CN206337498U - Column with spiral hooping - Google Patents

Column with spiral hooping Download PDF

Info

Publication number
CN206337498U
CN206337498U CN201621246034.XU CN201621246034U CN206337498U CN 206337498 U CN206337498 U CN 206337498U CN 201621246034 U CN201621246034 U CN 201621246034U CN 206337498 U CN206337498 U CN 206337498U
Authority
CN
China
Prior art keywords
hoop
column
rib
spiral
hoop rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621246034.XU
Other languages
Chinese (zh)
Inventor
吴俊锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Kejia Engineering Design Co Ltd
Original Assignee
Jiangsu Kejia Engineering Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Kejia Engineering Design Co Ltd filed Critical Jiangsu Kejia Engineering Design Co Ltd
Priority to CN201621246034.XU priority Critical patent/CN206337498U/en
Application granted granted Critical
Publication of CN206337498U publication Critical patent/CN206337498U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of column with spiral hooping, it is related to bridge structure component technology field, including longitudinal reinforcement and concrete bodies, also include tie hoop group, tie hoop group include at least about two it is parallel and be close to the hoop ribs that arrange, hoop rib helically structure setting, longitudinal reinforcement is uniformly distributed along the inner ring of hoop rib, longitudinal reinforcement and hoop rib formation steel reinforcement cage, the inside of concrete bodies filling steel reinforcement cage and the outside for wrapping up steel reinforcement cage.This programme is easier to reach higher stirrup ratio, meets Seismic Design Requirements, reduce stirrup difficulty of construction by providing a kind of column with spiral hooping;Without processing the reinforcing bar of special diameter in addition, quantities is reduced;Uniform bearing capacity and good shock resistance can be possessed.

Description

Column with spiral hooping
Technical field
The utility model is related to bridge structure component technology field, more particularly to a kind of column with spiral hooping.
Background technology
Bridge pier is the important feature of bridge, and its major function is supporting bridge superstructure, and is made by basis by various With and dead weight pass to ground.The reinforced concrete pile of round screw thread stirrup has under repeatedly positive and negative repeated load effect Good ductility and bearing capacity stability, is a kind of preferable structural elements.Under moment of flexure and shearing action, the circular spiral shell in stake Rotation stirrup has following two effects:Effect of contraction has been deformed to the lateral expansion that curved compressive concrete is produced due to compression, The stress performance of the compressive region concrete is significantly improved, that is, play the effect of lateral confinement muscle;Play the anti-of resistance shearing Cut the effect of stirrup.
Application publication number discloses a kind of built-in tie hoop steel-enclosed concrete members for CN103615072A Chinese invention Post, including sole bar angle, transverse connection, tie hoop, longitudinal reinforcement and core concrete, each angle of post set one Connected between sole bar angle, sole bar angle with transverse connection, transverse connection is welded in the inner side or outer of sole bar angle flange plate Side, forms outsourcing steel skeleton, sets longitudinal reinforcement to constitute spiral reinforcement cage in tie hoop inwall, spiral reinforcement cage is placed in outer Core concrete is filled up in frame center of Baogang, Covered with Angles skeletal internal space.The spiral shell of built-in tie hoop steel-enclosed concrete members post Rotation stirrup has diametric requirements in selection, but is difficult to turn around curl using the big stirrup of diameter, and uses diameter small Stirrup then structural strength not enough, specially manufactures diameter suitable stirrup and then can increase quantities again.
Utility model content
The purpose of this utility model is to provide a kind of column with spiral hooping, can meet requirement, the reduction hoop of structural strength Muscle difficulty, can save the trouble for remanufacturing stirrup again.
Above-mentioned purpose of the present utility model technical scheme is that:A kind of column with spiral hooping, including Longitudinal reinforcement and concrete bodies, also including tie hoop group, tie hoop group include at least about two it is parallel and be close to arrange Hoop rib, hoop rib helically structure setting, longitudinal reinforcement is uniformly distributed along the inner ring of hoop rib, longitudinal reinforcement and hoop rib Form steel reinforcement cage, the inside of concrete bodies filling steel reinforcement cage and the outside for wrapping up steel reinforcement cage.
By using above-mentioned technical proposal, the reinforcing bar as hoop rib be one-level reinforcing bar, that is, wire rod, one-level reinforcing bar Diameter dimension is not more than 12mm, and single one-level reinforcing bar is used as low intensity during hoop rib, and the reinforcing bar with diameter greater than 12mm is two grades Reinforcing bar, two grades of reinforcing bars are difficult to turn around into hoop rib, therefore to meet the requirement of structural strength to remanufacture the one of major diameter Level reinforcing bar, but produce a kind of steel project of diameter again and can increase again.This programme less one-level reinforcing bar of several diameters Arranged in parallel and be wound in helical structure, in stirrup, the big reinforcing bar of the small reinforcing bar diameter group of diameter is easier curved coiling Shape;The small reinforcing bar of diameter does not allow frangibility compared with the big reinforcing bar of diameter simultaneously so that pact of the tie hoop group to concrete bodies Shu Zuoyong can be protected;On the other hand, the reinforcing bar for replacing major diameter with the reinforcing bar of several minor diameters may be omitted with again Manufacture a kind of trouble of the reinforcing bar of special diameter.Therefore structure can be reached by turning around into helical structure with several one-level parallel reinforced steel bars Intensity requirement, again will not be because diameter be too big and can not turn around, less with specially going to manufacture a kind of reinforcing bar of special diameter.
It is preferred that, the hoop rib quantity of tie hoop group is 2.
By using above-mentioned technical proposal, hoop rib quantity can reach column with spiral hooping to structural strength from 2 It is required that, the acquisition restriction ability good to concrete bodies and the enhancing to structural strength.
It is preferred that, a diameter of 8mm or 10mm of hoop rib.
By using above-mentioned technical proposal, the diameter dimension of one-level reinforcing bar has 6.5mm, 8mm, 10mm and 12mm, works as use When two one-level reinforcing bars are as hoop rib, 8mm and 10mm provide enough structural strengths and supported, and have reached stirrup difficulty again Little requirement.
It is preferred that, the hoop rib quantity of tie hoop group is 3.
By using above-mentioned technical proposal, hoop rib quantity can both reach that the constraint to concrete bodies was made when selecting 3 It is required that, while making stirrup difficulty be maintained in suitable extent and scope again.
It is preferred that, a diameter of 6.5mm or 8mm of hoop rib.
By using above-mentioned technical proposal, compared to two one-level reinforcing bars, three one-level reinforcing bars are main in diameter choosing value In view of stirrup operation difficulty, therefore the less diameter of selection reduces the performance performance that stirrup difficulty can guarantee that hoop rib again.
It is preferred that, the angle between the initiating terminal and horizontal plane of hoop rib is 5 ° ~ 10 °.
By using above-mentioned technical proposal, model of the angle control at 5 ° ~ 10 ° between the initiating terminal and horizontal plane of hoop rib In enclosing, it is ensured that tie hoop group possesses enough spiral number of turns, enough number of turns can provide foot for column with spiral hooping Enough bearing capacitys and structural strength.
It is preferred that, hoop rib is respectively arranged at two ends with one section of connection reinforcing bar parallel to horizontal plane.
By using above-mentioned technical proposal, one section of connection reinforcing bar is set respectively at the two ends of hoop rib, and horizontal plane is to level The active force that produces of connection reinforcing bar do not result in stress concentration at certain point, therefore the two ends of hoop rib are not easily broken.
It is preferred that, the vertical range d that hoop rib is located between two circles up and down of the same side is 10mm.
By using above-mentioned technical proposal, the vertical range between two circle hoop ribs is 10mm up and down, up and down two circle stirrups Bar distance both will not be oversize or will not be too short, column with spiral hooping is possessed enough bearing capacitys and structural strength, Tie hoop group can give play to the effect of contraction to concrete bodies, on the other hand there will not be too big quantities.
It is preferred that, the quantity of longitudinal reinforcement is no less than 4.
By using above-mentioned technical proposal, longitudinal reinforcement has supporting role to tie hoop and concrete bodies, makes spiral Stirrup and concrete bodies have uniform bearing capacity.
It is preferred that, a diameter of 12mm ~ 16mm of longitudinal reinforcement.
By using above-mentioned technical proposal, longitudinal reinforcement is when in use without bending, therefore in order to ensure its support strength The reinforcing bar being relatively large in diameter can be selected.
To sum up, a kind of column with spiral hooping described in the utility model, is easier to reach stirrup ratio, and meeting Aseismic Design will Ask, reduce stirrup difficulty of construction;Without processing the reinforcing bar of special diameter in addition, quantities is reduced;It can possess uniform Bearing capacity and good shock resistance.
Brief description of the drawings
Fig. 1 is the schematic perspective view of steel reinforcement cage;
Fig. 2 is the sectional view of steel reinforcement cage;
The enlarged drawing that Fig. 3 is part A in Fig. 2;
Fig. 4 is the top view of column with spiral hooping.
Reference:1st, steel reinforcement cage;101st, tie hoop group;1011st, hoop rib;1012nd, reinforcing bar is connected;102nd, longitudinal steel Muscle;2nd, concrete bodies;α, angle;D vertical ranges.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1
As shown in Fig. 1 ~ 3, a kind of column with spiral hooping, including tie hoop group 101, tie hoop group 101 is including on two Under it is parallel and be close to arrangement hoop rib 1011, hoop rib 1011 using a diameter of 8mm one-level reinforcing bar.Two hoop ribs 1011 The angle α size helically formed between structure setting, and the initiating terminal and horizontal plane of hoop rib 1011 is 10 °, positioned at same Vertical range d between the two neighbouring circle hoop ribs 1011 of side is 10mm.In addition, initiating terminal and the end of hoop rib 1011 End is respectively equipped with one section of connection reinforcing bar 1012 parallel to horizontal plane, connects the diameter of reinforcing bar 1012 and the diameter of hoop rib 1011 Unanimously.
As shown in figure 1, column with spiral hooping also includes longitudinal reinforcement 102, longitudinal reinforcement 102 is using two grades of reinforcing bars, its diameter For 14mm.Longitudinal reinforcement 102 is evenly distributed on the inner ring of hoop rib 1011, is fixed and connected by welding manner and hoop rib 1011 Connect, and there are eight along the circumferentially distributed of hoop rib 1011.
As shown in figure 4, longitudinal reinforcement 102 and the formation steel reinforcement cage 1 of hoop rib 1011.The inner ring of steel reinforcement cage 1 is cast with coagulation The soil body 2, outer ring is also cast with the concrete bodies 2 of parcel steel reinforcement cage 1.
When making column with spiral hooping, the mold exterior winding screw stirrup group 101 in cylinder first, by two hoop ribs About 1011 it is parallel and be close to arrangement, then turned around curl, the angle between its initiating terminal and horizontal plane is 10 °; The connection reinforcing bar 1012 of one section and plane-parallel is respectively welded in the initiating terminal of hoop rib 1011 and end again;Then by mould Take out, weld eight longitudinal reinforcements 102 in tie hoop inner ring, steel reinforcement cage 1 has thus just been made;Steel reinforcement cage 1 is put into ground In, and uniformly poured in its inner ring and outer ring and outpour concrete bodies, ultimately form tubular column with spiral hooping.
Embodiment 2
A kind of column with spiral hooping, the present embodiment and the difference of embodiment 1 be, the hoop rib 1011 of tie hoop group 101 Quantity is three, and hoop rib 1011 is from a diameter of 6.5mm one-level reinforcing bar.
This specific embodiment is only to explain of the present utility model, and it is not to limitation of the present utility model, ability Field technique personnel can make the modification without creative contribution to the present embodiment as needed after this specification is read, but As long as all being protected in right of the present utility model by Patent Law.

Claims (10)

1. a kind of column with spiral hooping, including longitudinal reinforcement(102)And concrete bodies(2), it is characterised in that:Also include tie hoop Group(101), tie hoop group(101)Including at least about two hoop ribs that are parallel and being close to arrangement(1011), hoop rib (1011)Helically structure setting, longitudinal reinforcement(102)Along hoop rib(1011)Inner ring be uniformly distributed, longitudinal reinforcement(102) With hoop rib(1011)Form steel reinforcement cage(1), concrete bodies(2)Fill steel reinforcement cage(1)Inside and wrap up steel reinforcement cage(1)It is outer Portion.
2. column with spiral hooping according to claim 1, it is characterised in that:The tie hoop group(101)Hoop rib (1011)Quantity is 2.
3. column with spiral hooping according to claim 2, it is characterised in that:The hoop rib(1011)A diameter of 8mm or 10mm。
4. column with spiral hooping according to claim 1, it is characterised in that:The tie hoop group(101)Hoop rib (1011)Quantity is 3.
5. column with spiral hooping according to claim 4, it is characterised in that:The hoop rib(1011)A diameter of 6.5mm Or 8mm.
6. column with spiral hooping according to claim 1, it is characterised in that:The hoop rib(1011)Initiating terminal and level Angle between face(α)For 5 ° ~ 10 °.
7. column with spiral hooping according to claim 1, it is characterised in that:The hoop rib(1011)Be respectively arranged at two ends with One section of connection reinforcing bar parallel to horizontal plane(1012).
8. column with spiral hooping according to claim 1, it is characterised in that:The hoop rib(1011)Positioned at the upper of the same side Vertical range between lower two circle(d)For 10mm.
9. column with spiral hooping according to claim 1, it is characterised in that:The longitudinal reinforcement(102)Quantity be no less than 4 Root.
10. column with spiral hooping according to claim 9, it is characterised in that:The longitudinal reinforcement(102)A diameter of 12mm ~16mm。
CN201621246034.XU 2016-11-14 2016-11-14 Column with spiral hooping Active CN206337498U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621246034.XU CN206337498U (en) 2016-11-14 2016-11-14 Column with spiral hooping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621246034.XU CN206337498U (en) 2016-11-14 2016-11-14 Column with spiral hooping

Publications (1)

Publication Number Publication Date
CN206337498U true CN206337498U (en) 2017-07-18

Family

ID=59307138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621246034.XU Active CN206337498U (en) 2016-11-14 2016-11-14 Column with spiral hooping

Country Status (1)

Country Link
CN (1) CN206337498U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111618211A (en) * 2020-05-22 2020-09-04 江苏蓝圈新材料股份有限公司 High-strength concrete prefabricated part, special reinforcing steel bar binding machine thereof and binding method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111618211A (en) * 2020-05-22 2020-09-04 江苏蓝圈新材料股份有限公司 High-strength concrete prefabricated part, special reinforcing steel bar binding machine thereof and binding method thereof
CN111618211B (en) * 2020-05-22 2022-03-25 江苏蓝圈新材料股份有限公司 Special reinforcement binding machine for high-strength concrete prefabricated member and binding method thereof

Similar Documents

Publication Publication Date Title
CN105735113A (en) Pier pile transition connection structure for concrete-filled steel tube bridge and construction method of pier pile transition connection structure
CN103122676A (en) Corner-reinforced steel tube concrete composite column and manufacturing method thereof
CN111364352A (en) Prefabricated pipe pier and cast-in-place pile connecting structure and construction method
CN206337498U (en) Column with spiral hooping
CN206680888U (en) A kind of ruggedized construction of arch bridge spandrel arch circle
CN101408060A (en) Novel high-strength concrete column structure
CN107034793A (en) A kind of ruggedized construction of arch bridge spandrel arch circle
CN103572752A (en) Partial prestressed concrete bamboo joint pile
CN206474615U (en) A kind of circular frame trestle steel reinforcement cage system of processing
CN201420262Y (en) Circular solid preload-stress concrete tubular pile
CN205577260U (en) Concrete column
CN206752459U (en) Bamboo joint pile reinforcing bar basket assembly
CN107060208B (en) Profile steel concrete column and its casting method
CN205617657U (en) Concrete column roof beam
CN213925832U (en) Composite reinforced pier with circular single-column pier sleeved with horn-shaped straight-line curved-surface column
CN101307598B (en) Prestressing force square pile precast pile tip and its processing method
CN112854604A (en) High-strength concrete superposed column with crossed double-spiral hoop reinforcement steel and construction method
CN210315969U (en) Connection node structure and prefabricated building
CN104746799B (en) The environmentally friendly concrete combination columns of steel FRP and its method of construction
CN206800789U (en) A kind of single page hyperboloid armored concrete post
CN203729291U (en) Tension cast-in-place pile
CN219794411U (en) Reinforced concrete column
CN101914976A (en) Distributed steel bar concrete column and manufacturing method thereof
CN206438678U (en) A kind of Reinforced Concrete Double repeats gynostemium
CN104929316B (en) A kind of cement concrete pillar and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant