CN206204702U CN201621113106.3U CN201621113106U CN206204702U CN 206204702 U CN206204702 U CN 206204702U CN 201621113106 U CN201621113106 U CN 201621113106U CN 206204702 U CN206204702 U CN 206204702U
Authority
CN
China
Prior art keywords
rail
railway roadbed
rail groove
sleeper
concrete layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621113106.3U
Other languages
Chinese (zh)
Inventor
周凯
李丽莉
郑海军
李怀珠
马旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Railway Survey & Design Institute Co Ltd
Original Assignee
Jilin Railway Survey & Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Railway Survey & Design Institute Co Ltd filed Critical Jilin Railway Survey & Design Institute Co Ltd
Priority to CN201621113106.3U priority Critical patent/CN206204702U/en
Application granted granted Critical
Publication of CN206204702U publication Critical patent/CN206204702U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The utility model is related to railroad track applied technical field, specifically provides a kind of combined embedded solid concrete roabed, including bed course, railway roadbed concrete layer, sleeper and rail component, and bed course is divided into sand folder cobble bottom, sand pad middle level and rubble upper strata;Railway roadbed concrete layer surrounds rail groove by concrete-pouring template in rubble upper strata, is poured in rail groove and formed;Sleeper laying is in railway roadbed concrete layer;Rail component is provided with two groups, including rail, connection fastener, strong part and rubble overcoat, rail is fixedly connected by connection fastener in the rail groove encircled a city by railway roadbed concrete layer with sleeper, pre-buried strong part in the sleeper of in the railway roadbed concrete layer of rail groove both sides and lower end, rail groove others space middle berth fills out metalling, and inner side Ballast Layer Height be less than outside metalling, outside metalling, rail, railway roadbed concrete layer upper surface it is contour with ground.Be saved the area by this is new, the requirement of aesthetic property in cities and towns can be significantly met again.

Description

Combined embedded solid concrete roabed
Technical field
The utility model is related to railroad track applied technical field, specifically provides a kind of combined embedded overall road Bed.
Background technology
In the past when narrow gauge railway is laid in cities and towns, can only pass through its rolling stock, road in the range of railway line position Vehicle cannot be using the plan-position in its railway line position;And track is using there is ballast bed, there is that land used is more, investment is big, profile The cosmetic requirements in cities and towns can not be met.
Utility model content
In order to solve the above-mentioned technical problem, the utility model provides a kind of combined embedded solid concrete roabed, you can Save the area, the requirement of aesthetic property in cities and towns can be significantly met again.
The utility model is achieved in that a kind of combined embedded solid concrete roabed of offer, including:
Bed course, is divided into sand folder cobble bottom, sand pad middle level and rubble upper strata;
Railway roadbed concrete layer, rail groove is surrounded by concrete-pouring template in the rubble upper strata, is poured in rail groove Build and form;
Sleeper, is laid in the railway roadbed concrete layer;
Rail component, is provided with two groups, including rail, connection fastener, strong part and rubble overcoat, and rail is by the road It is fixedly connected with the sleeper by connection fastener in the rail groove in bed concrete layer besieged city, the railway roadbed concrete of rail groove both sides Pre-buried strong part in the sleeper of layer neutralization lower end, rail groove others space middle berths fill out metalling, and inner side rubble floor height Degree be less than outside metalling, outside metalling, rail, railway roadbed concrete layer upper surface it is contour with ground.
Further, rubble upper thickness be 290-310mm, sand pad intima-media thickness be 240-260mm.
Further, track well width is that the distance between 1750mm, two rail inside edges are 762mm.
Further, strong part includes embedded bar and angle steel, in the railway roadbed concrete layer of the rail groove both sides, angle Steel is pre-buried around the corner, and embedded bar oblique cutting since its adjacent angular is pre-buried, and welds together with angle steel;In the sleeper In, embedded bar inserts pre-buried from rail groove both sides of the edge.
Further, metalling is divided into the pure metalling of lower floor and the bituminous macadam on upper strata.
Compared with prior art, the utility model has the advantage of nervous in land used condition, circuit (route) is through capable place When required highway and public its plan-position of railway, the combined embedded solid concrete roabed provided with the utility model, tool There are safety and stability, good appearance, save the area, reduce investment, shorten the duration.
Brief description of the drawings
Below in conjunction with the accompanying drawings and implementation method is described in further detail to the utility model:
Fig. 1 is the utility model cross-sectional view at sleeper;
Fig. 2 is A point mplifying structure schematic diagrams in Fig. 1;
Fig. 3 is the utility model bearing of trend structural representation.
Specific embodiment
In order that the purpose of this utility model, technical scheme and advantage become more apparent, below in conjunction with the accompanying drawings and implement Example, is further elaborated to the utility model.It should be appreciated that specific embodiment described herein is used only for explaining The utility model, is not used to limit the utility model.
Cannot be used to solve the problems, such as that railway takes up an area highway, the utility model provides a kind of combined embedded Solid concrete roabed, with reference to Fig. 1, Fig. 2 and Fig. 3, including bed course, railway roadbed concrete layer 4, sleeper 6 and rail component, bed course is divided into sand folder Cobble bottom 1, sand pad middle level 2 and rubble upper strata 3, are laid in railway foundation successively;Railway roadbed concrete layer 4 is by concreting Template surrounds rail groove in rubble upper strata 3, is poured in rail groove and formed;Sleeper 6 is laid in railway roadbed concrete layer 4;Iron Rail assembly is provided with two groups, including rail 7, connection fastener 8, strong part 9 and rubble overcoat 10, and rail 7 is by railway roadbed concrete It is fixedly connected with sleeper 6 by connection fastener 8 in the rail groove that layer 4 is surrounded, in the railway roadbed concrete layer 4 of rail groove both sides with Pre-buried strong part 9 in the sleeper 6 at end, rail groove others space middle berth fills out metalling 10, and inner side Ballast Layer Height less than outer Side metalling, outside metalling, rail, railway roadbed concrete layer upper surface it is contour with ground.
When the combined embedded solid concrete roabed that the utility model is provided is laid, first online curb line is by railway foundation Dig, 3 layers of bed course are laid successively, then erect concreting masterplate, first pour the concrete layer of sleeper bottom, then lay Sleeper, then the concrete on upper strata is poured, after rail is laid after intensity scale, rail is fixed with sleeper by connection fastener, will be strong After part position is fixed, then this pours railway roadbed concrete layer, and finally rubble overcoat is completed.
In order to form strong support to track, prevent from rolling repeatedly and cause rail to be recessed, as changing for technical scheme Enter, rubble upper thickness is 290-310mm, sand pad intima-media thickness is 240-260mm, sand folder cobble underlayer thickness need to be according to geology Situation and maximum frozen depth determine its thickness.
The utility model is applied to narrow gauge track applied technical field, as a kind of perferred technical scheme, track well width For the distance between 1750mm, two rail inside edges are 762mm.
As one kind preferably, strong part 9 includes embedded bar 91 and angle steel 92, in the railway roadbed concrete layer of rail groove both sides In 4, angle steel 92 is pre-buried around the corner, and the oblique cutting since its adjacent angular of embedded bar 91 is pre-buried, and welds together with angle steel 91; In sleeper 6, embedded bar 91 inserts pre-buried from the groove both sides of the edge of rail 7.
Used as the improvement of technical scheme, metalling is divided into the pure metalling 11 of lower floor and the bituminous macadam 12 on upper strata.

Claims (5)

1. combined embedded solid concrete roabed, it is characterised in that including:
Bed course, is divided into sand folder cobble bottom, sand pad middle level and rubble upper strata;
Railway roadbed concrete layer, rail groove is surrounded by concrete-pouring template in the rubble upper strata, poured in rail groove and Into;
Sleeper, is laid in the railway roadbed concrete layer;
Rail component, is provided with two groups, including rail, connection fastener, strong part and rubble overcoat, and rail is mixed by the railway roadbed It is fixedly connected with the sleeper by connection fastener in the rail groove in solidifying soil layer besieged city, in the railway roadbed concrete layer of rail groove both sides With pre-buried strong part in the sleeper of lower end, rail groove others space middle berth fills out metalling, and inner side Ballast Layer Height is low In outside metalling, outside metalling, rail, railway roadbed concrete layer upper surface it is contour with ground.
2. according to the combined embedded solid concrete roabed described in claim 1, it is characterised in that the rubble upper thickness is 290-310mm, the sand pad intima-media thickness are 240-260mm.
3. according to the combined embedded solid concrete roabed described in claim 1, it is characterised in that the track well width is The distance between 1750mm, two rail inside edges are 762mm.
4. according to the combined embedded solid concrete roabed described in claim 1, it is characterised in that the strong part includes pre-buried Reinforcing bar and angle steel, in the railway roadbed concrete layer of the rail groove both sides, angle steel is pre-buried around the corner, and embedded bar is adjacent from its It is pre-buried that angle starts oblique cutting, and welds together with angle steel;In the sleeper, embedded bar is pre- from the insertion of rail groove both sides of the edge Bury.
5. according to the combined embedded solid concrete roabed described in claim 1, it is characterised in that the metalling is divided into lower floor Pure metalling and upper strata bituminous macadam.
CN201621113106.3U 2016-10-11 2016-10-11 Combined embedded solid concrete roabed Expired - Fee Related CN206204702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621113106.3U CN206204702U (en) 2016-10-11 2016-10-11 Combined embedded solid concrete roabed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621113106.3U CN206204702U (en) 2016-10-11 2016-10-11 Combined embedded solid concrete roabed

Publications (1)

Publication Number Publication Date
CN206204702U true CN206204702U (en) 2017-05-31

Family

ID=58761515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621113106.3U Expired - Fee Related CN206204702U (en) 2016-10-11 2016-10-11 Combined embedded solid concrete roabed

Country Status (1)

Country Link
CN (1) CN206204702U (en)

Similar Documents

Publication Publication Date Title
CN105887587B (en) A kind of low circuit switch area of putting of medium-and low-speed maglev is with non-switch area transition section structure
CN103276639B (en) Roadbed structure for deep soft soil region
CN103321118B (en) Bridge road transition section roadbed structure of deep layer yielding ground regions
CN103614961B (en) Stepped reinforced concrete slab capable of preventing abutment vehicle skips and construction method
CN210134291U (en) Broad structure of side of existing passenger dedicated line road bed
CN106192646A (en) Vcehicular tunnel car-driving shock-absorbing denoising structure and construction method thereof
KR100768777B1 (en) Earth reinforcement method for railway track on the concrete base
CN207130543U (en) The embedded tracks structure of new precast track plate
CN204959479U (en) Embedded frame track board and track structure thereof
CN106049201A (en) Medium and low speed maglev traffic engineering low line solid bearing-trail beam structure and construction method thereof
WO2017185917A1 (en) Inter-segment limiting structure having clawed ends for track-bearing beam in single track section of low-set line of mid-to-low speed magnetic levitation transportation project
CN105926391A (en) Method for widening shoulder of existing railway subgrade
CN207017093U (en) New-old concrete bond widens seam-line removal structure
CN109162741A (en) The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN205557205U (en) Low circuit switch area NOT AND switch area changeover portion structure of putting of moderate -low speed magnetic levitation
CN206204702U (en) Combined embedded solid concrete roabed
CN210031493U (en) Embedded orbital beam-ends telescoping device
CN208995842U (en) Level crossing mouth railway roadbed
CN203960701U (en) The relative settlement coordination structure of soft soil roadbed the old and new's subgrade and pavement joining place
CN104594188B (en) Composite pavement and bridge connection transition structure and constructing process thereof
CN102787533A (en) Modification structure of railway subgrade bed surface layer
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
CN107988854A (en) A kind of later stage of subway upper cover vehicle base stopping train checkup shed reserves structure
CN106758586B (en) The method that railway is reinforced on sharp radius curve and easement curve
CN206385393U (en) Non-fragment orbit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531

Termination date: 20211011

CF01 Termination of patent right due to non-payment of annual fee