CN206225888U - A kind of power construction is with portable split conductor fixing-line device - Google Patents
A kind of power construction is with portable split conductor fixing-line device Download PDFInfo
- Publication number
- CN206225888U CN206225888U CN201621264575.5U CN201621264575U CN206225888U CN 206225888 U CN206225888 U CN 206225888U CN 201621264575 U CN201621264575 U CN 201621264575U CN 206225888 U CN206225888 U CN 206225888U
- Authority
- CN
- China
- Prior art keywords
- inserted link
- sleeve
- spring
- line device
- coupler body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004020 conductor Substances 0.000 title claims abstract description 22
- 238000010276 construction Methods 0.000 title claims abstract description 16
- 230000037431 insertion Effects 0.000 claims 1
- 238000003780 insertion Methods 0.000 claims 1
- 125000006850 spacer group Chemical group 0.000 description 5
- 230000007547 defect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Abstract
The utility model discloses a kind of power construction with portable split conductor fixing-line device, including inserted link, sleeve, the inserted link right side is provided with fixed support, the inserted link left upper part is provided with spring button, the inserted link is inserted from described sleeve one end, and inserted link is connected with sleeve by spring, the sleeve is provided with circular hole corresponding with spring button, and the sleeve left side is provided with fixed support.The structure combined by spring button and circular hole, after solving two ends coupler body two wires of connection, extruding two ends support inserted link is fixed on the problem of stress in sleeve, after allowing workman to extrude two ends support, spring button buckle and circular hole, ensure that inserted link will not be slided again with sleeve, workman is allowed to be taken over the baton between changing well, by being provided with the structure of torsion spring at coupler body two ends hinge openings plate and hinge, when solving workman's carrying or doing manual work, the problem of object is hooked because of coupler body imprudence, allows workman to be more convenient to carry and work.
Description
Technical field
The utility model is related to electric construction tool technical field, specially a kind of portable split conductor of power construction
Fixing-line device.
Background technology
Ultra-high-tension power transmission line is chronically at wild environment, and with social constantly progress, running environment becomes increasingly complex,
It is building a house around protection zone, construction site, more and more across thing, cause shaft tower to build higher and higher, in the winter time spring strong wind season,
Conductor spacer on wire can be caused to disconnect with vibrations, shifts, damaged, and serious meeting causes wire whiplash, causes wire to be damaged,
220KV line outages are caused, power network reliability service is had a strong impact on, therefore hotline maintenance work on 220kv wires is increasingly
It is many.220kv wires are double bundle conductor, in different shaft tower spans, due to sag deviation, from the distance between wire simultaneously
It is not fixed 400mm, when on-line treatment conductor spacer damages defect, it is excessive or too small sub-conductor spacing often occur, especially
When equipotential staff works on wire, can further change sub-conductor spacing, cause new conductor spacer to be difficult correct installation,
Conductor spacer is being changed, operating personnel are difficult to be brought to two wires in two mounting grooves of conductor spacer, due to being work high above the ground,
Operation difficulty is big, and working strength is big, and the set-up time is long, so many inconvenience can be brought to staff in service work, very
The treatment of some defects can not extremely be completed.
Utility model content
The purpose of this utility model is to provide a kind of power construction with portable split conductor fixing-line device, above-mentioned to solve
The problem proposed in background technology.
To achieve the above object, the utility model provides following technical scheme:A kind of power construction is led with portable division
Line fixing-line device, including inserted link, sleeve, the inserted link right side are provided with fixed support, and the inserted link left upper part is provided with spring
Button, the inserted link is inserted from described sleeve one end, and inserted link is connected with sleeve by spring, and the sleeve is provided with and spring
The corresponding circular hole of button, the sleeve left side is provided with fixed support, and coupler body, the coupler body two ends are provided with the fixed support
Hinge openings plate, torsion spring is provided with the hinge.
Preferably, the coupler body medial surface is provided with the cable stay hook of arc-shaped.
Preferably, the top of the spring button is provided with circular surface.
Preferably, the length that stretches of spring is less than length of the inserted link in sleeve.
Compared with prior art, the beneficial effects of the utility model are:The power construction is with portable split conductor card line
Device, it is scientific and reasonable for structure, it is easy to use that inserted link and tube-in-tube structure are efficiently connected by spring, solve inserted link and slide sleeve
Problem, allows workman to use or carries more convenient, and the structure combined by spring button and circular hole is solved two ends coupler body and connects two
After individual wire, extruding two ends support inserted link is fixed on the problem of stress in sleeve, after allowing workman to extrude two ends support, spring button
Buckle and circular hole, it is ensured that inserted link will not be slided again with sleeve, allow well workman to be taken over the baton between changing, by coupler body two ends hinge openings plate
And the structure of torsion spring is provided with hinge, and when solving workman and carrying or do manual work, the problem of object is hooked because of coupler body imprudence, allow work
People is more convenient to be carried and works.
Brief description of the drawings
Fig. 1 is the structural representation after the inserted link retraction of the portable split conductor fixing-line device of the utility model power construction
Figure;
Fig. 2 stretches out structural representation for the utility model power construction with the inserted link of portable split conductor fixing-line device;
Fig. 3 is fixing rack structure figure of the present utility model.
In figure:1 inserted link, 2 sleeves, 3 spring buttons, 4 springs, 5 fixed supports, 51 torsion springs, 52 open plates, 53 coupler bodies, 6 circles
Hole.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment for being obtained, belongs to the scope of the utility model protection.
Fig. 1-3 are referred to, the utility model provides a kind of technical scheme:A kind of power construction is with portable split conductor card
Line device, including inserted link 1, sleeve 2, the right side of the inserted link 1 are provided with fixed support 5, and the left upper part of the inserted link 1 is provided with spring
Button 3, the inserted link 1 is inserted from the one end of the sleeve 2, and inserted link 1 is connected with sleeve 2 by spring 4, and the sleeve 2 is set
There is circular hole 6 corresponding with spring button 3, the left side of the sleeve 2 is provided with fixed support 5, the fixed support (5) and is provided with hook
Body (53), the coupler body (53) two ends hinge openings plate (52), is provided with torsion spring (51) at the hinge.
The fixed support 5 includes torsion spring 51, open plate 52, coupler body 53, the two ends hinge openings plate 52 of the coupler body 53, institute
State and be provided with hinge torsion spring 51, the opening that open plate can be made random about 52 is then only needed to two openings in work man-hour
The junction card of plate 52 is pressed on wire, you can allow coupler body 53 to hook together wire, the medial surface of the coupler body 53 is provided with the cable of arc-shaped
Stay hook, the cable stay hook of arc-shaped firmly, stably can hook together wire, it is to avoid the problem of sliding leakage, the spring button 3
Top be provided with circular surface, when the setting of arc surface slides in and out inserted link 1, spring button 3 can easily, efficiently, stabilization
Compressed in inserted link 1 by sleeve 2, slide or buckle all asked solves the problems, such as stress, spring 4 stretches length less than inserted link
1 length in sleeve 2, it is ensured that inserted link 1 will not skid off sleeve 2.
Operation principle:Split conductor fixing-line device is taken out, pressing spring button 3 draws inserted link 1 and slides in and out to suitable simultaneously
Length, by the junction of open plate 52 extrude wire to wire enter coupler body 53, after two ends all hook together, workman extruding fixing-line device two
The fixed support 5 at end to spring button 3 is fastened in circular hole 6, you can change or clipping room is taken over the baton.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out various changes in the case where principle of the present utility model and spirit is not departed from, repaiies
Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.
Claims (4)
1. a kind of power construction portable split conductor fixing-line device, including inserted link (1), sleeve (2), it is characterised in that:It is described
Inserted link (1) right side is provided with fixed support (5), and inserted link (1) left upper part is provided with spring button (3), the inserted link (1)
It is connected by spring (4) with sleeve (2) from the insertion of the sleeve (2) one end, and inserted link (1), the sleeve (2) is provided with and bullet
The corresponding circular hole (6) of spring button (3), sleeve (2) left side is provided with fixed support (5), the fixed support (5) and is provided with
Coupler body (53), the coupler body (53) two ends hinge openings plate (52), is provided with torsion spring (51) at the hinge.
2. a kind of power construction according to claim 1 is with portable split conductor fixing-line device, it is characterised in that:The hook
Body (53) medial surface is provided with the cable stay hook of arc-shaped.
3. a kind of power construction according to claim 1 is with portable split conductor fixing-line device, it is characterised in that:The bullet
The top of spring button (3) is provided with circular surface.
4. a kind of power construction according to claim 1 is with portable split conductor fixing-line device, it is characterised in that:Spring
(4) the length that stretches is less than length of the inserted link (1) in sleeve (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621264575.5U CN206225888U (en) | 2016-11-24 | 2016-11-24 | A kind of power construction is with portable split conductor fixing-line device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621264575.5U CN206225888U (en) | 2016-11-24 | 2016-11-24 | A kind of power construction is with portable split conductor fixing-line device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206225888U true CN206225888U (en) | 2017-06-06 |
Family
ID=58791143
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621264575.5U Active CN206225888U (en) | 2016-11-24 | 2016-11-24 | A kind of power construction is with portable split conductor fixing-line device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206225888U (en) |
-
2016
- 2016-11-24 CN CN201621264575.5U patent/CN206225888U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207581076U (en) | A kind of communication cable wrap-up | |
CN207303796U (en) | One kind is used for electric power apparatus examination Portable lifting device | |
CN202602171U (en) | A tool for power-on replacing multi-loop double split conductor insulator of 220kV line | |
CN206225888U (en) | A kind of power construction is with portable split conductor fixing-line device | |
CN206401811U (en) | A kind of leap net of crossing live-line Poling Construction | |
CN102832571B (en) | Cable bending radius controller and cable bending method | |
CN205442567U (en) | Steel -pipe pole operation platform | |
CN109462184A (en) | A kind of hot line maintenance device and its application method | |
CN103247972B (en) | Wire tractor | |
CN202059095U (en) | High-speed rail power cable climbing frame | |
CN205846663U (en) | A kind of height-adjustable overhead line structures | |
CN208782373U (en) | Line lifter bracket and the line lifter for applying it | |
CN204167794U (en) | Insulation stringing fixed mount | |
CN208937785U (en) | A kind of angle steel tower of power transmission line optical cable insulated down lead clamp | |
CN204046065U (en) | A kind of wiring operations platform | |
CN204188856U (en) | Transmission line of electricity straight line pole OPGW optical cable syndeton | |
CN203932929U (en) | The erecting device of the anti-fall guide rail of level on a kind of electric pole | |
CN206251283U (en) | Wavelength division multiplexing passive optical network device based on Discrete multi-tune | |
CN203103832U (en) | Supporting rack for cable maintenance | |
CN207800949U (en) | A kind of earthing wire clip | |
CN204028424U (en) | A kind of underground cable, optical cable auxiliary conveying appliance | |
CN205173916U (en) | Mounting structure of transformer substation monitoring camera convenient to overhaul | |
CN205017362U (en) | Electric power communication system | |
CN205160015U (en) | Support is laid with high tension cable to tunnel construction | |
CN204333780U (en) | Bundle conductor fixing-line device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |