CN206245776U - A kind of construction walling surface crack fix tool - Google Patents
A kind of construction walling surface crack fix tool Download PDFInfo
- Publication number
- CN206245776U CN206245776U CN201621281232.XU CN201621281232U CN206245776U CN 206245776 U CN206245776 U CN 206245776U CN 201621281232 U CN201621281232 U CN 201621281232U CN 206245776 U CN206245776 U CN 206245776U
- Authority
- CN
- China
- Prior art keywords
- base plate
- storing box
- surface crack
- fix tool
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 22
- 239000000945 filler Substances 0.000 claims abstract description 19
- 239000007789 gas Substances 0.000 description 6
- VYPSYNLAJGMNEJ-UHFFFAOYSA-N Silicium dioxide Chemical compound O=[Si]=O VYPSYNLAJGMNEJ-UHFFFAOYSA-N 0.000 description 4
- 239000011083 cement mortar Substances 0.000 description 4
- 238000005336 cracking Methods 0.000 description 4
- 238000007789 sealing Methods 0.000 description 4
- 239000004568 cement Substances 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 239000000741 silica gel Substances 0.000 description 1
- 229910002027 silica gel Inorganic materials 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The utility model discloses a kind of construction walling surface crack fix tool, it includes base plate, and three injector heads are provided with the plate face of the base plate, and the position near two ends of the length direction of the base plate is respectively arranged with an injector head;The side of the base plate is connected with material-storing box, three injector heads are connected to the lower end of the material-storing box by pipeline, the upper end of the material-storing box is provided with air admission hole, the air admission hole is connected by air inlet pipe with air accumulator, it is provided with the material-storing box for the lid that filler is injected in box, the lid to coordinate with the material-storing box detachable-type sealed;The side away from the metope of the base plate is additionally provided with is easy to hand-held handle.Construction walling surface crack fix tool of the present utility model is filled dedicated for construction walling surface crack and repaired, and filler can be injected into crack depths, and crack is tamped, and then has carried metope repairing quality high, and ensure that the security of wall.
Description
Technical field
The utility model is related to building implement technical field, and more particularly to a kind of construction walling surface crack repairs work
Tool.
Background technology
Construction walling particularly brick wall, fine sand cement concrete paint metope etc. often because many reasons and caused by metope
Crack is produced, according to the difference of wall, the width in crack is also not quite similar, narrow there are several millimeters, and wide is even up to 2 centimetres
It is many, because without special repair outfit, workman is often directly to daub into cement or yellow sand cement mortar from wall outer side with trowel,
Cracking of wall surface can only be filled into a small amount of cement or yellow sand cement mortar by this mode of squeegeeing from appearance, and the depth squeegeeed typically only has
0.5-2 centimetres of depth, it is difficult to the crack of wall is tamped, although from the appearance seem to have reached standard, but this is to cover
The crack inside wall has been hidden, can not be up to standard from for construction reference, for some load bearing walls, if metope is satirized not
Can tamp, very big potential safety hazard be had for a long time, therefore need a kind of specialty dedicated for surface crack repairing of building a wall of exploitation badly
Instrument.
The content of the invention
Therefore, the technical problems to be solved in the utility model is to overcome to lack in the prior art to be repaiied dedicated for cracking of wall surface
This is not enough for the instrument of benefit, and then provides a kind of construction walling surface crack fix tool.
To achieve the above object, the utility model uses following technical scheme:
A kind of construction walling surface crack fix tool, it includes the base plate for being fitted with metope, the plate of the base plate
Be provided with three injector heads on face, three injector heads along the base plate length direction arranged for interval, the length of the base plate
The position near two ends for spending direction is respectively arranged with an injector head, plate face of the injector head perpendicular to the base plate
Set;The side away from the metope of the base plate is fixedly connected with the material-storing box for storing filler, three sprays
The lower end that head is connected to the material-storing box by pipeline is penetrated, the upper end of the material-storing box is provided with air admission hole, and the air admission hole leads to
Air inlet pipe is crossed to be connected with air accumulator, be provided with the material-storing box in box inject filler lid, the lid with
The material-storing box detachable-type sealed coordinates;The side away from the metope of the base plate is additionally provided with is easy to hand-held handle
Hand.
Preferably, the one or both ends of the base plate are provided with the arc struck off for the filler that will be overflowed on wall and scrape
Plate, the arc scraper plate bends to the side away from the metope.
Preferably, the material-storing box with tell base plate be integral type structure, set in three feeding pipes of the injector head
In in the base plate body.
Preferably, the air admission hole is arranged on the lid.
Preferably, three injector heads protrude from the plate face of the base plate and set.
Preferably, the control button for controlling gas break-make in the air inlet pipe is provided with the handle.
The beneficial effects of the utility model:
Construction walling surface crack fix tool of the present utility model is filled dedicated for construction walling surface crack and repaired,
Filler can be injected crack depths, crack is tamped, and then carry metope repairing quality high, and ensure that the safety of wall
Property.
Brief description of the drawings
In order that content of the present utility model is more likely to be clearly understood, below in conjunction with the accompanying drawings, the utility model is made
Further details of explanation, wherein:
Fig. 1 is the dimensional structure diagram of construction walling surface crack fix tool of the present utility model;
Fig. 2 is the side structure schematic view of construction walling surface crack fix tool of the present utility model.
Reference is expressed as in figure:
1- base plates;2- injector heads;3- material-storing boxs;30- lids;4- air inlet pipe;5- air accumulators;6- handles;7- arc scraper plates;
8- control buttons.
Specific embodiment
Referring to Fig. 1-2, a kind of construction walling surface crack fix tool, it includes the base plate 1 for being fitted with metope, institute
Three injector heads 2 are provided with the plate face for stating base plate 1, three injector heads 2 are spaced cloth along the length direction of the base plate 1
Put, and the position near two ends of the length direction of the base plate 1 is respectively arranged with an injector head 2(Namely Fig. 1's is upper
Lower two ends), plate face setting of the injector head 2 perpendicular to the base plate 1;The side away from the metope of the base plate 1 is consolidated
Surely it is connected with for storing filler(The crack fillers such as cement mortar or cement mortar)Material-storing box 3, three injector heads 2
The lower end of the material-storing box 3 is connected to by pipeline, the upper end of the material-storing box 3 is provided with air admission hole, and the air admission hole passes through
Air inlet pipe 4 is connected with air accumulator 5, and the internal memory of the air accumulator 5 contains pressure-air, the air inlet pipe can also directly with air pump
Gas outlet connects, and is provided with the material-storing box 3 for the lid 30 that filler is injected in box, the lid 30 and the storage
The detachable-type sealed of magazine 3 coordinates;The side away from the metope of the base plate 1 is additionally provided with is easy to hand-held handle 6.This
The construction walling surface crack fix tool of utility model connects air inlet pipe first to filler is injected in material-storing box, then hand-held
Be close to base plate at cracking of wall surface by handle, and three injector heads is directed at crack, then opens air valve and is injected in material-storing box
Gas, the gas of injection gathers in the upper end of material-storing box, raises in material-storing box air pressure, and the gases at high pressure in box are by material-storing box bottom
The filler in portion is projected by injector head in crack, and the two of the crack area that two injector heads at base plate two ends cover base plate
End filling, forms a relative sealing area between these sides, positioned at middle injector head then in the presence of high pressure to
Injection filler in the sealing area, under base plate and the injection neck effect of two, two ends, the region being close to above in crack is
Sealed, there is the gap that supply stream passes through in the region of only crack depths, therefore in the presence of pressure is sprayed, filler is pressed
To the depths in crack, and the air that crack is stretched out squeezes away to realize being filled up completely with.If crack is more long, can one section of one section of ground enter
Row filling, in order to base plate plate face with have preferable sealing effectiveness between the walls, one layer of flexibility can be attached in the plate face of base plate
Rubber layer or layer of silica gel, to improve base plate with sealing property between the walls.
In the present embodiment, the two ends of the base plate 1 are provided with the arc struck off for the filler that will be overflowed on wall
Scraper plate 7, the arc scraper plate 7 bends to the side away from the metope.After one section of crack filling is finished, hand-held handle will be repaiied originally
Multiple tool tilt certain angle, makes the cambered surface of arc scraper plate be fitted with wall, is then moved along crack, you can will be overflow at crack
The filler for going out is scraped to metope and flushed.
In the present embodiment, the material-storing box 3 with tell base plate 1 be integral type structure, three feed pipes of the injector head 2
In road in the body of the base plate 1.This setup can reduce the parts such as external pipeline, simplify whole reparation work
The topology layout of tool, and its bulk strength can be improved, the instrument is more robust, and service life is longer.
In the present embodiment, the air admission hole may be provided at the body that this fix tool interior can also be located on the lid 30
It is interior.Three injector heads 2 protrude from the plate face setting of the base plate 1, can be stretched into crack in order to three injector heads, enter
And improve filling effect.Three spray-hole internal diameters of shower nozzle can set various types according to the difference of applicable cracking of wall surface width
Number, hole internal diameter preferably between 1-8 millimeters, between the length of injector head is preferred 3-15 millimeters.Applicable crack is wider, then empty interior
Through bigger, the length of injector head is more long.
In the present embodiment, the control button 8 for controlling gas break-make in the air inlet pipe 4 is provided with the handle 6,
Air admission hole can be now arranged on handle, in order to set air inlet control button on handle.Air inlet button is arranged on handle
On hand, it is easy to user to control filler to inject or stop in time.
Above-mentioned specific embodiment is that the technical solution of the utility model is explained in detail, and the utility model is not
Only be limited only to above-described embodiment, it will be understood by those skilled in the art that it is every according to above-mentioned principle and spirit in this practicality
Improvement, replacement on novel foundation, all should be within protection domain of the present utility model.
Claims (6)
1. a kind of construction walling surface crack fix tool, it is characterised in that:Including the base plate for being fitted with metope, the bottom
Be provided with three injector heads in the plate face of plate, three injector heads along the base plate length direction arranged for interval, the bottom
The position near two ends of the length direction of plate is respectively arranged with an injector head, and the injector head is perpendicular to the base plate
Plate face set;The side away from the metope of the base plate is fixedly connected with the material-storing box for storing filler, three
The injector head is connected to the lower end of the material-storing box by pipeline, and the upper end of the material-storing box is provided with air admission hole, it is described enter
Stomata is connected by air inlet pipe with air accumulator, is provided with the material-storing box for the lid that filler is injected in box, described
Lid coordinates with the material-storing box detachable-type sealed;The side away from the metope of the base plate be additionally provided be easy to it is hand-held
Handle.
2. construction walling surface crack fix tool according to claim 1, it is characterised in that:One end of the base plate or
Two ends are provided with the arc scraper plate struck off for the filler that will be overflowed on wall, and the arc scraper plate is to away from the metope
Side bends.
3. construction walling surface crack fix tool according to claim 2, it is characterised in that:The material-storing box with told
Base plate is integral type structure, in three feeding pipes of the injector head in the base plate body.
4. construction walling surface crack fix tool according to claim 3, it is characterised in that:The air admission hole is arranged on
On the lid.
5. the construction walling surface crack fix tool according to claim any one of 1-4, it is characterised in that:Described in three
The plate face that injector head protrudes from the base plate is set.
6. construction walling surface crack fix tool according to claim 5, it is characterised in that:It is provided with the handle
Control button for controlling gas break-make in the air inlet pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621281232.XU CN206245776U (en) | 2016-11-28 | 2016-11-28 | A kind of construction walling surface crack fix tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621281232.XU CN206245776U (en) | 2016-11-28 | 2016-11-28 | A kind of construction walling surface crack fix tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206245776U true CN206245776U (en) | 2017-06-13 |
Family
ID=59002516
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621281232.XU Expired - Fee Related CN206245776U (en) | 2016-11-28 | 2016-11-28 | A kind of construction walling surface crack fix tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206245776U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952208A (en) * | 2018-09-25 | 2018-12-07 | 深圳市志纵四海科技有限公司 | Object crack fix tool |
CN109488002A (en) * | 2018-11-22 | 2019-03-19 | 蔡嘉丽 | A kind of crack filling device |
CN113026987A (en) * | 2021-03-22 | 2021-06-25 | 中国建筑第五工程局有限公司 | Anti-leakage method for controlling stress crack of steel-concrete main structure |
-
2016
- 2016-11-28 CN CN201621281232.XU patent/CN206245776U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952208A (en) * | 2018-09-25 | 2018-12-07 | 深圳市志纵四海科技有限公司 | Object crack fix tool |
CN108952208B (en) * | 2018-09-25 | 2024-03-26 | 深圳市志纵四海科技有限公司 | Object crack repairing tool |
CN109488002A (en) * | 2018-11-22 | 2019-03-19 | 蔡嘉丽 | A kind of crack filling device |
CN109488002B (en) * | 2018-11-22 | 2024-05-24 | 南京多产国际贸易咨询服务有限公司 | Crack filling device |
CN113026987A (en) * | 2021-03-22 | 2021-06-25 | 中国建筑第五工程局有限公司 | Anti-leakage method for controlling stress crack of steel-concrete main structure |
CN113026987B (en) * | 2021-03-22 | 2022-04-26 | 中国建筑第五工程局有限公司 | Anti-leakage method for controlling stress crack of steel-concrete main structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206245776U (en) | A kind of construction walling surface crack fix tool | |
CN103775104B (en) | Underground coal mine Wet-type concrete shotcreting process | |
CN102758456A (en) | Construction method of basement waterproofing projects | |
CN104533067A (en) | Ceramic tile pointing gun | |
CN203654485U (en) | Polyurethane foam plugging structure for bolt hole of shear wall | |
CN105756688A (en) | Sprayer device and construction method for improving concrete spraying quality | |
CN206487458U (en) | Hydraulic blast | |
CN207959289U (en) | Structure is repaired in a kind of leak for basement post-pouring zone position | |
CN107227836A (en) | A kind of portable pair of brush wall plaster device | |
CN106639247A (en) | Construction technique for paving ceramic floor tiles | |
CN203348731U (en) | Cable bracket | |
CN207154051U (en) | A kind of practical weather proofing sealant glue injection machine | |
KR20130113568A (en) | Concrete crack repair method and repair mortar manufacturing method | |
CN110081267A (en) | PCCP pipeline breaking renovation technique | |
CN204435808U (en) | A kind of tile pointing rifle | |
CN220464331U (en) | Tool for cleaning gaps during repairing of building wall | |
JPH1061201A (en) | Waterproofing repair method for crack of concrete and air spray can used in the method | |
CN205474767U (en) | Two ingredient bituminous paving cracks cementation of fissures rifle | |
KR101618183B1 (en) | Dry cracks in concrete bridge structure maintenance device | |
CN203729188U (en) | Highway pavement crack sealing machine | |
US5358751A (en) | Ferrocement lining units, methods of making them and methods of lining a water course with them | |
CN206722445U (en) | Roof caulking machine | |
KR101230430B1 (en) | Wet blasting apparatus | |
CN207079839U (en) | A kind of cobble metope structure | |
CN216076395U (en) | Portable seam plugging tool with graduated scale |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170613 |