CN206487457U - A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means - Google Patents

A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means Download PDF

Info

Publication number
CN206487457U
CN206487457U CN201720117917.9U CN201720117917U CN206487457U CN 206487457 U CN206487457 U CN 206487457U CN 201720117917 U CN201720117917 U CN 201720117917U CN 206487457 U CN206487457 U CN 206487457U
Authority
CN
China
Prior art keywords
horizontal well
simulation
multistage fracturing
fracturing horizontal
low
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720117917.9U
Other languages
Chinese (zh)
Inventor
丁冠阳
黄世军
张雪娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Petroleum Beijing
Original Assignee
China University of Petroleum Beijing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Petroleum Beijing filed Critical China University of Petroleum Beijing
Priority to CN201720117917.9U priority Critical patent/CN206487457U/en
Application granted granted Critical
Publication of CN206487457U publication Critical patent/CN206487457U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model provides a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means, is related to oil drilling and extracting equipment field.Its technical scheme:The horizontal segment of dummy level pit shaft is welded with simulation time crack provided with simulation major fracture, simulation major fracture.Copper-bath is provided with lucite groove and there are two mouth molds to intend multistage fracturing horizontal well.The simulation major fracture and simulation time crack for simulating multistage fracturing horizontal well are immersed in copper-bath.Simulation multistage fracturing horizontal well is connected to the low-pressure end and high-pressure side of constant-voltage DC source by wire.Voltmeter wire is connected with constant-voltage DC source and the probe.The utility model is by simulating the major fracture of multistage fracturing horizontal well and the form in time crack, when characterizing low-permeability oil deposit multistage fracturing horizontal well development, the pressure of diverse location in stratum, so as to provide foundation for the deployment for optimizing multistage fracturing horizontal well.

Description

A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means
Technical field
The utility model is related to oil field development experiment field, more particularly to a kind of low-permeability oil deposit multistage fracturing horizontal well pressure Force distribution analogue means.
Background technology
China's low-permeability oil deposit total resources is enriched, but its reservoir properties is poor, and traditional mining type can not be opened effectively Send out oil reservoir such.Multistage fracturing horizontal well by improving the seepage flow condition of low-permeability oil deposit near wellbore zone and increasing drainage area, Oil well output is improved, the development effectiveness of oil reservoir is improved.The pressure break series of multistage fracturing horizontal well is general more than 5 grades, often One-level pressure break will all form two symmetrical major fractures, will expand time crack again from major fracture.Split from master in secondary crack Sew on and extend to oil reservoir, the branch as extended from trunk.Major fracture and the complicated fracture network system of time cracking initiation, expand Big draining scope, but also increase the complexity of flowing.The natural production capacity wretched insufficiency of low-permeability oil deposit, to improve opening for oil reservoir Send out effect, many technical measures developed using early-stage waterflooding or Advance Water Injection.In the hyposmosis both at home and abroad such as Changqing oilfields During the actual development in oil field, water filling and oil recovery are often carried out using multistage fracturing horizontal well, imitated with the exploitation for improving oil reservoir Really.
Due to the complexity of the seam net of multistage fracturing horizontal well formation, existing theoretical study method and method for numerical simulation Pressure distribution situation when being difficult to analyze multistage fracturing horizontal well development in stratum.And existing experimental provision lacks targetedly Research, it is therefore desirable to provide a kind of multistage fracturing horizontal well pressure field distribution analogue means, has studied the life of multistage fracturing horizontal well Pressure distribution during production in stratum.
Utility model content
The purpose of this utility model is to provide a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution simulation dress Put, by simulating the distribution that the major fracture and secondary fissure of multistage fracturing horizontal well are sewn in oil reservoir, determine the strata pressure in oil reservoir Distribution situation.
The purpose of this utility model can reach by using following technical scheme:
A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means described in utility model includes constant pressure Dc source, simulation multistage fracturing horizontal well, copper-bath, voltmeter, wire, probe, lucite groove.
Simulating multistage fracturing horizontal well includes dummy level pit shaft, simulation major fracture, simulation time crack.In the simulation water The appropriate location of the horizontal segment of horizontal well cylinder is welded with the simulation major fracture, adjacent simulation major fracture symmetric arrays.Each On the individual simulation major fracture, the simulation time crack, adjacent simulation time crack symmetric arrays are welded with.The dummy level Pit shaft is made up of the copper wire of 2.5 millimeters of diameter.The simulation major fracture is made up of the copper wire of 1.5 millimeters of diameter.The simulation time Crack is made up of the copper wire of 1 millimeter of diameter.
Appropriate copper-bath is provided with the lucite groove, the reservoir to simulate oil reservoir.In the machine Two mouth molds are provided with glass guide channel and intend multistage fracturing horizontal well.The simulation major fracture of the simulation multistage fracturing horizontal well and simulation Secondary crack is immersed in copper-bath.Simulation multistage fracturing horizontal well described in a bite is connected to described constant pressure by wire The low-pressure end of dc source, the simulation multistage fracturing horizontal well described in another mouth is connected to described constant voltage DC electricity by wire The high-pressure side in source.
The voltmeter connects the low-pressure end and the probe of the constant-voltage DC source by wire.
After the utility model is connected, one end of the probe is immersed in copper-bath, probe institute can be measured Magnitude of voltage in position.By changing position of the probe in copper-bath, the life of multistage fracturing horizontal well can be obtained Pressure distribution during production in stratum.
Advantageous effects of the present utility model:The utility model uses above technical scheme, simulates multistage fracturing water The major fracture of horizontal well and the form in time crack, according to the water power principle of similitude, can characterize low-permeability oil deposit pressure break horizontal well development When, the pressure of diverse location in stratum, so as to provide foundation for the deployment for optimizing multistage fracturing horizontal well.
Brief description of the drawings
The following drawings is only intended to, in doing utility model schematic illustration and explanation, not limit model of the present utility model Enclose.
A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means that Fig. 1 provides for the utility model Structural representation.
Fig. 2 is the structural representation of simulation multistage fracturing horizontal well.
In figure:1- constant-voltage DC sources, 2- simulation multistage fracturing horizontal wells, 3- copper-baths, 4- voltmeters, 5- is led Line, 6- probes, 7- lucite grooves, 8- dummy level pit shafts, 9- simulation major fractures, 10- simulations time crack.
Embodiment
To make those skilled in the art more clear and clear and definite the technical solution of the utility model, with reference to embodiment and Accompanying drawing is described in further detail to the utility model, but embodiment not limited to this of the present utility model.
As shown in figure 1, the utility model is related to a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution simulation dress Put, including it is constant-voltage DC source 1, simulation multistage fracturing horizontal well 2, copper-bath 3, voltmeter 4, wire 5, probe 6, organic Glass guide channel 7.
As shown in figure 1, two mouth molds are provided with the machine glass guide channel 7 intends multistage fracturing horizontal well 2.Simulate major fracture 9 It is immersed in simulation time crack 10 in copper-bath 3.
As shown in figure 1, described simulation multistage fracturing horizontal well 2 is connected to described constant voltage DC by wire 5 respectively The low-pressure end and high-pressure side of power supply 1.
As shown in figure 1, the voltmeter 4 connects the low-pressure end and the probe of the constant-voltage DC source 1 by wire 5 6。
As shown in Fig. 2 simulation multistage fracturing horizontal well 2 includes dummy level pit shaft 8, simulation major fracture 9, simulation time crack 10。
As shown in Fig. 2 the horizontal segment in the dummy level pit shaft 8 is provided with the simulation major fracture 9, adjacent simulation The symmetric arrays of major fracture 9.The simulation time crack 10, adjacent simulation time crack 10 are welded with the simulation major fracture 9 Symmetric arrays.
Further, the dummy level pit shaft 8 is made up of the copper wire of 2.5 millimeters of diameter.
Further, the simulation major fracture 9 is made up of the copper wire of 1.5 millimeters of diameter.
Further, the simulation time crack 10 is made up of the copper wire of 1 millimeter of diameter.
As shown in figure 1, copper-bath 3 is provided with the lucite groove 7, the reservoir to simulate oil reservoir.
After the utility model is connected, one end of the probe 6 is immersed in copper-bath 3, probe 6 can be measured The magnitude of voltage of position.By changing position of the probe 6 in copper-bath 3, multistage fracturing level can be obtained Pressure distribution when well is produced in stratum.
Finally it should be noted that:Various embodiments above is only limited to illustrate the technical solution of the utility model, rather than to it System;Although the utility model is described in detail with reference to foregoing embodiments, one of ordinary skill in the art should Understand:It can still modify to the technical scheme described in foregoing embodiments, or to which part or whole Technical characteristic carries out equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from this practicality newly The scope of each embodiment technical scheme of type.

Claims (3)

1. a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means, including constant-voltage DC source, simulate it is many Level pressure break horizontal well, copper-bath, voltmeter, wire, probe, lucite groove, simulation multistage fracturing horizontal well, organic glass Copper-bath is provided with glass groove and there are two mouth molds to intend multistage fracturing horizontal well, the simulation master of simulation multistage fracturing horizontal well is split Seam and simulation time crack are immersed in copper-bath, and two mouth molds intend multistage fracturing horizontal well and are connected to constant pressure by wire respectively The low-pressure end and high-pressure side of dc source, voltmeter wire are connected with constant-voltage DC source and the probe.
2. a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means, its feature according to claim 1 It is:The simulation multistage fracturing horizontal well includes dummy level pit shaft, simulation major fracture, simulation time crack, simulation water horizontal well The horizontal segment of cylinder is welded with simulation time crack provided with simulation major fracture, simulation major fracture.
3. a kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means, its feature according to claim 1 It is:The simulation time crack is made up of the copper wire of 1 millimeter of diameter.
CN201720117917.9U 2017-02-09 2017-02-09 A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means Expired - Fee Related CN206487457U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720117917.9U CN206487457U (en) 2017-02-09 2017-02-09 A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720117917.9U CN206487457U (en) 2017-02-09 2017-02-09 A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means

Publications (1)

Publication Number Publication Date
CN206487457U true CN206487457U (en) 2017-09-12

Family

ID=59764070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720117917.9U Expired - Fee Related CN206487457U (en) 2017-02-09 2017-02-09 A kind of low-permeability oil deposit multistage fracturing horizontal well pressure field distribution analogue means

Country Status (1)

Country Link
CN (1) CN206487457U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110988041A (en) * 2019-12-26 2020-04-10 中国石油大港油田勘探开发研究院 Low-permeability condensate gas reservoir productivity testing device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110988041A (en) * 2019-12-26 2020-04-10 中国石油大港油田勘探开发研究院 Low-permeability condensate gas reservoir productivity testing device and method
CN110988041B (en) * 2019-12-26 2022-04-08 中国石油大港油田勘探开发研究院 Low-permeability condensate gas reservoir productivity testing device and method

Similar Documents

Publication Publication Date Title
CN105888630B (en) Method for improving recovery efficiency by huff-puff oil recovery of tight oil fracturing horizontal well
CN106321054B (en) A kind of acid fracturing method of carbonate reservoir
CN107965305B (en) Layered repeated fracturing method
CN106246150B (en) Oil field fracturing transformation method
CN106437674B (en) Imitative water injection of horizontal well well pattern adaptation method
CN110318675A (en) A kind of Deep Coalbed Methane heat is total to mining method
WO2016082188A1 (en) Hot dry rock multi-cycle heating system and production method therefor
CN109838223A (en) A kind of volume fracturing method of deep layer complexity shale gas
CN109458168A (en) Composite temporary plugging diversion fracturing method for improving productivity of gas well in sandstone reservoir
CN104141481A (en) Horizontal well spacing method for ultra-low permeability tight reservoir
CN104314569B (en) The exploitation method of a kind of deep Pore brine and low-grade solid kalium mine
CN113738317A (en) Method for combined exploitation of deep coal bed gas and dry hot rock type geothermal
CN105443121A (en) Carbonate acidizing and fracturing simulation sample, preparation method, simulation device and method
CN105181927B (en) The hypotonic coal seam hydraulic fracture simulation experiment method of multi- scenarios method
CN106194244A (en) Lower permeability seam liquid phase CO2phase transformation fracturing is anti-reflection grid type gas pumping method
CN104100245B (en) Method for screening and evaluating artificial edge water drive fault block oil reservoir
CN109505577B (en) Method for exploiting dry hot rock
CN109209306A (en) Horizontal well CO injection for ultra-low permeability tight oil reservoir2Asynchronous throughput energy supplementing method
CN103206199A (en) Device and method for exploiting natural gas hydrates by means of thermal fluid fracturing
CN106761612B (en) The asynchronous water injection oil extraction method of double different wells of pressure break horizontal well of zip mode cloth seam
CN206071560U (en) Variable seam is wide to stitch net device
Kaijun et al. Three-dimensional physical modeling of waterflooding in metamorphic fractured reservoirs
CN107939357A (en) Improve oilfield development system efficiency method
CN108661616B (en) Layered fracturing method suitable for sandstone oil and gas reservoir
CN107780913A (en) A kind of horizontal wellbore passes through the normal pressure shale gas volume fracturing method of multilayer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170912

Termination date: 20180209

CF01 Termination of patent right due to non-payment of annual fee