CN206201459U - A kind of blowning installation for blow moulding machine - Google Patents

A kind of blowning installation for blow moulding machine Download PDF

Info

Publication number
CN206201459U
CN206201459U CN201620928847.0U CN201620928847U CN206201459U CN 206201459 U CN206201459 U CN 206201459U CN 201620928847 U CN201620928847 U CN 201620928847U CN 206201459 U CN206201459 U CN 206201459U
Authority
CN
China
Prior art keywords
blow pipe
gas blow
cylinder
gas
switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620928847.0U
Other languages
Chinese (zh)
Inventor
王伟
黄兴来
曹昀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhangjiagang Long Machinery Co Ltd
Original Assignee
Zhangjiagang Long Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhangjiagang Long Machinery Co Ltd filed Critical Zhangjiagang Long Machinery Co Ltd
Priority to CN201620928847.0U priority Critical patent/CN206201459U/en
Application granted granted Critical
Publication of CN206201459U publication Critical patent/CN206201459U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Blow-Moulding Or Thermoforming Of Plastics Or The Like (AREA)

Abstract

The utility model is related to a kind of blowning installation for blow moulding machine, base to be provided with rail plate;Rail plate front end is provided with the fixed seat on base;Fixed seat is provided with enclosed mechanism;The enclosed mechanism side is provided with air inlet;Rail plate is provided with bearing plate;Bearing plate is provided with the first cylinder and the second cylinder being oppositely arranged;First gas blow pipe and the second gas blow pipe are slidably disposed on bearing plate by the first cylinder and the second cylinder respectively, and enclosed mechanism is pointed in the front end of the first gas blow pipe and the second gas blow pipe;Heating mantle is arranged with first gas blow pipe;The diameter of the first gas blow pipe and the second gas blow pipe is identical with the diameter of air inlet;Base is provided with first switch, second switch and the slide switch being connected with the first cylinder, the second cylinder and rail plate respectively, the utility model gas at normal temperature or high-temperature gas can be blown from the first gas blow pipe or the second gas blow pipe according to demand, be had a safety feature and air blowing efficiency high.

Description

A kind of blowning installation for blow moulding machine
Technical field
The utility model is related to a kind of blowning installation, more particularly to a kind of blowning installation for blow moulding machine.
Background technology
In bottle blowing machine, it is necessary to enclosed mechanism is docked with bottle base mouth seal when carrying out bottle blowing moulding to bottle embryo, and it is blown into Appropriate gas, bottle is blown out by bottle embryo.The gas at normal temperature that is mostly of bottle embryo inner chamber is blown into, and according to reality during bottle blowing Process requirements are normal temperature sometimes for the gas blown, and sometimes for the gas high for temperature blown, if using single Gas blow pipe carry out the air blowing after normal temperature air blowing and heating, easily scrapped using rear gas blow pipe for a long time, to actual use band Inconvenience is carried out.
Utility model content
The utility model purpose is to provide a kind of easy to operate to overcome the deficiencies in the prior art, improves bottle blowing effect Rate, it is to avoid gas blow pipe is because be heated the blowning installation for blow moulding machine caught a cold and easily scrap.
To reach above-mentioned purpose, the technical solution adopted in the utility model is:A kind of blowning installation for blow moulding machine, bag Include base, rail plate, fixed seat, enclosed mechanism, bearing plate, the first cylinder, the second cylinder, the first gas blow pipe, the second air blowing Pipe, heating mantle, first switch, second switch and slide switch;The base is provided with rail plate;The rail plate front end It is provided with the fixed seat on base;The fixed seat is provided with enclosed mechanism;The enclosed mechanism side is provided with air inlet;Institute State rail plate and be provided with bearing plate;The bearing plate is provided with the first cylinder and the second cylinder being oppositely arranged;Described first Gas blow pipe and the second gas blow pipe are slidably disposed on bearing plate by the first cylinder and the second cylinder respectively, and first blows Point to enclosed mechanism in the front end of pipe and the second gas blow pipe;Heating mantle is arranged with first gas blow pipe;First gas blow pipe It is identical with the diameter of air inlet with the diameter of the second gas blow pipe;The base be provided with respectively with the first cylinder, the second cylinder and The connected first switch of rail plate, second switch and slide switch.
Preferably, it is additionally provided with temperature sensor in the heating mantle;The temperature sensor and the alarm being located on base Device is connected.
Preferably, first gas blow pipe and the second gas blow pipe are L-shaped, and both structures are identical.
Preferably, further respectively have connecting tube on first gas blow pipe and the second gas blow pipe, for air-out apparatus phase Even.
Due to the utilization of above-mentioned technical proposal, the utility model has following advantages compared with prior art:
The blowning installation for blow moulding machine of the utility model scheme, its is simple and practical, can normal temperature according to demand Gas or high-temperature gas are blown from the first gas blow pipe or the second gas blow pipe, are had a safety feature, air blowing efficiency high and Quality is good, meets actual use demand.
Brief description of the drawings
Technical solutions of the utility model are described further below in conjunction with the accompanying drawings:
Accompanying drawing 1 is structural representation of the present utility model;
Wherein:1st, base;2nd, rail plate;3rd, fixed seat;4th, enclosed mechanism;5th, bearing plate;6th, the first cylinder;7th, second Cylinder;8th, the first gas blow pipe;9th, the second gas blow pipe;10th, heating mantle;11st, first switch;12nd, second switch;13rd, slide switch; 14th, temperature sensor;15th, alarm;16th, air inlet;17th, connecting tube.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment the utility model is described in further detail.
Described in the utility model a kind of blowning installation for blow moulding machine as shown in Figure 1, including base 1, slip Guide rail 2, fixed seat 3, enclosed mechanism 4, bearing plate 5, the first cylinder 6, the second cylinder 7, the first gas blow pipe 8, the second gas blow pipe 9, Heating mantle 10, first switch 11, second switch and slide switch 13;The base 1 is provided with rail plate 2;The slip is led The front end of rail 2 is provided with the fixed seat 3 on base 1;The fixed seat 3 is provided with enclosed mechanism 4;The side of the enclosed mechanism 4 It is provided with air inlet 16;The rail plate 2 is provided with bearing plate 5;The bearing plate 5 is provided with the first cylinder 6 being oppositely arranged With the second cylinder 7;The gas blow pipe 9 of first gas blow pipe 8 and second is slidable by the first cylinder 6 and the second cylinder 7 respectively It is arranged on bearing plate 5, and enclosed mechanism 4 is pointed in the front end of the first gas blow pipe 8 and the second gas blow pipe 9;First gas blow pipe 8 On be arranged with heating mantle 10;The diameter of the gas blow pipe 9 of first gas blow pipe 8 and second is identical with the diameter of air inlet 16;It is described Base 1 be provided be connected with the first cylinder 6, the second cylinder 7 and rail plate 2 respectively first switch 11, second switch 12 and Slide switch 13;Temperature sensor 14 is additionally provided with the heating mantle 10;The temperature sensor 14 and the report being located on base 1 Alert device 15 is connected;The gas blow pipe 9 of first gas blow pipe 8 and second is L-shaped;And both structures are identical;First gas blow pipe 8 Connecting tube 17 is further respectively had with the second gas blow pipe 9, for being connected with air-out apparatus.
In actual use, enclosed mechanism is docked with bottle embryo mouth seal, when the gas for needing to be blown into normal temperature, first will Second gas blow pipe is connected with air-out apparatus, is then turned on second switch and slide switch, is adjusted by the second cylinder and rail plate The position of whole second gas blow pipe so that the second gas blow pipe is aligned with air inlet, to being blown inside bottle embryo after then ventilating ;When needing to be blown into temperature gas high, the first gas blow pipe is connected with air-out apparatus first, is then turned on first and opens Close and slide switch, the position of the first gas blow pipe adjusted by the first cylinder and rail plate, then open heating mantle, so when When gas at normal temperature is by the position of the second gas blow pipe that is arranged with heating mantle, the temperature of gas at normal temperature is raised, then in bottle embryo Blown in portion.
Further, temperature sensor is also equipped with heating mantle, when the temperature of heating mantle is too high, temperature sensor meeting Alarm is transmitted a signal to, this ensure that safe operation of the present utility model.
Blowning installation for blow moulding machine of the present utility model, its is simple and practical, can gas at normal temperature according to demand Or high-temperature gas is blown from the first gas blow pipe or the second gas blow pipe, is had a safety feature, air blowing efficiency high and quality It is good, meet actual use demand.
The above is only concrete application example of the present utility model, any limit is not constituted to protection domain of the present utility model System.All use equivalents or equivalence replacement and the technical scheme that is formed, all fall within the utility model rights protection scope it It is interior.

Claims (4)

1. a kind of blowning installation for blow moulding machine, it is characterised in that:Including base, rail plate, fixed seat, enclosed mechanism, Bearing plate, the first cylinder, the second cylinder, the first gas blow pipe, the second gas blow pipe, heating mantle, first switch, second switch and slip Switch;The base is provided with rail plate;The rail plate front end is provided with the fixed seat on base;The fixed seat It is provided with enclosed mechanism;The enclosed mechanism side is provided with air inlet;The rail plate is provided with bearing plate;The bearing plate It is provided with the first cylinder and the second cylinder being oppositely arranged;First gas blow pipe and the second gas blow pipe pass through the first cylinder respectively It is slidably disposed on bearing plate with the second cylinder, and enclosed mechanism is pointed in the front end of the first gas blow pipe and the second gas blow pipe; Heating mantle is arranged with first gas blow pipe;The diameter of first gas blow pipe and the second gas blow pipe and the diameter phase of air inlet Together;The base is provided with first switch, second switch and the cunning being connected with the first cylinder, the second cylinder and rail plate respectively Dynamic switch.
2. the blowning installation for blow moulding machine according to claim 1, it is characterised in that:Temperature is additionally provided with the heating mantle Degree sensor;The temperature sensor is connected with the alarm on base.
3. the blowning installation for blow moulding machine according to claim 2, it is characterised in that:First gas blow pipe and second Gas blow pipe is L-shaped, and both structures are identical.
4. the blowning installation for blow moulding machine according to claim 1, it is characterised in that:First gas blow pipe and second Connecting tube is further respectively had on gas blow pipe, for being connected with air-out apparatus.
CN201620928847.0U 2016-08-24 2016-08-24 A kind of blowning installation for blow moulding machine Expired - Fee Related CN206201459U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620928847.0U CN206201459U (en) 2016-08-24 2016-08-24 A kind of blowning installation for blow moulding machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620928847.0U CN206201459U (en) 2016-08-24 2016-08-24 A kind of blowning installation for blow moulding machine

Publications (1)

Publication Number Publication Date
CN206201459U true CN206201459U (en) 2017-05-31

Family

ID=58759761

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620928847.0U Expired - Fee Related CN206201459U (en) 2016-08-24 2016-08-24 A kind of blowning installation for blow moulding machine

Country Status (1)

Country Link
CN (1) CN206201459U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108181049A (en) * 2017-12-21 2018-06-19 重庆晓微城企业孵化器有限公司 A kind of watertightness airtightness test table blow-dry device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108181049A (en) * 2017-12-21 2018-06-19 重庆晓微城企业孵化器有限公司 A kind of watertightness airtightness test table blow-dry device
CN108181049B (en) * 2017-12-21 2019-07-23 重庆晓微城企业孵化器有限公司 A kind of watertightness airtightness test table blow-dry device

Similar Documents

Publication Publication Date Title
CN205200161U (en) Rod water cooling attacks water installation in retaliation
CN206286554U (en) A kind of selective laser fusing former automatic charging device for preheating
CN206201459U (en) A kind of blowning installation for blow moulding machine
CN105197986B (en) A kind of method utilizing air stream quickly to prepare Plumbum preparatium
CN204153931U (en) A kind of air channel structure of central air conditioner system
CN203738003U (en) Air and water hybrid cooling system
CN203080283U (en) Tentering setting machine oven
CN104368269B (en) A kind of cooling device for paste mixing machine
CN206361411U (en) A kind of heat-conducting oil system head tank nitrogen protection device
CN202769657U (en) Safe burner
CN205823321U (en) Mine pneumatic cooling and warming booster
CN209126160U (en) Utilize the inflation film air cooling equipment in underground cold wind source
CN205529150U (en) A energy -conserving cooling cooling device for sapphire mechanical refining stove
CN203908306U (en) Bi-directional symmetric circulating air inflow furnace for crosslinked polyethylene foam processing
CN204936488U (en) A kind of letterpress being equipped with drying unit
CN202164131U (en) Novel vapor collecting and discharging device
CN207388416U (en) A kind of horizontal sealing film separator with refrigerating function
CN204933694U (en) Produce the exhaust gas processing device of MBS
CN204936487U (en) A kind of letterpress with drying mechanism
CN205310793U (en) Novel blown film device
CN213006499U (en) Bottle blowing machine bottleneck is fixed, cooling device
CN204352567U (en) A kind of reboiler with warning function
CN204310119U (en) A kind of air-supply exhaust system of disinfecting drying machine
CN203422677U (en) Explosion-proof positive pressure control device
CN203333308U (en) Energy-saving carbon dioxide preparation electric furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531

Termination date: 20190824