CN206233404U - The attachment structure of shear wall and after-pouring concrete secondary beam - Google Patents
The attachment structure of shear wall and after-pouring concrete secondary beam Download PDFInfo
- Publication number
- CN206233404U CN206233404U CN201621272431.4U CN201621272431U CN206233404U CN 206233404 U CN206233404 U CN 206233404U CN 201621272431 U CN201621272431 U CN 201621272431U CN 206233404 U CN206233404 U CN 206233404U
- Authority
- CN
- China
- Prior art keywords
- secondary beam
- shear wall
- concrete secondary
- reinforcement
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 84
- 230000002787 reinforcement Effects 0.000 claims abstract description 50
- 238000004873 anchoring Methods 0.000 claims description 10
- 210000003205 muscle Anatomy 0.000 claims description 9
- 230000003014 reinforcing effect Effects 0.000 claims description 8
- 238000005266 casting Methods 0.000 claims description 7
- 238000005452 bending Methods 0.000 claims description 6
- 239000002689 soil Substances 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 8
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 238000009415 formwork Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000010008 shearing Methods 0.000 description 3
- 241001669679 Eleotris Species 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000009408 flooring Methods 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- 241000196324 Embryophyta Species 0.000 description 1
- 240000002853 Nelumbo nucifera Species 0.000 description 1
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 1
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 1
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 229920006328 Styrofoam Polymers 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- VIKNJXKGJWUCNN-XGXHKTLJSA-N norethisterone Chemical compound O=C1CC[C@@H]2[C@H]3CC[C@](C)([C@](CC4)(O)C#C)[C@@H]4[C@@H]3CCC2=C1 VIKNJXKGJWUCNN-XGXHKTLJSA-N 0.000 description 1
- 230000008447 perception Effects 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 239000008261 styrofoam Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model provides the attachment structure of a kind of shear wall and after-pouring concrete secondary beam, it connects shear wall and after-pouring concrete secondary beam, vertical reinforcement and horizontal reinforcement are set in wall, pouring basin after secondary beam is reserved in attachment structure, shear wall sets connecting parts in the concrete secondary beam longitudinal reinforcement correspondence position of after-pouring concrete secondary beam, the collar extension of connecting parts is flushed exposed to shear wall body surface and with metope, and the horizontal reinforcement and vertical reinforcement in wall expose to pour in the rear and stay rooved face.The utility model is connected using concrete secondary beam longitudinal reinforcement by pre-buried connecting parts, will not the concrete shear force wall that pour completion be caused to damage.Pour afterwards and stay shear wall horizontal reinforcement and shear wall vertical reinforcement in groove to expose, improve the reliability of the contact surface cohesive force of new-old concrete, pour afterwards stay groove presence make after pour secondary beam and be embedded into inside shear wall, the construction quality of node structure is easily controlled, and with comparatively ideal outward appearance.
Description
Technical field
The utility model is related to a kind of shear wall, the more particularly to attachment structure of shear wall and concrete secondary beam.
Background technology
Shear wall is to be primarily subjected to horizontal loading and the vertical lotus that wind load or geological process cause in house or structures
The wall of load, prevents structure shear from destroying, and is typically made by armored concrete.In following kind of engineering, it is desirable to shear wall
Poured prior to floor beam:
1st, the building of high-rise frame core wall structure, when building, is accelerating construction progress, the concrete core cylinder of high building
Shear wall is generally using the arrangement and method for construction of creeping formwork so that the contignation 3 ~ 5 of the advanced flooring of construction speed of Core Walls Structure shear wall
Layer.
2nd, the clear-water concrete structural wall of multilayer structure, to strengthen the airtight performance of template, is prevented in construction
Spillage, it is ensured that wall associative perception, it is desirable to after completing the overall pouring construction of dry concrete wall, then the building for carrying out outside functional areas
The construction of face beam slab.
In said structure, floor beam need could be constructed after shear wall concrete reaches preset strength, shear wall with it is rear
The node of casting concrete floor beam is a difficult point, and generally for this difficult point is avoided, floor beam generally selects girder steel, uses
The pre-embedded steel slab in shear wall, girder steel and pre-buried plate weld or bolted method, between such shear wall and floor beam
Connecting node is easier to treatment.But the cost of steel structure floor is higher.
When flooring secondary beam uses reinforced concrete structure, the connection of the shear wall and the secondary beam of after-pouring that first pour at present
The processing method of node is:
First pouring reinforcement concrete shear wall, after shear wall concrete reaches preset strength, by concrete secondary beam longitudinal direction
Reinforcing bar plants concrete shear within the walls in the way of bar planting, afterwards digs the contact surface of shear wall surface and concrete secondary beam
Hair, and the contact surface after dabbing is cleared up.Colligation concrete time beam steel simultaneously sets up template, last casting concrete secondary beam
And conserve.
Shortcoming is stated in the presence of shear wall and the connecting node of the secondary beam of after-pouring:
1st, concrete secondary beam longitudinal reinforcement is that concrete shear is planted in the way of bar planting within the walls, is needed during bar planting
Bar planting hole is opened up on concrete shear force wall.Reinforcing bar in shear wall is easy to be destroyed when bar planting hole is opened up, especially secondary beam
Position be exactly in when on shear wall sleeper position, the missing of reinforcing bar will bring hidden danger to the security of structure in sleeper.
2nd, bar planting is a kind of technology being bonded in reinforcing bar by chemical constitution glue in bar planting hole, to the quality of structure glue with
And the operating technology requirement of operator is higher, the quality control at scene is more difficult.
3rd, the vertical force of concrete secondary beam is to bond to pass to shear wall by the contact surface of secondary beam and shear wall, although
Dabbing treatment has been carried out to contact surface, but the reliability of the cohesive force of the contact surface of new-old concrete is also to be studied, secondary beam
Root easily becomes the weak spot of structure, when especially the larger load of secondary beam span is heavier, the safety stock of this connecting node
It is not enough.
4th, this node easily produces crack in stress at the contact surface of concrete secondary beam and shear wall, and influence is outer
See effect.
The content of the invention
The utility model technical problem to be solved first be to provide a kind of power transmission directly, possess reliable stress performance
The attachment structure of shear wall and after-pouring concrete secondary beam.Therefore, the utility model uses following technical scheme:
The attachment structure connects and vertical reinforcement and level is set in shear wall and after-pouring concrete secondary beam, the wall
Reinforcing bar, reserves pouring basin, concrete secondary beam of the shear wall in after-pouring concrete secondary beam after secondary beam in the attachment structure
Longitudinal reinforcement correspondence position sets connecting parts, and the collar extension of the connecting parts is flushed exposed to shear wall body surface and with metope,
Horizontal reinforcement and vertical reinforcement in wall expose to pour in the rear and stay rooved face.
Further, the after-pouring concrete secondary beam is provided with concrete secondary beam longitudinal reinforcement, and the concrete secondary beam is indulged
Mechanically connected with the collar extension of the connecting parts to reinforcing bar, the after-pouring concrete secondary beam is provided with the vertical muscle of anchoring, the anchoring is indulged
Muscle is mechanically connected with the internal orifice of the connecting parts, and in shear wall inner bending anchoring.
Further, being poured after described stays the width of groove fewer 50-100 millimeters than the width of after-pouring concrete secondary beam, after pour
Stay the height of groove fewer 150-200 millimeters than after-pouring concrete time depth of beam, after pour that to stay the depth of groove be 30 millimeters.
, in colligation, concrete cover to reinforcement thickness takes 30 for the shear wall horizontal reinforcement and shear wall vertical reinforcement
Millimeter.
Poured after described and stay groove to be located at secondary beam installation node middle part.
As a result of the technical solution of the utility model, the utility model is using concrete secondary beam longitudinal reinforcement by pre-
The connecting parts connection buried, is anchored directly to concrete shear within the walls, and the concrete shear force wall that pour completion will not be caused
Damage.Pour afterwards and stay shear wall horizontal reinforcement and shear wall vertical reinforcement in groove to expose, improve the contact surface of new-old concrete
The reliability of cohesive force, after pour stay groove presence make after pour secondary beam and be embedded into inside shear wall, it is ensured that the root of secondary beam with cut
Globality between power wall, this node is especially suitable for being used in the heavier shear wall of the larger load of span with after-pouring secondary beam
In connecting node, the construction quality of node structure is easily controlled, and with comparatively ideal outward appearance.
Brief description of the drawings
Fig. 1 is the schematic diagram of shear wall described in the utility model and after-pouring concrete secondary beam.
Fig. 2 is the schematic diagram of reinforcing bar and connecting parts in shear wall described in the utility model.
Fig. 3 is the profile of shear wall closing template described in the utility model and embedded plugging device.
Fig. 4 is the front view of shear wall closing template described in the utility model and embedded plugging device.
Fig. 5 is that shear wall described in the utility model completes concreting, the profile after form removal and plugging device.
Fig. 6 shear wall described in the utility model completes the schematic diagram after secondary beam is poured.
In figure, 1:Shear wall, 2:After-pouring concrete secondary beam, 3:Shear wall vertical reinforcement, 4:Shear wall horizontal reinforcement, 5:
After pour and stay groove, 6:Secondary beam longitudinal reinforcement, 7:Connecting parts, 8:The vertical muscle of anchoring, 9:Shear wall formwork, 10:Plugging device, 11:Lath,
12:Steel nail, 21:Concrete time beam stirrup, 81:Bending part.
Specific embodiment
The utility model is further elaborated below in conjunction with accompanying drawing.
Embodiment one:
As shown in figure 1, the shear wall 1 that the utility model is provided, including shear wall horizontal reinforcement 4, shear wall vertical reinforcement
3, the shear wall 1 is connected with after-pouring concrete secondary beam 2 in the middle part of shear wall as depicted, and the tie point is that shear wall is pre-
The secondary beam 2 for staying pours node, and the secondary beam is poured for the later stage.Shear wall 1 is provided with connecting parts in the link position of concrete secondary beam
7, the connecting parts 7 are arranged on the correspondence position of secondary beam longitudinal reinforcement 6, and collar extension is exposed to the exterior surface of wall of shear wall 1, is poured with after
The longitudinal reinforcement 6 of the concrete secondary beam built is connected, and internal orifice is connected with the vertical muscle 8 of anchoring, and the vertical muscle 8 of anchoring is in the shear wall 1
Inner bending is anchored.Poured after reserved secondary beam in shear wall 1 and stay groove 5, the horizontal reinforcement 4 and vertical reinforcement 3 in wall are exposed at described
After pour and stay the surface of groove 5.
The shear wall 1 sets connecting parts 7, and rear pouring concrete secondary beam longitudinal reinforcement 6 is connected by pre-buried connecting parts 7,
It is anchored directly to concrete shear within the walls, will not the concrete shear force wall that pour completion is caused to damage.As a kind of machine
Tool connected mode, the operating technology to operator is less demanding, and the quality at scene is easily ensured.
Poured after described and stay shear wall horizontal reinforcement 4 and shear wall vertical reinforcement 3 in groove 5 to expose, improve after-pouring and mix
The reliability of solidifying soil secondary beam and first casting concrete shear wall contact surface cohesive force.Pour afterwards and stay the presence of groove 5 to make after-pouring coagulation
Native secondary beam 2 is embedded into inside shear wall 1, it is ensured that the globality between the root of secondary beam and shear wall, due to new-old concrete
Contact surface cohesive force reliability and globality greatly enhance, this attachment structure is not easy in concrete secondary beam and shear wall
Contact surface produce crack, appearance is good.
Embodiment two:
As shown in Fig. 2-Fig. 6.
Shear wall described in the utility model is comprised the following steps with the casting method of after-pouring concrete secondary beam:
1st, as shown in Fig. 2 colligation shear wall vertical reinforcement 3 and shear wall horizontal reinforcement 4, thickness of protection tier is according to 30
Millimeter control, in the link position with concrete secondary beam, according to the position of secondary beam longitudinal reinforcement 6, reserves in shear wall 1 and plugs into
7, the colligation of connecting parts 7 is fixed on nigh shear force wall reinforcing steel bar, and the collar extension of connecting parts 7 is flushed with shearing metope;The internal orifice of connecting parts 7
It is connected with the vertical muscle 8 of anchoring, the vertical muscle 8 of anchoring is anchored in shear wall inner bending, the bending part 81 is close to table in the wall of shear wall 1
Face.
2nd, as shown in Figure 3 and Figure 4, shear wall formwork 9, the center being connected with concrete secondary beam 2, shear wall mould are set up
Plate 9 reserves hole, 50 ~ 100 millimeters fewer than the width of concrete secondary beam of the width at hole, and the height at hole is than concrete secondary beam
Highly lack 150 ~ 200 millimeters;Embedded plugging device 10, the size and dimension of opening of plugging device 10 in shear wall formwork hole
Identical, thickness is+30 millimeters of template thickness;Plugging device is made of styrofoam, and plugging device outside uses lath 11 and steel
Nail 12 is fixed with shear wall formwork 9.
3rd, as shown in figure 5, pouring the concrete of shear wall 1, after the concrete of shear wall 1 reaches preset strength, dismounting is cut
When power wall form 9, taking-up plugging device 10,7 mouthfuls of connecting parts are exposed to the outer surface of shear wall 1, are formed in the position of plugging device 10
Reserved groove, the reserved groove is poured after being and stays groove 5, reserves width 50 ~ 100 milli fewer than the width of concrete secondary beam of groove
Rice, reserves the height of groove than few 150 ~ 200 millimeters of depth of beam of concrete time, and the depth for reserving groove is 30 millimeters;Dabbing
And the inner surface for reserving groove is cleared up, the shear wall horizontal reinforcement 4 and shear wall vertical reinforcement 3 in reserved groove are exposed.
4th, as shown in fig. 6, concrete secondary beam longitudinal reinforcement 6 is connected with connecting parts 7, and colligation concrete time beam stirrup
21, time beam forms is set up, complete the concreting of secondary beam.
By casting method of the present utility model, the vertical force of concrete secondary beam stays groove 5 by pouring after in shear wall
Shear wall is passed to, shear wall, power transmission reliability are embedded in equivalent to secondary beam.Shear wall horizontal reinforcement and the shearing stayed in groove 5 are poured afterwards
Wall vertical reinforcement exposes, and improves the reliability of the contact surface cohesive force of new-old concrete, it is ensured that the root of secondary beam and shearing
Globality between wall, this attachment structure be especially suitable for being used in the heavier after-pouring concrete secondary beam of the larger load of span with
In the connecting node of shear wall.
Claims (5)
1. the attachment structure of shear wall and after-pouring concrete secondary beam, the attachment structure connects shear wall(1)It is mixed with after-pouring
Solidifying soil secondary beam(2), the shear wall(1)Vertical reinforcement is set in wall(3)And horizontal reinforcement(4), it is characterised in that the company
Poured after reserved secondary beam in binding structure and stay groove(5), the shear wall(1)In after-pouring concrete secondary beam(2)Concrete secondary beam indulge
To reinforcing bar(6)Correspondence position sets connecting parts(7), the connecting parts(7)Collar extension be exposed to shear wall(1)Surface of wall and with
Metope is flushed, the horizontal reinforcement in wall(4)And vertical reinforcement(3)Expose to pour in the rear and stay groove(5)Surface.
2. the attachment structure of shear wall according to claim 1 and after-pouring concrete secondary beam, it is characterised in that after described
Casting concrete secondary beam(2)It is provided with concrete secondary beam longitudinal reinforcement(6), the concrete secondary beam longitudinal reinforcement(6)Connect with described
Refute part(7)Collar extension mechanically connect, the after-pouring concrete secondary beam(2)It is provided with the vertical muscle of anchoring(8), the vertical muscle of anchoring(8)
With the connecting parts(7)Internal orifice mechanically connect, and in the shear wall(1)Inner bending is anchored.
3. the attachment structure of shear wall according to claim 1 and after-pouring concrete secondary beam, it is characterised in that after described
Pour and stay groove(5)Width than after-pouring concrete secondary beam(2)Few 50-100 millimeters of width, after pour and stay groove(5)Height ratio after
Casting concrete secondary beam(2)Few 150-200 millimeters of height, after pour and stay groove(5)Depth be 30 millimeters.
4. the attachment structure of shear wall according to claim 1 and after-pouring concrete secondary beam, it is characterised in that described to cut
Power wall horizontal reinforcement(4)With shear wall vertical reinforcement(3)In colligation, concrete cover to reinforcement thickness takes 30 millimeters.
5. the attachment structure of shear wall according to claim 1 and after-pouring concrete secondary beam, it is characterised in that after described
Pour and stay groove(5)Node middle part is installed positioned at secondary beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621272431.4U CN206233404U (en) | 2016-11-24 | 2016-11-24 | The attachment structure of shear wall and after-pouring concrete secondary beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621272431.4U CN206233404U (en) | 2016-11-24 | 2016-11-24 | The attachment structure of shear wall and after-pouring concrete secondary beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206233404U true CN206233404U (en) | 2017-06-09 |
Family
ID=58979887
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621272431.4U Expired - Fee Related CN206233404U (en) | 2016-11-24 | 2016-11-24 | The attachment structure of shear wall and after-pouring concrete secondary beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206233404U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106760049A (en) * | 2016-11-24 | 2017-05-31 | 大象建筑设计有限公司 | The attachment structure and its casting method of shear wall and after-pouring concrete secondary beam |
CN108842927A (en) * | 2018-07-11 | 2018-11-20 | 上海应用技术大学 | Beam rigid connection node and construction method outside assembly concrete shear wall and face |
-
2016
- 2016-11-24 CN CN201621272431.4U patent/CN206233404U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106760049A (en) * | 2016-11-24 | 2017-05-31 | 大象建筑设计有限公司 | The attachment structure and its casting method of shear wall and after-pouring concrete secondary beam |
CN108842927A (en) * | 2018-07-11 | 2018-11-20 | 上海应用技术大学 | Beam rigid connection node and construction method outside assembly concrete shear wall and face |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106223360B (en) | Using the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN209457194U (en) | Steel ribs dislocation dock shear wall vertical connection structure | |
CN106245931A (en) | The underpinning device of load bearing wall and construction method in brick mix structure | |
CN107780576A (en) | A kind of assembled architecture bottom composite floor and its connected mode | |
CN107044177A (en) | A kind of assembly concrete shear wall fractionation, assembled attachment structure and connection method | |
CN108104284B (en) | Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method | |
CN204983662U (en) | To drawing screw rod and steel pipe framed bent combination unilateral formwork device | |
CN106545109A (en) | Overlaid plate type concrete shear wall longitudinal connection structure and method of attachment | |
CN209482591U (en) | Prefabricated molds shell structure column construction structure | |
CN106284655A (en) | Precast concrete beam stud connects node and method of attachment in succession | |
CN110205931A (en) | A kind of prefabricated assembled Collison fence for bridge | |
CN206245520U (en) | Overlaid plate type concrete shear wall longitudinal connection structure | |
CN106760050A (en) | The attachment structure and through processing method of shear wall and after-pouring concrete frame beam | |
CN107130715A (en) | Teeth groove is poured after a kind of to be linked and packed the construction method of formula building roof system | |
CN107119901A (en) | The cast-in-place system of formwork structure and shear wall and construction method of shear wall angle node | |
CN206233404U (en) | The attachment structure of shear wall and after-pouring concrete secondary beam | |
CN109267673A (en) | Steel ribs dislocation dock shear wall vertical connection structure and assembly method | |
CN206888506U (en) | The cast-in-place system of formwork structure and shear wall of shear wall angle node | |
CN105862912B (en) | A kind of agent on crack resistance of concrete sliding pile panelling construction method | |
CN110080299A (en) | A kind of shallow embedding mountain tunnel open-cut engineering method | |
CN106760049A (en) | The attachment structure and its casting method of shear wall and after-pouring concrete secondary beam | |
CN109868751A (en) | Notch, template and construction method are poured after a kind of assembled track girder concrete | |
CN106337530B (en) | A kind of construction of frame beam seams stifled construction method | |
CN109162741A (en) | The method in shield crossing piston air duct and piston air duct superstructure synchronous construction | |
CN109610706A (en) | A kind of assembled combined hollow floor and preparation method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170609 |