CN206431077U - A kind of large scale pipeline powder coal weak ignition explosive test system - Google Patents

A kind of large scale pipeline powder coal weak ignition explosive test system Download PDF

Info

Publication number
CN206431077U
CN206431077U CN201720143859.7U CN201720143859U CN206431077U CN 206431077 U CN206431077 U CN 206431077U CN 201720143859 U CN201720143859 U CN 201720143859U CN 206431077 U CN206431077 U CN 206431077U
Authority
CN
China
Prior art keywords
dust
pipeline
large scale
test
hydraulic test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720143859.7U
Other languages
Chinese (zh)
Inventor
杨书召
杜学胜
王振江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Institute of Engineering
Original Assignee
Henan Institute of Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Institute of Engineering filed Critical Henan Institute of Engineering
Priority to CN201720143859.7U priority Critical patent/CN206431077U/en
Application granted granted Critical
Publication of CN206431077U publication Critical patent/CN206431077U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of large scale pipeline powder coal weak ignition explosive test system, including venting of dust explosion tank and hydraulic test pipeline;The wind-borne dust device that dusts, igniter, ventilating dust-arrester, vacuum extractor, test device and controller are connected with hydraulic test pipeline;The wind-borne dust device, igniter, the test device of dusting are connected with controller;Dust and air compressor is connected with the wind-borne dust device, the output channel of air compressor is provided with oil water separator;Hydraulic test pipeline both sides outer wall is provided with some mounting holes, and the upper surface of hydraulic test pipeline, which is provided with instrument connection, instrument connection, is provided with sensor.The utility model is simple in construction, ingenious in design, is worth with higher experiment.

Description

A kind of large scale pipeline powder coal weak ignition explosive test system
Technical field
The utility model is related to dust explosion experimental provision, and in particular to a kind of large scale pipeline powder coal weak ignition blast examination Check system.
Background technology
Dust explosion, refers to dust in the range of explosion limit, runs into thermal source(Naked light or temperature), flame moment propagated in whole Individual mixed dust space, chemical reaction velocity is exceedingly fast, while discharging substantial amounts of heat, bears very high temperature and very big pressure, The energy of system is converted into the radiation of mechanical work and light and heat, with very strong destructive power.And coal dust explosion is to threaten boiler Room personnel's personal safety and the main contributor of equipment loss.And existing coal dust pipe explosion experimental rig is mainly characterized by pipeline chi Very little internal diameter is in 100mm or so, and size is smaller, and ignition intensity is big(More than 10kJ chemical point burning things which may cause a fire disaster), coal dust cloud is difficult to be formed, dust Cloud Density Distribution is uneven, not reproducible etc., and experimental data is inaccurate, and realistic simulation effect is not good, is unfavorable for actual tunnel quick-fried The research of fried situation.
Utility model content
For the deficiency in above-mentioned background technology, the utility model explodes there is provided a kind of large scale pipeline powder coal weak ignition Pilot system, to solve that pipeline in the prior art is small, test accuracy is low, the repeatable technical problem such as strong.
The technical solution of the utility model is:A kind of large scale pipeline powder coal weak ignition explosive test system, including venting of dust explosion Tank and hydraulic test pipeline;The wind-borne dust device that dusts, igniter are connected with hydraulic test pipeline, ventilating dust-arrester, takes out true Empty device, test device and controller;The wind-borne dust device, igniter, the test device of dusting are connected with controller;Dust and raise Air compressor is connected with dirt device, the output channel of air compressor is provided with oil water separator;Hydraulic test pipeline two Side outer wall is provided with mounting hole, and the upper surface of hydraulic test pipeline, which is provided with instrument connection, instrument connection, is provided with sensor.
The wind-borne dust device that dusts includes shower nozzle, powder room, plenum chamber;Shower nozzle is arranged on the output end of powder room, high pressure gas Room is arranged on the input of powder room, and check valve is provided between shower nozzle and powder room, and magnetic valve is provided between plenum chamber and powder room, high The input of plenum chamber is provided with manually-operated gate, and manually-operated gate is connected with air compressor.
The shower nozzle is hollow hemispheric and is arranged in mounting hole;Airborne dust hole is evenly distributed with shower nozzle.
124 airborne dust holes are uniformly distributed on the shower nozzle, 124 airborne dust holes constitute the different concentric circles of six radiuses;Raise A diameter of 1.0 ~ 1.6mm in dirt hole.
One end of the hydraulic test pipeline is provided with fire hole, igniting dress by flangeseal, the center of ring flange Put and be connected by fire hole with hydraulic test pipeline;The other end of hydraulic test pipeline is connected with venting of dust explosion tank, hydraulic test Venting of dust explosion film is provided between pipeline and venting of dust explosion tank.
The length of the hydraulic test pipeline is 30 ~ 40m;The internal diameter of hydraulic test pipeline is 200 ~ 300mm.
The both sides of the hydraulic test pipeline are altogether provided with 18 independent the wind-borne dust devices that dust.
The sensor includes pressure sensor and temperature sensor.
The utility model is dusted the wind-borne dust device using large-diameter pipeline multiple spot, blast Dust Concentration is evenly distributed, coal amount Controllable, test explosive parameters are actual closer to tunnel blast, while because interior caliber size is big, coal dust cloud easily forms and reaches blast Concentration, can be put quick-fried using weak ignition energy, it is to avoid the problems such as the formula test of the chemical incendiary source of big energy, decreased and adopted Collect error of the data caused by ignition energy is big.Using this invention device, coal dust-air mixture is not only solved in weakness Fire(40J)Under the conditions of combustion explosion the problem of be difficult to realize, and test accuracy is high, and repeatability is strong, for research pipeline Simulate tunnel detonation propagation and provide new method and approach.The utility model is simple in construction, ingenious in design, with higher examination Test value.
Brief description of the drawings
Fig. 1 is the utility model structural representation,
Fig. 2 is the utility model shower nozzle schematic diagram.
Embodiment
Embodiment 1:As shown in Figure 1-2, a kind of large scale pipeline powder coal weak ignition explosive test system, including venting of dust explosion tank 1 With hydraulic test pipeline 16;Be connected with hydraulic test pipeline 16 the wind-borne dust device that dusts, igniter 5, ventilating dust-arrester 4, Vacuum extractor 3, test device 7 and controller 6;The wind-borne dust device, igniter 5, the test device 7 of dusting with the phase of controller 6 Connection;Ventilating dust-arrester 4 mainly after each experiment is finished, removes the product and unreacted dust in pipeline.Take out true Empty device 3 is vavuum pump, for taking out certain vacuum, vacuum meter 0~0.1MPa of range, to ensure in advance to pipeline before the test When the wind-borne dust device that dusted in process of the test is ejected into horizontal pipe by high pressure draught entrainment of dust, the pressure in pipe is normal Pressure condition.Dust and air compressor 2 is connected with the wind-borne dust device, the output channel of air compressor 2 is provided with oil water separator 19;Oil water separator removes the moisture in air in the course of conveying of compressed air, is dry air with ensure conveying, together When avoid being mixed into impurity in compressed air the electrical parts such as magnetic valve caused damage.The both sides outer wall of hydraulic test pipeline 16 is provided with Some mounting holes 17, the upper surface of hydraulic test pipeline 16, which is provided with instrument connection 18, instrument connection 18, is provided with sensor 20.Control Device 6 includes delayed injection controller and firing delay controller two parts, for controlling magnetic valve to open, light a fire and triggering Dynamic Data Acquiring analysis system start recording.Test device 7 is by pressure sensor, sensor adapter, the high quick-actions of TST6300 State tester Dynamic Data Acquiring analysis system is constituted, and mainly coal dust-air mixture blast pressure, flame ripple etc. are exploded and joined Number communication process carries out experimental test research.
Further preferably, the wind-borne dust device that dusts includes shower nozzle 21, powder room 9, plenum chamber 11;Shower nozzle 21 is arranged on powder room 9 Output end, plenum chamber 11 be arranged on powder room 9 input, between shower nozzle 21 and powder room 9 be provided with check valve 13, plenum chamber Magnetic valve 10 is provided between 11 and powder room 9, the input of plenum chamber 11 is provided with manually-operated gate 12, manually-operated gate 12 and air pressure Contracting machine 2 is connected.
Further preferably, shower nozzle 21 is hollow hemispheric and is arranged in mounting hole 17;It is evenly distributed with and raises on shower nozzle 21 Dirt hole 22.
Further preferably, 124 airborne dust holes are uniformly distributed on shower nozzle 21, it is different that 124 airborne dust holes constitute six radiuses Concentric circles, is axially and radially evenly distributed with the dust cloud concentration ensured in hydraulic test pipeline along pipeline;Airborne dust hole 22 it is straight Footpath is 1.0 ~ 1.6mm.
Further preferably, one end of hydraulic test pipeline 16 is sealed by ring flange 15, and the center of ring flange 15 is provided with Fire hole, igniter 5 is connected by fire hole with hydraulic test pipeline 16;The other end and venting of dust explosion of hydraulic test pipeline 16 Tank 1 is connected, and venting of dust explosion film is provided between hydraulic test pipeline 16 and venting of dust explosion tank 1.
Further preferably, the length of hydraulic test pipeline 16 is 30 ~ 40m;The internal diameter of hydraulic test pipeline 16 be 200 ~ 300mm。
Further preferably, the both sides of hydraulic test pipeline 16 are altogether provided with 18 independent the wind-borne dust devices that dust.
Further preferably, the ignition energy that igniter 5 is exported is 40J.
Further preferably, sensor 20 includes pressure sensor and temperature sensor, for measuring pressure and flare up fire, Blast wave is obtained along the pressure at different measuring points during pipe transmmision, flame, temperature and time course curve.
The course of work:Step one, install and dust the wind-borne dust device and close check valve 13, coal dust is fitted into powder room 9, install Venting of dust explosion film 8, connection air compressor 2, vacuum extractor 3, dust arrester 4, igniter 5, control system 6 and test device 7, close hand-operated valve 12, inspection system air-tightness;Ensure after system air-tightness, open hand-operated valve 12, close check valve 13;Then Start vacuum extractor and hydraulic test pipeline inner air pressure is evacuated to 0.03-0.06MPa;
Step 2, opens and starts air compressor 2 pressure-air press-in plenum chamber 11, be then shut off hand-operated valve 12, check valve 13 is opened, while starting control system 6, test device 7 and igniter 5, is gathered and automatic record data;
Step 3, closes check valve 13, starts dust arrester 4 until reaching test requirements document in pipeline.
It is described above, only the utility model preferably embodiment, but protection domain of the present utility model is not This is confined to, any one skilled in the art can readily occur in the technical scope that the utility model is disclosed Change or replacement, should all cover within protection domain of the present utility model.

Claims (8)

1. a kind of large scale pipeline powder coal weak ignition explosive test system, it is characterised in that:Including venting of dust explosion tank(1)And hydraulic test Pipeline(16);Hydraulic test pipeline(16)On be connected with the wind-borne dust device that dusts, igniter(5), ventilating dust-arrester(4), take out Vacuum plant(3), test device(7)And controller(6);Dust the wind-borne dust device, igniter(5), test device(7)With control Device processed(6)It is connected;Dust and be connected with air compressor on the wind-borne dust device(2), air compressor(2)Output channel be provided with Oil water separator(19);Hydraulic test pipeline(16)Both sides outer wall is provided with mounting hole(17), hydraulic test pipeline(16)It is upper Surface is provided with instrument connection(18), instrument connection(18)It is interior to be provided with sensor(20).
2. large scale pipeline powder coal weak ignition explosive test system according to claim 1, it is characterised in that:It is described to dust The wind-borne dust device includes shower nozzle(21), powder room(9), plenum chamber(11);Shower nozzle(21)Installed in powder room(9)Output end, high pressure Air chamber(11)Installed in powder room(9)Input, shower nozzle(21)With powder room(9)Between be provided with check valve(13), plenum chamber (11)With powder room(9)Between be provided with magnetic valve(10), plenum chamber(11)Input be provided with manually-operated gate(12), manually-operated gate (12)With air compressor(2)It is connected.
3. large scale pipeline powder coal weak ignition explosive test system according to claim 2, it is characterised in that:The shower nozzle (21)For hollow hemispheric and installed in mounting hole(17)It is interior;Shower nozzle(21)On be evenly distributed with airborne dust hole(22).
4. large scale pipeline powder coal weak ignition explosive test system according to claim 3, it is characterised in that:The shower nozzle (21)On be uniformly distributed 124 airborne dust holes, 124 airborne dust holes constitute the different concentric circles of six radiuses;Airborne dust hole(22)It is straight Footpath is 1.0 ~ 1.6mm.
5. large scale pipeline powder coal weak ignition explosive test system according to claim 1, it is characterised in that:The level Test pipe(16)One end by ring flange(15)Sealing, ring flange(15)Center be provided with fire hole, igniter(5) Pass through fire hole and hydraulic test pipeline(16)It is connected;Hydraulic test pipeline(16)The other end and venting of dust explosion tank(1)It is connected, Hydraulic test pipeline(16)With venting of dust explosion tank(1)Between be provided with venting of dust explosion film.
6. large scale pipeline powder coal weak ignition explosive test system according to claim 5, it is characterised in that:The level Test pipe(16)Length be 30 ~ 40m;Hydraulic test pipeline(16)Internal diameter be 200 ~ 300mm.
7. the large scale pipeline powder coal weak ignition explosive test system according to claim 1 or 5 or 6, it is characterised in that:Institute State hydraulic test pipeline(16)Both sides altogether provided with 18 independent the wind-borne dust devices that dust.
8. large scale pipeline powder coal weak ignition explosive test system according to claim 1, it is characterised in that:The sensing Device(20)Including pressure sensor and temperature sensor.
CN201720143859.7U 2017-02-17 2017-02-17 A kind of large scale pipeline powder coal weak ignition explosive test system Expired - Fee Related CN206431077U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720143859.7U CN206431077U (en) 2017-02-17 2017-02-17 A kind of large scale pipeline powder coal weak ignition explosive test system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720143859.7U CN206431077U (en) 2017-02-17 2017-02-17 A kind of large scale pipeline powder coal weak ignition explosive test system

Publications (1)

Publication Number Publication Date
CN206431077U true CN206431077U (en) 2017-08-22

Family

ID=59590106

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720143859.7U Expired - Fee Related CN206431077U (en) 2017-02-17 2017-02-17 A kind of large scale pipeline powder coal weak ignition explosive test system

Country Status (1)

Country Link
CN (1) CN206431077U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108535446A (en) * 2018-04-19 2018-09-14 河南工程学院 Pipeline gas explosion causes the experimental provision and method that deposit coal dust subsequent explosion
CN111879819A (en) * 2020-07-31 2020-11-03 上海化工研究院有限公司 Closed-loop circulating type volatile liquid explosion limit measuring device
CN113888947A (en) * 2021-08-31 2022-01-04 中国人民解放军陆军工程大学 Large-equivalent underground multipoint aggregation explosive bomb pit effect simulation device and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108535446A (en) * 2018-04-19 2018-09-14 河南工程学院 Pipeline gas explosion causes the experimental provision and method that deposit coal dust subsequent explosion
CN108535446B (en) * 2018-04-19 2023-08-22 河南工程学院 Experimental device and method for secondary explosion of deposited coal dust caused by gas explosion of pipeline
CN111879819A (en) * 2020-07-31 2020-11-03 上海化工研究院有限公司 Closed-loop circulating type volatile liquid explosion limit measuring device
CN113888947A (en) * 2021-08-31 2022-01-04 中国人民解放军陆军工程大学 Large-equivalent underground multipoint aggregation explosive bomb pit effect simulation device and method

Similar Documents

Publication Publication Date Title
CN206431077U (en) A kind of large scale pipeline powder coal weak ignition explosive test system
CN205426830U (en) Gas explosion causes coal dust explosion's analogue means
CN108802100B (en) Combustible gas explosion experimental device with concentration gradient and use method
CN203287341U (en) Explosion experiment device for unevenly distributed methane gas
CN103075270B (en) High-pressure-intensity external pulse excitation device for T-shaped burner
CN107064452B (en) Experimental device for simulating instantaneous burning and explosion of combustible gas and application method
CN102879427A (en) Multifunctional testing system for suppressing explosion of flammable gas by water mist and testing method implementing same
CN102935275B (en) A kind of test method and device evaluating total flooding extinguishing property
CN204594950U (en) The constant volume combustion system analyzed is detected for solid fuel ignition
CN201156037Y (en) Pyrotechnic compound combustion and explosion performance detector
CN109374677A (en) Combustible medium explosion limit fast testing system and method under a kind of high temperature and pressure
CN107247127A (en) Consider the spontaneous combustion in goaf model test platform and test method of atmospheric pressure
CN108535320A (en) The experimental system that goaf coal spontaneous combustion induces gas and coal dust list, repeatedly explodes
CN104931531A (en) Method for testing pressure during heating process of explosive and propellant columns
CN104181199A (en) Ignition energy variable completely-transparent pipeline gas explosion experiment platform and method
CN105181745A (en) Combustible gas explosion testing device in explosion venting space
CN109557277A (en) A kind of gas and dust explosive characteristic test device
CN111255723B (en) System and method for testing explosion-proof performance of explosion-proof fan
CN206906014U (en) A kind of inflammable gas pipeline spark arrester Performance Test System
CN115308263A (en) Coal mine early warning experimental equipment
CN206019982U (en) Gas burst pressure is produced and loading experimental apparatus
CN208606585U (en) For smoke exhaust fan high temperature resistant trial furnace
CN106226021A (en) Gas burst pressure produces and loading experimental apparatus
CN108389636A (en) Combustible gas explosion experiment system and method in a kind of small size pipeline
CN113552169A (en) Device and method for testing characteristic parameters of combustible gas flowing and blasting process

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170822

Termination date: 20180217