CN206209847U - The multi-functional management and control devices of electric power system capital construction safe mass - Google Patents

The multi-functional management and control devices of electric power system capital construction safe mass Download PDF

Info

Publication number
CN206209847U
CN206209847U CN201620856907.2U CN201620856907U CN206209847U CN 206209847 U CN206209847 U CN 206209847U CN 201620856907 U CN201620856907 U CN 201620856907U CN 206209847 U CN206209847 U CN 206209847U
Authority
CN
China
Prior art keywords
module
capital construction
inquiry
terminal machine
power system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620856907.2U
Other languages
Chinese (zh)
Inventor
郭成功
陈锦翔
许龙
王生强
杨建国
许文婷
袁雄
陈佳妮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Nantong Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201620856907.2U priority Critical patent/CN206209847U/en
Application granted granted Critical
Publication of CN206209847U publication Critical patent/CN206209847U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model discloses a kind of multi-functional management and control devices of electric power system capital construction safe mass, the on-site terminal machine that supervisory terminal machine including power system capital construction management librarian use, outsourcing unit project leader person use, the supervisory terminal machine, on-site terminal machine are connected by internet with host communication mode.The utility model is rational in infrastructure, and management of performance is good.

Description

The multi-functional management and control devices of electric power system capital construction safe mass
Technical field
The utility model is related to a kind of multi-functional management and control devices of capital construction safe mass.
Background technology
At present, capital construction system safety quality management personnel's number is relatively on the low side, infrastructure project safety quality management and supervision Means are also only rested in the off-line devices such as camera, video camera, recording pen, and data processing is delayed.As power grid construction is to external-open Put, capital construction is held(Point)The proportion of middle sorts of systems other unit of contracting project increasingly is increased, its project manager, on-site personnel management And technical merit is uneven, make job site security management and control difficulty increasing, and relatively weak safety quality management power Measure and have an opportunity to take advantage of to a small number of violators, risk operator.In recent years, as power network is newly-built, technological transformation construction task be continuously increased, Largely the standing of system other units, construction operation personnel identity, safe qualification, technical qualification and security information need administrative staff Go to distinguish, at present because that cannot compare Field Force's identity and differentiation so that our security management and control seems and is pale and weak. In addition, transmission line of electricity group tower work major part is all located in wilderness field, hard to get to place, the personnel's row in engineering process For, operational method, fire-proof and theft-proof the problems such as cannot all accomplish reliable security management and control always.
The content of the invention
The purpose of this utility model is to provide a kind of rational in infrastructure, good electric power system capital construction safe mass of management of performance Multi-functional management and control devices.
Technical solution of the present utility model is:
A kind of multi-functional management and control devices of electric power system capital construction safe mass, it is characterized in that:Including power system capital construction management The on-site terminal machine that the supervisory terminal machine of librarian use, outsourcing unit project leader person use, the supervisory terminal machine, scene Terminating machine is connected by internet with host communication mode;The supervisory terminal machine includes carrying out the file money of documentation inquiry It is material enquiry module, the engineering enquiry module of inquiry project situation, the personal information module of inquiry workmen's information, existing to construction On-the-spot record module that situation is recorded, to site administrator, situation carries out positioning the locating module of supervise and examine, hair in place The file distribution module of cloth capital construction file;The terminating machine includes carrying out the documentation enquiry module of documentation inquiry, looks into The engineering enquiry module for asking project situation, the on-the-spot record module, the geographical position by oneself that are recorded to job site situation Put the locating module for being committed to main frame, the file reception module for receiving capital construction file.
The utility model is rational in infrastructure, and the inquiry of collection personnel identity, the inquiry of all kinds of workmen's qualifications, subpackage unit in charge of construction enter Enclose etc. data check, live project manager to hilllock in place long-range work attendance positioning scenarios, managerial data inquire about, secure file and notice Immediately issue, site safety record are uploaded in one immediately.Management of performance is excellent.
Brief description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 is the structural representation of the utility model one embodiment.
Specific embodiment
A kind of multi-functional management and control devices of electric power system capital construction safe mass, including power system capital construction management librarian use The on-site terminal machine 2 that supervisory terminal machine 1, outsourcing unit project leader person use, the supervisory terminal machine 1, on-site terminal machine 2 It is connected with the communication modes of main frame 4 by internet 3;The supervisory terminal machine includes that the documentation for carrying out documentation inquiry is looked into Ask module 5, the engineering enquiry module 6 of inquiry project situation, the personal information module 7 of inquiry workmen's information, existing to construction On-the-spot record module 8 that situation is recorded, to site administrator in place situation position the locating module 9 of supervise and examine, Issue the file distribution module 10 of capital construction file;The terminating machine includes carrying out the documentation enquiry module of documentation inquiry 11st, inquiry project situation engineering enquiry module 12, job site situation is recorded on-the-spot record module 13, by oneself Geographical position be committed to main frame locating module 13, receive capital construction file file reception module 15.
Above-mentioned each functional module uses related mature technology means of the prior art.

Claims (1)

1. a kind of multi-functional management and control devices of electric power system capital construction safe mass, it is characterized in that:Including power system capital construction management people The on-site terminal machine that the supervisory terminal machine that uses of member, outsourcing unit project leader person use, the supervisory terminal machine, scene end Terminal is connected by internet with host communication mode;The supervisory terminal machine includes carrying out the documentation of documentation inquiry Enquiry module, inquiry project situation engineering enquiry module, inquiry workmen's information personal information module, to job site On-the-spot record module that situation is recorded, to site administrator, situation carries out positioning the locating module of supervise and examine, issue in place The file distribution module of capital construction file;The terminating machine includes carrying out the documentation enquiry module of documentation inquiry, inquiry The engineering enquiry module of project situation, the on-the-spot record module recorded to job site situation, the geographical position by oneself Be committed to main frame locating module, receive capital construction file file reception module.
CN201620856907.2U 2016-08-10 2016-08-10 The multi-functional management and control devices of electric power system capital construction safe mass Expired - Fee Related CN206209847U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620856907.2U CN206209847U (en) 2016-08-10 2016-08-10 The multi-functional management and control devices of electric power system capital construction safe mass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620856907.2U CN206209847U (en) 2016-08-10 2016-08-10 The multi-functional management and control devices of electric power system capital construction safe mass

Publications (1)

Publication Number Publication Date
CN206209847U true CN206209847U (en) 2017-05-31

Family

ID=58755663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620856907.2U Expired - Fee Related CN206209847U (en) 2016-08-10 2016-08-10 The multi-functional management and control devices of electric power system capital construction safe mass

Country Status (1)

Country Link
CN (1) CN206209847U (en)

Similar Documents

Publication Publication Date Title
CN203720889U (en) Handheld polling terminal
CN203720890U (en) Wearable polling terminal
CN211509189U (en) Electric power operation field supervision equipment and system
CN104656719A (en) Dust removing system
CN207097042U (en) A kind of electric power apparatus integrated information digitalization management system
CN203325039U (en) Routing-inspection supporting system for power transformation operation and maintenance
CN202841210U (en) Real-time control recording system applied to safety production of electric power working fields
CN105809575A (en) Mobile operation system and method for water and electricity production management
CN207799760U (en) Intelligent building management system
CN111581417A (en) Identity recognition method, terminal, system and storage medium for power distribution room constructors
CN103048976A (en) Security management and control command system
CN206209847U (en) The multi-functional management and control devices of electric power system capital construction safe mass
CN104076799A (en) Transformer substation personnel location monitoring system
CN103426060A (en) Capital construction field operation management system
CN105279610A (en) Safety supervision auxiliary method
CN103164817B (en) Multi-purpose intelligent safety supervision method
CN103559652A (en) Communication work-ticket management system based on unattended substation and operation method of communication work-ticket management system
CN207264418U (en) A kind of electric power tunnel management system based on Cloud Server and mobile terminal
CN103442073A (en) Remote control field investigation evidence collecting device
CN103116328A (en) Portable intelligent security remote monitoring device
CN111290323A (en) Equipment monitoring system and method
CN203616787U (en) Novel location inspection system for wind power generation
CN206850810U (en) Engineering information management system based on cloud platform
CN206272758U (en) A kind of building fire-fighting construction monitoring system based on Internet of Things
CN105321225A (en) Management instrument for installation and maintenance of engineering machinery and application of management instrument

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531