CN206283191U - A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable - Google Patents

A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable Download PDF

Info

Publication number
CN206283191U
CN206283191U CN201621436134.9U CN201621436134U CN206283191U CN 206283191 U CN206283191 U CN 206283191U CN 201621436134 U CN201621436134 U CN 201621436134U CN 206283191 U CN206283191 U CN 206283191U
Authority
CN
China
Prior art keywords
cable
scaffold
extra large
logged
large cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621436134.9U
Other languages
Chinese (zh)
Inventor
袁舟龙
董益军
丁兆冈
张志刚
虞文杰
公言强
何旭涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hailan Engineering Company Zhejiang Zhoushan Qiming Power Group Co Ltd
State Grid Corp of China SGCC
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Hailan Engineering Company Zhejiang Zhoushan Qiming Power Group Co Ltd
State Grid Corp of China SGCC
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hailan Engineering Company Zhejiang Zhoushan Qiming Power Group Co Ltd, State Grid Corp of China SGCC, Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Hailan Engineering Company Zhejiang Zhoushan Qiming Power Group Co Ltd
Priority to CN201621436134.9U priority Critical patent/CN206283191U/en
Application granted granted Critical
Publication of CN206283191U publication Critical patent/CN206283191U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable, is related to submarine cable logon device, extremely difficult using traditional system of laying, and laying speed is slow, and frictional resistance is big on the way, and very big tractive force is needed when laying.The utility model includes extra large cable ship, extra large cable ship is sequentially provided with transition ditch and scaffold to the cable direction that goes out of transformer station, on scaffold since the transition ditch front end at interval of 300 ~ 800 meters between be uniformly provided with cable laying machine, each cable laying machine is equipped with strand grinding machine towards the side of transformer station, multiple floating moulding beds for supporting extra large cable are provided with along going out cable direction in transition ditch, fairlead is fixed with along going out the arrangement of cable direction on scaffold, and scaffold is provided with multiple extra large cable scaffold buffer tables for extra large cable buffering.The technical program reduces the frictional resistance in laid processes, reduces the damage caused to cable in laid processes, improves the security that extra large cable is laid, and accelerates intertidal belt submarine cable laying speed.

Description

A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable
Technical field
The utility model is related to submarine cable logon device, and especially one kind is logged in for long range intertidal zone submarine cable The operating system of cable laying operation.
Background technology
Because voltage levels, large load current determine that the cross-section of cable is big, substance big, intertidal zone has more complicated applying Extremely difficult using traditional system of laying if environment, laying speed is slow, and frictional resistance is big on the way, is needed when laying very big Tractive force, and tractive force is excessive, easily causes cable body, cable pulling brain injury, influence power cable is safe and reliable to operation Property.
Utility model content
The technical problems to be solved in the utility model and propose technical assignment be to prior art carry out improve with Improve, there is provided a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable, with solve over long distances tide between Band extra large cable is logged in for the purpose of operation technique equipment problem.Therefore, the utility model takes following technical scheme.
A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable, including extra large cable ship, it is described Extra large cable ship is sequentially provided with transition ditch and scaffold to the cable direction that goes out of transformer station, on described scaffold since transition ditch front end Cable laying machine uniformly is provided with interval of between 300 ~ 800 meters, each cable laying machine is equipped with strand grinding machine, institute towards the side of transformer station Multiple floating moulding beds for supporting extra large cable are provided with along going out cable direction in the transition ditch stated, along going out cable direction row on described scaffold Row are fixed with fairlead, and described scaffold is provided with multiple extra large cable scaffold buffer tables for extra large cable buffering.By twisting The steel wire rope of grinding machine traction extra large cable front end, the extra large cable that traction is pulled out from extra large cable ship, and extra large cable is located in the middle of floating moulding bed top surface, warp By cable laying machine, fairlead and extra large cable scaffold buffer table, lay forward successively, until transformer station, lays conveniently, safely may be used Lean on.
Used as further improving and supplementing to above-mentioned technical proposal, the utility model also includes that following supplementary technology is special Levy.
Side of the described extra large cable scaffold buffer table located at each strand grinding machine position.Extra large cable scaffold buffer table The position of grinding machine side is twisted located at cable laying machine side rear, is easy to the buffering of extra large cable to place, it is operationally more convenient.
Floating moulding bed described in each keeps flat the tyre bead of adjacent regions in the middle of colligation, tied rope colligation, colligation for 2 one group of floating tires Floating moulding bed the widest part afterwards is 2 times of floating tire diameter.2 one group of square of colligations, increased buoyancy, and extra large cable is fixed on two The lashing location of the centre above floating tire, makes floating moulding bed be folded upward at from centre using extra large cable gravity, makes extra large cable(7)It is suspended in water In, prevent extra large cable side from slipping.
Transitional region of the described transition ditch located at the adjacent extra large cable ship in intertidal zone.Due to the ambiguity feature of transitional region, By the way of ditching, then can easily make extra large cable be suspended in water by floating moulding bed to pass through, reduce when extra large cable is laid Resistance.
Between 1 ~ 1.8 meter described of the transition ditch depth of water, between 1.5 ~ 2.5 meters wide.The size range is easy to excavate and extra large cable Lay and with the space in making extra large cable be suspended in water.
Described scaffold is divided into support frame, scaffold upper strata and scaffold lower floor, and described support frame includes steel The joint managed and be fixedly connected steel pipe, described scaffold upper strata and scaffold lower floor is laid and is fixed by bed board, described Fairlead, cable laying machine, strand grinding machine are located at scaffold upper strata, and the both sides of described scaffold lower floor are provided with is extended with bed board Erect position.Upper strata scaffold draws platform as extra large cable, by two-layer scaffold, increased the support force and structure of scaffold Intensity, scaffold lower floor sets standing when erect position is easily installed operation.
Described fairlead is to be set to the pulley being fixed on scaffold by nip roll, and described pulley is included along pin hand Frame orientation pulley arranged in a straight line and the angle pulley turned to for extra large cable.Pulley application is universal, and simple structure is easy for installation, Low cost.
Described orientation pulley and angle pulley include pulley fixed frame and pulley body, described pulley fixed frame by Pipe is welded, and the race of described pulley is circular cross-section groove, and race section radius are more than extra large cable radius.Pulley fixed frame Facilitated by pipe welding manufacture, and shape can be designed according to actual needs, and race section radius are easy to sea more than extra large cable radius Cable is positioned in race and the lower end of extra large cable can abut in the wheel trench bottom of pulley, improves support effect, makes extra large cable in cunning There is preferable sliding effect on wheel.
Described transition ditch and scaffold is fold-line-shaped arrangement.Fold-line-shaped arrangement makes the extra large cable between transformer station and extra large cable ship Length is more than straight length, makes extra large cable relative loose, not tight.
Beneficial effect:The frictional resistance in laid processes is reduced, the damage caused to cable in laid processes is reduced, The security that extra large cable is laid is improved, intertidal belt submarine cable laying speed is accelerated.
Brief description of the drawings
Fig. 1 is the utility model engineering schematic layout pattern.
Fig. 2 is that the floating moulding bed extra large cable of the utility model places schematic diagram.
Fig. 3 is the utility model pulley structure schematic diagram.
Fig. 4 is the utility model scaffold and pulley arrangement structural representation.
In figure:1- extra large cable ships;2- ship anchors;3- transition ditches;4- intertidal zones;5- cable laying machines;6- twists grinding machine;7- extra large cables;8- becomes Power station;9- scaffolds;10- extra large cable scaffold buffer tables;11- floats moulding bed;12- pulleys;901- scaffolds upper strata;902- pin hands Frame lower floor;903- erect positions;904- steel pipes;905- joints;906- nip rolls;907- bed boards;1101- tied ropes;1102- floats tire; 1201- pulley fixed frames;1202- pulley bodies.
Specific embodiment
The technical solution of the utility model is described in further detail below in conjunction with Figure of description.
As Figure 1-4, a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable, including sea Cable ship 1, described extra large cable ship 1 is sequentially provided with transition ditch 3 and scaffold 9, described scaffold 9 to the cable direction that goes out of transformer station 8 On since the front end of transition ditch 3 at interval of 300 ~ 800 meters between be uniformly provided with cable laying machine 5, each cable laying machine 5 is towards transformer station 8 side is equipped with strand grinding machine 6, and multiple floating moulding beds for supporting extra large cable 7 are provided with along going out cable direction in described transition ditch 3 11, fairlead is fixed with along going out the arrangement of cable direction on described scaffold 9, described scaffold 9 is provided with multiple for sea The extra large cable scaffold buffer table 10 of the buffering of cable 7.The steel wire rope of the front end of extra large cable 7 is drawn by twisting grinding machine 6, traction is drawn from extra large cable ship 1 The extra large cable 7 for going out, and extra large cable 7 is located in the middle of the floating top surface of moulding bed 11, buffered via cable laying machine 5, fairlead and extra large cable scaffold Platform 10, lays forward successively, until transformer station 8, lays conveniently, it is safe and reliable.
For the convenience that the buffering of extra large cable 7 is placed, described extra large cable scaffold buffer table 10 is where each strand grinding machine 6 The side of position.Extra large cable scaffold buffer table 10 is twisted located at the side rear of cable laying machine 5 position of the side of grinding machine 6, be easy to extra large cable 7 Buffering is placed, operationally more convenient.
For the ease of placing extra large cable 7 and preventing the side of extra large cable 7 from slipping, the floating moulding bed 11 of each described is 2 1,102 1 groups of floating tires The tyre bead of adjacent regions in the middle of colligation, the colligation of tied rope 1101 is kept flat, the widest part of floating moulding bed 11 after colligation is 2 times of floating tire 1102 Diameter.2 one group of square of colligations, increased buoyancy, and extra large cable 7 is fixed on the colligation position of the centre above two floating tires 1102 Put, floating moulding bed 11 is folded upward at from centre using the gravity of extra large cable 7, extra large cable 7 is suspended in water, and prevent the side of extra large cable 7 from slipping.
For the ease of laying extra large cable 7 in transitional region, described transition ditch 3 is located at the transition of the adjacent extra large cable ship 1 in intertidal zone 4 Region.Due to the ambiguity feature of transitional region, by the way of ditching, then extra large cable 7 can easily be made by floating moulding bed 11 Suspended in water and passed through, reduce resistance when extra large cable 7 is laid.
Laid with extra large cable 7 for the ease of excavating, 1.5 meters described of 3 depth of water of transition ditch is wide 2 meters.The size be easy to excavate and Extra large cable 7 is laid and with the space in making extra large cable be suspended in water.
In order to increase the support strength of scaffold 9,9 points described of scaffold is support frame, scaffold upper strata 901 and pin Hand cradle lower floor 902, described support frame includes steel pipe 904 and the joint 905 for being fixedly connected steel pipe, described scaffold upper strata 901 and scaffold lower floor 902 laid by bed board 907 and fixed, described fairlead, cable laying machine 5, twist grinding machine 6 and be located at Scaffold upper strata 901, the both sides of described scaffold lower floor 902 are provided with the erect position 903 extended with bed board 907.Upper strata pin Hand cradle 9 draws platform as extra large cable 7, by two-layer scaffold 9 and support frame, increased the support force and structure of scaffold 9 Intensity, scaffold lower floor 902 sets standing when erect position is easily installed operation.
In order to simplify structure, convenient to install, described fairlead is to be fixed on scaffold upper strata 901 by nip roll 906 Pulley 12, described pulley 12 includes that the steering turned to along the orientation pulley arranged in a straight line of scaffold 9 and for extra large cable 7 is slided Wheel.The application of pulley 12 is universal, simple structure, low cost.
There are preferable sliding effect, described orientation pulley and steering on pulley 12 for the ease of manufacturing and making extra large cable 7 Pulley includes pulley fixed frame 1201 and pulley body 1202, and described pulley fixed frame 1201 is welded by pipe, institute The race of the pulley body 1202 stated is circular cross-section groove, and race section radius are more than the radius of extra large cable 7.Pulley fixed frame 1201 by Pipe welding manufacture is convenient, and shape can be designed according to actual needs, and race section radius are easy to extra large cable more than the radius of extra large cable 7 7 are positioned in race and the lower end of extra large cable 7 can abut in the wheel trench bottom of pulley body 1202, improve support and lead cable effect Really.
In order that extra large cable 7 is not tight, described transition ditch 3 and scaffold 9 is fold-line-shaped arrangement.Fold-line-shaped arrangement makes power transformation The length of extra large cable 7 stood between 8 and extra large cable ship 1 is more than straight length, makes the relative loose of extra large cable 7, not tight.
A kind of operation process following steps of the operating system that cable laying operation is logged in for long range intertidal zone submarine cable:
1 transitional region near intertidal zone 4 and extra large cable ship 1 digs transition ditch 3, and row sets floating moulding bed 11 in transition ditch 3;
2 set up double-deck scaffold 9 since the front end of transition ditch 3 to the direction of transformer station 8;
3 set cable laying machine 5 one by one since the scaffold 9 of the front end of transition ditch 3, and going out cable direction in each cable laying machine 5 is set Twist grinding machine 6;
4 walk cable direction on scaffold 9 along extra large cable 7 lays pulley 12, and angle pulley is laid in the pin hand of the turning point of extra large cable 7 On frame 9;
Lead cable frame of 5 extra large cables 7 from extra large cable ship 1 is passed through, and the steel wire rope of the front end of extra large cable 7 is moved on strand grinding machine 6, is ground by twisting The operating pulling steel wire rope of machine 6 makes extra large cable 7 go out cable, and sea is positioned in the middle of floating moulding bed 11 after going out cable, due to the gravity of extra large cable 7, floats tire Frame 11 sinks and closes up upwards, and the floating bottom of moulding bed 11 suspends in water;
The front end of 6 extra large cable 7 passes through cable laying machine 5, and draws clamping by cable laying machine 5, in extra large cable 7 by after first cable laying machine 5, The steel wire rope of the front end of extra large cable 7 is pulled to next strand grinding machine 6 along fairlead, is drawn by next strand grinding machine 6, and extra large cable 7 is by sea Go out cable forward along fairlead again after cable scaffold buffer table 10, and by above same operation until transformer station 8.
In this example, extra large cable ship 1 is gone out before cable and is cast anchor fixation by 4 ship anchors for being distributed in corner;Cable laying machine 5 leads for 8 tons Gravitation;Strand grinding machine 6 is 3 tons of tractive force.
A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable shown in Fig. 1-4 is this practicality New specific embodiment, has embodied the utility model substantive distinguishing features and progress, can according to actual use needs, Under enlightenment of the present utility model, carry out the equivalent modifications of the aspects such as shape, structure to it, this programme protection domain it Row.

Claims (9)

1. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable, including extra large cable ship(1), its feature It is:Described extra large cable ship(1)To transformer station(8)The cable direction that goes out be sequentially provided with transition ditch(3)And scaffold(9), it is described Scaffold(9)On from transition ditch(3)Front end starts uniformly to be provided with cable laying machine at interval of between 300 ~ 800 meters(5), each cloth cable Machine(5)Towards transformer station(8)Side be equipped with strand grinding machine(6), described transition ditch(3)Middle edge goes out cable direction and is provided with multiple use In support extra large cable(7)Floating moulding bed(11), described scaffold(9)Upper edge goes out the arrangement of cable direction and is fixed with fairlead, described Scaffold(9)It is provided with multiple for extra large cable(7)The extra large cable scaffold buffer table of buffering(10).
2. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 1, It is characterized in that:Described extra large cable scaffold buffer table(10)Located at each strand grinding machine(6)The side of position.
3. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 1, It is characterized in that:Floating moulding bed described in each(11)It is 2 floating tires(1102)One group keeps flat colligation, tied rope(1101)In the middle of colligation The tyre bead of adjacent regions, the floating moulding bed after colligation(11)The widest part is 2 times of floating tire(1102)Diameter.
4. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 1, It is characterized in that:Described transition ditch(3)Located at intertidal zone(4)Adjacent extra large cable ship(1)Transitional region.
5. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 4, It is characterized in that:Described transition ditch(3)Between 1 ~ 1.8 meter of the depth of water, between 1.5 ~ 2.5 meters wide.
6. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 1, It is characterized in that:Described scaffold(9)It is divided into support frame, scaffold upper strata(901)With scaffold lower floor(902), it is described Support frame include steel pipe(904)With the joint for being fixedly connected steel pipe(905), described scaffold upper strata(901)With pin hand Frame lower floor(902)By bed board(907)Lay and fix, described fairlead, cable laying machine(5), twist grinding machine(6)It is located at pin Hand cradle upper strata(901), described scaffold lower floor(902)Both sides be provided with and use bed board(907)The erect position for extending(903).
7. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 6, It is characterized in that:Described fairlead is by nip roll(906)It is fixed on scaffold upper strata(901)Pulley(12), it is described Pulley(12)Including along scaffold(9)Orientation pulley arranged in a straight line and for extra large cable(7)The angle pulley of steering.
8. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 7, It is characterized in that:Described orientation pulley and angle pulley include pulley fixed frame(1201)And pulley body(1202), institute The pulley fixed frame stated(1201)It is welded by pipe, described pulley body(1202)Race be circular cross-section groove, wheel Slot cross-section radius is more than extra large cable(7)Radius.
9. a kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable according to claim 1, It is characterized in that:Described transition ditch(3)And scaffold(9)For fold-line-shaped is arranged.
CN201621436134.9U 2016-12-26 2016-12-26 A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable Active CN206283191U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621436134.9U CN206283191U (en) 2016-12-26 2016-12-26 A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621436134.9U CN206283191U (en) 2016-12-26 2016-12-26 A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable

Publications (1)

Publication Number Publication Date
CN206283191U true CN206283191U (en) 2017-06-27

Family

ID=59071795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621436134.9U Active CN206283191U (en) 2016-12-26 2016-12-26 A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable

Country Status (1)

Country Link
CN (1) CN206283191U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786193A (en) * 2016-12-26 2017-05-31 浙江舟山启明电力集团公司海缆工程公司 Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN110556745A (en) * 2019-08-30 2019-12-10 北京海瑞兴能源科技有限责任公司 Cable tension monitoring method for landing section cable laying system
CN114825187A (en) * 2022-05-09 2022-07-29 南通市海洋水建工程有限公司 220kV submarine cable embankment-crossing repair construction method for offshore wind farm foundation construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786193A (en) * 2016-12-26 2017-05-31 浙江舟山启明电力集团公司海缆工程公司 Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN106786193B (en) * 2016-12-26 2018-08-21 浙江舟山启明电力集团公司海缆工程公司 Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN110556745A (en) * 2019-08-30 2019-12-10 北京海瑞兴能源科技有限责任公司 Cable tension monitoring method for landing section cable laying system
CN114825187A (en) * 2022-05-09 2022-07-29 南通市海洋水建工程有限公司 220kV submarine cable embankment-crossing repair construction method for offshore wind farm foundation construction
CN114825187B (en) * 2022-05-09 2024-05-10 南通市海洋水建工程有限公司 220KV sea cable dike crossing restoration construction method for offshore wind farm foundation construction

Similar Documents

Publication Publication Date Title
CN106786193B (en) Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN206283191U (en) A kind of operating system that cable laying operation is logged in for long range intertidal zone submarine cable
CN212210305U (en) Transmission line strides across block structure
CN109506044A (en) A kind of pipeline under the ocean construction technology
CN105952967B (en) A kind of immersed tube operational method using floating ball sinking pipeline
CN103452117A (en) Deepwater bagged sand construction device and deepwater bagged sand construction technology
CN105905815A (en) Work method of seating-type self-balance holding pole
CN102094412B (en) Mud-water amphibious plate-inserting device for soft foundation
CN212863938U (en) Pipeline embedding device for hydraulic engineering
WO2023025325A1 (en) Construction method for corrugated pipe to pass through pipeline by means of rail sliders in small underground space
CN107165124A (en) A kind of deep water soft raft is to drawing laying construction method
CN103332271B (en) A kind of blast is used can travelling floating platform
CN201924338U (en) Mud-water amphibious soft foundation spile device
CN108018778B (en) Catwalk cable erection traction system and catwalk cable rapid erection method for non-navigable water area
CN108590676A (en) A kind of shield machine front carriage track platform
CN206466801U (en) A kind of lift cable unreeling rack
CN202405729U (en) Cable protection device at pipe well head
CN206986897U (en) A kind of tethered sliding formula toe slab grouting system
CN213139094U (en) Mooring head rotation test device
CN207466909U (en) A kind of dynamic traction device suitable for soft raft mattress sinking construction
CN208416564U (en) Two grommets with mobile arc track are to reinforcing steel bar laying trolley
CN106505479A (en) High-rise shelf cable laying method and device in tunnel
CN201310105Y (en) Dredging and leveling device
CN207775722U (en) The cat road rope in navigable waters does not set up trailer system
CN204992430U (en) Novel perpendicular circulation of cable is laid device