CN206160759U - Metal packing subassembly cooling tower - Google Patents

Metal packing subassembly cooling tower Download PDF

Info

Publication number
CN206160759U
CN206160759U CN201621110508.8U CN201621110508U CN206160759U CN 206160759 U CN206160759 U CN 206160759U CN 201621110508 U CN201621110508 U CN 201621110508U CN 206160759 U CN206160759 U CN 206160759U
Authority
CN
China
Prior art keywords
tower body
air
metal packing
water
outlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621110508.8U
Other languages
Chinese (zh)
Inventor
贺颂钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU LAXUN TECHNOLOGY EXPLOIT Co Ltd
Original Assignee
GUANGZHOU LAXUN TECHNOLOGY EXPLOIT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU LAXUN TECHNOLOGY EXPLOIT Co Ltd filed Critical GUANGZHOU LAXUN TECHNOLOGY EXPLOIT Co Ltd
Priority to CN201621110508.8U priority Critical patent/CN206160759U/en
Application granted granted Critical
Publication of CN206160759U publication Critical patent/CN206160759U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a metal packing subassembly cooling tower, including tower body, fan, receipts hydrophone, water distribution system and metal packing subassembly, water distribution system and metal packing subassembly top -down are fixed in in the tower body and separate into the tower body air inlet area and go out the wind zone, and air inlet area passes through the metal packing subassembly and go out the wind zone to feed through, water distribution system is used for spraying hot water towards the metal packing subassembly, tower body side wall has seted up the intercommunication air inlet area's side air intake, the air outlet that feeds through a wind zone is offered to the tower body, the fan is used for the air supply toward air inlet area, it installs in a wind zone and the sealing cover air outlet to receive the hydrophone. The utility model discloses a metal packing subassembly and the combination of receipts hydrophone form xeothermic air escape at last, avoid fog to produce, can realize the environmental protection, the air outlet sets up at roof or lateral wall, makes the pit of its air pipe that can be applied to the basement, building etc. Reduces the noise outwards to propagate, solves the current noise burning fire control problem that disturbs residents and pack.

Description

Metal packing component cooling tower
Technical field
This utility model is related to metal packing component cooling tower.
Background technology
As China's industry and Development of Urbanization, the generation of fog cause very big pressure for environmental conservation, adopt Various types of cooling towers and cooling technology are a developing direction for realizing environmental protection.
Cooling tower is that, to carry out heat exchange and produce steam, the steam of generation is arranged from air outlet by water and air contact Go out, so as to reduce air themperature in tower, to reach the preheating for dispersing industry generation the device of water temperature is reduced.Traditional cooling tower In use, by blower fan cold dry air is pumped in tower body and through with filler assembly on moisture film carry out heat exchange after formed Damp-heat air, and discharge from the air outlet of tower body, exchange the damp-heat air for producing and be externally formed with fog, and environmental conservation is made Into very big pressure.
Utility model content
In order to overcome the deficiencies in the prior art, the purpose of this utility model is to provide metal packing component cooling tower, its Damp-heat air can be converted into heated dry air, realize environmental protection.
The purpose of this utility model employs the following technical solutions realization:
Metal packing component cooling tower, including tower body, blower fan, water collection device, water distribution system and metal packing component, the cloth Water system and metal packing component are fixed on from top to bottom in tower body and air intake area and wind outlet area will be separated into inside tower body, described Air intake area is connected by the metal packing component with the wind outlet area;The water distribution system is used for towards metal packing component spray Hot water;The tower body sidewall offers the side air inlet for connecting the air intake area, and the tower body offers the connection wind outlet area Air outlet;The blower fan is used for toward the air-supply of air intake area;The water collection device is installed in wind outlet area and sealing cover air outlet.
Preferably, the tower body is provided with the overflow pipe connected with tower body inner bottom, and on the overflow pipe use is provided with In the full water valve of control overflow pipe break-make;The control for also including the level switch being arranged in tower body and being electrically connected with full water valve Device processed, the level switch is used to detect in the tower body height of water level and send the signal to controller;The control Device is used for the opening and closing for receiving the signal of level switch transmission and controlling full water valve.
Preferably, the blow-off pipe connected with tower body inner bottom is also provided with the tower body, the blow-off pipe is provided with For the blowoff valve that control of sewage disposal Gutron is broken.
Preferably, also including the outlet pipe of connection water collection device, the outlet pipe is provided with for controlling outlet pipe break-make Outlet valve.
Preferably, the metal packing component includes the multi-disc packing sheet being arranged in order to tower body bottom from tower body top, Each described filler piece is made up of metal material;Each packing sheet surface is respectively provided with lines and is provided with multiple water flowings on packing sheet surface Mouthful;Be provided with multiple convex portions and recess on each described filler piece, the wherein a piece of packing sheet of any two adjacent packing sheets it is convex Portion is with the recesses fit of a piece of packing sheet in addition and forms vent passages;The vent passages are formed as near the one end in air intake area Air intake, the vent passages are formed as outlet air end near one end of wind outlet area.
Preferably, the water distribution system includes water inlet pipe and the multiple shower nozzles for connecting with water inlet pipe respectively.
Preferably, the water distribution system also includes water fender, and the water fender top is fixed on tower body, the water fender bottom End it is inconsistent with the metal packing component, the water fender, tower body inwall and metal packing component three enclose to be formed for The installation cavity of the air intake area and the wind outlet area is sealed off, the water distribution system is installed on the installation intracavity.
Preferably, the air outlet is opened on the tower body side wall relative with the side air inlet.
Preferably, the air outlet is opened on the roof of tower body.
Preferably, also include being arranged on air guide structure of the tower body near the side of air outlet, the air guide structure is used for will The wind of wind outlet area is directed to air outlet.
Compared to existing technology, the beneficial effects of the utility model are:This utility model by tower body from top to bottom Water distribution system and metal packing component are set, and blower fan and water collection device, dry and cold sky are respectively provided with the both sides of metal packing component Gas be pumped in tower body and through with filler assembly on moisture film carry out heat exchange after form damp-heat air, damp-heat air is again through receiving Hydrophone absorbs the moisture in damp-heat air, damp-heat air is become into heated dry air and is then exhausted from outside tower body, does not directly discharge to external world Damp-heat air, that is, be not formed as fog, is capable of achieving environmental protection;Meanwhile, the moisture that water collection device absorbs can recirculate utilization, realize section Water is reduced discharging;Furthermore, by opening up, side air inlet and side open up air outlet or roof opens up air outlet and coordinates so as to Ke Yiying For needing ventilation shaft, the melt pit of building etc. of the basement of side wall air-out or roof air-out, while coordinating blower fan With metal flavoring agent component, noise can be reduced and outwards propagated, solve the problems, such as that the noise that existing cooling tower is present disturbs residents and fills out Material burning fire fighting problem.
Description of the drawings
Fig. 1 is the structural representation of this utility model metal packing component cooling tower;
Fig. 2 is the structural representation that this utility model metal packing component air outlet of cooling tower is opened in roof;
Fig. 3 is the structural representation of the metal packing component of this utility model metal packing component cooling tower;
Fig. 4 is the side view of the metal packing component of this utility model metal packing component cooling tower.
In figure:1st, tower body;11st, air intake area;12nd, wind outlet area;2nd, water distribution system;21st, shower nozzle;22nd, water inlet pipe;3rd, metal is filled out Material component;31st, packing sheet;311st, vent passages;4th, blower fan;5th, water collection device;6th, full water valve;7th, outlet valve;8th, blowoff valve;9th, pacify It behave affectedly.
Specific embodiment
Below, with reference to accompanying drawing and specific embodiment, this utility model is described further:
As Figure 1-4, metal packing component cooling tower, including tower body 1, blower fan 4, water collection device 5, water distribution system 2 and gold Category filler assembly 3, the water distribution system 2 and metal packing component 3 are fixed on from top to bottom in tower body 1 and are separated into tower body 1 Air intake area 11 and wind outlet area 12, the air intake area 11 is connected by the metal packing component 3 with the wind outlet area 12;The cloth Water system 2 is used to spray hot water towards metal packing component 3;The side wall of the tower body 1 offers the side air inlet in connection air intake area 11, The tower body 1 offers the air outlet of connection wind outlet area 12;The blower fan 4 is used to toward air intake area 11 blow;The water collection device 5 is pacified Loaded on the interior simultaneously sealing cover air outlet in wind outlet area 12.
When using, water distribution system 2 sprays hot water towards metal packing component 3, and hot water is downward along the surface of metal packing component 3 Stream, and form moisture film on the surface of metal packing component 3;Blower fan 4 is simultaneously pumped into cold dry air in air intake area 11 from air inlet, does Cold air stream can carry out heat exchange in air intake area 11 through metal packing component 3 and with the moisture film on metal packing component 3, Cold dry air becomes damp-heat air and leaves metal packing component 3 after lowering the temperature to hot water with moisture film heat exchange, then flows to air-out Area 12;Water collection device 5 due to being provided with sealing cover air outlet in wind outlet area 12, carry the damp-heat air of large quantity of moisture will first pass through Water collection device 5 could be discharged from air outlet, and when water collection device 5, water collection device 5 can absorb the moisture in damp-heat air to damp-heat air, Damp-heat air is become after heated dry air again by air outlet discharge.
During being somebody's turn to do, by the cooperation of metal packing component 3 and water collection device 5, made by metal packing component 3 outside dry and cold Air takes away internal heat, and absorbs the moisture in damp-heat air by water collection device 5, and damp-heat air becomes again heated dry air Just discharge, will not be externally formed with as fog, achievable environmental protection;Meanwhile, the moisture that water collection device 5 absorbs can recirculate utilization, Realize water-saving and emission-reducing.
In order to prevent the inner product water excess of tower body 1, in the present embodiment, the tower body 1 is provided with and is connected with the inner bottom of tower body 1 Overflow pipe, the full water valve 6 for controlling overflow pipe break-make is provided with the overflow pipe;Also include being arranged in tower body 1 Level switch and the control device being electrically connected with full water valve 6, the level switch is used for and detects water in the tower body 1 Position height simultaneously sends the signal to controller;The controller is used to receive the signal of level switch transmission and control full water valve 6 opening and closing.When level switch detects water level higher than setting value, control device control full water valve 6 is opened so as to by tower body 1 Interior hydrops are discharged from overflow pipe;When level switch detects water level less than setting value, controller control full water valve 6 is closed Close.
Further, and when needing to cleaning inside tower body 1, for the ease of the dirt in tower body 1 is discharged, institute The blow-off pipe for being also provided with connecting on tower body 1 with the bottom of tower body 1 is stated, the blow-off pipe is provided with what is broken for control of sewage disposal Gutron Blowoff valve 8;Meanwhile, can for convenience to the cleaning of metal packing component 3, metal packing component 3 can be using dismountable installation Mode.
Meanwhile, the water inside water collection device 5 is reclaimed for convenience, also including the outlet pipe of connection water collection device 5, the outlet pipe It is provided with the outlet valve 7 for controlling outlet pipe break-make.
The metal packing component 3 includes the multi-disc packing sheet 31 being arranged in order to the bottom of tower body 1 from the top of tower body 1, respectively Described filler piece 31 is made up of metal material;The surface of each packing sheet 31 is respectively provided with lines and is provided with the surface of packing sheet 31 multiple logical The mouth of a river;Multiple convex portions and recess, the wherein a piece of filler of any two adjacent packing sheets 31 are provided with each described filler piece 31 The convex portion of piece 31 is with the recesses fit of a piece of packing sheet 31 in addition and forms vent passages 311;The vent passages 311 near enter The one end in wind area 11 is formed as air intake, and the vent passages 311 are formed as outlet air end near one end of wind outlet area 12.Cloth water system The hot water that system 2 sprays can be covered with the surface of packing sheet 31 along outlet pass, and the lines on the surface of packing sheet 31 can make hot water and filler The surface of piece 31 forms moisture film and does not splash down, so that hot water can be fully contacted with air, is imitated with the heat exchange of reinforcer component Really, further, the side that cooperatively forms of multiple ventilating ducts is in cellular structure.
In order to realize that simultaneously water distribution system 2 described in spray hot water large range of to metal packing component 3 includes water inlet pipe 22 and multiple shower nozzles 21 for connecting with water inlet pipe 22 respectively.
In order to fully be lowered the temperature to the hot water that water distribution system 2 is sprayed, as a kind of preferred version, the water distribution system 2 also include water fender, and the water fender top is fixed on tower body 1, and the water fender bottom offsets with the metal packing component 3 Touch, the water fender, the inwall of tower body 1 and the three of metal packing component 3 enclose to be formed for sealing off the and of air intake area 11 The installation cavity 9 of the wind outlet area 12, the water distribution system 2 is installed in the installation cavity 9, and the water fender can be to water distribution system 2 hot water for spraying are formed and enclose guiding, the hot water for spraying are allow completely into metal packing component 3, fully to react.
Air outlet in the present embodiment opens up the preferable implementation below in position, and first, the air outlet is opened in On the side wall relative with the side air inlet of tower body 1;Second, the air outlet is opened on the roof of tower body 1, due to air outlet Side wall or roof are arranged on, are capable of achieving to apply tower body 1 and are similarly being descended chamber ventilated pipeline, building melt pit etc. to need side wall to enter Wind and the scene of air-out, due to application scenario it is more hidden, while employ blower fan 4 and metal packing, can reduce noise to Outer propagation, solves the problems, such as that the noise that existing cooling tower is present disturbs residents and filler burning fire fighting problem.
Second optimal way of above-mentioned air outlet set location, will air outlet be opened in the embodiment of the roof of tower body 1 In, in order to preferably direct the air to the air outlet of roof, also include that being arranged on wind-guiding of the tower body 1 near the side of air outlet ties Structure, the air guide structure is used for the wind of wind outlet area 12 and is directed to air outlet.
It will be apparent to those skilled in the art that technical scheme that can be as described above and design, make other various It is corresponding to change and deformation, and all these change and deformation should all belong to the protection of this utility model claim Within the scope of.

Claims (10)

1. metal packing component cooling tower, it is characterised in that including tower body, blower fan, water collection device, water distribution system and metal packing group Part, the water distribution system and metal packing component are fixed on from top to bottom in tower body and will be separated into inside tower body air intake area and go out Wind area, the air intake area is connected by the metal packing component with the wind outlet area;The water distribution system is used to be filled out towards metal Material component spray hot water;The tower body sidewall offers the side air inlet for connecting the air intake area, and the tower body offers connection The air outlet of the wind outlet area;The blower fan is used for toward the air-supply of air intake area;The water collection device is installed in wind outlet area and sealing cover goes out Air port.
2. metal packing component cooling tower as claimed in claim 1, it is characterised in that the tower body be provided with inside tower body The overflow pipe of bottom connection, is provided with the full water valve for controlling overflow pipe break-make on the overflow pipe;Also include being arranged on tower Internal level switch and the control device being electrically connected with full water valve, the level switch is used to detect in the tower body Height of water level simultaneously sends the signal to controller;The controller is used to receive the signal of level switch transmission and control full water The opening and closing of valve.
3. metal packing component cooling tower as claimed in claim 1, it is characterised in that be also provided with the tower body and tower body The blow-off pipe of inner bottom connection, the blow-off pipe is provided with the blowoff valve broken for control of sewage disposal Gutron.
4. metal packing component cooling tower as claimed in claim 1, it is characterised in that also including the water outlet of connection water collection device Pipe, the outlet pipe is provided with the outlet valve for controlling outlet pipe break-make.
5. metal packing component cooling tower as claimed in claim 1, it is characterised in that the metal packing component is included by tower The multi-disc packing sheet that body top is arranged in order to tower body bottom, each described filler piece is made up of metal material;Each packing sheet surface It is respectively provided with lines and is provided with multiple outlet passes on packing sheet surface;Multiple convex portions and recess are provided with each described filler piece, are appointed Anticipate two adjacent packing sheets the convex portion of wherein a piece of packing sheet is with the recesses fit of other a piece of packing sheet and to form ventilation logical Road;The vent passages are formed as air intake near the one end in air intake area, and the vent passages are formed near one end of wind outlet area For outlet air end.
6. metal packing component cooling tower as claimed in claim 1, it is characterised in that the water distribution system include water inlet pipe and The multiple shower nozzles for connecting with water inlet pipe respectively.
7. metal packing component cooling tower as claimed in claim 6, it is characterised in that the water distribution system also includes dash Plate, the water fender top is fixed on tower body, and the water fender bottom is inconsistent with the metal packing component, the dash Plate, tower body inwall and metal packing component three enclose the installation to be formed for sealing off the air intake area and the wind outlet area Chamber, the water distribution system is installed on the installation intracavity.
8. metal packing component cooling tower as claimed in claim 1, it is characterised in that the air outlet is opened in tower body and institute State on the relative side wall of side air inlet.
9. metal packing component cooling tower as claimed in claim 1, it is characterised in that the air outlet is opened in the top of tower body On wall.
10. metal packing component cooling tower as claimed in claim 9, it is characterised in that also include being arranged on tower body near going out The air guide structure of the side in air port, the air guide structure is used to for the wind of wind outlet area to be directed to air outlet.
CN201621110508.8U 2016-10-09 2016-10-09 Metal packing subassembly cooling tower Active CN206160759U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621110508.8U CN206160759U (en) 2016-10-09 2016-10-09 Metal packing subassembly cooling tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621110508.8U CN206160759U (en) 2016-10-09 2016-10-09 Metal packing subassembly cooling tower

Publications (1)

Publication Number Publication Date
CN206160759U true CN206160759U (en) 2017-05-10

Family

ID=58652708

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621110508.8U Active CN206160759U (en) 2016-10-09 2016-10-09 Metal packing subassembly cooling tower

Country Status (1)

Country Link
CN (1) CN206160759U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106288856A (en) * 2016-10-09 2017-01-04 广州览讯科技开发有限公司 Metal packing assembly cooling tower
CN107218819A (en) * 2017-05-31 2017-09-29 广州览讯科技开发有限公司 Fire-retardant type all-metal cooling tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106288856A (en) * 2016-10-09 2017-01-04 广州览讯科技开发有限公司 Metal packing assembly cooling tower
CN107218819A (en) * 2017-05-31 2017-09-29 广州览讯科技开发有限公司 Fire-retardant type all-metal cooling tower

Similar Documents

Publication Publication Date Title
CN106288855A (en) Axial-flow type air blast crossing current open cooling tower
KR100719858B1 (en) Hybrid ventilation system using draft effect in high-rise buiding
CN207065793U (en) A kind of ventilation unit of energy saving building
CN206160759U (en) Metal packing subassembly cooling tower
CN106288858A (en) A kind of ground pit type mixes earth cooling tower
CN106288856A (en) Metal packing assembly cooling tower
CN206160760U (en) Pit type mixes earth cooling tower
CN207365265U (en) A kind of application technology of stack effect on computer room cabinet
CN206073752U (en) Axial-flow type air blast crossing current open cooling tower
CN201434491Y (en) Water heater structure of increasing thermal efficiency
CN207753100U (en) A kind of curing chamber of accumulator plate
CN207555884U (en) A kind of household kitchen air-makeup system
CN206556460U (en) A kind of concrete air blast open cooling tower
CN206531144U (en) A kind of clean type heating and ventilation air-conditioning device
CN212720975U (en) Water-saving and fog-dispersing cooling tower
CN106197063A (en) Centrifugal air blast crossing current closed cooling tower
CN206479059U (en) A kind of concrete air blast open cooling system for subway tunnel
CN205740918U (en) Biomass gasifying furnace recuperation of heat feed arrangement
CN204943552U (en) Boiler rotation flow impact combustion side wall zone high temperature corrosion resistance device
CN206073755U (en) Axle stream air blast crossing current closed cooling tower
CN207962731U (en) Passive type secondary ventilation device on gas-cooker
CN207945984U (en) A kind of multilayer dry kiln dehumidifier flue gas utilization system
CN207537476U (en) A kind of high-altitude cast house workshop smoke evacuation building structure
CN106766992A (en) A kind of concrete air blast open cooling system for subway tunnel