CN206368331U CN201621161007.2U CN201621161007U CN206368331U CN 206368331 U CN206368331 U CN 206368331U CN 201621161007 U CN201621161007 U CN 201621161007U CN 206368331 U CN206368331 U CN 206368331U
Authority
CN
China
Prior art keywords
steel plate
bridge
grouting pipe
crack
bracing means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621161007.2U
Other languages
Chinese (zh)
Inventor
焦美菊
刘建华
刘通
刘志
蔡雨阳
韦赛男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
Original Assignee
Zhengzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University filed Critical Zhengzhou University
Priority to CN201621161007.2U priority Critical patent/CN206368331U/en
Application granted granted Critical
Publication of CN206368331U publication Critical patent/CN206368331U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of Bridge Crack bracing means, including bridge main body, steel plate and bolt, the steel plate is covered in crack mouthful, the bolt-through Interal fixation is on bridge main body, the center of the steel plate is provided with injected hole, the lower end of the injected hole is vertically installed with Grouting Pipe, the Grouting Pipe is located in bridge main body, the surface of the Grouting Pipe is provided with several extravasating holes, the bottom of the steel plate is provided with vertical reinforcement, transverse steel is provided with the vertical reinforcement, the surface attachment of the steel plate has waterproof coating layer, the surface attachment of the waterproof coating layer has mixed mud layer, the Bridge Crack bracing means, construction is simple, it is easy to operate, cost is relatively low, so that bridge filling slurries diffusion is more uniform, maintenance axle casing crack no longer expands, and there is water-proof function at the crack, safety muchly plays its function.

Description

A kind of Bridge Crack bracing means
Technical field
The utility model is related to Bridge Crack reinforcement technique field, specially a kind of Bridge Crack bracing means.
Background technology
Bridge is after use year after year, and its structural behaviour is also all, in degeneration slowly, to have much The problem of side is damaged, also there is the situation in crack in bridge for example, is repaired in order to ensure the safety of bridge it is necessary to pass through Come more long, the structural crack occurred on bridge and the active fissure ratio that allows bridge to play its function and can use More difficult to repair, structural crack is the crack as caused by external load, and it is distributed and width is relevant with external load, and this crack goes out It is existing, it imply that structural bearing capacity is possible not enough or there are other serious problems, active fissure is fracture width in existing environment With under condition of work all the time can not stablize, easily with the stress of structural elements, deformation or environment temperature, humidity change and when, When the crack closed, both cracks are filled up after maintenance by common when repairing, can tieed up again former by shorter time crack The place of repairing occurs again, and fracture maintenance process again is needed again, and maintenance effect so again and again is not fine, and at crack It is non-watertight, there are infiltration or drainage, the safety to bridge causes certain hidden danger;
At present, maintenance is filled up to Bridge Crack, it is general that mixed mud, this filling mode, slurry are directly filled into crack Liquid diffusion is uneven, occur at the top of reinforcing body and the diffusion of edge fraction region slurries less than, containing part fissure-plane and sheet, The irregular structure such as bulk.
Utility model content
The purpose of this utility model is to provide a kind of Bridge Crack bracing means, to solve to propose in above-mentioned background technology The problem of.
To achieve the above object, the utility model provides following technical scheme:A kind of Bridge Crack bracing means, including bridge Beam main body, steel plate and bolt, the steel plate are covered in crack mouthful, and the bolt-through Interal fixation is described on bridge main body The center of steel plate is provided with injected hole, and the lower end of the injected hole is vertically installed with Grouting Pipe, and the Grouting Pipe is located at bridge In beam main body, the surface of the Grouting Pipe is provided with several extravasating holes, and the bottom of the steel plate is provided with vertical reinforcement, described Transverse steel is provided with vertical reinforcement.
It is preferred that, the surface attachment of the steel plate has waterproof coating layer, and the surface attachment of the waterproof coating layer has mixed mud Soil layer.
It is preferred that, the Grouting Pipe caliber is 35-45mm, and the aperture of the extravasating hole is 4-6mm.
It is preferred that, the extravasating hole assumes diamond in shape netted layout, the hanging down with two extravasating holes on one side positioned at rhombus Straight spacing is 10cm-18cm.
It is preferred that, the two ends of the steel plate are double-decker, and centre is single layer structure.
It is preferred that, the front end of the Grouting Pipe is insertion end, and the rear end of the Grouting Pipe is slip casting end, slip casting end end Mouth diameter is more than insertion end port diameter.
Compared with prior art, the beneficial effects of the utility model are:The utility model, crack is covered in by steel plate Mouthful, bolt-through Interal fixation is on bridge main body so that it is more firm that steel plate is fixed after the compression of bolt with bridge main body Gu, injected hole is provided with by the center of steel plate, the lower end of injected hole is vertically installed with Grouting Pipe, and the front end of Grouting Pipe is Insertion end, the rear end of Grouting Pipe is slip casting end, and slip casting end port diameter is more than insertion end port diameter, it is ensured that grouting pressure, The surface of Grouting Pipe is provided with several extravasating holes, makes the distribution of slurries more uniform, it is to avoid slurries directly flow out from slip casting end, There is waterproof coating layer by the surface attachment of steel plate, the surface attachment of waterproof coating layer has mixed mud layer so that have at the crack There is water-proof function, the Bridge Crack bracing means, construction is simple, and easy to operate, cost is relatively low so that bridge filling slurries diffusion It is more uniform, maintenance axle casing crack no longer expands, and has water-proof function at the crack, and safety muchly plays its work( Energy.
Brief description of the drawings
Fig. 1 is the utility model structural representation.
In figure:Bridge 1 beam main body, 2 steel plates, 3 bolts, 4 injected holes, 5 Grouting Pipes, 6 extravasating holes, 7 vertical reinforcements, 8 horizontal steel Muscle, 9 waterproof coating layers, 10 mixed muds layer.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belongs to the scope of the utility model protection.
Referring to Fig. 1, the utility model provides a kind of technical scheme:A kind of Bridge Crack bracing means, including bridge main Body 1, steel plate 2 and bolt 3, steel plate 2 are covered in crack mouthful, and the two ends of steel plate 2 are double-decker, and centre is single layer structure, bolt 3 It is fixed on through steel plate 2 on bridge main body 1, crack mouthful is covered in by steel plate 2, bolt 3 is fixed on bridge main body through steel plate 2 On 1 so that it is more firm that steel plate 2 is fixed after the compression of bolt 3 with bridge main body 1, and the center of steel plate 2 is provided with note Hole 4 is starched, the lower end of injected hole 4 is vertically installed with Grouting Pipe 5, and the front end of Grouting Pipe 5 is insertion end, and the rear end of Grouting Pipe 5 is note End is starched, slip casting end port diameter is more than insertion end port diameter, and Grouting Pipe 5 is located in bridge main body 1, and the surface of Grouting Pipe 5 is set Be equipped with several extravasating holes 6, extravasating hole 6 assumes diamond in shape netted layout, positioned at rhombus with two extravasating holes 6 on one side it is vertical between Away from for 10cm-18cm, the caliber of Grouting Pipe 5 is 35-45mm, and the aperture of extravasating hole 6 is 4-6mm, is installed by the centre bit of steel plate 2 Injected hole 4 is equipped with, the lower end of injected hole 4 is vertically installed with Grouting Pipe 5, after the front end of Grouting Pipe 5 is insertion end, Grouting Pipe 5 Hold as slip casting end, slip casting end port diameter is more than insertion end port diameter, it is ensured that grouting pressure, the surface of Grouting Pipe 5 is set There are several extravasating holes 6, make the distribution of slurries more uniform, it is to avoid slurries directly flow out from slip casting end, the bottom of steel plate 2 is set Have and transverse steel 8 is provided with vertical reinforcement 7, vertical reinforcement 7, the surface attachment of steel plate 2 has waterproof coating layer 9, water-repellent paint The surface attachment of layer 9 has mixed mud layer 10, has waterproof coating layer 9, the surface of waterproof coating layer 9 by the surface attachment of steel plate 2 It is attached with mixed mud layer 10 so that there is water-proof function at the crack.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out in the case where not departing from principle of the present utility model and spirit a variety of changes, repaiies Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of Bridge Crack bracing means, including bridge main body (1), steel plate (2) and bolt (3), it is characterised in that:The steel Plate (2) is covered in crack mouthful, and the bolt (3) is fixed on bridge main body (1) through steel plate (2), the center of the steel plate (2) Position is provided with injected hole (4), and the lower end of the injected hole (4) is vertically installed with Grouting Pipe (5), and the Grouting Pipe (5) is located at In bridge main body (1), the surface of the Grouting Pipe (5) is provided with several extravasating holes (6), and the bottom of the steel plate (2) is set Have and be provided with transverse steel (8) on vertical reinforcement (7), the vertical reinforcement (7).
2. a kind of Bridge Crack bracing means according to claim 1, it is characterised in that:The surface of the steel plate (2) is attached Waterproof coating layer (9), the surface attachment of the waterproof coating layer (9) has mixed mud layer (10).
3. a kind of Bridge Crack bracing means according to claim 1, it is characterised in that:Grouting Pipe (5) caliber is 35-45mm, the aperture of the extravasating hole (6) is 4-6mm.
4. a kind of Bridge Crack bracing means according to claim 1, it is characterised in that:The extravasating hole (6) assumes diamond in shape Netted layout, described is 10cm-18cm with the vertical interval of two extravasating holes (6) on one side positioned at rhombus.
5. a kind of Bridge Crack bracing means according to claim 1, it is characterised in that:The two ends of the steel plate (2) are Double-decker, centre is single layer structure.
6. a kind of Bridge Crack bracing means according to claim 1, it is characterised in that:The front end of the Grouting Pipe (5) For insertion end, the rear end of the Grouting Pipe is slip casting end, and slip casting end port diameter is more than insertion end port diameter.
CN201621161007.2U 2016-11-01 2016-11-01 A kind of Bridge Crack bracing means Expired - Fee Related CN206368331U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621161007.2U CN206368331U (en) 2016-11-01 2016-11-01 A kind of Bridge Crack bracing means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621161007.2U CN206368331U (en) 2016-11-01 2016-11-01 A kind of Bridge Crack bracing means

Publications (1)

Publication Number Publication Date
CN206368331U true CN206368331U (en) 2017-08-01

Family

ID=59389932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621161007.2U Expired - Fee Related CN206368331U (en) 2016-11-01 2016-11-01 A kind of Bridge Crack bracing means

Country Status (1)

Country Link
CN (1) CN206368331U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108330849A (en) * 2018-04-28 2018-07-27 洛阳理工学院 A kind of road and bridge crack ruggedized construction device
CN109056550A (en) * 2018-10-17 2018-12-21 安徽升建工程管理有限公司 Bridge bottom, which reinforces, under hot environment uses high-pressure slip-casting equipment
CN109339053A (en) * 2018-11-12 2019-02-15 檀煜 A kind of bridge Grouting Pipe
CN110735389A (en) * 2019-11-04 2020-01-31 江西科技学院 Assembled concrete pier and assembling method thereof
CN111501578A (en) * 2020-04-14 2020-08-07 中铁二十四局集团江苏工程有限公司 Reinforcing structure for bridge pier cracks and reinforcing method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108330849A (en) * 2018-04-28 2018-07-27 洛阳理工学院 A kind of road and bridge crack ruggedized construction device
CN109056550A (en) * 2018-10-17 2018-12-21 安徽升建工程管理有限公司 Bridge bottom, which reinforces, under hot environment uses high-pressure slip-casting equipment
CN109339053A (en) * 2018-11-12 2019-02-15 檀煜 A kind of bridge Grouting Pipe
CN110735389A (en) * 2019-11-04 2020-01-31 江西科技学院 Assembled concrete pier and assembling method thereof
CN110735389B (en) * 2019-11-04 2024-01-23 江西科技学院 Assembled concrete bridge pier and assembling method thereof
CN111501578A (en) * 2020-04-14 2020-08-07 中铁二十四局集团江苏工程有限公司 Reinforcing structure for bridge pier cracks and reinforcing method thereof

Similar Documents

Publication Publication Date Title
CN206368331U (en) A kind of Bridge Crack bracing means
CN206553864U (en) A kind of road and bridge crack bracing means
WO2013117089A1 (en) Semi-assembled ecotype debris dam for mudflow and construction method thereof
CN102296573A (en) Frame-type debris flow dam and construction method thereof
CN202055558U (en) Concrete crack roulette grouting device
CN206816274U (en) A kind of repairing and reinforcement structure of shield duct piece
CN109487760A (en) A kind of hydraulic structure large volume backfill structure and method
CN203320555U (en) Layout structure of ballast water tanks of immersed tube tunnel
CN210343359U (en) Prevent pressing of tunnel invert uplift and float structure
CN205662948U (en) Cold area road surface manhole cover
WO2019153567A1 (en) Single-compartment utility tunnel and assembled multi-compartment flat-bottom underground comprehensive utility tunnel
CN204875404U (en) Pre -buried formula pipeline intersecting structure in road surface
CN201148613Y (en) Anti-ice pier
CN207176527U (en) Bridge Crack bracing means
CN204489562U (en) A kind of supporting construction depositing steel box-girder
CN204023527U (en) A kind of reinforcement leakage preventing structure of pressure diversion tunnel
CN205776259U (en) A kind of deep basal pit retaining wall one side formwork constructing device
CN206337511U (en) A kind of concrete pier based on aluminium alloy/post bracing means
CN205421352U (en) Adopt reverse construction method post -cast strip reinforced structure of dowel steel
CN104314583A (en) Support method of coal seam roadway empty area
CN211773666U (en) Spillway bottom plate concrete penetrating crack chemical grouting hole arrangement structure
CN203625917U (en) Cast-in-place hollow floor type reinforced concrete storage tank base
CN207672342U (en) A kind of pressure type box High Speed Railway Subgrade
CN206360708U (en) Cavern's shallow-layer landslide supporting construction under unfavorable geological condition
CN206034483U (en) Hydraulic engineering retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170801