CN206461552U - Take root formula photovoltaic plate solar TRT in a kind of desert region - Google Patents
Take root formula photovoltaic plate solar TRT in a kind of desert region Download PDFInfo
- Publication number
- CN206461552U CN206461552U CN201720178749.4U CN201720178749U CN206461552U CN 206461552 U CN206461552 U CN 206461552U CN 201720178749 U CN201720178749 U CN 201720178749U CN 206461552 U CN206461552 U CN 206461552U
- Authority
- CN
- China
- Prior art keywords
- plate
- concrete
- steel pipe
- mounting bracket
- hydraulic cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Formula photovoltaic plate solar TRT is taken root the utility model discloses a kind of desert region, including solar energy photovoltaic panel, installing plate, fixed plate, mounting bracket, steel plate, steel pipe, concrete, hydraulic cylinder, solar energy photovoltaic panel is arranged on installing plate by fixed buckle, installing plate is arranged in the fixed plate in mounting bracket, mounting bracket is welded on hydraulic cylinder, hydraulic cylinder is fixedly mounted on the steel plate of concrete top screw fastening, penstock installation is in the penstock installation hole of concrete side, this construction prefabricated concrete block in factory according to drawing requirement, and reserved penstock installation hole, after installation site of having good positioning at the construction field (site), ground is done to put down with spade and chooses the height for taking root stake;Ensure that the center for taking root stake of a construction body is horizontal flat hard straight;It is all to take root planar horizontal in stake;The small-sized electric such as workman's impact drill equipment or sledgehammer, galvanized steel pile tube is driven underground in soil along prefabricated hole, and the present apparatus is applied to the installation of desert region solar power plant.
Description
Technical field
The utility model is related to solar energy mechanical field, and the generating of formula photovoltaic plate solar is taken root in particularly a kind of desert region
Device.
Background technology
, can be again as representative using solar energy, wind energy as oil, natural gas are reduced year by year for the fossil fuel yield of representative
The raw energy is increasingly paid attention to by countries in the world.Nowadays, solar energy has turned into the maximum regenerative resource of the market share, the mankind
Desert is extended to from the sky to the utilization scene of solar energy, due to the sandy soil property of desert in itself, device of solar generating is installed
Compare consuming man-hour, conventional installation cost is higher.
Utility model content
The purpose of this utility model is to overcome the shortcoming of prior art to take root formula photovoltaic panel too there is provided a kind of desert region
Positive energy TRT.The utility model uses following technical scheme to achieve the above object:
Take root formula photovoltaic plate solar TRT, including solar energy photovoltaic panel, installing plate, fixation in a kind of desert region
Plate, mounting bracket, steel plate, steel pipe, concrete, hydraulic cylinder, solar energy photovoltaic panel are arranged on installing plate by fixed buckle, peace
Fill in the fixed plate that plate is arranged in mounting bracket, mounting bracket is welded on hydraulic cylinder, and hydraulic cylinder is fixedly mounted on concrete
On the steel plate of top screw fastening, penstock installation is in the penstock installation hole of concrete side.
It is preferred that, the concrete top has been drilled with the fixation screw hole for installing steel plate.
It is preferred that, the steel pipe uses hot galvanized steel pipe, and three kinds of forms of steel pipe lower end are:4 points of sharp formulas, 45 degree of slope formulas,
45 degree of taper types.
It is preferred that, 4 millimeters of 50 millimeters of diameter Ф, wall thickness, the length 1.4m/ roots of the steel-pipe pile;Totally four.
Compared with prior art, the utility model has advantages below:This construction according to drawing requirement in factory it is pre-
Make after concrete block, and reserved penstock installation hole, installation site of having good positioning at the construction field (site), flat selection is done on ground with spade
The height of stake is taken root well;Ensure that the center for taking root stake of a construction body is horizontal flat hard straight;It is all to take root planar horizontal in stake;Workman
With the small-sized electric such as impact drill equipment or sledgehammer, galvanized steel pile tube is driven underground in soil along prefabricated hole, the present apparatus is applicable
In the installation of desert region solar power plant;Construction is fast, solar energy photovoltaic panel fixing-stable.
Brief description of the drawings
Fig. 1 is the structural representation that formula photovoltaic plate solar TRT is taken root in the utility model desert region.
Fig. 2 is the structural representation of the utility model concrete.
Fig. 3 is the structural representation of 45 degree of vertebra degree formula steel pipes of the utility model.
Fig. 4 is the structural representation of 45 degree of slope formula steel pipes of the utility model.
Fig. 5 is the structural representation of the sharp formula steel pipe of 4 points of the utility model.
In figure:1st, solar energy photovoltaic panel, 2, installing plate, 3, fixed plate, 4, mounting bracket, 5, steel plate, 6, steel pipe, 7, coagulation
Soil, 8, hydraulic cylinder, 9, fixation screw hole, 10, penstock installation hole.
Embodiment
The utility model is further elaborated with specific embodiment below in conjunction with the accompanying drawings.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4 and Fig. 5, formula photovoltaic plate solar TRT is taken root in a kind of desert region, bag
Include solar energy photovoltaic panel 1, installing plate 2, fixed plate 3, mounting bracket 4, steel plate 5, steel pipe 6, concrete seven, hydraulic cylinder 8, solar energy
Photovoltaic panel 1 is arranged on installing plate 2 by fixed buckle, and installing plate 2 is arranged on the fixed plate 3 in mounting bracket 4 by bolt
On, mounting bracket 4 is welded on hydraulic cylinder 8, and hydraulic cylinder 8 is mounted by means of bolts on the steel of concrete seven top screw fastening
On plate 5, steel pipe 6 is arranged in the penstock installation hole 10 of concrete seven side.
The concrete seven top has been drilled with uses screw hole 9 for installing the fixed of steel plate 5.The steel pipe 6 uses galvanizing
Steel pipe, three kinds of forms of the lower end of steel pipe 6 are:4 points of sharp formulas, 45 degree of slope formulas, 45 degree of taper types.The diameter Ф 50 of the steel pipe 6
Millimeter, 4 millimeters of wall thickness, length 1.4m/ roots;Totally four.
Utility model works principle:This construction prefabricated concrete block in factory according to drawing requirement, and reserve
After penstock installation hole, installation site of having good positioning at the construction field (site), ground is done to put down with spade choosing the height for taking root stake;Ensure
The center for taking root stake of one construction body is horizontal flat hard straight;It is all to take root planar horizontal in stake;The small-sized electrics such as workman's impact drill
Equipment or sledgehammer, galvanized steel pile tube is driven underground in soil along prefabricated hole, and the present apparatus is sent out suitable for desert region solar energy
The installation of electric equipment.Specific work process is:
1st, the making and maintenance of solidifying native stake are taken root.It is precast concrete foundation to take root solidifying native stake, with pre-embedded steel slab and pre-buried
The concrete block of part dowel is machined in factory.Penstock installation hole need to be reserved according to design drawing during prefabrication;With elder generation
Ready-made template four sides is made to buckle well;The reinforcing bar of 6 mm dias tied is put into mould frame again;Ensure reinforcing bar away from template side
Following there are 4 centimeters of distance, the position made by direction with upper;The plastic tube four of the mm dia of diameter 55 is plugged, with 3,
2nd, 1 ratio(3 sand, 2 stone diameter, 1 centimetre of 1 cement);Poured into after being mixed with water in template;Template is folded down after waiting 72 hours
It can be used within 22 days with water curing.
2nd, the transport of solidifying native stake is taken root.Concrete block final set is treated, project scene is sent to, concrete block is steadily placed
In basic point;Upper plane wants level;
3rd, the construction of solidifying native stake is taken root.Galvanized steel pile tube is inserted to reserved hole.Workman is this with similar impact drill
Small-sized electric equipment(Electrical equipment is carried by unit in charge of construction), galvanized steel pile tube is driven underground in soil along prefabricated hole;
4th, the detection for taking root solidifying native stake is coordinated.Detection unit is coordinated to carry out taking root a stress performance detection;Prefabricated C30 arrangements of reinforcement
Concrete block 210*460*460, construction content require adjustment, construction quality must in construction to be defined shown in drawing according to owner
National regulation, drawing and owner must be met to require.
5th, take root steel plate above concrete-pile can be drilled with into Luo Zhu mounting holes be convenient to install leveling.
6th, steel pipe upper end with steel plate soldering and sealing to prevent raindrop erosion(Steel pipe uses galvanizing)Three kinds of steel pipe lower end form four
Sharp 45 degree of formula, 45 degree of the slope formula taper type of point.
7th, the vertical hack lever of mounting bracket two is welded on two hydraulic cylinders, and two tilt linkages of mounting bracket pass through rotating shaft
Connection is installed, by adjusting the height of hydraulic cylinder, can directly adjust the height of two vertical hack levers, and then adjust solar energy tabula rasa
Irradiating angle.
Described above is the utility model preferred embodiment, for the ordinary skill in the art, according to this reality
With new teaching, in the case where not departing from principle of the present utility model and spirit, the change that is carried out to embodiment, repair
Change, replace and modification is still fallen within protection domain of the present utility model.
Claims (4)
1. formula photovoltaic plate solar TRT is taken root in a kind of desert region, it is characterised in that including solar energy photovoltaic panel(1)、
Installing plate(2), fixed plate(3), mounting bracket(4), steel plate(5), steel pipe(6), concrete(7), hydraulic cylinder(8), solar energy
Lie prostrate plate(1)Installing plate is arranged on by fixed buckle(2)On, installing plate(2)Mounting bracket is arranged on by bolt(4)On consolidate
Fixed board(3)On, mounting bracket(4)It is welded on hydraulic cylinder(8)On, hydraulic cylinder(8)It is mounted by means of bolts on concrete(7)Top
Hold the steel plate of screw fastening(5)On, steel pipe(6)Installed in concrete(7)The penstock installation hole of side(10)It is interior.
2. formula photovoltaic plate solar TRT is taken root in a kind of desert region according to claim 1, it is characterised in that institute
State concrete(7)Top has been drilled with for installing steel plate(5)Fixation screw hole(9).
3. formula photovoltaic plate solar TRT is taken root in a kind of desert region according to claim 1, it is characterised in that institute
State steel pipe(6)Using hot galvanized steel pipe, steel pipe(6)Three kinds of forms of lower end are:4 points of sharp formulas, 45 degree of slope formulas, 45 degree of taper types.
4. formula photovoltaic plate solar TRT is taken root in a kind of desert region according to claim 1, it is characterised in that institute
State steel pipe(6)50 millimeters of diameter Ф, 4 millimeters of wall thickness, the length 1.4m/ roots of stake;Totally four.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720178749.4U CN206461552U (en) | 2017-02-27 | 2017-02-27 | Take root formula photovoltaic plate solar TRT in a kind of desert region |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720178749.4U CN206461552U (en) | 2017-02-27 | 2017-02-27 | Take root formula photovoltaic plate solar TRT in a kind of desert region |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206461552U true CN206461552U (en) | 2017-09-01 |
Family
ID=59690254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720178749.4U Expired - Fee Related CN206461552U (en) | 2017-02-27 | 2017-02-27 | Take root formula photovoltaic plate solar TRT in a kind of desert region |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206461552U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106602980A (en) * | 2017-02-27 | 2017-04-26 | 山东鑫宏光电科技有限公司 | Desert land root-type photovoltaic panel solar power generation device |
-
2017
- 2017-02-27 CN CN201720178749.4U patent/CN206461552U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106602980A (en) * | 2017-02-27 | 2017-04-26 | 山东鑫宏光电科技有限公司 | Desert land root-type photovoltaic panel solar power generation device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10253473B2 (en) | Rock anchor foundation structure suitable for mountain photovoltaic module and construction method of rock anchor foundation structure | |
CN103195158B (en) | Municipal drainage pipeline slurry balance pipe-jacking construction method | |
CN205152976U (en) | Marine precast concrete cushion cap wind turbine foundation | |
CN101555689B (en) | Method and device for pre-consolidating mixed hydraulically-filled soft soil foundation | |
CN104762937B (en) | A kind of pumped-storage power station being applied to ecological reservoir and sewage water treatment method thereof | |
CN103046557A (en) | Foundation pit water-sealing supporting method by using long spiral cement soil mixing structural steel pile | |
CN100363560C (en) | Method for treating collapsed road surface around inspection-pit for underground lines | |
CN102322155B (en) | Unconcerned table Great Wall extra large, multi-functional and Prevention of Sandstorm | |
CN103938644A (en) | Prefabricated concrete bearing platform with reserved pile nest holes and fabricated multi-pile foundation installation method based on prefabricated concrete bearing platform with reserved pile nest holes | |
CN201826325U (en) | Foundation structure of tower crane | |
CN108035376A (en) | A kind of resistance to deformation suitable for goaf place Wind turbines can rectify a deviation basis and its construction method | |
CN106602980A (en) | Desert land root-type photovoltaic panel solar power generation device | |
CN205171528U (en) | Recoverable underground structure | |
CN102251537A (en) | Construction method for installing block slurry of sizing block by equipment | |
CN103015429A (en) | Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method | |
CN101597888A (en) | Construction method of municipal drainage culvert sinking trough | |
CN114484073B (en) | Artificial pipe jacking construction method | |
CN206461552U (en) | Take root formula photovoltaic plate solar TRT in a kind of desert region | |
CN202117073U (en) | Eccentric assembly type foundation of transmission line tower | |
CN205329709U (en) | Mountain region photovoltaic support foundation structure | |
CN102628277B (en) | Transition section-free monopile offshore wind turbine foundation structure | |
CN206503157U (en) | The embedding rock mixing pile foundation of offshore wind farm | |
CN203498860U (en) | Anchor rod foundation structure with concrete blocks for photovoltaic module brackets | |
CN110144872B (en) | Horizontal dynamic consolidation drainage device and construction method | |
CN208056088U (en) | A kind of resistance to deformation suitable for goaf place Wind turbines can rectify a deviation basis |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170901 Termination date: 20180227 |
|
CF01 | Termination of patent right due to non-payment of annual fee |