Utility model content
In order to solve in conventional art to set fabric filter filtered airflow to cause powder material in gas pressure balancing
The closing space easily reached by fabric filter below discharge bucket is unfavorable for the problem of tank container is subsequently used, this practicality
It is new to provide a kind of powder tank container.
The utility model provides a kind of powder tank container, including:
Tank body;
Discharge bucket, the bottom in the tank body, the discharge bucket has multiple flow guiding inclined plates, and the flow guiding inclined plate will
The inner space of tank body is divided into the closing space below the flow guiding inclined plate and the storage above the flow guiding inclined plate
Deposit space;
Admission line, is arranged on the outer side-lower of the tank body, and the admission line passes through the first branch pipe and closing space
Connection, the admission line is connected by the second branch pipe with the storage area;
Equalizing main, is arranged on the outside of the tank body, and the equalizing main connects the closing space and the storage
Check-valves is provided with space, the equalizing main;
When the gas pressure in the closing space exceedes the gas pressure in the storage area, the closing space
Interior gas is flowed into the storage area by the equalizing main.
Optionally, the equalizing main is connected on the admission line, and the equalizing main passes through the admission line
Connect first branch pipe.
Optionally, branch pipe check-valves is provided with the admission line, the flow direction of the branch pipe check-valves is the air inlet
The airintake direction of pipeline, second branch pipe is located between the branch pipe check-valves and the air inlet of the admission line.
Optionally, the equalizing main is connected directly between on first branch pipe.
Optionally, the equalizing main is connected by the 3rd branch pipe with the closing space, and the 3rd branch pipe is arranged on
On the outside of the tank body and one end of the 3rd branch pipe is connected from outside through the tank body with the closing space.
Optionally, the equalizing main includes the first balance pipe and the second balance pipe, and second balance pipe is placed on institute
State the top on the outside of tank body and connected with the storage area of the tank interior, first balance pipe is empty from the closing
Between connectivity part extend to the top of the tank body, and be connected with second balance pipe.
Optionally, the top in the tank body is provided with the first auxiliary blowing apparatus, first auxiliary blowing apparatus and described second flat
The pipe that weighs is connected, and exhaust outlet is provided with first auxiliary blowing apparatus, and the exhaust outlet is directed at the flow guiding inclined plate and the tank body
Junction.
Optionally, the top in the tank body is provided with the second auxiliary blowing apparatus, second auxiliary blowing apparatus and described second flat
The pipe that weighs is connected, and exhaust outlet is provided with second auxiliary blowing apparatus, and the exhaust outlet is directed at the sky below the manhole of the tank body
Between, to dispel the gradient of the material caused by angle of repose in charging.
Optionally, the discharge bucket has multiple, and second branch pipe has multiple, and every one second branch pipe and a discharge bucket connect
Lead to, and the exhaust outlet of second branch pipe is connected with the discharge bucket.
Optionally, the powder tank container also includes discharge duct, and the discharge duct includes multiple discharge branch pipes and common
With discharge duct, each discharge branch pipe is connected with shared discharge duct, and the discharging of each discharge branch pipe correspondence one discharge bucket of connection
Mouthful, the material in each discharge bucket passes through the discharge branch pipe and the outside discharging of shared discharge duct.
Optionally, the admission line is connected with the shared discharge duct, and gas enters institute by the admission line
State in shared discharge duct.
The technical scheme that embodiment of the present utility model is provided can include the following benefits:
The utility model outside tank body by setting equalizing pipe road, and it is oblique that equalizing main connection is located at water conservancy diversion respectively
Plate top, the storage area of lower section and closing space so that when the gas pressure in closing space exceedes the gas in storage area
During body pressure, the gas in closing space is flowed into storage area by equalizing main, to balance flow guiding inclined plate top, lower section
Gas pressure, and check-valves is set in equalizing main, prevents that the air-flow containing material passes through balance pipe in storage area
Road is back in closing space.Compared with conventional art, the utility model need not set fabric filter, and in balance water conservancy diversion
While swash plate top, underlying gas pressure, additionally it is possible to prevent powder material from entering in closing space.
It should be appreciated that the general description of the above and detailed description hereinafter are only exemplary, this can not be limited
Utility model.
Embodiment
In order to further illustrate principle of the present utility model and structure, it is preferable to carry out in conjunction with accompanying drawing to of the present utility model
Example is described in detail.
Powder tank container is used for transport particles or powdered material, for example, cement, flying dust or lime etc..Such as Fig. 1
Shown in Fig. 3, Fig. 1 is the structural representation of powder tank container of the present utility model, and Fig. 2 is the utility model powder pot type
The rear end structure schematic diagram of container, Fig. 3 is the front-end architecture schematic diagram of the utility model powder tank container.Powder pot type
Container 100 includes framework 20 and the tank body 10 in framework 20.Bottom inside tank body 10 is provided with multiple discharge buckets 11.
The bottom of discharge bucket 11 is provided with discharge gate, as shown in figure 3, being provided with blind flange 115 at discharge gate, after discharging terminates, leads to
Cross opening blind flange 115 and remove clout.The side wall of discharge bucket 11 is provided with discharging opening, and the discharging opening is located at the upper of the discharge gate
Side, the discharging opening is used to be connected with discharge duct.
Discharge bucket 11 includes multiple flow guiding inclined plates 111, and the plurality of flow guiding inclined plate 111, which is welded together to form, tapered to be gone out
Hopper 11.The top edge of flow guiding inclined plate 111 and the inwall of tank body 10 are welded, weld formation weld seam 112.
The inner space of tank body 10 is divided into two spaces spaced apart from each other by flow guiding inclined plate 111, that is, is divided into be located at and is led
The closing space 113 and the storage area 114 positioned at the top of flow guiding inclined plate 111 of the lower section of swash plate 111 are flowed, closing space 113 is by institute
There is flow guiding inclined plate 111 to be formed with the inwall of tank body 10 positioned at the lower section of flow guiding inclined plate 111.
Storage area 114 is formed by flow guiding inclined plate 111 with the inner tank wall positioned at the top of flow guiding inclined plate 111, and the storage is empty
Between 114 be used for store material.
Admission line 12 is arranged on the outside of tank body 10 and positioned at the lower section of tank body 10.The compressed gas that pump or compressor are produced
Entered by admission line 12 in tank body 10.
Admission line 12 connects closing space 113 by the first branch pipe 121, and empty by the connection storage of the second branch pipe 122
Between 114.
One end of first branch pipe 121 is connected with admission line 12, and the other end is connected through tank body 10 with closing space 113.
Second branch pipe 122 include it is multiple, the quantity of the second branch pipe 122 can be identical with the quantity of discharge bucket 11.One second
The exhaust outlet of branch pipe 122 is connected with discharge bucket 11, and discharge bucket 11 is blown.Make the goods fluid in discharge bucket 11, flow
Material after change is discharged by discharging opening and discharge duct 15.
Discharge duct 15 include multiple discharge branch pipes 152 and shared discharge duct 151, each discharge branch pipe 152 with shared discharging
Pipe 151 is connected, and correspondence one discharge bucket 11 of connection of each discharge branch pipe 152.Each discharge branch pipe 152 converges in material same
Share in discharge duct 151, and discharged material by sharing discharge duct 151.
Admission line 12 is connected by gas blow pipe 126 with shared discharge duct 151 so that the compressed gas in inlet pipeline 12
Blown by being entered in gas blow pipe 126 in shared discharge duct 151, and to sharing the material in discharge duct 151, to help
Material is discharged along shared discharge duct 151, accelerates discharge rate.
Powder tank container of the present utility model also includes equalizing main 13.Equalizing main 13 is arranged on the outer of tank body 10
Side, and the equalizing main 13 connection closing space 113 and storage area 114.
When the gas pressure in closing space 113 exceedes the gas pressure in storage area 114, in closing space 113
Gas flowed into by equalizing main 13 in storage area 114, to balance the gas of closing space 113 and storage area 114
Pressure.
In addition, being provided with check-valves 133 on equalizing main 13, the flow direction that check-valves 133 allows is by closing space 113
Storage area 114 is flowed to, to prevent that the gas backstreaming with powder is into equalizing main 13 in storage area 114.
When the atmospheric pressure in storage area 114 is too high, the gas in storage area 114 can't pass through equalizing main
13 flow back into closing space 113, in such cases, can be by opening the valve member at the top of tank body 10, to the gas of storage area 114
Body carries out pressure release, to reduce the gas pressure of storage area 114.
The mode of the connection closing space 113 of equalizing main 13 has a variety of, is exemplified below three kinds of modes:
First way, equalizing main 13 is connected by the 3rd branch pipe with closing space 113.3rd branch pipe is arranged on tank body
10 outsides, after one end of the 3rd branch pipe is from outside through the inner and outer wall of tank body 10, are connected with closing space 113.Balance pipe
Road 13 can be connected by connecting the 3rd branch pipe with closing space 113 so that when the gas pressure in closing space 113 is more than
During gas pressure in storage area 114, pass through equalizing main 13 and flow into storage area 114.
The second way, equalizing main 13 connects closing space 113 by way of being directly connected to the first branch pipe 121.The
One end of one branch pipe 121 is connected from outside through tank body 10 with the closing space 113 of tank interior, its other end and admission line
12 connections.Admission line 12 is blown by the first branch pipe 121 into closing space 113, the gas pressure in closing space 113 with
The increase of gas flow and raise, when the gas pressure in closing space 113 is more than the gas pressure in storage area 114,
Gas in closing space 113 is flowed out by the first branch pipe 121, and by equalizing main 13 to the low storage area 114 of pressure
Exhaust, thereby, the gas pressure in balance closing space 113 and storage area 114, and then balance the upper surface of flow guiding inclined plate 111
With the gas pressure of lower surface, prevent flow guiding inclined plate 111 from deforming.
The third mode, equalizing main 13 connects closing space 113 by the first branch pipe 121 with admission line 12.Balance
Pipeline 13 is connected on admission line 12, the first branch pipe 121 connection closing space 113 and admission line 12, thereby, equalizing main
13 connection closing spaces 113.When the gas pressure in closing space 113 is more than the gas pressure in storage area 114, closing
Gas in space 113 is vented by the first branch pipe 121 to admission line 12, and admission line 12 discharges the first branch pipe 121
Gas is blown by equalizing main 13 to the low storage area 114 of pressure.To balance in closing space 113 and storage area 114
Gas pressure.
In the third mode, branch pipe check-valves 123 is provided with admission line 12.The flow direction of branch pipe check-valves 123 is
The airintake direction of admission line 12, to prevent air inlet of the gas that the first branch pipe 121 is discharged along admission line 12 from discharging so that
The gas of first branch pipe 121 discharge is only by the row of equalizing main 13 to storage area 114.Second branch pipe 122 is located at branch pipe non-return
Between the air inlet of valve 123 and admission line 12.Specifically, along the airintake direction of admission line 12, on admission line 12 successively
Connect the second branch pipe 122, branch pipe check-valves 123, the branch pipe 121 of equalizing main 13 and first.Pressure release is additionally provided with admission line 12
Valve 124 and safety valve 125.In another embodiment, the second branch pipe 122, branch pipe check-valves 123, equalizing main 13 and first
The arrangement of pipe 121 can also be:Along the airintake direction of admission line 12, the second branch pipe 122, branch pipe check-valves are laid successively
123rd, the first branch pipe 121 and equalizing main 13.
In above-mentioned second and the third mode, the first branch pipe 121 is used to be vented, and is also used for air inlet, as shown in figure 1,
Arrow in first branch pipe 21 represents the flow direction of gas, that is, has the arrow flowed to inwards, also there is the arrow flowed outwardly toward.
It should be noted that, what the arrow in Fig. 1 in each pipeline was represented is the flow direction of gas or the flow direction of material.
Above-mentioned enumerate is mode that equalizing main 13 connects closing space 113, but is not limited to this, as long as balance pipe
Road 13 is arranged on outside tank body, and protection model of the present utility model is belonged to for connecting closing space 113 and storage area 114
Enclose.
Equalizing main 13 includes the first balance pipe 131 and the second balance pipe 132.Second balance pipe 132 is placed on tank body 10
Top, and outside the tank body 10.First balance pipe 131 extends to the top of tank body 10 from the connectivity part with closing space 113
Portion, and be connected with the second balance pipe 132.Wherein, the connectivity part of the first balance pipe 131 and closing space 113 can be first flat
Weigh the junction of pipe 131 and admission line 12 or the junction of the first balance pipe 131 and the 3rd branch pipe or
The junction of first balance pipe 131 and the first branch pipe 121.
The exhaust ports of second balance pipe 132 set the first auxiliary blowing apparatus.Multiple air drafts are provided with first auxiliary blowing apparatus
Mouthful, the junction of exhaust outlet alignment flow guiding inclined plate 111 and the inwall of tank body 10 is directed at flow guiding inclined plate 111 and the inwall of tank body 10
The weld seam 112 of formation.When tank body 10 carries out discharging, the gas in the second balance pipe 132 is by the exhaust outlet to flow guiding inclined plate
111 are blown with the junction of the inwall of tank body 10, are lumpd with dispelling the dead angle caused inside tank body 10 through transporting for a long time, with
Discharge rate is improved, discharging is reduced remaining.
In another embodiment, the exhaust ports of the second balance pipe 132 are additionally provided with the second auxiliary blowing apparatus, the second auxiliary blowing apparatus
On be provided with exhaust outlet, the space below the exhaust outlet alignment manhole of tank body 10, to dispel material caused by angle of repose in charging
The gradient.The manhole is located at the top of tank body 10, and tank body 10 can be fed by the manhole.
It is general, tank body 10 in charging, easily manhole a triangle formed below bank, block manhole,
Prevent material is from loading tank body 10, it is often necessary to which by manually carrying out flat material, the utility model blows dress by setting second to help
Put, the exhaust outlet of second auxiliary blowing apparatus dispels slope of the granule materials caused by angle of repose directly to being blown below manhole
Degree, it is to avoid artificial to carry out flat material, and then feed rate is improved, increase efficient loading amount.
The utility model outside tank body by setting equalizing pipe road, and it is oblique that equalizing main connection is located at water conservancy diversion respectively
Plate top, the storage area of lower section and closing space so that when the gas pressure in closing space exceedes the gas in storage area
During body pressure, the gas in closing space is flowed into storage area by equalizing main, to balance flow guiding inclined plate top, lower section
Gas pressure, and check-valves is set in equalizing main, prevents that the air-flow containing material passes through balance pipe in storage area
Road is back in closing space.
The utility model outside tank body by setting equalizing main and providing check valves to prevent storage in equalizing main
The material deposited in space is entered in closing space, is entered without setting fabric filter, can also be prevented powder material from entering
In closing space.
In addition, the utility model is also provided with the first auxiliary blowing apparatus at the top of tank body, when tank body carries out discharging, this
One auxiliary blowing apparatus is blown to the junction of flow guiding inclined plate and inner tank wall, is caused with dispelling tank interior through long-time transport
Dead angle caking, and then it is remaining to reduce discharging, improves discharge rate.
In addition, the utility model is provided with the second auxiliary blowing apparatus, when tank body is fed, second auxiliary blowing apparatus can
The gradient of the granule materials caused by angle of repose is dispelled in time, increases efficient loading amount.
Preferable possible embodiments of the present utility model are these are only, protection domain of the present utility model, all fortune is not limited
Changed with the equivalent structure made by the utility model specification and accompanying drawing content, be all contained in protection domain of the present utility model
It is interior.