcing bar two, it is described after pour the upper surface of beam and put down with the upper surface of the precast beam Together;
Some prefabricated boards, the prefabricated board is fixed on the ring beam, precast beam and the after-pouring beam.
Preferably, beam is poured after described to be included positioned at the ultra-high performance concrete layer of bottom and superposed normal concrete Layer.
Preferably, the end of the precast beam is provided with link slot or linking arm.
Preferably, steel corbel is provided with the ring beam, the precast beam ends rest is on the steel corbel.
Preferably, being provided at both ends with for the prefabricated board connects reinforcing bar three, in the end stitching portion of two prefabricated boards, The connection reinforcing bar three is welded and fixed.
Preferably, two prefabricated boards are arranged at intervals in stitching portion, and the plate parcel connection reinforcing bar three is poured after.
The utility model is allowed to compared with prior art, have the following advantages that and accumulate due to using above technical scheme Pole effect:
(1) contrary sequence method that the present embodiment is provided fetches earth outspoken fast closure construction connecting node, and splice point is poured beam after using and entered Row is combined, and carries out the closure construction of mouth of fetching earth using prefabricated board, and scene only carries out concrete to precast beam and ring beam stitching portion Pour, and precast beam, prefabricated board are prefabrication, only need on-site hoisting, so as to reach raising efficiency of construction, shorten construction work The purpose of phase, meanwhile, prefabrication uses normal process, and precast beam, the quality of prefabricated board are also ensured;
(2) beam is poured after and uses the double-decker being made up of ultra-high performance concrete layer and normal concrete layer, makes stitching portion After pour beam and be rapidly achieved design strength, prefabricated board lifting construction is carried out as early as possible, shortens the construction period, very-high performance can be reduced again The consumption of concrete, reaches cost-effective purpose;
(3) by setting steel corbel, to support precast beam, and the bottom template of beam can be poured after, can act also as forever Long property supporting construction, increases connecting node overall structure stability;
Brief description of the drawings
Fig. 1 fetches earth the plan of mouth for contrary sequence method in the prior art;
Fig. 2 is along A-A sectional views in Fig. 1;
The contrary sequence method that Fig. 3 is provided by the embodiment of the utility model one fetches earth the structure of outspoken fast closure construction connecting node Schematic diagram;
The schematic diagram that the precast beam that Fig. 4 is provided by the embodiment of the utility model one is connected with ring beam;
Fig. 5 is along B-B sectional views in Fig. 4;
Fig. 6 splices schematic diagram for two prefabricated board ends that the embodiment of the utility model one is provided;
Fig. 7 fetches earth the flow chart of outspoken fast closure construction method for the contrary sequence method that another embodiment of the utility model is provided.
Label is as follows in figure:
Fetch earth mouth 100;Ring beam 110;Connect reinforcing bar 1;Steel corbel 112;Column 120;Precast beam 130;Connect reinforcing bar 2 131;After pour beam 140;Prefabricated board 150;Connect reinforcing bar 2 151;After pour plate 160.
Embodiment
The contrary sequence method provided below in conjunction with the drawings and specific embodiments the utility model the outspoken fast closure construction that fetches earth connects Node is connect to be described in further detail.With reference to following explanation and claims, advantages and features of the present utility model will be more clear Chu.It should be noted that, accompanying drawing is using very simplified form and uses non-accurately ratio, only to conveniently, lucidly Aid in illustrating the purpose of the utility model embodiment.
Embodiment one
The structure of outspoken fast closure construction connecting node referring to Fig. 3, the contrary sequence method that Fig. 3 is provided by the present embodiment fetches earth Schematic diagram.With reference to shown in Fig. 1 to Fig. 3, the connecting node include ring beam 110, precast beam 130, after pour beam 140 and prefabricated board 150, Wherein ring beam 110 is arranged on the surrounding of mouth 100 that fetches earth, and is supported by the fixation of column 120, is provided with to stretch on ring beam 110 and fetches earth The connection reinforcing bar 1 of mouth 100;Precast beam 130 is provided at both ends with connection reinforcing bar 2 131, and the connection reinforcing bar 2 131 can be vertical Muscle stretches out section, and precast beam 130 is welded and fixed between the mouth 100 that fetches earth, connection reinforcing bar 2 131 and connection reinforcing bar 1; After pour beam 140 and be located between ring beam 110 and precast beam 130, parcel connection reinforcing bar 1 with being connected reinforcing bar 2 131, and after pour beam 140 upper surface is concordant with the upper surface of precast beam 130;Prefabricated board 150 be fixed on ring beam 110, precast beam 130 and after pour beam On 140.
The contrary sequence method that the present embodiment is provided fetches earth outspoken fast closure construction connecting node, by using precast beam 130 with The ring beam 110 poured splices, and splice point is poured beam 140 after using and is combined, and carries out the mouth 100 that fetches earth using prefabricated board 150 Closure construction, scene only carries out concreting to precast beam 130 and the stitching portion of ring beam 110, and precast beam 130, prefabricated board 150 It is prefabrication, only needs on-site hoisting, so that the purpose for improving efficiency of construction, shortening the construction period is reached, meanwhile, factory is pre- System uses normal process, and precast beam 130, the quality of prefabricated board 150 are also ensured.
Refer to Fig. 4 and Fig. 5, the schematic diagram that the precast beam that wherein Fig. 4 is provided by the present embodiment is connected with ring beam, Fig. 5 For in Fig. 4 along B-B sectional views.A mouthful side of fetching earth is provided with steel corbel 112 on ring beam 110, one end of precast beam 130 is shelved On steel corbel 112.The longitudinal reinforcement of precast beam 130 stretches out to form connection reinforcing bar 2 131, and with being arranged on ring beam 110 Connection reinforcing bar 1 be welded and fixed, after pour beam 140 be located between ring beam 110 and precast beam 130, parcel connection reinforcing bar 1 with Connect reinforcing bar 2 131.By setting steel corbel 112 in the present embodiment, to support precast beam 130, and beam 140 can be poured after Bottom template, can act also as permanent supporting construction, increase connecting node overall structure stability.As an example, steel corbel 112 can include the horizontal steel plate and vertical steel plate that at right angles set, and vertical steel plate is welded by dowel and is close to ring beam 110 On, weld steel ribs between horizontal steel plate and vertical steel plate.
As shown in figure 4, in order to pour the resistance to overturning between beam 140 and precast beam 130 after increasing, in precast beam 130 End sets link slot 132.It is of course also possible to set linking arm in the end of precast beam 130, so-called linking arm is just provided in The projection cube structure of the end of precast beam 130.
Preferably, beam 140 is poured after to be included positioned at the ultra-high performance concrete layer of bottom and superposed normal concrete Layer.Ultra-high performance concrete, also referred to as abbreviation UHPC (Ultra-High Performance Concrete), reactive powder are mixed Solidifying soil (RPC, Reactive Powder Concrete).As an example, ultra-high performance concrete, can use grade particulate cancellous bone Stockpile is accumulated, and gap is filled by materials such as the cement, flyash, miberal powder of micron particles, is equipped with very-high performance water reducer and is formed The composite with the features such as intensity is high, hardening is fast.Ultra-high performance concrete, which makes to pour beam 140 behind stitching portion, to be rapidly achieved Design strength, so as to enter the lifting construction of prefabricated board 150 as early as possible, shortens the construction period.In order to reduce ultra-high performance concrete Consumption, it is cost-effective, can control ultra-high performance concrete layer thickness, normal concrete is poured above it.
Prefabricated board 150 can directly rest on precast beam 130, after pour on beam 140 and ring beam 110, it is certainly, prefabricated in order to increase Splicing seams are set between the monolithic stability of plate 150, preferably prefabricated board 150, to carrying out concrete construction at splicing seams, after pouring Pour plate 160.As shown in fig. 6, prefabricated board 150 is provided at both ends with connection reinforcing bar 3 151, connection reinforcing bar 3 151 can stretch out pre- The longitudinal reinforcement of the end of making sheet 150, the connection reinforcing bar 3 151 of two ends of prefabricated board 150 is welded and fixed.By connecting reinforcing bar Three are welded and fixed, and pour plate 160 after pouring, so that polylith prefabricated board 150 turns into the stable overall of good mechanical properties.It is preferred that For the end of prefabricated board 150 is provided with link slot 152 or linking arm, link slot or linking arm class with being arranged at prefabricated beam end Seemingly, therefore not to repeat here.Preferably, poured after plate 160 include positioned at bottom ultra-high performance concrete layer and it is superposed general Logical concrete layer, pours beam, therefore not to repeat here after being similar to.
Embodiment two
Fig. 7 fetches earth the flow chart of outspoken fast closure construction method for the contrary sequence method that the present embodiment is provided.With reference to Fig. 1 to Fig. 7 Shown, the construction method specifically includes following steps:
S1. the mouth 100 that fetched earth to contrary sequence method plans that the size to precast beam 130, prefabricated board 150 is designed, then Prefabricated processing precast beam 130, prefabricated board 150.In design, the size of beam 140 is poured after should reserving;If in addition, being poured after setting Plate 160, pours the size of plate 160 after also reserving.
S2. with the ring beam 110 of the junction of precast beam 130, setting the steel corbel 112 of support precast beam 130.
S3. hoisting prefabricated beam 130, makes the two ends of precast beam 130 be held on the steel corbel for being located at the both sides of mouth 100 of fetching earth respectively On 112, it is arranged at intervals between the precast beam 130 and ring beam 110, forms connecting sewing.
S4. the connection reinforcing bar 2 131 of the connection reinforcing bar 1 and precast beam 130 of ring beam 110 is welded and fixed, and even Seam crossing sets a pair of side templates, and side template is shelved on steel corbel 112.
S5. casting concrete, shape in the region that steel corbel 112, side template, ring beam 110 and precast beam 130 are enclosed Beam 140 is poured after.Supporting construction when steel corbel 112 is lifted as precast beam 130, and after when pouring 140 concreting of beam End template.
Preferably, in step S5, after pour pouring for beam 140 and be divided into two steps, i.e.,:S5-1. poured at connecting sewing super High performance concrete;S5-2. after ultra-high performance concrete reaches design strength, secondary grouting maintenance is carried out.After-pouring beam 140 So as to be formed including the ultra-high performance concrete layer and superposed normal concrete layer positioned at bottom.Ultra-high performance concrete The concrete of stitching portion is rapidly achieved design strength, so as to enter the lifting construction of prefabricated board 150 as early as possible, shorten construction work Phase.And normal concrete layer, the consumption of ultra-high performance concrete can be reduced, it is cost-effective.
S6. pour beam 140 after to reach after design strength, hoisting prefabricated plate 150 makes prefabricated board 150 be fixedly installed on ring beam 110th, precast beam 130, after pour on beam 140, closing is fetched earth mouth.
In the present embodiment, the contrary sequence method mouthful closure construction that fetches earth mainly employs precast beam 130 and prefabricated board 150, without adopting With cumbersome cast in situs construction technology, the construction technology for mouth closing of fetching earth is greatly simplify, and the construction method is carried out Fetch earth a mouthful closure construction, has the advantages that efficiency effect is high, quality is good, mechanical property is strong.
It is preferred embodiment that in step s 6, two end of prefabricated board 150 splicings comprise the following steps:
S6-1. the stitching portion of prefabricated board 150 is provided with precast beam 130, make prefabricated board 150 splicing end be shelved on it is pre- On beam 130 processed;
S6-2. the splicing of the connection reinforcing bar 3 151 of prefabricated board 150 is carried out using sleeve grouting connection method;
S6-3. concreting is carried out in the stitching portion of the end of prefabricated board 150, plate 160 is poured after formation.
Further, in step S6-3, the casting method of after-pouring plate 160 specifically includes following steps:
S6-3-1. ultra-high performance concrete is poured in stitching portion;
S6-3-2. after ultra-high performance concrete reaches design strength, secondary grouting maintenance is carried out.
In summary, the contrary sequence method that the utility model is provided fetches earth outspoken fast closure construction method, can be quickly by precast beam 130th, prefabricated board 150 splices on the ring beam 110 for fetching earth mouth 100, with process is succinct, stitching portion good mechanical performance, construction The advantages of short time limit.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the utility model scope Calmly, the those of ordinary skill in the utility model field does according to the disclosure above content any change, modification, belonging to right will Seek the protection domain of book.

Claims (6)

  1. The outspoken fast closure construction connecting node 1. a kind of contrary sequence method fetches earth, it is characterised in that including:
    Ring beam, the ring beam is arranged on mouthful surrounding that fetches earth, and is supported by column fixation, is provided with the ring beam described in stretching to Fetch earth the connection reinforcing bar one of mouth;
    Precast beam, the precast beam is provided at both ends with connection reinforcing bar two, and the precast beam is across the mouth that fetches earth, the connection steel It is welded and fixed between muscle two and the connection reinforcing bar one;
    After pour beam, it is described after pour beam and be located between the ring beam and the precast beam, wrap up the ring beam and the precast beam it Between connection reinforcing bar one with it is described connection reinforcing bar two, it is described after pour beam upper surface it is concordant with the upper surface of the precast beam;
    Some prefabricated boards, the prefabricated board is fixed on the ring beam, precast beam and the after-pouring beam.
  2. The outspoken fast closure construction connecting node 2. contrary sequence method as claimed in claim 1 fetches earth, it is characterised in that beam is poured after described Including the ultra-high performance concrete layer and superposed normal concrete layer positioned at bottom.
  3. The outspoken fast closure construction connecting node 3. contrary sequence method as claimed in claim 1 fetches earth, it is characterised in that the precast beam End be provided with link slot or linking arm.
  4. The outspoken fast closure construction connecting node 4. contrary sequence method as claimed in claim 1 fetches earth, it is characterised in that on the ring beam Steel corbel is provided with, the precast beam ends rest is on the steel corbel.
  5. The outspoken fast closure construction connecting node 5. contrary sequence method as claimed in claim 1 fetches earth, it is characterised in that the prefabricated board Be provided at both ends with connection reinforcing bar three, in the end stitching portion of two prefabricated boards, the connection reinforcing bar three is welded and fixed.
  6. The outspoken fast closure construction connecting node 6. contrary sequence method as claimed in claim 5 fetches earth, it is characterised in that two described pre- Making sheet is arranged at intervals in stitching portion, and the plate parcel connection reinforcing bar three is poured after.
CN201720103218.9U 2017-01-26 2017-01-26 Contrary sequence method fetches earth outspoken fast closure construction connecting node Expired - Fee Related CN206503164U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720103218.9U CN206503164U (en) 2017-01-26 2017-01-26 Contrary sequence method fetches earth outspoken fast closure construction connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720103218.9U CN206503164U (en) 2017-01-26 2017-01-26 Contrary sequence method fetches earth outspoken fast closure construction connecting node

Publications (1)

Publication Number Publication Date
CN206503164U true CN206503164U (en) 2017-09-19

Family

ID=59833258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720103218.9U Expired - Fee Related CN206503164U (en) 2017-01-26 2017-01-26 Contrary sequence method fetches earth outspoken fast closure construction connecting node

Country Status (1)

Country Link
CN (1) CN206503164U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638683A (en) * 2017-01-26 2017-05-10 上海建工二建集团有限公司 Reverse building method soil sampling opening rapid sealing construction connecting joint and construction method
CN109736355A (en) * 2019-01-19 2019-05-10 杭州联纵规划建筑设计院有限公司 A kind of contrary sequence method basement construction method in old factory rehabilitation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638683A (en) * 2017-01-26 2017-05-10 上海建工二建集团有限公司 Reverse building method soil sampling opening rapid sealing construction connecting joint and construction method
CN106638683B (en) * 2017-01-26 2019-04-05 上海建工二建集团有限公司 Contrary sequence method takes the outspoken fast closure construction connecting node of soil and construction method
CN109736355A (en) * 2019-01-19 2019-05-10 杭州联纵规划建筑设计院有限公司 A kind of contrary sequence method basement construction method in old factory rehabilitation
CN109736355B (en) * 2019-01-19 2020-09-25 杭州联纵规划建筑设计院有限公司 Reverse construction method basement construction method in factory building transformation

Similar Documents

Publication Publication Date Title
CN106869172B (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN106284412B (en) A kind of prefabricated pipe gallery and construction method
CN107938504A (en) A kind of wet seam construction of floorings using T reinforcing bars and its construction method
CN106638683B (en) Contrary sequence method takes the outspoken fast closure construction connecting node of soil and construction method
CN106555453A (en) A kind of prefabricated overlapped hollow plate of prestressing force and its construction method
CN103290784B (en) Arched girder conjugative bridge construction method for hanging
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN109083320A (en) Combine prefabricated panel and laminated floor slab structure and laminated floor slab construction method
CN208151833U (en) A kind of construction of novel RC-masonry combination arch bridge
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN209703525U (en) A kind of side slope precast assembly lattice girder connected by wet seam
CN104594193B (en) A kind of Hollow Slab Beam Bridge superstructure and construction method thereof
CN103452350B (en) Assembling electronic workshop and construction method thereof
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN206503164U (en) Contrary sequence method fetches earth outspoken fast closure construction connecting node
CN111350187A (en) Template system suitable for large-diameter manual hole digging annular foundation pile and construction method
CN105951987B (en) Node and construction method are poured after the secondary external permanent aluminium sheet external mold of frame
CN201753530U (en) Simple support box girder reinforcing steel bar integral binding pedestal, hanger frame and bracket thereof
CN206769199U (en) After wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN112796198A (en) Hollow arch bridge system connected by UHPC wet joints and construction method
CN108221637A (en) A kind of prefabricated assembled arch
CN107100322A (en) Post stretching vertical prestressing cast-in-place concrete rod structure and construction method
CN208884808U (en) Combine prefabricated panel and laminated floor slab structure
CN207525906U (en) A kind of assembled frame-shear structure wall splitlevel connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Long Libo

Inventor after: Zhang Rui

Inventor after: Li Juanyi

Inventor after: Zhong Chengwei

Inventor after: Wang Xiwei

Inventor before: Long Libo

Inventor before: Zhang Rui

Inventor before: Zhong Chengwei

Inventor before: Wang Xiwei

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170919