CN206256930U - A kind of safety pre-warning system of constructing tunnel - Google Patents

A kind of safety pre-warning system of constructing tunnel Download PDF

Info

Publication number
CN206256930U
CN206256930U CN201621264393.8U CN201621264393U CN206256930U CN 206256930 U CN206256930 U CN 206256930U CN 201621264393 U CN201621264393 U CN 201621264393U CN 206256930 U CN206256930 U CN 206256930U
Authority
CN
China
Prior art keywords
warning
data
constructing tunnel
analysis
safety pre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621264393.8U
Other languages
Chinese (zh)
Inventor
王志杰
季晓峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201621264393.8U priority Critical patent/CN206256930U/en
Application granted granted Critical
Publication of CN206256930U publication Critical patent/CN206256930U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of safety pre-warning system of constructing tunnel, including filed detection system, data collecting system, data transmission system, information early warning analysis system, center control platform and prior-warning device;The filed detection system includes sensor and detection means, and the filed detection system is connected by CAN with data collecting system;The data transmission system includes the micro-control module and the data transmission module that are sequentially connected;The data collecting system gathers the data by filed detection system detection and is transferred to information early warning analysis system by the data transmission system and is analyzed;Analysis result is transferred to center control platform by described information prewarning analysis system;Described information prewarning analysis system controls the opening and closing of prior-warning device according to analysis result;The opening and closing of the center control platform control data acquisition system.

Description

A kind of safety pre-warning system of constructing tunnel
Technical field
The utility model belongs to technical field of tunnel construction, more particularly to a kind of safety pre-warning system of constructing tunnel.
Background technology
China's tunnel construction is presented large-scale high speed development trend in recent years, but due to the unilateral pursuit duration, over the ground The objective law of lower engineering recognize impenetrable it is thorough, construction with design there is deviation, field management not science, workmen's awareness of safety Numerous reasons such as thin, cause the security incident that taken place frequently during constructing tunnel.Therefore constructing tunnel especially excessive risk ground In the constructing tunnel of matter section, the safe early warning of construction seems and is even more important, and unit in charge of construction can not only in time be obtained by early warning information The field condition of constructing tunnel is taken, and can effectively instruct constructing tunnel, it is ensured that the safe construction in tunnel.
In traditional tunnel monitoring, generally based on the pattern of " personal monitoring, papery report ", because constructing tunnel is existing The interference of the complexity and human factor of field, causes the authenticity of Site Detection data poor with reliability, and construction information is often Cannot in time, correctly feed back so that manager is difficult to, to the whole real-time management of construction, greatly hinder tunnel Information-aided construction.
Utility model content
Based on above-mentioned the deficiencies in the prior art, technical problem to be solved in the utility model is to provide one kind and can obtain in real time Take tunnel construction site security situation and can real-time management tunnel construction site early warning system.
The technical scheme that the utility model solution above-mentioned technical problem is used is for a kind of safe early warning system of constructing tunnel System, including filed detection system, data collecting system, data transmission system, information early warning analysis system, center control platform and Prior-warning device;The filed detection system includes sensor and detection means, and the filed detection system passes through CAN and number Connected according to acquisition system;The data transmission system includes the micro-control module and the data transmission module that are sequentially connected;The number According to acquisition system collection information early warning point is transferred to by the data of filed detection system detection and by the data transmission system Analysis system is analyzed;Analysis result is transferred to center control platform by described information prewarning analysis system;Described information early warning Analysis system controls the opening and closing of prior-warning device according to analysis result;The center control platform control data collection system The opening and closing of system.
Filed detection system be able to will simultaneously be detected by sensor and detection means real-time detection tunnel construction site environment As a result real-time Transmission is to information early warning analysis system.Information early warning analysis system is compared by by testing result with preset value Can confirm that tunnel construction site whether there is potential safety hazard, and prior-warning device can be passed through in time when there is potential safety hazard Reminded, be easy to commanding's remote command and the staff at tunnel scene to make timely counter-measure.Information early warning Analysis result is transferred to center control platform by analysis system, is easy to commanding to control tunnel construction site situation in real time.It is logical Cross the safe of CAN transmission data and the degree of accuracy is high, help timely and accurately to transmit the detection of filed detection system Data.The CAN is the abbreviation of controller local area network, is one of fieldbus for being most widely used in the world.
As a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the center control platform and data Between transport module, between micro-control module and data collecting system, between data transmission module and information early warning analysis system, Wireless communication is used between information early warning analysis system and center control platform and prior-warning device.Carried out by wireless network Communication may insure that the commanding under any circumstance positioned at center control platform can remotely and in real time grasp tunnel The situation of job site, it is also possible to notify the staff of tunnel construction site in time in the case where there is any potential safety hazard.
As a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the wireless network be GPRS and/ Or 3G network, with ensure under any circumstance all can real-time Transmission tunnel construction site detection data and issue command adapted thereto.
Used as a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the sensor includes carbon monoxide Sensor, methane transducer, Smoke Sensor and temperature sensor;The detection means include concrete strain gauge, surface meter, Three-dimensional laser profiler.The concrete strain gauge is embedded in concrete support, and the surface meter is arranged on bracing members surface, Size for detecting support of tunnel axle power.The three-dimensional laser profiler be used to detecting the surface displacement of tunnel construction site with And 3 D deformation.The sensor and detection means act synergistically, the potential safety hazard that will likely can exist to the full extent and When be transferred to information early warning analysis system and be analyzed, help to lift the security of constructing tunnel.
Used as a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the three-dimensional laser profiler is set At tunnel vault and/or haunch.The three-dimensional laser profiler set at vault can detect the deflection in tunnel, in haunch The three-dimensional laser profiler for locating to set can be detected to the perimeter convergence degree in tunnel.
As a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the model of the micro-control module MSP430F149 single-chip microcomputers.Empirical tests, may insure in constructing tunnel using MSP430F149 single-chip microcomputers as micro-control module Disposal ability higher is still kept under this special operation environment.
Used as a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the center control platform is including being System management module, data management module, instruction distribution module.In system management module, user can set up different engineering letters Breath and monitoring project, so as to realize the management simultaneously of multiple engineerings and the classification of the data to the collection of concrete engineering filed detection system Management.In data management module, for the data for detecting, the statistical chart of various patterns can be generated with the time by monitoring mileage, It is easy to analyze the risk of tunnel construction situation, at the same time it can also the monitor video of incoming tunnel job site, realizes visualization behaviour Make, help to understand the situation of tunnel construction site multi-facetedly comprehensively.In instruction distribution module, number is assigned by wireless network According to acquisition instructions, the operating types such as the frequency acquisition at scene are controlled, realize the remote control at scene, be easy to commanding to be managed Reason.
Used as a kind of above-mentioned further improvement of the safety pre-warning system of constructing tunnel, the prior-warning device is reported including LED Warning lamp and/or buzzer siren.By LED alarm lamp alarm function visually and buzzer siren in police acoustically Show function, it can be ensured that the staff of tunnel construction site in case of emergency tackles in time.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the safety pre-warning system of constructing tunnel of the present utility model.
Specific embodiment
Early warning system as shown in Figure 1, including filed detection system, data collecting system, data transmission system, information are pre- Alert analysis system, center control platform and prior-warning device;The filed detection system includes that carbon monoxide transducer, methane are sensed Device, Smoke Sensor, temperature sensor, concrete strain gauge, surface meter and three-dimensional laser profiler, wherein, in tunnel haunch With three-dimensional laser profiler is provided with vault.The data transmission system includes micro-control module and data transmission module, It is described for control module be MSP430F149 single-chip microcomputers.The prior-warning device includes LED alarm lamp and buzzer siren.In described Heart control platform includes system management module, data management module and instruction distribution module.
The instruction distribution module of center control platform issues data acquisition instructions by GPRS network;Data transmission system Data transmission module transmits commands to micro-control molding again after data acquisition instructions are received by way of wired connection Block, micro-control module transmits commands to data collecting system by GPRS network, and data collecting system will be referred to by CAN Order is sent to filed detection system.
Carbonomonoxide concentration, methane concentration, smokescope, the temperature of the tunnel construction site that filed detection system will be detected Degree, axial force of the supports and Tunnel Displacement data are sent to data collecting system by CAN, and data collecting system is by detection data Micro-control module is wirelessly transmitted to GPRS network, then detection data is wirelessly sent out by GPRS network by data transmission module Deliver to information early warning analysis system.
Information early warning analysis system will be to detection after the data that predetermined position filed detection system is detected are obtained Data are analyzed treatment, and analysis result are sent to the data management module of center control platform.Particularly, when analysis is tied When any index is more than corresponding preset value in the concentration that transfinites, overtime, deflection, rate of deformation in fruit, information early warning Alarm command is wirelessly transmitted to prior-warning device by analysis system by GPRS network, and prior-warning device sends strong flash of light and height immediately Sound alarm bell sound, job site takes relative measure according to prior-warning device in time, has ensured safe construction.

Claims (8)

1. a kind of safety pre-warning system of constructing tunnel, it is characterised in that:Including filed detection system, data collecting system, number According to Transmission system, information early warning analysis system, center control platform and prior-warning device;
The filed detection system includes sensor and detection means, and the filed detection system is adopted by CAN with data Collecting system is connected;
The data transmission system includes the micro-control module and the data transmission module that are sequentially connected;The data collecting system is adopted Collect the data by filed detection system detection and information early warning analysis system is transferred to by the data transmission system and divided Analysis;
Analysis result is transferred to center control platform by described information prewarning analysis system;Described information prewarning analysis system according to Analysis result controls the opening and closing of prior-warning device;
The opening and closing of the center control platform control data acquisition system.
2. a kind of safety pre-warning system of constructing tunnel as claimed in claim 1, it is characterised in that:The center control platform Between data transmission module, between micro-control module and data collecting system, data transmission module and information early warning analysis system Wireless communication is used between system, between information early warning analysis system and center control platform and prior-warning device.
3. a kind of safety pre-warning system of constructing tunnel as claimed in claim 2, it is characterised in that:The wireless network is GPRS and/or 3G network.
4. a kind of safety pre-warning system of constructing tunnel as claimed in claim 1, it is characterised in that:The sensor includes one Oxidation carbon sensor, methane transducer, Smoke Sensor and temperature sensor;The detection means include concrete strain gauge, Surface meter, three-dimensional laser profiler.
5. a kind of safety pre-warning system of constructing tunnel as claimed in claim 4, it is characterised in that:The three-dimensional laser section Instrument is arranged at tunnel vault and/or haunch.
6. a kind of safety pre-warning system of constructing tunnel as claimed in claim 1, it is characterised in that:The micro-control module Model MSP430F149 single-chip microcomputers.
7. a kind of safety pre-warning system of constructing tunnel as claimed in claim 1, it is characterised in that:The center control platform Including system management module, data management module, instruction distribution module.
8. a kind of safety pre-warning system of constructing tunnel as claimed in claim 1, it is characterised in that:The prior-warning device includes LED alarm lamp and/or buzzer siren.
CN201621264393.8U 2016-11-24 2016-11-24 A kind of safety pre-warning system of constructing tunnel Expired - Fee Related CN206256930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621264393.8U CN206256930U (en) 2016-11-24 2016-11-24 A kind of safety pre-warning system of constructing tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621264393.8U CN206256930U (en) 2016-11-24 2016-11-24 A kind of safety pre-warning system of constructing tunnel

Publications (1)

Publication Number Publication Date
CN206256930U true CN206256930U (en) 2017-06-16

Family

ID=59027856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621264393.8U Expired - Fee Related CN206256930U (en) 2016-11-24 2016-11-24 A kind of safety pre-warning system of constructing tunnel

Country Status (1)

Country Link
CN (1) CN206256930U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109115983A (en) * 2018-08-29 2019-01-01 安徽辰控智能科技有限公司 A kind of city excavation safe construction real time on-line monitoring system
CN110298548A (en) * 2019-05-27 2019-10-01 同济大学 The long-range real-time diagnosis of Rock Tunnel life cycle management engineering information and feedback system
CN110778362A (en) * 2019-09-18 2020-02-11 安徽亚浩智能科技有限公司 Intelligent construction management platform for tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109115983A (en) * 2018-08-29 2019-01-01 安徽辰控智能科技有限公司 A kind of city excavation safe construction real time on-line monitoring system
CN110298548A (en) * 2019-05-27 2019-10-01 同济大学 The long-range real-time diagnosis of Rock Tunnel life cycle management engineering information and feedback system
CN110778362A (en) * 2019-09-18 2020-02-11 安徽亚浩智能科技有限公司 Intelligent construction management platform for tunnel

Similar Documents

Publication Publication Date Title
CN109461325A (en) A kind of safe joint control system and method in construction of the highway area
CN207163500U (en) A kind of tall and big support shuttering safety monitoring system
CN206256930U (en) A kind of safety pre-warning system of constructing tunnel
CN201819697U (en) Bridge safety monitoring and warning system
CN204926382U (en) Coal yard spontaneous combustion monitoring system based on zigBee technique
CN205541020U (en) Flow of people statistical system of library based on pressure sensor
CN206409275U (en) A kind of safety monitoring system of tunnel operation stage
CN205007474U (en) Subway fire detection reports to police and fire extinguishing systems
CN205449138U (en) Remote monitoring system based on internet of things
CN110057971A (en) A kind of multiple groups part monitoring poisonous gas device based on Internet of Things
CN205388766U (en) Building engineering safety construction informatization monitoring system
CN205177214U (en) Training system is felt to perpendicular cat ladder of high altitude construction body
CN207133370U (en) A kind of novel electric power detector
CN205541198U (en) Early warning system is prevented destroying by tower mast
CN209623750U (en) A kind of power engineering Field Force operating environment state intelligent monitoring identification device
CN205740066U (en) The monitoring of gantry crane container unbalance-loading and intelligent early-warning system
CN205121278U (en) Gaseous remote monitoring control system of dangerous chemical
CN107085921A (en) Power plant's specific region method for safety monitoring
CN204231516U (en) Based on the SF of IMAQ 6density meter meter pointer recognition device
CN213457756U (en) Equipment remote operation and maintenance and fault diagnosis system
CN204917778U (en) Tower crane
CN204082446U (en) Based on the offshore wind farm unit comprehensive monitoring system of 6LoWPAN radio sensing network
CN202897708U (en) Monitoring device of traction machine used for elevator
CN203480649U (en) Fatigue driving alarm device and fatigue driving management system
CN217085902U (en) Highway engineering equipment construction site safety warning system

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170616

Termination date: 20191124

CF01 Termination of patent right due to non-payment of annual fee