A kind of replaceable high-strength prestress screw arbor assembly Download PDF

Info

Publication number
CN206308704U
CN206308704U CN201621437088.4U CN201621437088U CN206308704U CN 206308704 U CN206308704 U CN 206308704U CN 201621437088 U CN201621437088 U CN 201621437088U CN 206308704 U CN206308704 U CN 206308704U
Authority
CN
China
Prior art keywords
screw rod
screw
threaded portion
arbor assembly
anchor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621437088.4U
Other languages
Chinese (zh)
Inventor
霍宏斌
高建辉
张文东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Acer Engineering Technology (beijing) Co Ltd
Original Assignee
Acer Engineering Technology (beijing) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Acer Engineering Technology (beijing) Co Ltd filed Critical Acer Engineering Technology (beijing) Co Ltd
Priority to CN201621437088.4U priority Critical patent/CN206308704U/en
Application granted granted Critical
Publication of CN206308704U publication Critical patent/CN206308704U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of replaceable high-strength prestress screw arbor assembly, including screw rod, position of the screw rod near lower end and the position near upper end are respectively equipped with threaded portion, threaded portion near upper end is provided with clamp nut, anchor slab ring is provided near the threaded portion of lower end, the upper end of screw rod is provided with six square toes, and the lower end of screw rod is provided with nose cone or round platform head.The hole inwall of anchor slab ring is provided with T-shaped screw thread or light wall; the inclination angle of the nose cone of screw rod lower end or the side wall of round platform head is more than or equal to 30 °; small 3~the 5mm of the diagonal length screw diameter of six square toes of screw rod upper end; in one group of opposite side of six square toes, one through hole is set; threaded portion is provided with the intermediate zone of 40 50mm with screw rod middle part; screw surface smears anti-corrosion grease, and PE pipes are cased with the middle part of screw rod, and the two ends of the screw rod are cased with PVC protection cap bags.Not easy to break with high intensity, toughness elasticity is good, the advantages of convenient displacement, it is adaptable to all blower foundation forms, and meet anchorage screw occur quality problems can not normally use and it is unbroken in the case of displacement.

Description

A kind of replaceable high-strength prestress screw arbor assembly
Technical field
The utility model is related to a kind of anchorage screw of wind power plant unit foundation, more particularly to a kind of replaceable High-strength prestress screw arbor assembly.
Background technology
External advanced technology is quoted in domestic blower foundation construction at present, and its basis steel is high-strength deformed steel bar rod; Domestic to have used spiral for prestressed concrete when with external blower foundation advanced technology, this kind of product is a kind of Hot rolling type carries discontinuous externally threaded straight steel bar, is adapted to be used in concreting process, with the common structure of concrete Into prestressed component;Spiral for prestressed concrete has the following disadvantages for blower foundation:
Though the 1, lever strength is high, material fragility is big, poor toughness, poor flexibility, fatigue life are low;
2nd, be mounted in when spiral for prestressed concrete is used in blower foundation construction inside pvc pipe not with it is mixed Solidifying native contact, every spiral after installation to blower foundation applies tension force, because the fragility of spiral is big, is applying to open Power rear thread reinforcing bar there occurs delayed fracture, and inconvenience displacement, and serious potential safety hazard is brought on fan basis.So that blower fan base The advanced technology that plinth is built, due to being stagnated without the high-strength deformed steel bar rod that can meet use requirement.
The fatigue life that spiral for prestressed concrete exists in use is low, and fragility is big, poor toughness, elasticity Difference, after stretching force the problems such as poor mechanical property, easy fracture,
Utility model content
It is elastic good, convenient displacement replaceable that the purpose of this utility model is to provide a kind of high intensity, not easy to break, toughness High-strength prestress screw arbor assembly.
The purpose of this utility model is achieved through the following technical solutions:
Replaceable high-strength prestress screw arbor assembly of the present utility model, including screw rod, the screw rod is near lower end Position and threaded portion is respectively equipped near the position of upper end, the threaded portion near upper end is provided with clamp nut, near lower end Threaded portion is provided with anchor slab ring, and the upper end of the screw rod is provided with six square toes, and the lower end of the screw rod is provided with nose cone or round platform head.
The technical scheme that is there is provided by above-mentioned the utility model as can be seen that the utility model embodiment provide it is replaceable High-strength prestress screw arbor assembly, not easy to break with high intensity, toughness elasticity is good, conveniently the advantages of displacement, it is adaptable to all Blower foundation form, and meet anchorage screw occur quality problems can not normally use and it is unbroken in the case of displacement.
Brief description of the drawings
The structural representation of the replaceable high-strength prestress screw arbor assembly that Fig. 1 is provided for the utility model embodiment.
Fig. 2 is the cross-sectional view of anchorage screw in the utility model embodiment;
Fig. 3 is the termination schematic diagram of anchorage screw in the utility model embodiment;
Fig. 4 is the protection cap bag schematic diagram of anchorage screw in the utility model embodiment;
Fig. 5 is anchorage screw and anchor slab ring connection diagram in the utility model embodiment.
In figure:
1st, screw rod, 2, clamp nut, 3, PE pipes, 4, anchor slab ring.
Specific embodiment
With reference to the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out clearly Chu, it is fully described by, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole realities Apply example.Based on embodiment of the present utility model, those of ordinary skill in the art are obtained under the premise of creative work is not made The every other embodiment for obtaining, belongs to protection domain of the present utility model.
Replaceable high-strength prestress screw arbor assembly of the present utility model, its preferably specific embodiment is:
Including screw rod, position of the screw rod near lower end and the position near upper end are respectively equipped with threaded portion, near upper The threaded portion at end is provided with clamp nut, and anchor slab ring is provided near the threaded portion of lower end, and the upper end of the screw rod is provided with six sides Head, the lower end of the screw rod is provided with nose cone or round platform head.
The hole inwall of the anchor slab ring is provided with T-shaped screw thread, is engaged near the threaded portion of lower end with the screw rod, on anchor slab ring The screw rod in portion is provided with thin nut.
The hole wall of the anchor slab ring is smooth without screw thread, and bore dia about screw rod 3mm, and the screw rod on anchor slab ring top is provided with Thin nut, the screw rod of anchor slab ring bottom is provided with high nut.
The inclination angle of the nose cone of the screw rod lower end or the side wall of round platform head is more than or equal to 30 °, and in screw rod under Threaded portion at end in the range of 350mm sets T-shaped screw thread.
The diagonal length small 3~5mm of the screw diameter of six square toes of the screw rod upper end, at one group couple of six square toes Side sets a through hole, and through-hole diameter is 20mm, and lead to the hole site is away from screw rod end 28 to 32mm.
The diagonal structural texture of six square toes of the screw rod upper end can be mechanically connected as separate construction parts with the body of rod Mode is combined.The diagonal structural texture of six square toes of the screw rod upper end also can directly be processed on body of rod top.
The threaded portion and screw rod middle part are provided with the intermediate zone of 40-50mm, and the screw thread of intermediate zone is by rolling central diameter progressively mistake Cross to diameter of thread.
The screw surface smears anti-corrosion grease, and PE pipes are cased with the middle part of the screw rod, and the two ends of the screw rod are cased with PVC Protection cap bag.
The screw rod uses rapid thermal treatment, and firing rate is in 100 DEG C/more than s.
Replaceable high-strength prestress screw arbor assembly of the present utility model, by screw rod one end port shape and another Hold structural form improvement, change prestress anchoraging screw rod in blower foundation practical application processing and fabricating, in-site installation, put The problems such as changing, can be used for succeeding in developing for the high-strength prestressed anchor screw rod replaced, and solve prestress anchoraging screw rod in wind The phenomenon of hardly possible is replaced in the practical application of machine basis, construction period significantly shortens, and basic service life is extended.
The screw arbor assembly has high intensity, not easy to break, and toughness elasticity is good, is conveniently applied to the advantages of displacement and removes foundation ring Outer all blower foundation forms, and meet anchorage screw occur quality problems can not normally using and it is unbroken in the case of put Change.
Specific embodiment:
As shown in Figures 1 to 5, including anchor slab ring, screw rod and screw rod two ends threaded portion etc..
The anchor slab ring has two kinds of forms, a kind of for anchor slab ring screw hole inwall is provided with T-shaped screw thread, with the T-shaped screw thread of screw rod It coincide, used as the anchored end of screw rod, anchor slab ring upper screw can be fixed with thin nut, and bottom does not use typically nut to fix, Using PVC protection cap bag sealing protections after installation;
Another form anchor slab ring screw hole inwall does not set screw thread, and anchor slab ring upper screw can be fixed with thin nut, under Portion is fixed with high nut, using PVC protection cap bag sealing protections after installation;
One end moulding of the threaded portion is:End screw rod is circular cone or truncated cone-shaped, i.e. end thinner than body of rod position, is inclined Angle α is more than or equal to 30 °, and is T-shaped screw thread in the range of the 350mm of end, and it is the PE protective cases of 160mm to be configured with height Cap, after screw rod installation, sealing protection screw rod end prevents from being contacted with concrete, and preservative treatment;
Other end moulding is:End is hexagon, diagonal length 3~5mm small compared with screw diameter, wherein one group of opposite side One through hole is set, and through-hole diameter is 20mm, and lead to the hole site is not more than 2mm away from screw rod end 30mm, position deviation.
Screw surface smears anti-corrosion grease, and screw rod is inserted in PE sleeve pipes, isolates with concrete.
The excessive place of the threaded portion and screw rod sets the intermediate zone of 40-50mm, the screw thread of intermediate zone by passed through in rolling by Step is transitioned into diameter of thread.
Screw rod Technology for Heating Processing is rapid thermal treatment:Firing rate reaches 100 DEG C/more than s.
The utility model solves the problems, such as that domestic blower foundation anchoring material displacement is difficult, effectively increases blower foundation Service life.
The above, only the utility model preferably specific embodiment, but protection domain of the present utility model is not This is confined to, any one skilled in the art can readily occur in the technical scope that the utility model is disclosed Change or replacement, should all cover within protection domain of the present utility model.Therefore, protection domain of the present utility model should It is defined by the protection domain of claims.

Claims (8)

1. a kind of replaceable high-strength prestress screw arbor assembly, it is characterised in that including screw rod, the screw rod is near lower end Position and threaded portion is respectively equipped near the position of upper end, the threaded portion near upper end is provided with clamp nut, near lower end Threaded portion is provided with anchor slab ring, and the upper end of the screw rod is provided with six square toes, and the lower end of the screw rod is provided with nose cone or round platform head.
2. replaceable high-strength prestress screw arbor assembly according to claim 1, it is characterised in that the anchor slab ring Hole inwall is provided with T-shaped screw thread, is engaged near the threaded portion of lower end with the screw rod, and the screw rod on anchor slab ring top is provided with thin spiral shell It is female.
3. replaceable high-strength prestress screw arbor assembly according to claim 1, it is characterised in that the anchor slab ring Hole inwall is light wall, and the screw rod on anchor slab ring top is provided with thin nut, and the screw rod of anchor slab ring bottom is provided with high nut.
4. replaceable high-strength prestress screw arbor assembly according to claim 1, it is characterised in that the screw rod lower end Nose cone or the inclination angle of side wall of round platform head be more than or equal to 30 °, and the screw thread in screw rod at the lower end in the range of 350mm Portion sets T-shaped screw thread.
5. replaceable high-strength prestress screw arbor assembly according to claim 1, it is characterised in that the screw rod upper end Six square toes the diagonal length small 3~5mm of the screw diameter, in one group of opposite side of six square toes, one through hole is set, through hole is straight Footpath is 20mm, and lead to the hole site is away from screw rod end 28 to 32mm.
6. replaceable high-strength prestress screw arbor assembly according to claim 1, it is characterised in that the threaded portion with Screw rod middle part is provided with the intermediate zone of 40-50mm, and the screw thread of intermediate zone is progressively transitioned into diameter of thread by rolling central diameter.
7. the replaceable high-strength prestress screw arbor assembly according to any one of claim 1 to 6, it is characterised in that institute State screw surface and smear anti-corrosion grease, PE pipes are cased with the middle part of the screw rod, the two ends of the screw rod are cased with PVC protection cap bags.
8. the replaceable high-strength prestress screw arbor assembly according to any one of claim 1 to 6, it is characterised in that institute State screw rod and use rapid thermal treatment, firing rate is in 100 DEG C/more than s.
CN201621437088.4U 2016-12-26 2016-12-26 A kind of replaceable high-strength prestress screw arbor assembly Active CN206308704U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621437088.4U CN206308704U (en) 2016-12-26 2016-12-26 A kind of replaceable high-strength prestress screw arbor assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621437088.4U CN206308704U (en) 2016-12-26 2016-12-26 A kind of replaceable high-strength prestress screw arbor assembly

Publications (1)

Publication Number Publication Date
CN206308704U true CN206308704U (en) 2017-07-07

Family

ID=59246361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621437088.4U Active CN206308704U (en) 2016-12-26 2016-12-26 A kind of replaceable high-strength prestress screw arbor assembly

Country Status (1)

Country Link
CN (1) CN206308704U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522264A (en) * 2016-12-26 2017-03-22 惠宏工程技术(北京)有限公司 Replaceable high-strength prestress screw assembly

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522264A (en) * 2016-12-26 2017-03-22 惠宏工程技术(北京)有限公司 Replaceable high-strength prestress screw assembly

Similar Documents

Publication Publication Date Title
CN204826419U (en) Bury ground tackle deeply
CN204591323U (en) Large elongation is anti-corrosion anchor pole
CN202787668U (en) Rear bolt anchoring system for cantilever steel I-beam
CN204081445U (en) To encorbelment i iron anchor device
CN206308704U (en) A kind of replaceable high-strength prestress screw arbor assembly
CN209642270U (en) A kind of novel power cable protection pipe
CN106522264A (en) Replaceable high-strength prestress screw assembly
CN103256285B (en) Small head nail for wall cement slab
CN204001980U (en) The steel structure enclosure wall that a kind of building site is special
CN206680951U (en) A kind of channel protection structure of hydraulic engineering
CN204001743U (en) Three sections of energy-saving environment-protecting type sealing up screw
CN203775121U (en) Universal metal roof fixture
CN211817997U (en) Portable antiseep steel sleeve
CN207987918U (en) A kind of precast concrete pile and pilework
CN208934463U (en) A kind of concreting profiled template support component
CN205709591U (en) The novel flexible attachment device of derrick crane
CN204871182U (en) A horizontal pull rod device for connecting adjustable length of frame and axle
CN212388541U (en) Anti-extrusion glass fiber reinforced plastic displaceable composite anchoring rod device
CN205839990U (en) Staircase built-in fitting
CN209244267U (en) One kind pouring preserved pipeline hole support mode
CN218719584U (en) Anti-creeping three-way pipe fitting for water supply
CN207160422U (en) A kind of reinforcing bar with anchored end
CN203297237U (en) Wall body cement board small-head nail
CN208604954U (en) Marked rod
CN207563627U (en) A kind of reinforcing bar crotch tool

Legal Events