Height specially becomes simulation system for low meter
Technical field
The utility model belongs to electric power analogue means technical field, and in particular to a kind of height specially becomes simulation system for low meter.
Background technology
Power information acquisition system is the important component that intelligent grid is built, according to State Grid Corporation of China's intelligent grid
The general requirement of construction, the construction of power information acquisition system will realize the overall goal of " all standing, full collection, control in full ".
Operation, the maintenance of electric energy metrical relevant device are completed by the electric energy metrical personnel at scene, because system architecture is complicated,
It is also higher to the skill set requirements of field personnel, and workflow is comparatively laborious, during failure, failure mode is also more numerous
Many, a large amount of with field apparatus use, and the workload of attendant is also therewith into the increase of geometry multiple, company of prefectures and cities fortune
Dimension personnel can only by virtue of experience go handling failure.The experiment test place for setting up a set of dry run environment is needed badly, for scene fortune
Row attendant, measurement centre supervisory engineering staff carry out operation maintenance rehearsal, the experimental site of system equipment test.
, can be using massive quantity power supply and measurement and height for being counted by the way of low meter when being measured using electric power meter to electric energy
Amount, massive quantity power supply and measurement refers to that high-voltage line is powered, and high-pressure side metering, height refers to that high-voltage line is powered for low meter, low-pressure side metering.Set up high
Be necessarily required to build during for low meter simulated scenario system it is high specially become simulation system for low meter so that analogue simulation is closer to actual field
Scape.
Utility model content
Technical problem to be solved in the utility model is that there is provided a kind of high special for low meter in view of the shortcomings of the prior art
Become simulation system, each electric energy meter of virtual load power drives controlled by industrial computer is shown, height can be carried out and specially become for low meter
The presentation directly perceived of user power utilization information, and by mobile terminal apparatus, realize that the teaching to operator and security control are made
With.
In order to solve the above technical problems, the technical scheme that the utility model is used is:
It is a kind of high specially to become simulation system for low meter, including simulation table, fault simulator, communication transponder, control centre and
Mobile terminal, the simulation table include base station, line bar, simulation 10kV high pressures inlet wire, simulation low-pressure line-outgoing, analogue transformer,
Special transformer acquisition terminal and three-phase intelligent electric-energy meter, the bottom of the line bar are fixedly connected with the base station, and the line bar is two
Support platform is set between the insulating bar being oppositely arranged, the line bar, and the top of the support platform sets analogue transformer, under
Portion sets special transformer acquisition terminal and three-phase intelligent electric-energy meter, the simulation 10kV high pressures inlet wire and simulate low-pressure line-outgoing respectively with institute
State and virtual load power supply is set inside analogue transformer connection, the analogue transformer, the control centre includes industrial computer, described
Mobile terminal includes monitoring of pulse module and video conversation module, and the video conversation module includes being arranged on safety cap front end
Camera and side earphone, the three-phase intelligent electric-energy meter, special transformer acquisition terminal and control centre be sequentially connected, described three
Phase intelligent electric energy meter and special transformer acquisition terminal respectively successively with fault simulator, virtual load power supply, communication transponder, control centre
Connection.
Preferably, the three-phase intelligent electric-energy meter is attached with the special transformer acquisition terminal by RS485 communication interfaces,
The special transformer acquisition terminal is connected by GPRS or Ethernet with control centre.
Preferably, the base station is followed successively by insulation top layer, compoiste wood floor layer, concrete layer and ground from top to bottom.
Preferably, the line bar is polyurethane-steel composite parts.
Preferably, the camera is arranged on the safety cap front end by Rotatable base, and the camera is infrared
Camera.
Preferably, the monitoring of pulse module includes wearable bracelet, and the survey pulse point of the bracelet correspondence wrist is set
Put and control unit and communication unit, the pulse transducer, control unit, communication are additionally provided with pulse transducer, the bracelet
Unit is sequentially connected with control centre.
Preferably, fixed patch is set on the bracelet, and the fixed patch correspondence wrist sets adhesive linkage.
Compared with prior art, the beneficial effects of the utility model are as follows:
The utility model passes through above-mentioned technical proposal, it is proposed that a kind of height specially becomes simulation system for low meter, by industrial computer control
Each electric energy meter of virtual load power drives of system is shown that can carry out height for what low meter specially became user power utilization information is in intuitively
It is existing, and by mobile terminal apparatus, realize the teaching and security control effect to operator.The utility model constructs one
It is kind high specially to become in simulation system, the system simulation table surrounding when specifically used for low meter and use ornament materials, build high for low
The installation and operation environment in Ji Zhuanbiantai areas, arrangement building and natural environment picture concerned, decoration style highlight third dimension and
Stereovision;Simultaneously in user's scenario simulation, the scenario simulation three-phase for building school's scene, small hospital's scene or semiworks is used
Family, makes have sensation on the spot in person during start-up's real training.The utility model system is three-phase intelligent electricity by virtual load power supply
Energy table, special transformer acquisition terminal provide operating load, and the simulation of metering line and communication fault is realized by fault simulator.
Fault simulation part can realize the wrong line sequence of the common voltage of each meter measurement loop, broken voltage line, current open, short circuit current
Etc. most common failure.Meter and the communication failure of terminal 485 can be simulated, meter inside three-phase simulation three-phase intelligent electric-energy meter can be simulated
Measure failure, including voltage, current acquisition and display failure.Mobile terminal is the monitoring device of Worn type, passes through monitoring of pulse
Module is monitored to the palmic rate of simulation operator, then is cooperated with video conversation module, and behaviour can be recognized at any time
The psychological condition of author, can constantly be commanded when being operated for operator, be palpitated quickly when its is nervous, can be dredged in time,
Avoid the generation of maloperation under stressful situation, it is ensured that safety.The guidance mode significantly reduces the pressure of training teacher, also can
Increase the simulation times of operator, the culture to the talent is rapider.
The utility model is shown by each electric energy meter of virtual load power drives controlled by industrial computer, can carry out height
Specially become the presentation directly perceived of user power utilization information, including summary table, point table relation for low meter, loss calculation, multiple communication modes show
Field teaching, communication failure, size of current, phase angle size, wiring faults, the load management of main website server, Controlling line loss, marketing
Management training etc., the voltage of virtual load power supply is very low, solve well present in prior art by visit can not have
The problem of effect is imparted knowledge to students and there is potential safety hazard.Height of the present utility model supplies low meter, and specially change simulation system more presses close to scene reality,
Installation effectiveness is high, safe, and good Training Environment is provided for start-up.
Brief description of the drawings
The utility model is described in further detail below in conjunction with the accompanying drawings,
Fig. 1:The structural representation of the utility model simulation table;
Fig. 2:The utility model height specially becomes the system construction drawing of simulation system for low meter;
Fig. 3:The system construction drawing of the utility model monitoring of pulse module;
Fig. 4:The structural representation of the utility model monitoring of pulse module;
Fig. 5:The structural representation of the utility model video conversation module;
Wherein, 1- fault simulators, 2- communication transponders, 3- control centres, 4- base stations, 5- line bars, 6- simulations 10kV is high
Line is pressed into, 7- simulation low-pressure line-outgoings, 8- analogue transformers, 9- special transformer acquisition terminals, 10- three-phase intelligent electric-energy meters, 11- supports are flat
Platform, 12- virtual load power supplys, 13- safety caps, 14- cameras, 15- earphones, 16- Rotatable bases, 17- bracelets, 18- pulses are passed
Sensor, 19- control units, 20- communication units, 21- fixes patch, 22- adhesive linkages.
Embodiment
In order to more fully understand the utility model, further fairly set out with reference to embodiment in of the present utility model
Hold, but protection content of the present utility model is not limited solely to the following examples.In the following description, a large amount of tools are given
The details of body is more thoroughly understood the utility model to provide.However, aobvious and easy to those skilled in the art
See, the utility model can be carried out without one or more of these details.
Embodiment 1
Refering to Fig. 1 ~ 5, one kind is high for low meter specially change simulation system, including simulation table, fault simulator 1, communication transponder
2nd, control centre 3 and mobile terminal, the simulation table include base station 4, line bar 5, simulation 10kV high pressures inlet wire 6, simulation low pressure
Outlet 7, analogue transformer 8, special transformer acquisition terminal 9 and three-phase intelligent electric-energy meter 10, the bottom of the line bar are consolidated with the base station
Fixed connection, the line bar is to set support platform 11, the support platform between two insulating bars being oppositely arranged, the line bar
Top analogue transformer is set, bottom sets special transformer acquisition terminal and three-phase intelligent electric-energy meter, and the simulation 10kV height is pressed into
Line and simulation low-pressure line-outgoing are connected with the analogue transformer respectively, and virtual load power supply 12 is set inside the analogue transformer,
The control centre includes industrial computer, and the mobile terminal includes monitoring of pulse module and video conversation module, the video
Session module include be arranged on the front end of safety cap 13 camera 14 and side earphone 15, the three-phase intelligent electric-energy meter, specially
Become acquisition terminal to be sequentially connected with control centre, the three-phase intelligent electric-energy meter and special transformer acquisition terminal distinguish successively with failure mould
Intend device, virtual load power supply, communication transponder, control centre's connection.
In the utility model, three-phase intelligent electric-energy meter 10 can set multiple according to specific simulated scenario, for example:2,
It is 3, even more.
In the utility model, the three-phase intelligent electric-energy meter passes through RS485 communication interfaces with the special transformer acquisition terminal
It is attached, the special transformer acquisition terminal is connected by GPRS or Ethernet with control centre.
In the utility model, the base station is followed successively by insulation top layer 4-1, compoiste wood floor layer 4-2, coagulation from top to bottom
Soil layer 4-3 and ground 4-4.Base station is used to support the parts such as line bar, while the need for adapting to indoor insulation and decoration, with simulating chamber
Interior surrounding environment is adapted, and is that start-up builds sensation on the spot in person.It is further preferred that the insulation top layer is exhausted
Edge paint film layer, to strengthen the insulating properties of base station, improves security performance.
In the utility model, the line bar be polyurethane-steel composite parts, such product high-strength light, good insulating,
Practice have shown that, install easy to make, be adapted to do simulation line bar and use.
In the utility model, the two ends of the support platform are connected by anchor ear with the line bar, and special become gathers
Terminal and three-phase intelligent electric-energy meter are connected by damping anchor ear with the line bar.Preferably, anchor ear is compound using polyurethane-steel
Product, adapts to intensity needs, while good insulation preformance, light weight, can mitigate the load of support platform.Damping anchor ear is anchor ear
It is made with rubber shock-absorbing layer, rubber shock-absorbing layer is arranged on the side that anchor ear is contacted with the line bar.
In the utility model, the transformer is connected by damping base with the support platform.In order to real with scene
Border is engaged, while strengthening anti-seismic performance, damping base is set between transformer and support platform, the damping base can be used
Damping base generally in the art.
Embodiment 2
Refering to Fig. 5, the height described by the present embodiment specially becomes simulation system for low meter, is carried out on the basis of embodiment 1
Improve, be a difference in that:
The camera 14 is arranged on the safety cap front end by Rotatable base 16, and the camera is infrared photography
Head.
Definition in the case of dark can be ensured using infrared camera, it is ensured that the complete display of video surveillance
Property, camera set by rotating base, and teacher can be carried out in control centre by operating desk to the shooting angle of camera
Change, the preferably operation to operator is observed, to carry out corresponding guidance and prompting.
Embodiment 3
Refering to Fig. 3 ~ 4, the height described by the present embodiment specially becomes simulation system for low meter, is entered on the basis of embodiment 1
Row is improved, and is a difference in that:
The monitoring of pulse module includes wearable bracelet 17, and the survey pulse point of the bracelet correspondence wrist sets pulse
Control unit 19 and communication unit 20, the pulse transducer, control unit, communication are additionally provided with sensor 18, the bracelet
Unit is sequentially connected with control centre.Pulse transducer is fixed at the monitoring of pulse of wrist by Wearable bracelet.Realize
Monitoring to operator's pulse.Pulse transducer can use piezoelectricity sensing chip, be connected with control unit, realize to monitoring of pulse,
Communication unit sends the pulse information monitored to control centre.
Fixed patch 21 is set on the bracelet, and the fixed patch correspondence wrist sets adhesive linkage 22.In order to realize to pulse
Monitoring, bracelet can not rotate in wrist, otherwise can influence the effect of monitoring, although can be consolidated using elastic bracelet
It is fixed, but to be on the safe side, fixed patch is set on bracelet, bracelet is fixed on by hand by the cooperation of adhesive linkage and fixing band
On wrist.Avoid sensor from staggering with monitoring of pulse point, influence monitoring effect.
Although the foregoing describing the embodiment of the present invention, those familiar with the art should manage
Solution, the specific embodiment described by us is merely exemplary, rather than for the restriction to the scope of the present invention, is familiar with this
The equivalent modification and change that the technical staff in field is made in the spirit according to the present invention, should all cover the present invention's
In scope of the claimed protection.