CN206289989U - A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures - Google Patents

A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures Download PDF

Info

Publication number
CN206289989U
CN206289989U CN201621304002.0U CN201621304002U CN206289989U CN 206289989 U CN206289989 U CN 206289989U CN 201621304002 U CN201621304002 U CN 201621304002U CN 206289989 U CN206289989 U CN 206289989U
Authority
CN
China
Prior art keywords
sliding
post
steel column
steel
tie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621304002.0U
Other languages
Chinese (zh)
Inventor
卢福生
叶翔
张伟
王垒
施元强
王强强
杨林
胡广龙
王柏森
马国良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinggong Steel Structure Group Co Ltd
Original Assignee
Zhejiang Jinggong Steel Structure Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinggong Steel Structure Group Co Ltd filed Critical Zhejiang Jinggong Steel Structure Group Co Ltd
Priority to CN201621304002.0U priority Critical patent/CN206289989U/en
Application granted granted Critical
Publication of CN206289989U publication Critical patent/CN206289989U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Utility model belongs to steel building field, the absolute altitudes such as specifically related to a kind of large span spatial structure high position band post Sliding Structures, including the intercolumniation beam that brace steel post is vertically fixedly connected with brace steel post, sliding rail is equipped with intercolumniation beam, slided on sliding rail and be provided with by sliding steel column, piston shoes are fixedly installed by the both sides of sliding steel column, the piston shoes of side are connected with the hydraulic top thruster being slideably positioned on sliding rail.The utility model is high to solve large span spatial structure roof system center of gravity, real abdomen post without lateral support in the case of stability it is poor, it is difficult to implement post bottom sliding problem.

Description

A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures
Technical field
Utility model belongs to steel building field, and in particular to a kind of absolute altitude such as large span spatial structure high position band post slides Structure.
Background technology
After China's building system widely popularize with industry for many years flourish, steel construction already turn into building system In an indispensable part, with reference to its intensity it is high, from heavy and light, the plurality of advantages that integral rigidity is good, deformability is strong, steel construction It is used in the building of large span, Super High and superduty.
With the application of New Technologies, accumulation slippage construction technology is gradually widely used in greatly across sky by industry Between in structure construction, the current technology is mainly used in smooth roof structure, post bottom or the consistent structure of capital absolute altitude, and runs into Roof structure height relief is big, capital height of support is small or the post bottom skimble-scamble special circumstances of absolute altitude, often interim using setting Sliding jig or change roof system absolute altitude carry out sliding construction to lift the method for scope of operation height, the first construction method, not only The financial cost that interim measure is brought is considerably increased, and roof system sliding needs to mend in place after filling and fills section afterwards, and difficulty of construction is big, Merging precision is low, and shaping structures quality is difficult to ensure that;Second construction method, roof system sliding needs after integral jacking again afterwards in place Unloading dropping place, high-altitude difficulty of construction is big, totally unfavorable to construction safety.Thus, accumulation slippage construction technology is in applicability, economy Property and security aspect also have it is to be developed and improve.
Utility model content
The purpose of this utility model is to provide a kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures, to solve Large span spatial structure roof system center of gravity is high, real abdomen post without lateral support in the case of stability it is poor, it is difficult to implement post bottom sliding difficulty Topic, and capital roof system bearing random fluctuation or height of support it is less in the case of, it is difficult to implement capital sliding problem.
To achieve the above object, the technical scheme of the specific offer of the utility model is:A kind of large span spatial structure high position etc. Absolute altitude band post Sliding Structures, including the intercolumniation beam that brace steel post is vertically fixedly connected with brace steel post, cunning is equipped with intercolumniation beam Track is moved, is slided on sliding rail and is provided with by sliding steel column, piston shoes, the cunning of side are fixedly installed by the both sides of sliding steel column Boots are connected with the hydraulic top thruster being slideably positioned on sliding rail.
Further, it is horizontally disposed with to have inter-tie and intersect between the adjacent steel column by sliding and is provided with intersection system Bar, inter-tie and intersection tie-rod are located at by the same tie point on sliding steel column outer peripheral face;Wherein inter-tie lower edge and institute Piston shoes are stated to be connected.
Further, it is described that rail hole was provided with by sliding steel column and sliding rail junction, this cross rail hole with it is described Sliding rail is matched;The brace steel post and expansion shrouding is provided between sliding steel column.
A kind of absolute altitudes such as large span spatial structure high position band post gliding method, comprises the following steps:(1)It is determined that sliding work , be divided into steel column by sliding steel column and brace steel post as boundary with sliding working face by face;
(2)Rail hole is crossed in factory's cutting completion, piston shoes and by sliding steel column in factory's spelling by sliding steel column bottom Complete, together deliver to scene;
(3)After brace steel post, intercolumniation beam and sliding rail are installed in place, first sliding element is carried out in slipping and assembling area High-altitude spelling, comprising by sliding steel column and piston shoes, inter-tie, intersect tie-rod, roof structure and hydraulic pressure creep machine;It is assembled After the completion of, a step pitch is slid forward;
(4)Continuation carry out second high-altitude spelling of sliding element in build-up area, and carried out with a upper sliding element it is right Connect, after the completion of assembly, a step pitch is slid forward;
(5)Circulation carries out step 4 until completing the accumulation slippage construction of superstructure;
(6)After sliding onto target position, carry out being slid verticality of steel column and upper and lower steel column horizontal displacement difference checks adjustment.
Further, wherein in step 6:After the check adjustment by sliding steel column, carry out being slid steel column after inspection is errorless With expansion shrouding full penetration at the capital of bottom;Then piston shoes, sliding rail are cut off, what repair welding sliding was opened up crosses rail hole, Sliding construction interim stabilization measure is cut off, sliding construction is completed.
The beneficial effects of the utility model:The utility model makes roof system assembly protect all the time by accumulation slippage construction technology Hold in a fixed interval, improve the controllability of splicing accuracy, process with reducing consolidation shed with moulding bed fall with etc. be constructed into This;Creeped system by fully automatic hydraulic, realize and manually merged with mechanical intelligence, shorten the construction period, reduce people Work cost;By accumulation slippage technology, solve building bottom In Great Basement or large area civil engineering structure caused by hang Machine cannot be introduced into the problem of construction, reduce site operation difficulty.
Brief description of the drawings
Fig. 1 is structure axonometric schematic diagram of the present utility model;Fig. 2 is texture edge schematic diagram of the present utility model;Fig. 3 It is sliding node detail side elevation of the present utility model;Fig. 4 surveys detail drawing for sliding node axle of the present utility model;Fig. 5 is this reality With novel bottom brace steel post and by sliding steel column relation schematic diagram;Fig. 6 is the expansion at the top of the brace steel post of the utility model bottom Big shrouding schematic diagram;Fig. 7 is that the utility model crosses rail hole schematic diagram by sliding steel column bottom.
Specific embodiment
The utility model is further illustrated with case study on implementation below in conjunction with the accompanying drawings:
Explained in detail referring to Fig. 1-7 case study on implementation:A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures, including support The intercolumniation beam 2 that steel column 1 is vertically fixedly connected with brace steel post 1, is equipped with sliding rail 3 on intercolumniation beam 2, sliding on sliding rail 3 It is dynamic to be provided with by sliding steel column 4, be fixedly installed piston shoes 9 by the both sides of sliding steel column 4, the piston shoes 9 of side be slideably positioned in Hydraulic top thruster 10 on sliding rail 3 is connected.
Adjacent described being horizontally disposed between sliding steel column 4 has inter-tie 8 and intersecting to be provided with intersection tie-rod 7, Inter-tie 8 and intersection tie-rod 7 are located at by the same tie point on the post outer peripheral face of sliding steel 4;The wherein lower edge of inter-tie 8 and institute Piston shoes 9 are stated to be connected.
Described that sliding steel column 4 and the junction of sliding rail 3 were provided with rail hole 6, this crosses rail hole 6 with the sliding Track 3 is matched;The brace steel post 1 and be provided between sliding steel column 4 expansion shrouding 11.
A kind of absolute altitudes such as large span spatial structure high position band post gliding method, comprises the following steps:(1)It is determined that sliding work , be divided into steel column by sliding steel column 4 and brace steel post 1 as boundary with sliding working face by face;
(2)Rail hole 6 is crossed in factory's cutting completion, piston shoes 9 and by sliding steel column 4 in factory by the bottom of sliding steel column 4 Spelling is completed, and is together delivered to scene;
(3)After brace steel post 1, intercolumniation beam 2 and sliding rail 3 are installed in place, first sliding is carried out in slipping and assembling area The high-altitude spelling of unit, comprising by sliding steel column 4 and piston shoes 9, inter-tie 8, intersect tie-rod 7, roof structure 5 and hydraulic pressure and climb Row device;After the completion of assembly, a step pitch is slid forward;
(4)Continuation carry out second high-altitude spelling of sliding element in build-up area, and carried out with a upper sliding element it is right Connect, after the completion of assembly, a step pitch is slid forward;
(5)Circulation carries out step 4 until completing the accumulation slippage construction of superstructure;
(6)After sliding onto target position, carry out being slid verticality of steel column and upper and lower steel column horizontal displacement difference checks adjustment, institute State after checking adjustment by sliding steel column, carry out being slid expansion shrouding full penetration weldering at steel column 4 and bottom capital after inspection is errorless Connect;Then piston shoes 9, sliding rail 3 are cut off, what repair welding sliding was opened up crosses rail hole 6, cuts off sliding construction interim stabilization and arranges Apply, complete sliding construction.
The large-span roof structure 5 leads to not carry out sliding construction in capital in the presence of two kinds of architectural characteristics.Structure is special Property one:The roof structure height relief is larger, generally in folding shape or waveform, causes capital absolute altitude different;Structure is special Property two:The roof structure is less than 500mm with the height of support of lower support steel column, causes working space too small.
The brace steel post 1 and the support column of large-span roof structure 5 is by sliding steel column 4, in order to solve capital absolute altitude The too small problem of inconsistent or height of support and blocked in a high position, make the sliding construction scope of operation in same level.
It is described that sliding construction is together carried out with large-span roof structure 5 in work progress by sliding steel column 4.
The brace steel post 1 and intercolumniation beam 2 together constitute the lower support system of sliding construction.
The intersection tie-rod 7 is the lateral bracing system for being slid steel column 4, along glide direction by an arrangement, improves top Rigidity and stability of the Sliding Structures in glide direction.
The inter-tie 8 is arranged at by the bottom of sliding steel column 4 so that jacking force is only directly transmitted in bottom, is realized Pushing tow is force self-balanced, it is to avoid post bottom jacking force produces additional bending moment influence structure safety.
The steel column is crossed rail hole 6 and is arranged at by the bottom of sliding steel column 4, crosses rail hole size true according to sliding rail 7 It is fixed, hole upside and the left and right sides with a distance from sliding rail all should >=10mm, it is ensured that sliding rail can be passed through and slid Steel column;By opening up rail hole, made by the lateral Displacement that sliding steel column plays roof system span direction during sliding construction With raising construction safety performance.
The piston shoes 9 are arranged at the every both sides by sliding steel column 4, and bottom is fallen within sliding rail 7, piston shoes bottom mark Height crosses the upside of rail hole 6 about 10mm~15mm in steel column, makes to be slid steel column and is come to nothing with sliding rail, prevents sliding construction mistake Damage is produced to structure in journey.
The hydraulic pressure creep machine 6 is connected with piston shoes 9 by pushing tow otic placode, is the dynamical system during whole sliding construction System, uses with the coordinative composition of equipments such as hydraulic power system, computer control system, displacement transducer and pressure sensor.Hydraulic pressure Crawl device is manipulated using computer system completely in the propulsive force and fltting speed of slipping, by wedge type fixture block it is unidirectional from Lock function, auto lock sliding rail is creeped using middle hydraulic jack driving structure, is constructed by sensor real-time monitoring Dynamic.
The expansion shrouding 11 is arranged at the top of brace steel post 1, shrouding radius=steel column radius+1.5t(T is thick shrouding Degree), for adjusting after the completion of sliding construction by sliding steel column(4)With the horizontal departure between brace steel post 1.
Rail hole 6 and piston shoes 9 are crossed by steel column, make by slide between steel column 4 and brace steel post 1 reserve butt seam≤ 15mm, is directly docked after in place by sliding steel column sliding construction with bottom brace steel post, finally cuts off piston shoes and sliding rail Road, benefit filled tile at rail hole, in solving traditional sliding construction technique, need to mend behind structure sliding position fill after fill section or Need the technical barrier of high-altitude dropping place.
Specific implementation of the present utility model is described above.All institutes within spirit of the present utility model and principle Any modification made, equivalent and improvement, should be included within protection domain of the present utility model.

Claims (3)

1. a kind of absolute altitude such as large span spatial structure high position is with post Sliding Structures, it is characterised in that:Including brace steel post and supporting steel The intercolumniation beam that post is vertically fixedly connected, is equipped with sliding rail on intercolumniation beam, slided on sliding rail and be provided with by sliding steel column, Piston shoes are fixedly installed by the both sides of sliding steel column, the piston shoes of side connect with the hydraulic top thruster being slideably positioned on sliding rail Connect.
2. a kind of absolute altitude such as large span spatial structure high position according to claim 1 is with post Sliding Structures, it is characterised in that:Phase It is horizontally disposed with to have inter-tie and intersect between the adjacent steel column by sliding and is provided with intersection tie-rod, inter-tie and intersection Tie-rod is located at by the same tie point on sliding steel column outer peripheral face;Wherein inter-tie lower edge is connected with the piston shoes.
3. a kind of absolute altitude such as large span spatial structure high position according to claim 1 is with post Sliding Structures, it is characterised in that:Institute State and rail hole was provided with by sliding steel column and sliding rail junction, this is crossed rail hole and is matched with the sliding rail;It is described Brace steel post and expansion shrouding is provided between sliding steel column.
CN201621304002.0U 2016-11-30 2016-11-30 A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures Active CN206289989U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621304002.0U CN206289989U (en) 2016-11-30 2016-11-30 A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621304002.0U CN206289989U (en) 2016-11-30 2016-11-30 A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures

Publications (1)

Publication Number Publication Date
CN206289989U true CN206289989U (en) 2017-06-30

Family

ID=59097548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621304002.0U Active CN206289989U (en) 2016-11-30 2016-11-30 A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures

Country Status (1)

Country Link
CN (1) CN206289989U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592984A (en) * 2016-11-30 2017-04-26 浙江精工钢结构集团有限公司 High-position equal-elevation with-column slipping structure and method for large-span space structure
CN111705932A (en) * 2020-06-22 2020-09-25 中国五冶集团有限公司 Large-span structure overhanging structure and curtain wall sliding construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592984A (en) * 2016-11-30 2017-04-26 浙江精工钢结构集团有限公司 High-position equal-elevation with-column slipping structure and method for large-span space structure
CN111705932A (en) * 2020-06-22 2020-09-25 中国五冶集团有限公司 Large-span structure overhanging structure and curtain wall sliding construction method

Similar Documents

Publication Publication Date Title
CN103741604B (en) Totally-prefabricated assembling type reinforced concrete bridge splicing structure and attaching method thereof
CN105421771B (en) It is a kind of not wait absolute altitude string stretching girders post accumulation slippage construction method
CN106592984A (en) High-position equal-elevation with-column slipping structure and method for large-span space structure
CN106351333A (en) Precast concrete slab column node and connecting method thereof
CN104863597B (en) A kind of construction method transverse direction hole lid method in shallow buried covered excavation Large Underground space
CN104963354B (en) Whole body embedded type rigid pedestal and construction method thereof
CN206289989U (en) A kind of absolute altitudes such as large span spatial structure high position band post Sliding Structures
CN105401741B (en) A kind of basement roof strengthening construction device and its construction method
CN205475249U (en) Landing stage structure that fetches earth under deep basal pit annular supports
CN204715366U (en) A kind of large-area deep foundation pit subregion is along the support system under inverse operating mode
CN204139628U (en) Large cantilever asymmetric space multistory truss auxiliary sliding device
CN206917026U (en) A kind of steel disc shape node component for special-shaped Curtain wall frame
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN111794267B (en) Construction method for foundation of construction elevator
CN105970822A (en) 50 m twin-deck overlane type movable scaffold and corresponding beam manufacturing construction method thereof
CN109594759A (en) The double-deck outer protection rack device of height-adjustable pin-connected panel and its application method
CN107587885A (en) Two lining trolley structures and assembling method in a kind of standard cross-section of tunnel
CN105155418A (en) Construction method for bridge horizontal movement
CN105926637B (en) The prestressing force support system and design of a kind of existing subway of protection
CN209082498U (en) Locator under a kind of pile foundation construction casing
CN204401626U (en) A kind of П type assembling sheet pile supporting and protection structure
CN202744960U (en) Large-span steel truss suspension bridge closure device
CN104563127B (en) A kind of Brace in Deep Footing Groove construction method
CN113373907A (en) Composite driving type snowflake type pile system and construction method
CN206128082U (en) Foundation fit base plate or floor slab rebar wear transform structure of shaped steel stand