CN202787668U - Rear bolt anchoring system for cantilever steel I-beam - Google Patents

Rear bolt anchoring system for cantilever steel I-beam Download PDF

Info

Publication number
CN202787668U
CN202787668U CN 201220397676 CN201220397676U CN202787668U CN 202787668 U CN202787668 U CN 202787668U CN 201220397676 CN201220397676 CN 201220397676 CN 201220397676 U CN201220397676 U CN 201220397676U CN 202787668 U CN202787668 U CN 202787668U
Authority
CN
China
Prior art keywords
steel
fixed
bolts
nut
nuts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220397676
Other languages
Chinese (zh)
Inventor
陈汉彬
杨毅
刘家甫
顾辰欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN 201220397676 priority Critical patent/CN202787668U/en
Application granted granted Critical
Publication of CN202787668U publication Critical patent/CN202787668U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a rear bolt anchoring system for a cantilever steel I-beam. The system is characterized by comprising two bolts, a fixed plate, nuts and a PVC (Poly Vinyl Chloride) sleeve; two ends of the bolts are threaded; the lower ends of the bolts penetrate through the PVC sleeve which is pre-buried in a concrete floor slab, and are fixed with the nuts by the fixed plate; and the steel I-beam is fixed between the parts of the two bolts above the concrete floor slab, and are fixed with the nuts by the fixed plate. Each nut is fixed by two nuts. The bolts adopt round steels with phi of 20; and the threaded lengths on two ends are respectively in a range from 70-75 mm. The fixed plate is a steel plate. The phi of the PVC sleeve is 25, and the PVC sleeve is vertically pre-buried. Compared with the traditional method of welding after pre-burying by applying round steel pressure rings, the rear bolt anchoring system for the cantilever steel I-beam disclosed by the utility model avoids the economic loss caused by inaccurate pre-burying of the round steel pressure rings, and has the obvious advantages of reduced risks in safety and technique, decreased unnecessary welding workload, quick construction speed, beautiful appearance, capacity of turnover use and the like.

Description

A kind of rearmounted bolt anchoring of steel I-beam system of encorbelmenting
Technical field
The utility model relates to the realm of building construction, relates in particular to a kind of rearmounted bolt anchoring of the steel I-beam system of encorbelmenting in the steel I-beam anchoring construction of encorbelmenting.
Background technology
At present, highrise building is encorbelmented in the steel I-beam anchoring construction, conventional way is to adopt pre-buried, the way of welded limiting reinforcing bar again of round steel pressure ring, but builds the situation that pre-buried round steel off normal often occurs behind the floorslab concrete easily, cause pre-buried round steel pressure ring invalid with waste; On the other hand the welded limiting reinforcing bar occur pre-buried round steel excessively the situation of burn also happen occasionally.How to avoid round steel pressure ring off normal, the steel I-beam anchorage point that guarantees to encorbelment is accurate, and anchoring quality is reliable, guarantees that construction safety becomes common problem in the high-building construction.
The utility model content
Technical problem to be solved in the utility model provides a kind of rearmounted bolt anchoring of steel I-beam system of encorbelmenting, and has solved the problems referred to above.
Technical problem to be solved in the utility model is achieved through the following technical solutions:
A kind of rearmounted bolt anchoring of steel I-beam system of encorbelmenting is characterized in that: comprise 2 bolts, fixed head, nut and PVC sleeve pipe; The equal mantle fiber in the two ends of described bolt, described bolt lower end pass the PVC sleeve pipe that is embedded in the concrete floor and fix with fixed head and nut; Steel I-beam is fixed on 2 bolts and fixes between the part on the concrete floor and by fixed head and nut.
The fixing double nut that adopts of described nut is fixed.
Described bolt adopts Ф 20 round steel, and two ends rod thread processing length respectively is 70-75mm.
Described fixed head is steel plate.
Described PVC sleeve pipe adopts Ф 25, and is vertically pre-buried.
The beneficial effects of the utility model:
The utility model uses round steel pressure ring way pre-buried, again welding to compare with tradition, avoided the pre-buried inaccurate economic loss that causes of round steel pressure ring, have that to reduce safety, technical risk, minimizing unnecessary welding job amount, speed of application fast, impression is attractive in appearance, can have enough to meet the need the obvious advantages such as utilization.
Description of drawings
Fig. 1 the utility model rearmounted bolt anchoring system schematic of steel I-beam of encorbelmenting.
Fig. 2 the utility model steel plate floor map of bearing down on one.
Fig. 3 the utility model rearmounted bolt anchoring 3D of system of steel I-beam schematic diagram of newly encorbelmenting.
Among the figure, 1-bolt, the 2-steel plate that bears down on one, 3-nut, 4-PVC sleeve pipe, the 5-i iron of encorbelmenting.
The specific embodiment
Shown in Fig. 1-3, a kind of rearmounted bolt anchoring of steel I-beam system of encorbelmenting is characterized in that: comprise 2 bolts, fixed head, nut and PVC sleeve pipe; The equal mantle fiber in the two ends of described bolt, described bolt lower end pass the PVC sleeve pipe that is embedded in the concrete floor and fix with fixed head and nut; Steel I-beam is fixed on 2 bolts and fixes between the part on the concrete floor and by fixed head and nut.
The fixing double nut that adopts of described nut is fixed; Described nut 3 supports the use with bolt 1, adopts double nut to prevent that single nut is loosening in the use procedure.
Described bolt adopts Ф 20 round steel, and two ends rod thread processing length respectively is 70-75mm.
Described fixed head is steel plate.The described steel plate 2 of bearing down on one adopts 200 * 100 * 12 steel plates, and has two Ф 20 bolts hole, and center distance is 108mm (establishing and being adopted the 16# i iron width of encorbelmenting is 88mm).
Described PVC sleeve pipe adopts Ф 25, and is vertically pre-buried, for bolt 1 interspersed floor is reserved vertical hole.

Claims (5)

1. the rearmounted bolt anchoring of the steel I-beam system of encorbelmenting is characterized in that: comprise 2 bolts, fixed head, nut and PVC sleeve pipe; The equal mantle fiber in the two ends of described bolt, described bolt lower end pass the PVC sleeve pipe that is embedded in the concrete floor and fix with fixed head and nut; Steel I-beam is fixed on 2 bolts and fixes between the part on the concrete floor and by fixed head and nut.
2. the rearmounted bolt anchoring of the steel I-beam of encorbelmenting as claimed in claim 1 system, it is characterized in that: the fixing double nut that adopts of described nut is fixed.
3. the rearmounted bolt anchoring of the steel I-beam of encorbelmenting as claimed in claim 1 system, it is characterized in that: described bolt adopts Ф 20 round steel, and two ends rod thread processing length respectively is 70-75mm.
4. the rearmounted bolt anchoring of the steel I-beam of encorbelmenting as claimed in claim 1 system, it is characterized in that: described fixed head is steel plate.
5. the rearmounted bolt anchoring of the steel I-beam of encorbelmenting as claimed in claim 1 system, it is characterized in that: described PVC sleeve pipe adopts Ф 25, and is vertically pre-buried.
CN 201220397676 2012-08-07 2012-08-07 Rear bolt anchoring system for cantilever steel I-beam Expired - Fee Related CN202787668U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220397676 CN202787668U (en) 2012-08-07 2012-08-07 Rear bolt anchoring system for cantilever steel I-beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220397676 CN202787668U (en) 2012-08-07 2012-08-07 Rear bolt anchoring system for cantilever steel I-beam

Publications (1)

Publication Number Publication Date
CN202787668U true CN202787668U (en) 2013-03-13

Family

ID=47814947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220397676 Expired - Fee Related CN202787668U (en) 2012-08-07 2012-08-07 Rear bolt anchoring system for cantilever steel I-beam

Country Status (1)

Country Link
CN (1) CN202787668U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103615121A (en) * 2013-11-29 2014-03-05 中建四局第六建筑工程有限公司 Floor edge-near protective handrail with turnover function
CN104120873A (en) * 2013-04-23 2014-10-29 昆山友进智能建筑工程有限公司 Dual-fixing type cantilever beam fixing piece
CN106968695A (en) * 2017-05-03 2017-07-21 云南建投基础工程有限责任公司 A kind of prefabrication type tunnel lock foot anchoring stock and steelframe connecting elements
CN107420689A (en) * 2016-05-24 2017-12-01 江苏宜安建设有限公司 A kind of integral combined column bolt fixture
CN108149927A (en) * 2017-11-16 2018-06-12 上海二十冶建设有限公司 A kind of Cantilever Beams tension and compression constrainer and its application method
CN109441094A (en) * 2018-12-20 2019-03-08 上海建工七建集团有限公司 The fixed pre-embedded device of builder's jack I-steel and its installation method
CN112938393A (en) * 2021-03-08 2021-06-11 机械工业第九设计研究院有限公司 Elevator locking mechanism

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104120873A (en) * 2013-04-23 2014-10-29 昆山友进智能建筑工程有限公司 Dual-fixing type cantilever beam fixing piece
CN103615121A (en) * 2013-11-29 2014-03-05 中建四局第六建筑工程有限公司 Floor edge-near protective handrail with turnover function
CN107420689A (en) * 2016-05-24 2017-12-01 江苏宜安建设有限公司 A kind of integral combined column bolt fixture
CN106968695A (en) * 2017-05-03 2017-07-21 云南建投基础工程有限责任公司 A kind of prefabrication type tunnel lock foot anchoring stock and steelframe connecting elements
CN106968695B (en) * 2017-05-03 2023-10-20 云南建投基础工程有限责任公司 Prefabricated tunnel lock foot stock and steelframe connecting element
CN108149927A (en) * 2017-11-16 2018-06-12 上海二十冶建设有限公司 A kind of Cantilever Beams tension and compression constrainer and its application method
CN109441094A (en) * 2018-12-20 2019-03-08 上海建工七建集团有限公司 The fixed pre-embedded device of builder's jack I-steel and its installation method
CN112938393A (en) * 2021-03-08 2021-06-11 机械工业第九设计研究院有限公司 Elevator locking mechanism

Similar Documents

Publication Publication Date Title
CN202787668U (en) Rear bolt anchoring system for cantilever steel I-beam
CN202577934U (en) Screw thread wall-connection member of scaffold and building
CN203654299U (en) Steel support loose end
CN202745359U (en) U-shaped steel bar bolt pull ring system for fixing cantilever frame steel beam
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN201546436U (en) Platform for construction of high-altitude suspension structures
CN204081445U (en) To encorbelment i iron anchor device
CN202577939U (en) Reusable overhanging I-beam fixing device
CN204591306U (en) A kind of combined steel pipe concrete bow member for supporting
CN204608776U (en) A kind of recoverable anchor rod of falling wedge-type
CN204960953U (en) Vertical waterstop of formula of burying device of flare -outing in tunnel
CN204456159U (en) A kind of steel kind design concrete anchor location structure
CN203238951U (en) Box girder steel pipe arc bracket
CN203924656U (en) A kind of high-altitude overlength cable-stayed type shaped steel job platform structure
CN202809492U (en) Dragging system of steel truss girder obliquely crossing existing line through continuous jack in guide rail-free way
CN205259361U (en) Connected node of reinforced concrete column and light -duty girder steel
CN208440996U (en) A kind of novel inlet pipe
CN204343642U (en) Builder's jack corner support frame
CN205153504U (en) Detachable cantilever frame body base
CN201250516Y (en) Single-side wall mould holder strengthening device
CN204139570U (en) Containing the pre-buried fastening devices of detachable overhanging type steel beam of horizontal fixation kit
CN203097291U (en) Reinforcing and counter-pulling device of building construction formwork
CN202544875U (en) Front canopy type temporary supporting suspension device for anchor pole supporting tunnel construction
CN203603490U (en) Supporting structure used for erecting formwork truss on prefabricated beam
CN203271105U (en) Auxiliary device of building hoist wall attaching frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20200807