CN206307932U - A kind of hitch in lifting device - Google Patents

A kind of hitch in lifting device Download PDF

Info

Publication number
CN206307932U
CN206307932U CN201621446600.1U CN201621446600U CN206307932U CN 206307932 U CN206307932 U CN 206307932U CN 201621446600 U CN201621446600 U CN 201621446600U CN 206307932 U CN206307932 U CN 206307932U
Authority
CN
China
Prior art keywords
rod
support frame
lifting device
suspension mechanism
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621446600.1U
Other languages
Chinese (zh)
Inventor
沈小伟
胡蔚
柏彬
韩超
刘寅莹
陈倩茜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
State Grid Jiangsu Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
State Grid Jiangsu Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd, State Grid Jiangsu Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Jiangsu Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical NANJING ELECTRIC POWER ENGINEERING DESIGN Co Ltd
Priority to CN201621446600.1U priority Critical patent/CN206307932U/en
Application granted granted Critical
Publication of CN206307932U publication Critical patent/CN206307932U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

本实用新型公开了一种提升装置中的悬挂机构,包括支撑架、夹板、紧固螺钉、支撑杆以及操作杆,两所述夹板分别插接在支撑架的两侧,且夹板与支撑架之间形成有夹紧腔,紧固螺钉螺纹连接在支撑架上,且紧固螺钉的底端抵接于夹板上,支撑杆和操作杆均铰接于支撑架的下端面上。本实用新型结构简单,便于操作,稳定性好,适用性广,使用安全。

The utility model discloses a suspension mechanism in a lifting device, which comprises a support frame, a splint, a fastening screw, a support rod and an operating rod. A clamping cavity is formed between them, the fastening screw is threadedly connected to the support frame, and the bottom end of the fastening screw abuts against the splint, and the support rod and the operating rod are both hinged on the lower end surface of the support frame. The utility model has the advantages of simple structure, convenient operation, good stability, wide applicability and safe use.

Description

一种提升装置中的悬挂机构A suspension mechanism in a lifting device

技术领域:Technical field:

本实用新型涉及一种提升装置中的悬挂机构。The utility model relates to a suspension mechanism in a lifting device.

背景技术:Background technique:

在电线杆的横担上安装电线时,常常是通过绝缘斗臂车将施工人员与送至电线杆一侧,然后通过施工人员将电线吊升并安装至电线杆横担上,由于带电作业,施工人员在吊升电线时,施工人员与电线之间必须留有安全间隙,然而该施工方式的安全间隙难以得到保证,因此给施工人员造成了极大的安全隐患。When installing wires on the cross-arm of the utility pole, the construction personnel are often sent to the side of the utility pole by an insulated bucket arm truck, and then the construction personnel lift the wire and install it on the cross-arm of the utility pole. Due to live work, When the construction workers are hoisting the wires, a safety gap must be left between the construction workers and the wires. However, the safety gap of this construction method is difficult to be guaranteed, thus causing great safety hazards to the construction workers.

电线杆的横担包括直线横担、转角横担和双横担,专利号201520555258.8,公开了一种35kV及以下多回路中相带电作业专用提升器(如图1),该提升器中的悬挂结构只能适用于双横担,适用性小。The cross-arms of utility poles include straight-line cross-arms, corner cross-arms and double cross-arms. Patent No. 201520555258.8 discloses a special lifter for 35kV and below multi-circuit mid-phase live work (as shown in Figure 1). The suspension in the lifter The structure can only be applied to double cross arms, and the applicability is small.

上述专利公开的提升器中的绳盘500位于安装架600的下方,安装架担在横担400上。在吊装电线时,由于绳盘500位于安装架600的下方,电线在吊升过程中,横担400必然会干涉电线的上升,因此电线只能始终位于横担下方。所以在电线吊升至横担下方时,还需要借助一绝缘杆,先将该电线挑至绝缘杆上,然后通过该绝缘杆绕过横担并将电线放置横担的上端面上,该操作过程繁琐,且电线容易滑落,安全隐患大。The rope reel 500 in the lifter disclosed in the above-mentioned patent is located under the installation frame 600 , and the installation frame is carried on the cross arm 400 . When hoisting electric wires, since the rope reel 500 is located under the mounting frame 600, the cross arm 400 will inevitably interfere with the rising of the electric wire during the hoisting process of the electric wire, so the electric wire can only be positioned under the cross arm all the time. Therefore, when the wire is hoisted to the bottom of the cross arm, it is necessary to use an insulating rod to pick the wire to the insulating rod first, then pass the insulating rod around the cross arm and place the wire on the upper end of the cross arm. The process is cumbersome, and the wires are easy to slip, which poses a great safety hazard.

因此,确有必要对现有技术进行改进以解决现有技术之不足。Therefore, it is necessary to improve the prior art to solve the deficiencies of the prior art.

发明内容:Invention content:

本实用新型是为了解决上述现有技术存在的问题而提供一种提升装置中的悬挂机构。The utility model provides a suspension mechanism in a lifting device in order to solve the above-mentioned problems in the prior art.

本实用新型所采用的技术方案有:一种提升装置中的悬挂机构,包括支撑架、夹板、紧固螺钉、支撑杆以及操作杆,两所述夹板分别插接在支撑架的两侧,且夹板与支撑架之间形成有夹紧腔,紧固螺钉螺纹连接在支撑架上,且紧固螺钉的底端抵接于夹板上,支撑杆和操作杆均铰接于支撑架的下端面上。The technical solution adopted in the utility model includes: a suspension mechanism in a lifting device, including a support frame, a splint, a fastening screw, a support rod and an operating rod, and the two splints are respectively inserted on both sides of the support frame, and A clamping cavity is formed between the splint and the support frame, the fastening screw is threadedly connected to the support frame, and the bottom end of the fastening screw abuts against the splint, and the support rod and the operating rod are both hinged on the lower end surface of the support frame.

进一步地,所述支撑架的两边垂直向下延伸并形成第一夹壁,夹板的末端垂直向下折弯并形成第二夹壁,第一夹壁和第二夹壁之间形成所述夹紧腔。Further, the two sides of the support frame extend vertically downward to form a first clamping wall, the ends of the clamping plate are bent vertically downward to form a second clamping wall, and the clamping wall is formed between the first clamping wall and the second clamping wall Tight cavity.

进一步地,所述第一夹壁和第二夹壁的内壁上均设有锥齿。Further, bevel teeth are provided on the inner walls of the first clamping wall and the second clamping wall.

进一步地,所述支撑架的中心处设有通孔。Further, a through hole is provided at the center of the support frame.

进一步地,所述支撑杆为二折杆,在支撑杆的底端设有摩擦轮。Further, the support rod is a two-fold rod, and a friction wheel is provided at the bottom end of the support rod.

进一步地,所述支撑杆和操作杆均设有两根,且两支撑杆位于两操作杆之间。Further, there are two supporting rods and two operating rods, and the two supporting rods are located between the two operating rods.

进一步地,所述操作杆为可伸缩杆。Further, the operating rod is a telescopic rod.

本实用新型具有如下有益效果:The utility model has the following beneficial effects:

本实用新型结构简单,便于操作,稳定性好,适用性广,使用安全。The utility model has the advantages of simple structure, convenient operation, good stability, wide applicability and safe use.

附图说明:Description of drawings:

图 1 为背景技术中提升装置的悬挂结构图。Figure 1 is a suspension structure diagram of the lifting device in the background technology.

图 2 为本实用新型悬挂机构的主视图。Fig. 2 is the front view of the suspension mechanism of the utility model.

图 3 为本实用新型悬挂机构的左视图。Fig. 3 is the left view of the suspension mechanism of the utility model.

图 4 为本实用新型悬挂机构的应用结构图。Figure 4 is the application structure diagram of the suspension mechanism of the present invention.

具体实施方式:detailed description:

下面结合附图对本实用新型作进一步的说明。Below in conjunction with accompanying drawing, the utility model is further described.

如图2和图3所示,本实用新型一种提升装置中的悬挂机构,包括支撑架21、夹板22、紧固螺钉23、支撑杆4以及操作杆5,两夹板22分别插接在支撑架21的两侧,且夹板22与支撑架21之间形成有夹紧腔20,紧固螺钉23螺纹连接在支撑架21上,且紧固螺钉23的底端抵接于夹板22上,并将夹板22固定于支撑架21上。支撑杆4和操作杆5均铰接于支撑架21的下端面上。As shown in Figures 2 and 3, a suspension mechanism in a lifting device of the present invention includes a support frame 21, a splint 22, a fastening screw 23, a support rod 4 and an operating rod 5, and the two splints 22 are respectively inserted into the support The two sides of frame 21, and clamping cavity 20 is formed between splint 22 and support frame 21, fastening screw 23 is screwed on the support frame 21, and the bottom end of fastening screw 23 abuts on splint 22, and The splint 22 is fixed on the supporting frame 21 . Both the support rod 4 and the operating rod 5 are hinged on the lower end surface of the support frame 21 .

本实用新型中支撑架21的两边垂直向下延伸并形成第一夹壁210,夹板22的末端垂直向下折弯并形成第二夹壁220,第一夹壁210和第二夹壁220之间形成所述夹紧腔20。In the utility model, the two sides of the support frame 21 extend vertically downwards to form the first clamping wall 210, and the end of the splint 22 is bent vertically downwards to form the second clamping wall 220, between the first clamping wall 210 and the second clamping wall 220 The clamping cavity 20 is formed between them.

为增加本实用新型悬挂机构与电线塔杆上横担之间的摩擦力,在第一夹壁210和第二夹壁220的内壁上均设有锥齿。In order to increase the frictional force between the suspension mechanism of the present invention and the upper cross arm of the electric tower pole, bevel teeth are provided on the inner walls of the first clamping wall 210 and the second clamping wall 220 .

为防止吊绳12上升与下降过程中,吊钩13发生沿收线盘11轴线方向的摆动,在支撑架21的中心处设有用于穿设吊绳12的通孔218。该通孔218可以有效的防止吊钩13发生上述摆动。In order to prevent the lifting hook 13 from swinging along the axis of the take-up reel 11 during the lifting and lowering of the lifting rope 12 , a through hole 218 for passing the lifting rope 12 is provided at the center of the support frame 21 . The through hole 218 can effectively prevent the suspension hook 13 from swinging.

为便于适用于不同管径的电线塔杆,本实用新型中的支撑杆4为二折杆。为便于支撑杆4更好的抵接于电线塔杆上,在支撑杆4的底端设有摩擦轮41。In order to be applicable to the wire tower rods of different pipe diameters, the support rod 4 in the utility model is a two-fold rod. In order to make it easier for the support rod 4 to abut against the wire tower rod better, a friction wheel 41 is provided at the bottom end of the support rod 4 .

支撑杆4和操作杆5均设有两根,且两支撑杆4位于两操作杆5之间。两操作杆5便于操作,两支撑杆4增加本实用新型悬挂机构的稳定性。操作杆5为可伸缩杆,适用于不同高度的横杆。Two supporting rods 4 and two operating rods 5 are provided, and the two supporting rods 4 are located between the two operating rods 5 . Two operation rods 5 are convenient to operate, and two support rods 4 increase the stability of the suspension mechanism of the present utility model. Operating rod 5 is a telescopic rod, which is suitable for cross bars of different heights.

结合图4,施工人员通过绝缘斗臂车上升至待作业电线杆一侧,施工人员通过操作杆5将本实用新型悬挂机构悬挂在电线塔杆的横担上(本实施过程以直线横担为例),通过调整夹紧腔20的大小用以适用于不同尺寸的横担,支撑杆4底端的摩擦轮41抵靠在电线塔杆上,稳定性好。In conjunction with Fig. 4, construction workers rise to the side of the utility pole to be operated through the insulated bucket arm truck, and the construction workers hang the suspension mechanism of the utility model on the cross arm of the electric tower pole through the operating rod 5 (this implementation process uses a straight line cross arm as the For example), by adjusting the size of the clamping cavity 20 to be suitable for cross-arms of different sizes, the friction wheel 41 at the bottom end of the support rod 4 abuts against the electric tower rod, and the stability is good.

在使用本实用新型悬挂机构时,将收线盘11固定于支撑架21的上方,吊钩13穿过通孔218并伸于支撑架21的下发。由于收线盘11位于电线塔杆的横担的上方,收线盘11在吊升电线过程中,如果横杆干涉电线上升时,只需借助一根绝缘杆体拉动电线,使得电线偏离横杆的干涉位置,然后收线盘11继续吊升电线并将电线吊升至横杆的上方。若横杆不干涉电线上升,则收线盘11可直接将电线吊装至横担上方。后借助上述绝缘杆体将电线挑离吊钩13,即可实现将电线放置横担上。When using the suspension mechanism of the present utility model, the take-up reel 11 is fixed on the top of the support frame 21, and the suspension hook 13 passes through the through hole 218 and extends to the lower end of the support frame 21. Since the wire take-up reel 11 is located above the cross arm of the electric tower pole, if the wire take-up reel 11 is in the process of hoisting the wire, if the cross bar interferes with the rise of the wire, it only needs to pull the wire with the help of an insulating rod to make the wire deviate from the cross bar. interference position, then the take-up reel 11 continues to hoist the electric wire and the electric wire is hoisted to the top of the cross bar. If the crossbar does not interfere with the rise of the electric wires, the wire take-up reel 11 can directly lift the electric wires to the top of the crossbar. Afterwards, the electric wire is picked out of the suspension hook 13 by means of the above-mentioned insulating rod body, so that the electric wire can be placed on the cross arm.

在电线塔杆的横担为转角横担或者双横担时,只需将本实用新型提升装置放置至转角横担或者双横担的一侧边上,并使得提升装置的摩擦轮41抵靠在电线塔杆上,即可实现电线的吊装。When the cross arm of the electric tower pole is a corner cross arm or a double cross arm, it is only necessary to place the lifting device of the present invention on one side of the corner cross arm or the double cross arm, and make the friction wheel 41 of the lifting device lean against On the wire tower pole, the hoisting of wires can be realized.

以上所述仅是本实用新型的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下还可以作出若干改进,这些改进也应视为本实用新型的保护范围。The above is only a preferred embodiment of the utility model, it should be pointed out that for those of ordinary skill in the art, some improvements can be made without departing from the principle of the utility model, and these improvements should also be regarded as the present invention. Protection scope of utility model.

Claims (7)

1.一种提升装置中的悬挂机构,其特征在于:包括支撑架(21)、夹板(22)、紧固螺钉(23)、支撑杆(4)以及操作杆(5),两所述夹板(22)分别插接在支撑架(21)的两侧,且夹板(22)与支撑架(21)之间形成有夹紧腔(20),紧固螺钉(23)螺纹连接在支撑架(21)上,且紧固螺钉(23)的底端抵接于夹板(22)上,支撑杆(4)和操作杆(5)均铰接于支撑架(21)的下端面上。1. A suspension mechanism in a lifting device, characterized in that: it includes a support frame (21), a splint (22), a fastening screw (23), a support rod (4) and an operating rod (5), and the two splints (22) are inserted on both sides of the support frame (21), and a clamping cavity (20) is formed between the splint (22) and the support frame (21), and the fastening screw (23) is threaded on the support frame ( 21), and the bottom end of the fastening screw (23) abuts on the splint (22), and the support rod (4) and the operating rod (5) are hinged on the lower end surface of the support frame (21). 2.如权利要求1所述的提升装置中的悬挂机构,其特征在于:所述支撑架(21)的两边垂直向下延伸并形成第一夹壁(210),夹板(22)的末端垂直向下折弯并形成第二夹壁(220),第一夹壁(210)和第二夹壁(220)之间形成所述夹紧腔(20)。2. The suspension mechanism in the lifting device according to claim 1, characterized in that: the two sides of the support frame (21) extend vertically downward to form the first clamping wall (210), and the end of the clamping plate (22) is vertical Bending downwards to form a second clamping wall (220), the clamping cavity (20) is formed between the first clamping wall (210) and the second clamping wall (220). 3.如权利要求2所述的提升装置中的悬挂机构,其特征在于:所述第一夹壁(210)和第二夹壁(220)的内壁上均设有锥齿。3. The suspension mechanism in the lifting device according to claim 2, characterized in that: bevel teeth are provided on the inner walls of the first clamping wall (210) and the second clamping wall (220). 4.如权利要求1所述的提升装置中的悬挂机构,其特征在于:所述支撑架(21)的中心处设有通孔(218)。4. The suspension mechanism in the lifting device according to claim 1, characterized in that: a through hole (218) is provided at the center of the support frame (21). 5.如权利要求1所述的提升装置中的悬挂机构,其特征在于:所述支撑杆(4)为二折杆,在支撑杆(4)的底端设有摩擦轮(41)。5. The suspension mechanism in the lifting device according to claim 1, characterized in that: the support rod (4) is a two-fold rod, and a friction wheel (41) is provided at the bottom end of the support rod (4). 6.如权利要求1所述的提升装置中的悬挂机构,其特征在于:所述支撑杆(4)和操作杆(5)均设有两根,且两支撑杆(4)位于两操作杆(5)之间。6. The suspension mechanism in the lifting device according to claim 1, characterized in that: there are two support rods (4) and two operating rods (5), and the two support rods (4) are located between the two operating rods (5) Between. 7.如权利要求1所述的提升装置中的悬挂机构,其特征在于:所述操作杆(5)为可伸缩杆。7. The suspension mechanism in the lifting device according to claim 1, characterized in that: the operating rod (5) is a telescopic rod.
CN201621446600.1U 2016-12-27 2016-12-27 A kind of hitch in lifting device Withdrawn - After Issue CN206307932U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621446600.1U CN206307932U (en) 2016-12-27 2016-12-27 A kind of hitch in lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621446600.1U CN206307932U (en) 2016-12-27 2016-12-27 A kind of hitch in lifting device

Publications (1)

Publication Number Publication Date
CN206307932U true CN206307932U (en) 2017-07-07

Family

ID=59246184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621446600.1U Withdrawn - After Issue CN206307932U (en) 2016-12-27 2016-12-27 A kind of hitch in lifting device

Country Status (1)

Country Link
CN (1) CN206307932U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106517011A (en) * 2016-12-27 2017-03-22 国网江苏省电力公司经济技术研究院 Suspension mechanism in lifting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106517011A (en) * 2016-12-27 2017-03-22 国网江苏省电力公司经济技术研究院 Suspension mechanism in lifting device
CN106517011B (en) * 2016-12-27 2018-02-13 国网江苏省电力公司经济技术研究院 A kind of hitch in lifting device

Similar Documents

Publication Publication Date Title
CN104201613B (en) Far-end operation changes device and the application process thereof of straight line list insulator string
CN202880803U (en) Wire lifting device
CN203474231U (en) Steel bar tower safety hoisting device
CN102761077B (en) Insulating hoisting bracket for strain insulator string of 1000kV extra-high alternating current line
CN106429935B (en) A kind of lifting device
CN101378153A (en) Diverter for grounding wire
CN206307942U (en) A kind of lifting device
CN103199461B (en) Transmission line lightning conducter elevating method
CN203289011U (en) Tension cross arm hoisting device
CN203278097U (en) Electric pole cross arm erecting device
CN106517011B (en) A kind of hitch in lifting device
CN104283156B (en) Wire lifting device for power distribution line
CN202927423U (en) Hanging and fixing device universally used for overhead line structure cross arm angle iron
CN202124420U (en) Porcelain bushing blank hoisting device
CN203589426U (en) Lifting device for mounting grounding wire hanging hook
CN105060154A (en) Suspension installation machine of suspended load type transformer
CN203865843U (en) Special hanger for disassembly, assembly and craning of transformer
CN202850574U (en) Wire rod
CN205123134U (en) Lead wire fixing device
CN103138204A (en) Multifunctional installing rack used for replacing tension cross arm
CN204858403U (en) Change V -arrangement insulator hangs some fixing device to transmission line temporarily with electricity
CN204144792U (en) Far-end operation changes the device of straight line list insulator string
CN203942042U (en) Earth connection is hung and is torn insulating bar open
CN210779826U (en) Special gallows of multi-loop vertical arrangement wire equipotential operation special guidance ground wire
CN205282987U (en) A hoisting device for wire

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170707

Effective date of abandoning: 20180213