CN206309000U - A kind of new climbing frame lifting device - Google Patents
A kind of new climbing frame lifting device Download PDFInfo
- Publication number
- CN206309000U CN206309000U CN201621462409.6U CN201621462409U CN206309000U CN 206309000 U CN206309000 U CN 206309000U CN 201621462409 U CN201621462409 U CN 201621462409U CN 206309000 U CN206309000 U CN 206309000U
- Authority
- CN
- China
- Prior art keywords
- climbing frame
- anchor ear
- lifting device
- suspension centre
- frame lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Motor Or Generator Frames (AREA)
Abstract
The utility model is related to a kind of new climbing frame lifting device, it includes upper suspension centre, the bottom of described upper suspension centre is provided with chain, loop body is provided with the middle part of described chain, described loop body is connected with attached wall suspension centre, and the bottom of described chain is connected with rotation pleasure boat, the both sides of described rotation pleasure boat are provided with anchor ear, the bottom of described rotation pleasure boat is provided with suspension hook, and the right-hand member of described anchor ear is provided with matrix component, and the left end of described anchor ear is provided with power set;The utility model has the advantages that simple structure, stable, time saving and energy saving, efficiency high.
Description
Technical field
The utility model belongs to construction lifting equipment field, and in particular to a kind of new climbing frame lifting dress
Put.
Background technology
With social depth development, building trade is also to develop rapidly, and the climbing frame for being protected outside construction is used
Increased, the climbing frame lifting device for being used during construction at present power set in lifting are fixed, every time, it is necessary to will after lifting
Attached wall suspension centre is arranged on last layer building, then motivation package device is removed has bad luck to upper strata and reinstall, time-consuming, laborious,
It is less efficient, in consideration of it, my company improves a new lifting device, the synchronous sex chromosome mosaicism of climbing frame lifting is solved, significantly
Security of the climbing frame in rising or decline is improved, dust-proof in work progress of anti-lifting power set is also solved and is asked
Topic, greatly protects the safety of life and property of job site personnel.
The content of the invention
The purpose of this utility model be in order to overcome the deficiencies in the prior art, and provide a kind of simple structure, it is stable,
Time saving and energy saving, efficiency high new climbing frame lifting device.
What the purpose of this utility model was realized in:A kind of new climbing frame lifting device, it includes upper suspension centre, described
The bottom of upper suspension centre be provided with chain, loop body is provided with the middle part of described chain, described loop body is connected with attached wall
Suspension centre, the bottom of described chain is connected with rotation pleasure boat, and the both sides of described rotation pleasure boat are provided with anchor ear, described rotation
The wander bottom of wheel is provided with suspension hook, and the right-hand member of described anchor ear is provided with matrix component, and the left end of described anchor ear is provided with
Power set.
The top of described anchor ear is provided with dust excluding plate.
Described power set include motor and reduction box.
The output shaft of described motor connects the input shaft of reduction box.
Climbing frame support body is connected with described suspension hook.
The beneficial effects of the utility model:In lifting, power set are followed and are arranged on climbing on suspension hook the utility model
Frame support body is moved upwardly together, every time after lifting, it is only necessary to attached wall suspension centre is arranged on into last layer building, loop body is voluntarily
Fixed at operation to attached wall suspension centre, you can carry out lifting operation next time, solve climbing frame weight during being raised and lowered
The problem of power set, time-saving and efficiency are installed again;Anchor ear top of the present utility model is provided with dust excluding plate, prevents dust or foreign matter
Into;Total, the utility model has the advantages that simple structure, stable, time saving and energy saving, efficiency high.
Brief description of the drawings
Fig. 1 is a kind of structural representation of new climbing frame lifting device of the utility model.
Fig. 2 is A-A sectional views of Fig. 1.
Fig. 3 is the structural representation of routine climbing frame lifting device at present.
In figure:1st, matrix component 2, motor 3, reduction box 4, chain 5, dust excluding plate 6, anchor ear 7, suspension hook
8th, rotation pleasure boat 9, upper suspension centre 10, attached wall suspension centre 11, loop body.
Specific embodiment
The utility model is described further below in conjunction with the accompanying drawings.
Embodiment 1
As shown in Fig. 1-3, a kind of new climbing frame lifting device, it includes upper suspension centre 9, the bottom of described upper suspension centre 9
Chain 4 is provided with, the middle part of described chain 4 is provided with loop body 11, and described loop body 11 is connected with attached wall suspension centre 10, institute
The bottom of the chain 4 stated is connected with rotation pleasure boat 8, and the both sides of described rotation pleasure boat 8 are provided with anchor ear 6, described rotation
The bottom of pleasure boat 8 is provided with suspension hook 7, and the right-hand member of described anchor ear 6 is provided with matrix component 1, and the left end of described anchor ear 6 is set
Dynamic device.
In lifting, power set follow the climbing frame support body being arranged on suspension hook 7 to move upwardly together to the utility model, often
After secondary lifting, it is only necessary to which attached wall suspension centre 10 is arranged on into last layer building, loop body 11 is voluntarily run to attached wall suspension centre 10
Place is fixed, you can carry out lifting operation next time, solves climbing frame and repeats to install power set during being raised and lowered
Problem, time-saving and efficiency;The top of anchor ear of the present utility model 6 is provided with dust excluding plate 5, prevents dust or foreign matter from entering;Total, this
Utility model has the advantages that simple structure, stable, time saving and energy saving, efficiency high.
Embodiment 2
As shown in Fig. 1-3, a kind of new climbing frame lifting device, it includes upper suspension centre 9, the bottom of described upper suspension centre 9
Chain 4 is provided with, the middle part of described chain 4 is provided with loop body 11, and described loop body 11 is connected with attached wall suspension centre 10, institute
The bottom of the chain 4 stated is connected with rotation pleasure boat 8, and the both sides of described rotation pleasure boat 8 are provided with anchor ear 6, described rotation
The bottom of pleasure boat 8 is provided with suspension hook 7, and the right-hand member of described anchor ear 6 is provided with matrix component 1, and the left end of described anchor ear 6 is set
Dynamic device, the top of described anchor ear 6 is provided with dust excluding plate 5, and described power set include motor 2 and reduction box 3, institute
The output shaft of the motor 2 stated connects the input shaft of reduction box 3, and climbing frame support body is connected with described suspension hook 7.
In lifting, power set follow the climbing frame support body being arranged on suspension hook 7 to move upwardly together to the utility model, often
After secondary lifting, it is only necessary to which attached wall suspension centre 10 is arranged on into last layer building, loop body 11 is voluntarily run to attached wall suspension centre 10
Place is fixed, you can carry out lifting operation next time, solves climbing frame and repeats to install power set during being raised and lowered
Problem, time-saving and efficiency;The top of anchor ear of the present utility model 6 is provided with dust excluding plate 5, prevents dust or foreign matter from entering;This practicality
New power set include motor 2 and reduction box 3, and the output shaft of motor of the present utility model 2 connects the input of reduction box 3
Axle, is connected with climbing frame support body on suspension hook of the present utility model 7;Total, the utility model has simple structure, stable, province
The advantage of Shi Shengli, efficiency high.
Claims (5)
1. a kind of new climbing frame lifting device, it includes upper suspension centre, it is characterised in that:The bottom of described upper suspension centre is provided with
Chain, is provided with loop body in the middle part of described chain, described loop body is connected with attached wall suspension centre, the bottom of described chain
Rotation pleasure boat is connected with, the both sides of described rotation pleasure boat are provided with anchor ear, and the bottom of described rotation pleasure boat is provided with hangs
Hook, the right-hand member of described anchor ear is provided with matrix component, and the left end of described anchor ear is provided with power set.
2. a kind of new climbing frame lifting device according to claim 1, it is characterised in that:The top of described anchor ear sets
It is equipped with dust excluding plate.
3. a kind of new climbing frame lifting device according to claim 1, it is characterised in that:Described power set include
Motor and reduction box.
4. a kind of new climbing frame lifting device according to claim 3, it is characterised in that:The output shaft of described motor
Connect the input shaft of reduction box.
5. a kind of new climbing frame lifting device according to claim 1, it is characterised in that:It is connected with described suspension hook
Climbing frame support body.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621462409.6U CN206309000U (en) | 2016-12-29 | 2016-12-29 | A kind of new climbing frame lifting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621462409.6U CN206309000U (en) | 2016-12-29 | 2016-12-29 | A kind of new climbing frame lifting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206309000U true CN206309000U (en) | 2017-07-07 |
Family
ID=59248774
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621462409.6U Expired - Fee Related CN206309000U (en) | 2016-12-29 | 2016-12-29 | A kind of new climbing frame lifting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206309000U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108217501A (en) * | 2018-02-05 | 2018-06-29 | 河北宇雕起重装备科技有限公司 | Projecting circulation electric elevator |
CN109577633A (en) * | 2018-11-15 | 2019-04-05 | 深圳市特辰科技股份有限公司 | A kind of projecting cucurbit integrated circular hook |
-
2016
- 2016-12-29 CN CN201621462409.6U patent/CN206309000U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108217501A (en) * | 2018-02-05 | 2018-06-29 | 河北宇雕起重装备科技有限公司 | Projecting circulation electric elevator |
CN109577633A (en) * | 2018-11-15 | 2019-04-05 | 深圳市特辰科技股份有限公司 | A kind of projecting cucurbit integrated circular hook |
CN109577633B (en) * | 2018-11-15 | 2021-07-20 | 深圳市特辰科技股份有限公司 | Integral type circulation hook of inverted gourd |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206309000U (en) | A kind of new climbing frame lifting device | |
CN206448170U (en) | A kind of efficient Bridge Construction platform | |
CN203636994U (en) | Energy-saving type lifting system based on concrete mixing | |
CN205773024U (en) | A kind of convenient pipeline lifting auxiliary device | |
CN204418013U (en) | Bridge flange plate is constructed self-propelled cantilever hanging basket | |
CN201694778U (en) | Downhole hydraulic support assembling and disassembling crane | |
CN202039851U (en) | Lifting device of shaft sleeve inner wall construction assembling template | |
CN205890950U (en) | Hydroelectric power plant prevents fire door transfer car(buggy) | |
CN201610525U (en) | Suspended working platform for maintenance of bridges and culvers | |
CN205428636U (en) | Hoist and mount formula transformer installation device | |
CN203938973U (en) | Column | |
CN204416844U (en) | A kind of auxiliary device of building hoist | |
CN203781713U (en) | High slope support material transport device | |
CN203321338U (en) | Lifting working platform for vehicle-mounted deep well drilling machine | |
CN202687898U (en) | Special lift truck for dismantling main reducer assembly of crane | |
CN202672694U (en) | Shaft construction circulation operating platform | |
CN206220994U (en) | Long range mixed lifting inclines are equipped | |
CN202575694U (en) | Hoisting tool for circular-arc-surface equipment | |
CN207436974U (en) | Drive rotation casing pipe running device mounting bracket in top | |
CN202231353U (en) | Special tool for lifting post insulator | |
CN206457788U (en) | A kind of water conservancy lock for being easy to cleaning stands device for hoisting | |
CN201647224U (en) | Novel brick suspending box | |
CN204400518U (en) | The actuating device of a kind of high-altitude jacking equipment | |
CN203938975U (en) | A kind of connecting rod | |
CN204607367U (en) | A kind of carriage for Hydropower Plant recirculation cooler |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170707 Termination date: 20191229 |
|
CF01 | Termination of patent right due to non-payment of annual fee |