CN206458068U - Vertical equipment assembly platform - Google Patents

Vertical equipment assembly platform Download PDF

Info

Publication number
CN206458068U
CN206458068U CN201720063404.4U CN201720063404U CN206458068U CN 206458068 U CN206458068 U CN 206458068U CN 201720063404 U CN201720063404 U CN 201720063404U CN 206458068 U CN206458068 U CN 206458068U
Authority
CN
China
Prior art keywords
arc plate
plate
screw rod
vertical equipment
assembly platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720063404.4U
Other languages
Chinese (zh)
Inventor
王朝岭
姜友发
乔占永
徐林刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG QILU PETROCHEMICAL CONSTRUCTION CO Ltd
Original Assignee
SHANDONG QILU PETROCHEMICAL CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG QILU PETROCHEMICAL CONSTRUCTION CO Ltd filed Critical SHANDONG QILU PETROCHEMICAL CONSTRUCTION CO Ltd
Priority to CN201720063404.4U priority Critical patent/CN206458068U/en
Application granted granted Critical
Publication of CN206458068U publication Critical patent/CN206458068U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model, which is primarily adapted for use in outside the vertical equipment of all size, is being formed a team, weld seam is welded, work in terms of polishing, more particularly to a kind of vertical equipment assembly platform, including spaced apart first arc plate and the second arc plate, pass through hinge between the first adjacent arc plate and the second arc plate, the two ends of first arc plate set the installing plate stretched out, second arc plate two ends correspondence installing plate sets mounting groove, mounting hole is set respectively on installing plate and mounting groove, bearing pin is installed in mounting hole, the medium position of first arc plate and the second arc plate is radially arranged connecting hole, screw rod is installed in connecting hole, screw rod end sets attaching nut.The utility model shortens the engineering time.Original scaffold building, remove and need about 7 people 3~4 days to complete altogether, it is now this to only need to 2~3 people and complete for 1 day.

Description

Vertical equipment assembly platform
Technical field
The utility model is related to a kind of vertical equipment assembly platform, is primarily adapted for use in outside the vertical equipment of all size Portion is being formed a team, weld seam welding, the work in terms of polishing.
Background technology
Shandong Qilu Petrochemical Construction Co., Ltd. in 2015 is split in Shengli Refinery petrol and diesel oil upgrading (S-ZroB) and catalysis Change project construction, which has been built, is mounted with 6 towers, it is necessary to be divided to two sections to transport field assembly installation to.According to the original vertical equipment of my company Conventional construction method, be that scaffold from bottom to top is set up outside vertical equipment, equipment to be grouped, welding, polishing The work such as weld seam, Non-Destructive Testing, it is contemplated that so the amount of setting up of construction scaffolding is quite big, typically set up and remove a frame Son needs people more than 6 dry 3~4 days altogether, and with the increase of device diameters and height, the manpower and time for setting up and removing scaffold are got over Many, security risk, the influence of duration are big.
Utility model content
The technical problems to be solved in the utility model is:There is provided it is a kind of shorten construction period, increase security, flexibility and Versatility, reduces the vertical equipment assembly platform of total time of construction influence.
Vertical equipment assembly platform described in the utility model, including spaced apart first arc plate and the second arc Plate, by hinge between the first adjacent arc plate and the second arc plate, the two ends of the first arc plate set the installing plate stretched out, the Two arc plate two ends correspondence installing plate is set sets mounting pin in mounting hole, mounting hole respectively on mounting groove, installing plate and mounting groove The medium position of axle, the first arc plate and the second arc plate, which is radially arranged in connecting hole, connecting hole, installs screw rod, and screw rod end, which is set, to be connected Connected nut.
The first described arc plate and the second arc plate use steel plate.
Described screw head sets through hole.
High-altitude group is sub-assembly to frock, each other using types of attachment such as screw rod, bearing pins so that Assembling is simple Change and high-speeding.Single part weight is controlled within 25kg, and to ensure that it is dynamic that 1 people can be easier to take, 2~3 people are Can smoothly it be completed., can be with design using link form to ensure the vertical equipment for adapting to multiple diameter as far as possible The vertical equipment of different-diameter is adapted to by adjusting bolt or carrier bar quantity;Due to being in ground assembling, using can after finishing It is smaller than setting up scaffold security risk so that by removing a bearing pin, ground decomposition is adjusted to crane, using artificial few.This work Dress uses chain structure, good, the system safety and stability of rigidity, and to set up scaffold high for security ratio when using.
The beneficial effects of the utility model are:
1st, the engineering time is shortened.Original scaffold building, dismounting need about 7 people to complete for 3~4 days altogether, now this Only needing to 2~3 people can complete for 1 day.
2nd, highly versatile, produces once, and is used for multiple times, economical and practical.
3rd, the stability of a system is good, and security risk is small.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the structural representation of the first arc plate in Fig. 1.
Fig. 3 is Fig. 2 overlooking the structure diagram.
Fig. 4 is the structural representation of the second arc plate in Fig. 1.
Fig. 5 is Fig. 4 overlooking the structure diagram.
Fig. 6 is the structural representation of screw rod in Fig. 1.
In figure:1st, the first arc plate;2nd, bearing pin;3rd, the second arc plate;4th, attaching nut;5th, screw rod;6th, installing plate;7th, install Hole;8th, mounting groove;9th, connecting hole;10th, through hole.
Embodiment
The utility model is described further below in conjunction with the accompanying drawings:
As shown in Fig. 1~Fig. 6, vertical equipment assembly platform described in the utility model, including spaced apart One arc plate 1 and the second arc plate 3, are hinged, the two of the first arc plate 1 between the first adjacent arc plate 1 and the second arc plate 3 by bearing pin 2 The installing plate 6 for setting and stretching out is held, the two ends of the second arc plate 3 correspondence installing plate 6 is set to be divided on mounting groove 8, installing plate 6 and mounting groove 8 Not She Zhi mounting hole 7, bearing pin 2 is installed, the medium position of the first arc plate 1 and the second arc plate 3 is radially arranged connecting hole in mounting hole 7 9, connecting hole 9 is interior to install screw rod 5, and the end of screw rod 5 sets attaching nut 4.First arc plate 1 and the second arc plate 3 use steel plate.Spiral shell The head of bar 5 sets through hole 10.
Use process:
First the first arc plate 1, the second arc plate 3 and screw rod 5, attaching nut 4 are assembled and according to the diameter of vertical equipment alone Coarse adjustment screw rod 5.
The assembly of the first arc plate 1, the second arc plate 3, screw rod 5, attaching nut 4 are being stood with bearing pin 2, pad, split pin Connected on formula equipment is cylindrical.
Accurate adjustment screw rod 5 so that arc plate cycle basis sheet is coaxial with equipment, tightens adjustment attaching nut 4 after screw rod 5, makes connection spiral shell The spacing of mother 4 and equipment outer wall is hanger angle steel thickness.
Brandreth plate is spread after mounting hung rack, protection railing is set up, so whole group just completes to frock.

Claims (3)

1. a kind of vertical equipment assembly platform, it is characterised in that:Including spaced apart first arc plate (1) and the second arc plate (3), it is hinged between the first adjacent arc plate (1) and the second arc plate (3) by bearing pin (2), the two ends of the first arc plate (1), which are set, stretches The installing plate (6) gone out, second arc plate (3) two ends correspondence installing plate (6) sets mounting groove (8), installing plate (6) and mounting groove (8) It is upper that the medium position that bearing pin (2), the first arc plate (1) and the second arc plate (3) are installed in mounting hole (7), mounting hole (7) is set respectively It is radially arranged in connecting hole (9), connecting hole (9) and screw rod (5) is installed, screw rod (5) end sets attaching nut (4).
2. vertical equipment assembly platform according to claim 1, it is characterised in that:First arc plate (1) and the second arc Plate (3) uses steel plate.
3. vertical equipment assembly platform according to claim 1, it is characterised in that:Screw rod (5) head sets through hole (10)。
CN201720063404.4U 2017-01-19 2017-01-19 Vertical equipment assembly platform Expired - Fee Related CN206458068U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720063404.4U CN206458068U (en) 2017-01-19 2017-01-19 Vertical equipment assembly platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720063404.4U CN206458068U (en) 2017-01-19 2017-01-19 Vertical equipment assembly platform

Publications (1)

Publication Number Publication Date
CN206458068U true CN206458068U (en) 2017-09-01

Family

ID=59695689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720063404.4U Expired - Fee Related CN206458068U (en) 2017-01-19 2017-01-19 Vertical equipment assembly platform

Country Status (1)

Country Link
CN (1) CN206458068U (en)

Similar Documents

Publication Publication Date Title
CN207108387U (en) The adjustable maintenance hoisting frame of hoisting machinery
CN108425509B (en) Bolt ball joint net rack house steel structure replacement rod piece and bolt ball construction method
CN1987200A (en) Self unloading binding overhead torch, its loading and unloading system and its loading and unloading method
CN108002255A (en) Movable arm tower crane climbing beam support system and its application method
CN206458068U (en) Vertical equipment assembly platform
CN106239398A (en) Control arm lining endurancing fixture before a kind of
CN203235469U (en) Vertical type rapidly opened type pressure container inner part lifting mechanism
CN112211353A (en) Rope ladder for mounting metal roof panel and mounting method of metal roof panel
CN204282232U (en) Helicopter platform safety net
CN103663126B (en) A kind of detachable suspension hook group of hydraulic hoisting machine and the hoisting crane with this suspension hook group
DE202007018365U1 (en) Temporary paint booth
CN114837447A (en) Pushable overhanging horizontal protection device and construction method thereof
CN112903319A (en) Vibration testing device of wide-body vehicle
CN208763525U (en) A kind of anti-high wind composite electrical tower structure
CN106392997A (en) Detachment device for bottom flange cover of container
CN203390492U (en) Suspension supporting platform for detaching and installing large-scale diesel engine crankshaft bearing
DE102017128143B3 (en) Maintenance platform for maintenance of installations in a tower for a wind turbine and arrangement of a maintenance platform
CN102762804A (en) Telescopic structure and hoisting system thereof
RU172673U1 (en) COMPONENT STAND OF THE PLANE SUPPORT OF THE REM-500 METAL STRUCTURE
DE202018102433U1 (en) Support system for platforms in a tower of a wind turbine and tower with such a support system
CN204287566U (en) Lower sheave autocollimation device
CN212296725U (en) Wind generating set main frame climbing device and wind generating set
CN105297624B (en) Arch bridge inspection car rail device
CN220361200U (en) Detachable polytetrafluoroethylene grating
CN202924629U (en) Luffing jib tower crane and suspended platform thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170901

Termination date: 20190119