CN206279440U - A kind of pull rod device for improving Single column pier bridge anti-overturning energy - Google Patents

A kind of pull rod device for improving Single column pier bridge anti-overturning energy Download PDF

Info

Publication number
CN206279440U
CN206279440U CN201621171603.9U CN201621171603U CN206279440U CN 206279440 U CN206279440 U CN 206279440U CN 201621171603 U CN201621171603 U CN 201621171603U CN 206279440 U CN206279440 U CN 206279440U
Authority
CN
China
Prior art keywords
pull rod
single column
fork ear
pier stud
rod device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621171603.9U
Other languages
Chinese (zh)
Inventor
李攀
王文彪
盛勇
孙铁元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201621171603.9U priority Critical patent/CN206279440U/en
Application granted granted Critical
Publication of CN206279440U publication Critical patent/CN206279440U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model is related to a kind of pull rod device for improving Single column pier bridge anti-overturning energy, it is characterized in that being respectively provided with pull rod device in pier stud both sides, the pull rod device includes setting up separately the reinforcing pull rod of pier stud both sides, and the two ends of the reinforcing pull rod are fixed on beam bottom and pier stud by length adjustment mechanism respectively.Initial drawing, pressure are produced by adjusting reinforcing pull rod active length, to ensure that reinforcing pull rod is in running order all the time during overturn-preventing.The utility model mainly using the high-strength Anti-pull-press ability of steel, the anti-overturning energy of Single column pier bridge can be greatly improved using light-duty construction.The reinforcing pull rod of built-in monitoring module can real-time monitoring heavy duty, the situation by bridge of unbalance loading vehicle.The utility model proposes one, compared with other, raising Single column pier bridge antidumping performance methodology construction more facilitates, deadweight is lighter, be more easy to the method and thinking of maintenance, there is promotional value higher at aspects such as applicability, economy, high efficiency, improving anti-overturning to numerous built Single column pier bridges can provide reliable guarantee.

Description

A kind of pull rod device for improving Single column pier bridge anti-overturning energy
Technical field
The utility model is related to the overhaul of bridge, field of reinforcement, specifically a kind of to resist for improving Single column pier bridge The pull rod device of performance of toppling, and can be with real-time monitoring heavy-duty vehicle by situation, the risk of toppling to Single column pier bridge is done To it is early know, early prevention.
Background technology
Currently, only post Cast-in-Situ Continuous Beam structure type is used the curve bridge such as China's city intersection, high speed ring road more, should Planting the substructure form of bridge has the advantages that reduction occupation of land, the increase visual field and bridge are attractive in appearance.But current China load-carrying vehicle Generally existing overloading, individual vehicle overload even up to 200%~300%, causes this kind of bridge of structure type using During there are a lot of capsizing cases.
The bending resistance for focusing on bridge of current Bridge Design person's concern, shear resistant capacity aspect are accidental for bias Overload effect concern is not enough.Recent year Single column pier Continuous Box Girder Bridge capsizing case frequently occurs, and gradually causes related personnel Self-examination.To find out its cause, most accident bridge pier column direction across bridge are using single fulcrum support, under overloaded vehicle uneven loading action, knot The horizontal anti-overturning of structure is poor, and especially the bridge floor of only post ring road box girder bridge is narrow, conducts oneself with dignity small, and vehicular load is in Load Combination In shared ratio it is great.Simultaneously as existing the standard of highway bridge is for regulation of the transverse overturning stability without correlation, place The bridge lateral Stability Numerical Analysis under eccentric accidentally overload effect can often be ignored again when space state, design so that Structure under accidental action is using bringing hidden danger.
It is more complicated Mechanics Phenomenon that structure is toppled, and belongs to the category of bearing nonlinear analysis.Before structure is toppled, must Bearing so can be first produced to bias or even come to nothing phenomenon.After seat empty, the bearing for coming to nothing loses the supporting role to structure, only It is left remaining bearing and constraint is produced to structure, this inevitably results in the redistribution of end reaction, necessarily occurs during this Such as bearing vertical pressure causes support damage more than susceptor design intensity, and the deformation of bearing corner is excessive caused during toppling Girder slippage phenomenon, therefore structure topples with whether seat supports effect is failed and be closely related.
Utility model content
The purpose of this utility model is to provide a kind of pull rod device for improving Single column pier bridge anti-overturning energy, Single column pier sets reinforcing pull rod with box beam bottom, and by postponing the critical condition of bearing bias destruction, to improve, Single column pier bridge is anti-to incline Cover performance.
To achieve these goals, the technical solution of the utility model is as follows:For improving, Single column pier bridge is anti-to incline one kind Cover the pull rod device of performance, it is characterised in that be respectively provided with pull rod device in pier stud both sides, the pull rod device includes setting up pier separately The reinforcing pull rod of post both sides, the two ends of the reinforcing pull rod are fixed on beam bottom and pier stud by length adjustment mechanism respectively.
According to preferred embodiment of the present utility model, beam bottom billet is bolted on the girder beam of pier stud both sides Bottom, pier stud billet is fixed by bolts to the side of pier stud both sides, and billet lower section in beam bottom is provided with fork ear, foot stall steel pad It is provided with lower fork ear above plate, the upper fork ear screw corresponding with the setting of lower fork ear, the top of reinforcing pull rod is arranged on fork ear Screw in, the bottom of reinforcing pull rod is arranged in the screw of lower fork ear, and the upper and lower part of reinforcing pull rod is respectively provided with opposite spiral shell Line, is provided with the point of application in the middle part of reinforcing pull rod, and moment of face is applied at the point of application, adjusts reinforcing pull rod active length.
According to preferred embodiment of the present utility model, the point of application is provided with force application structure, the horizontal stroke of the force application structure Section outline is polygon, is easy to exert a force the point of application by mechanical device.
According to preferred embodiment of the present utility model, the built-in detection module of reinforcing pull rod, real-time monitoring heavy duty, unbalance loading car By the situation of bridge, by online acquisition, the means of collection are patrolled and examined, implement transmission data through cloud platform, to mobile phone or electricity Brain terminal, to judge time place of the overloaded vehicle by bridge.
The obvious technical characterstic that the utility model is made up of such scheme feature:First, being anchored in beam bottom and pier stud On connector and reinforcing pull rod, pier stud is connected as one with box beam, moulding is more succinct, deadweight lighter and late maintaining is more square Just, strong adaptability is easily promoted.Second, the reinforcing pull rod of built-in monitoring module can real-time monitoring heavy duty, unbalance loading vehicle by bridge Situation, by online acquisition, patrol and examine the means of collection, implement transmission data through cloud platform, to mobile phone or computer terminal, pass through Data analysis accurately to judge time place of the overloaded vehicle by bridge, for relevant departments' overload remediation provides effective means.This Utility model proposes one, and raising Single column pier bridge antidumping performance methodologies construction more facilitates, deadweight is lighter compared with other, be more easy to The method and thinking of maintenance, have promotional value higher at aspects such as applicability, economy, high efficiency, to numerous built Single column pier bridge improves anti-overturning and can provide reliable guarantee.
Brief description of the drawings
Fig. 1 is pull rod device direction across bridge structural map of the present utility model.
Fig. 2 is for pull rod device of the present utility model along bridge to structural map.
Fig. 3 is scheme of installation of the present utility model.
Fig. 4 is on-line monitoring schematic diagram.
Figure includes:Girder 1, pier stud 2, beam bottom billet 3, bolt 4, pier stud billet 5, upper fork ear 6, lower fork ear 7, steel Pull bar 8, locking bolt 9, the point of application 10.
Specific embodiment
The utility model is explained in detail with reference to the accompanying drawings and examples.
As depicted in figs. 1 and 2, bearing is provided between the beam bottom of girder 1 and pier stud 2, beam bottom billet 3 is passed through into bolt 4 The beam bottom of girder 1 of the both sides of pier stud 2 is fixed on, pier stud billet 5 is fixed on the side of pier stud both sides, beam bottom steel pad with bolt 4 The lower section of plate 3 is provided with fork ear 6, and the top of pier stud billet 5 is provided with lower fork ear 7, and upper fork ear is corresponding with the setting of lower fork ear Screw, the top of reinforcing pull rod 8 is arranged in the screw of fork ear 6, and the bottom of reinforcing pull rod 8 is arranged in the screw of lower fork ear 7, The upper and lower part of reinforcing pull rod 8 is respectively provided with opposite screw thread, and the point of application 10 is provided with the middle part of reinforcing pull rod 8, in the point of application 10 Place applies moment of face so that reinforcing pull rod 8 is tightened and connected as one with upper fork ear 6, the screw thread of lower fork ear 7, and wherein reinforcing pull rod 8 can pass through Tighten how much length carrys out adjustment length, being provided with for adjusting means is beneficial to construct and can solve the problems, such as construction error.Beam bottom steel pad The lower section of plate 3 is provided with the upper clip for disposing upper fork ear 6, and the top of pier stud billet 5 is provided with for disposing lower fork ear 7 Lower clamping piece, upper fork ear 6 and lower fork ear 7 are fixed on upper clip and lower clamping piece by locking bolt 9 respectively.
By taking Fig. 3 as an example, the design and installation process of pull rod device are illustrated.Determine that pull bar is reasonable according to concrete engineering is actual Installation site, with former bearing centre distance be d at its vertical beam bottom support, with beam bottom distance be H at pier stud fulcrum;According to both Fixed antidumping coefficient requirements, then can obtain the maximum weighted design load F of pull rod device, and then can determine that cutting for pull rod device Face size;The active length h of reinforcing pull rod 8 is primarily determined that, then reinforcing pull rod two ends are screwed into upper fork ear, lower fork ear, by regulation Tighten length and carry out adjustment work length, be beneficial to construction and installation, its maximum adjustable length is(L1+L2)/ 2, wherein L1, L2 point Not Wei reinforcing pull rod 8 initially expose the threaded upper ends length of fork ear, and initially expose lower end reach outside lower fork ear, figure Middle h1 is the height of upper fork ear, and h2 is the height of lower fork ear;After regulation to design length, upper fork ear 6 is put into upper clip, under Fork ear 7 is put into lower clamping piece, and installs locking bolt 9, and upper fork ear 6 and lower fork ear 7 are fixed, then 10 in the middle part of the reinforcing pull rod at Apply moment of face, continue to tighten reinforcing pull rod 8 so that reinforcing pull rod 8 produces starting force, its value is about 5%F, and the big I of force value passes through steel Monitoring modular control built-in in pull bar 8.
As shown in figure 4, the built-in detection module of reinforcing pull rod, the situation that real-time monitoring heavy duty, unbalance loading vehicle pass through bridge, By online acquisition, the means of collection are patrolled and examined, implement transmission data through cloud platform, to mobile phone or computer terminal, to judge to surpass Carry time place of the vehicle by bridge.
The above is only preferred embodiment of the present utility model, it is noted that for the common skill of the art Art personnel, on the premise of the utility model principle is not departed from, can also make some improvements and modifications, these improvements and modifications Should be regarded as protection domain of the present utility model.

Claims (5)

1. it is a kind of for improve Single column pier bridge anti-overturning can pull rod device, it is characterised in that be respectively provided with pier stud both sides Pull rod device, the pull rod device includes setting up separately the reinforcing pull rod of pier stud both sides, and the two ends of the reinforcing pull rod are adjusted by length respectively Section mechanism is fixed on beam bottom and pier stud.
2. it is used to improve the pull rod device of Single column pier bridge anti-overturning energy as claimed in claim 1, it is characterised in that:Beam bottom Billet is bolted on the girder beam bottom of pier stud both sides, and pier stud billet is fixed by bolts to the side of pier stud both sides Face, beam bottom billet lower section is provided with fork ear, and lower fork ear is provided with above pier stud billet, and upper fork ear and lower fork ear are set Corresponding screw, the top of reinforcing pull rod is arranged in the screw of fork ear, and the bottom of reinforcing pull rod is arranged on the screw of lower fork ear Interior, the upper and lower part of reinforcing pull rod is respectively provided with opposite screw thread, and the point of application is provided with the middle part of reinforcing pull rod.
3. it is used to improve the pull rod device of Single column pier bridge anti-overturning energy as claimed in claim 1, it is characterised in that:Beam bottom Billet lower section is provided with the upper clip for disposing upper fork ear, is provided with above pier stud billet for disposing lower fork ear Lower clamping piece, upper fork ear and lower fork ear are fixed on upper clip and lower clamping piece by locking bolt respectively.
4. it is used to improve the pull rod device of Single column pier bridge anti-overturning energy as claimed in claim 2, it is characterised in that:It is described The point of application is provided with force application structure, and the outline of the force application structure is polygon.
5. as any one of claim 1 ~ 4 for improve Single column pier bridge anti-overturning can pull rod device, it is special Levy and be:The built-in detection module of reinforcing pull rod.
CN201621171603.9U 2016-10-26 2016-10-26 A kind of pull rod device for improving Single column pier bridge anti-overturning energy Active CN206279440U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621171603.9U CN206279440U (en) 2016-10-26 2016-10-26 A kind of pull rod device for improving Single column pier bridge anti-overturning energy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621171603.9U CN206279440U (en) 2016-10-26 2016-10-26 A kind of pull rod device for improving Single column pier bridge anti-overturning energy

Publications (1)

Publication Number Publication Date
CN206279440U true CN206279440U (en) 2017-06-27

Family

ID=59082111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621171603.9U Active CN206279440U (en) 2016-10-26 2016-10-26 A kind of pull rod device for improving Single column pier bridge anti-overturning energy

Country Status (1)

Country Link
CN (1) CN206279440U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532474A (en) * 2018-03-29 2018-09-14 中冶华天工程技术有限公司 A kind of the overturn-preventing bracing means and installation method of Single column pier bridge
CN111576188A (en) * 2020-05-14 2020-08-25 上海市政工程设计研究总院(集团)有限公司 Steel construction bridge antidumping structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532474A (en) * 2018-03-29 2018-09-14 中冶华天工程技术有限公司 A kind of the overturn-preventing bracing means and installation method of Single column pier bridge
CN111576188A (en) * 2020-05-14 2020-08-25 上海市政工程设计研究总院(集团)有限公司 Steel construction bridge antidumping structure

Similar Documents

Publication Publication Date Title
CN106436557A (en) Method for improving overturning resistance of single-column pier bridge
CN103452053B (en) The antidumping bracing means of Single column pier bridge
CN204589822U (en) The two cantilever bent cap anchor ear Construction Support system of a kind of solely post
CN205313989U (en) Single -column mound bridge antidumping structure
CN103086282A (en) Intelligent early warning outside climbing system for heavy construction crane
CN206279440U (en) A kind of pull rod device for improving Single column pier bridge anti-overturning energy
CN203096598U (en) Outer cladding type steel-concrete combined structure beam bridge overturn-resistant device
CN206721653U (en) A kind of Single column pier bridge adds steel structure support antidumping bracing means
CN210134353U (en) Bracket type hoop bracket for bent cap construction
CN202433253U (en) Auxiliary device for pull-out test of hooked anchors
CN208056592U (en) A kind of tool-type inspection platform
CN202482772U (en) Collapse-proof stop block mounting system for railway bridge
CN205329738U (en) Novel umbelliform ground bearing capacity detecting device
CN109667228B (en) Straight beam type hanging basket and continuous beam cantilever pouring construction method
CN208668289U (en) Punching stick anchor ear support device
CN204876631U (en) Assembled steel structure installation uses interim support frame
CN202595640U (en) Anti-dumping reinforced tension device for bridge
CN203099228U (en) Anchor bolt leveling structure
CN201843081U (en) Flexible leg anchoring device of bridge girder erection machine with single nose girder
CN205313969U (en) Intelligent support
CN210268621U (en) Adjustable anti-loss foundation anchor rod
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN208964354U (en) For horizontal or low-angle moving sidewalk truss medial support structures
CN202688880U (en) Transverse prestress tension auxiliary device
CN217026738U (en) Bridge engineering bent cap construction bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant