CN206156757U - Device for recycling and purifying helium - Google Patents

Device for recycling and purifying helium Download PDF

Info

Publication number
CN206156757U
CN206156757U CN201621013204.XU CN201621013204U CN206156757U CN 206156757 U CN206156757 U CN 206156757U CN 201621013204 U CN201621013204 U CN 201621013204U CN 206156757 U CN206156757 U CN 206156757U
Authority
CN
China
Prior art keywords
helium
purifying plant
plant according
recovery purifying
helium recovery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621013204.XU
Other languages
Chinese (zh)
Inventor
宗立冬
金向华
夏致远
孙猛
陈琦峰
周珽
曹文权
许军州
唐璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinhong Gas Co ltd
Original Assignee
Suzhou Jinhong Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Jinhong Gas Co Ltd filed Critical Suzhou Jinhong Gas Co Ltd
Priority to CN201621013204.XU priority Critical patent/CN206156757U/en
Application granted granted Critical
Publication of CN206156757U publication Critical patent/CN206156757U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Gases By Adsorption (AREA)
  • Separation By Low-Temperature Treatments (AREA)

Abstract

The utility model discloses a device for recycling and purifying helium, including flowmeter, primary filter, vacuum pump, compressor, precision filter, first buffer tank, adsorption system, second buffer tank, the cryrogenic tower that connects gradually, the adsorption system includes the adsorption column that at least 2 groups establish ties, be equipped with the heat exchanger that at least three groups establish ties in the cryrogenic tower, make the helium purity more than or equal to 99.999% who purifys and obtain. The utility model discloses can be applicable to the industrial helium tail gas in each field of making of modern industry, and the verification, adopt the utility model discloses an after the device, the ultimate system purification rate of recovery is about 95%, helium purity more than or equal to 99.999% that final purification obtained, obvious effects are achieved.

Description

A kind of helium recovery purifying plant
Technical field
The utility model is related to a kind of recovery purifying plant of chemical gases, and in particular to a kind of helium recovery purification dress.
Background technology
Helium(He)It is a kind of colourless inert gas, the light of buff is sent out during electric discharge.At normal temperatures, it is a kind of extremely light Colourless, odorless, tasteless monoatomic gas.Helium is that liquefaction is most difficult in all gas, and being uniquely can not be in normal atmosphere The material of pressure solidification.The chemical property of helium very torpescence, is difficult under general state and other materials reacts.Helium is one Rare strategic resource is planted, China seems as one of Pin Hai states, long-term dependence on import, the reasonable distribution and application to helium resource It is particularly important.
Field is manufactured in modern industry, helium is widely used in military project, scientific research, petrochemical industry, refrigeration, medical treatment, semiconductor, pipeline Leak detection, superconducting experiment, metal manufacture, deep sea diving, precision welding, O-E Products production etc..However, industrial helium is general Directly consume, in being discharged into air, the post processing such as the helium in tail gas is not reclaimed, purified.Its reason typically accounts for product with helium Product cost of raw material proportion is not high, does not possess recovering condition or recovery difficult is big, based on the immature grade of purification technique.
Helium purity in industrial helium tail gas can typically reach 30% ~ 70%, if these helium resources are by wave in vain Expense is fallen, and this China to lean helium originally undoubtedly makes the matter worse.In recent years, the control with international market to helium resource, it is domestic Control of the industrial trade to product cost, the recovery purifying equipment of rich helium tail gas is ready to appear.For example, Chinese invention patent application CN103771362A discloses a kind of fiber manufacturing online purification system of useless helium, including recovery unit, film subdivision, supply Unit, the rich helium tail gas come by recovery unit Jing absorber carry out dust, grease, steam removal process after, by pipeline Purified into membrane separator, the rich helium tail gas through purifying is temporary into surge tank by pipeline again, the inspection of purity detecting instrument The helium purity of rich helium tail gas in surge tank is surveyed, rich helium tail gas purity reaches in surge tank when detecting Jing after membrane separator purification During the purity rubric of setting, then rich helium tail gas enters air supply unit by outlet pipe on surge tank.
However, purified because above-mentioned purification system relies primarily on membrane separator, and the efficiency comparison of membrane separator is low, A part of unstripped gas can be consumed, therefore final system purifies the rate of recovery typically 85 ~ 90% or so.Additionally, above-mentioned purification system The purity of purification only has 99%, the needs for also having further raising.Therefore, a kind of device of helium recovery purification is developed, with simultaneously Raising system purifies the rate of recovery and purification purity, it is clear that with positive realistic meaning.
Utility model content
The utility model purpose is to provide a kind of helium recovery purifying plant.
To achieve the above object of the invention, the technical solution adopted in the utility model is:A kind of helium recovery purifying plant, bag Include be sequentially connected flowmeter, primary filter, vavuum pump, compressor, accurate filter, the first surge tank, adsorption system, Two surge tanks, deep cooling tower;
The adsorption system includes the adsorption column of at least 2 groups of series connection, causes two in unstrpped gas after adsorption system The content of carbonoxide is less than or equal to 0.2 ppm, and the content of moisture is less than or equal to 1 ppm, and removes halogen gas;
The heat exchanger of at least three groups of series connection is provided with the deep cooling tower, is more than or equal to the helium purity that purification is obtained 99.999%。
Above, unstripped gas can adopt the industrial helium tail gas that field is manufactured from each modern industry, such as petrochemical industry, system Cold, medical, semiconductor, pipeline leak detection, superconducting experiment, metal manufacture, deep sea diving, precision welding, O-E Products production Deng;Helium purity is generally 30% ~ 70% in unstripped gas.
Above, the halogen gas are primarily referred to as the halogen gas that chlorine is representative.
In above-mentioned technical proposal, the flow is calculated as mass flowmenter.To the flow for controlling and adjusting unstripped gas.
In above-mentioned technical proposal, the compressor is piston compressor.
In above-mentioned technical proposal, the accurate filter is parallel connection two-stage accurate filter.
In above-mentioned technical proposal, the vavuum pump for extracting light component foreign gas is additionally provided with the deep cooling tower.
In above-mentioned technical proposal, between first surge tank and adsorption system catalyzing carbon monoxide system is additionally provided with.Should Catalyzing carbon monoxide system is used for for the carbon monoxide in unstripped gas being converted into carbon dioxide.
In above-mentioned technical proposal, the catalyzing carbon monoxide system includes heat exchanger, heater, catalytic bed and cooler.
In above-mentioned technical proposal, the adsorption system includes the adsorption column of 4 groups of series connection.In to remove unstripped gas two Carbonoxide, halogen gas and moisture.
In above-mentioned technical proposal, the adsorption system also includes nitrogen heater, nitrogen stream gauge and muffler.
Workflow of the present utility model is as follows:
(1) regulate and control feed gas flow rates through mass flowmenter, then filter out solid in unstripped gas via primary filter Particle;
(2) unstripped gas is extracted by vavuum pump, enters back into piston compressor and be compressed to 6 ~ 8 bar;Again via Accurate filter, removes the solid particulate matter brought through absorber to 0.1 micron;
(3) catalyzing carbon monoxide system is entered Jing after the first buffer tank pressure buffering, the carbon monoxide in unstripped gas is turned Turn to carbon dioxide;
(4) subsequently into adsorption system(It is in parallel that two groups of adsorption columns can be set in adsorption system, one group of work, one group is again It is raw), carbon dioxide, moisture, the halogen gas in absorption removing unstripped gas etc.;
(5) after the second surge tank compensator or trimmer pressure, enter compressor, after being pressurized to the bar of cold flow tower operating pressure 30, go out Deep cooling tower is entered after compressor, by gas component boiling-point difference under a certain pressure, heat exchange gasification separation is carried out, is finally purified Obtain helium of the purity more than or equal to 99.999%.
Because above-mentioned technical proposal is used, the utility model has compared with prior art following advantages:
1. the utility model develops a kind of helium recovery purifying plant, goes for each manufacture field of modern industry Industrial helium tail gas, and it is demonstrated experimentally that after using device of the present utility model, final system purifies the rate of recovery 95% Left and right, finally purifies the helium purity for obtaining and is more than or equal to 99.999%;Achieve significant effect;
2. the utility model first adopts carbon dioxide, halogen gas in adsorption system Adsorption unstripped gas etc., not only The purity of helium in unstripped gas is improve, and simplifies subsequent purification technique;Then deep cooling tower is adopted, on the basis of absorption Helium to being reclaimed carries out deeper purification, and its purity is purified empty up to 4.5N standards with good exploitation Between;
3. deep cooling tower of the present utility model can adopt high pressure purifying technique, be exchanged heat by liquid nitrogen refrigerant, with can The monitoring capacity for leaning on;
4. the purification efficiency of device of the present utility model is high, be easily understood, and can be designed as online operation equipment, Whole process On-line Control is capable of achieving, with good operating characteristics, popularization and application is suitable to.
Description of the drawings
Fig. 1 is the device flow chart of the utility model embodiment one.
Fig. 2 is the device flow chart of catalyzing carbon monoxide system in the utility model embodiment one.
Fig. 3 is the device flow chart of adsorption system in the utility model embodiment one.
Wherein:1st, flowmeter;2nd, primary filter;3rd, vavuum pump;4th, compressor;5th, accurate filter;6th, the first buffering Tank;7th, adsorption system;8th, the second surge tank;9th, the second compressor;10th, deep cooling tower;11st, catalyzing carbon monoxide system;12nd, exchange heat Device;13rd, heater;14th, catalytic bed;15th, cooler;16th, nitrogen heater;17th, nitrogen stream gauge;18th, muffler;19th, inhale Attached column;20th, the second accurate filter.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment is further described to the utility model:
Embodiment one:
Referring to shown in Fig. 1 ~ 3, a kind of helium recovery purifying plant, including the flowmeter 1, primary filter 2 being sequentially connected, Vavuum pump 3, compressor 4, accurate filter 5, the first surge tank 6, adsorption system 7, the second accurate filter 20, the second surge tank 8th, the second compressor 9, deep cooling tower 10;
The second compressor 9 is provided between second surge tank and deep cooling tower;
The adsorption system includes the adsorption column 19 of 4 groups of series connection, and after adsorption system dioxy in unstrpped gas is caused The content for changing carbon is less than or equal to 0.2 ppm, and the content of moisture is less than or equal to 1 ppm, and removes halogen gas;
The heat exchanger of at least three groups of series connection is provided with the deep cooling tower, is more than or equal to the helium purity that purification is obtained 99.999%。
The flow is calculated as mass flowmenter.The compressor is piston compressor.The accurate filter is in parallel double Level accurate filter.
The vavuum pump for extracting light component foreign gas is additionally provided with the deep cooling tower.
Catalyzing carbon monoxide system 11 is additionally provided between first surge tank and adsorption system.The catalyzing carbon monoxide System includes heat exchanger 12, heater 13, catalytic bed 14 and cooler 15.Cooler is carried out at cooling by water circulation system Reason.It is shown in Figure 2.
The adsorption system also includes nitrogen heater 16, nitrogen stream gauge 17 and muffler 18.
Workflow of the present utility model is as follows:
(1) regulate and control feed gas flow rates through mass flowmenter, then filter out solid in unstripped gas via primary filter Particle;
(2) unstripped gas is extracted by vavuum pump, enters back into piston compressor and be compressed to 6 ~ 8 bar;Again via Accurate filter, removes the solid particulate matter brought through absorber;
(3) catalyzing carbon monoxide system is entered Jing after the first buffer tank pressure buffering, the carbon monoxide in unstripped gas is turned Turn to carbon dioxide;
(4) subsequently into adsorption system(It is in parallel that two groups of adsorption columns can be set in adsorption system, one group of work, one group is again It is raw), carbon dioxide, moisture, the halogen gas in absorption removing unstripped gas etc.;
(5) again via accurate filter, the solid particulate matter brought through absorber is removed to 0.1 micron;Subsequently into Second surge tank, after the second surge tank compensator or trimmer pressure, enters compressor, after being pressurized to the bar of cold flow tower operating pressure 30, goes out Deep cooling tower is entered after compressor, by gas component boiling-point difference under a certain pressure, heat exchange gasification separation is carried out, is finally purified Obtain helium of the purity more than or equal to 99.999%.

Claims (10)

1. a kind of helium recovery purifying plant, it is characterised in that:Including the flowmeter (1), primary filter (2) being sequentially connected, Vavuum pump (3), compressor (4), accurate filter (5), the first surge tank (6), adsorption system (7), the second surge tank (8), depth Cold tower (10);
The adsorption system includes the adsorption column of at least 2 groups of series connection, and after adsorption system titanium dioxide in unstrpped gas is caused The content of carbon is less than or equal to 0.2 ppm, and the content of moisture is less than or equal to 1 ppm, and removes halogen gas;
The heat exchanger of at least three groups of series connection is provided with the deep cooling tower, makes the helium purity that purification is obtained be more than or equal to 99.999%.
2. helium recovery purifying plant according to claim 1, it is characterised in that:The flow is calculated as mass flowmenter.
3. helium recovery purifying plant according to claim 1, it is characterised in that:The compressor is piston compressor.
4. helium recovery purifying plant according to claim 1, it is characterised in that:The accurate filter is parallel connection two-stage Accurate filter.
5. helium recovery purifying plant according to claim 1, it is characterised in that:Extraction is additionally provided with the deep cooling tower light The vavuum pump of composition impurity gas.
6. helium recovery purifying plant according to claim 1, it is characterised in that:First surge tank and adsorption system Between be additionally provided with catalyzing carbon monoxide system (11).
7. helium recovery purifying plant according to claim 6, it is characterised in that:The catalyzing carbon monoxide system includes Heat exchanger (12), heater (13), catalytic bed (14) and cooler (15).
8. helium recovery purifying plant according to claim 1, it is characterised in that:The adsorption system includes 4 groups The adsorption column (19) of series connection.
9. helium recovery purifying plant according to claim 1, it is characterised in that:The adsorption system also adds including nitrogen Hot device (16), nitrogen stream gauge (17) and muffler (18).
10. helium recovery purifying plant according to claim 1, it is characterised in that:Second surge tank and deep cooling tower Between be additionally provided with the second compressor (9).
CN201621013204.XU 2016-08-31 2016-08-31 Device for recycling and purifying helium Active CN206156757U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621013204.XU CN206156757U (en) 2016-08-31 2016-08-31 Device for recycling and purifying helium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621013204.XU CN206156757U (en) 2016-08-31 2016-08-31 Device for recycling and purifying helium

Publications (1)

Publication Number Publication Date
CN206156757U true CN206156757U (en) 2017-05-10

Family

ID=58648810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621013204.XU Active CN206156757U (en) 2016-08-31 2016-08-31 Device for recycling and purifying helium

Country Status (1)

Country Link
CN (1) CN206156757U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026626A (en) * 2018-06-19 2018-12-18 安徽万瑞冷电科技有限公司 A kind of gas recycling compression set and the helium recovery system comprising the device
CN110624321A (en) * 2019-10-28 2019-12-31 苏州朗道节能技术有限公司 A preceding processing apparatus for waste gas recovery purifies
CN113086956A (en) * 2021-04-15 2021-07-09 衢州杭氧特种气体有限公司 Neon purification process and purification equipment thereof
CN113551850A (en) * 2021-07-15 2021-10-26 杭州中泰深冷技术股份有限公司 Multi-channel internal and external leakage detection, recovery and purification device and method for plate-fin heat exchanger
CN113983355A (en) * 2021-10-27 2022-01-28 中天上材增材制造有限公司 Gas supply system of equipment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026626A (en) * 2018-06-19 2018-12-18 安徽万瑞冷电科技有限公司 A kind of gas recycling compression set and the helium recovery system comprising the device
CN110624321A (en) * 2019-10-28 2019-12-31 苏州朗道节能技术有限公司 A preceding processing apparatus for waste gas recovery purifies
CN113086956A (en) * 2021-04-15 2021-07-09 衢州杭氧特种气体有限公司 Neon purification process and purification equipment thereof
CN113551850A (en) * 2021-07-15 2021-10-26 杭州中泰深冷技术股份有限公司 Multi-channel internal and external leakage detection, recovery and purification device and method for plate-fin heat exchanger
CN113983355A (en) * 2021-10-27 2022-01-28 中天上材增材制造有限公司 Gas supply system of equipment

Similar Documents

Publication Publication Date Title
CN206156757U (en) Device for recycling and purifying helium
CN103373716B (en) Method and device for purifying and recycling emitted argon in preparation process of monocrystalline silicon
CN106145037B (en) The method that the device and High Purity Hydrogen processed of hydrogen are recycled from silicon epitaxial furnace emptying end gas
CN104944393B (en) A kind of apparatus and method of concentrate purifying high-purity helium
CN106139890B (en) The device and method of cold-rolled steel sheet heat treatment nitrogen hydrogen mixed tail gas recycling purification
CN208406522U (en) Sulfur hexafluoride and nitrogen mixed gas purification separation purifying plant
CN103357262B (en) A kind of for reclaiming and the method for nitrous oxide in purifying industrial tail gas
CN105268282A (en) Method for preparing ultra pure hydrogen by low-temperature pressure-swing adsorption
CN108355461A (en) Sulfur hexafluoride and nitrogen mixed gas purification separation purifying plant and its reclaiming clean purify sulfur hexafluoride method
CN104176717A (en) Method and device for recycling and purifying helium gas
CN104406364A (en) Double-tower coupling type argon recovery and purifying equipment and argon recovery and purifying method
CN202141345U (en) Tail gas recovering system for annealing furnace
CN115634561A (en) Carbon dioxide capturing and washing device and method for thermal power plant
CN102173382B (en) Byproduct hydrogen purification recovery system and method in chlorine industry
CN101441023A (en) Energy-saving type air separation process
CN104556035A (en) Preparation method and preparation device of food-grade high-purity liquid carbon dioxide
CN203392864U (en) Device for recycling impure neon-helium gas mixture
CN103626129B (en) With industrial liquid chlorine for the method for electronic grade high-purity chlorine prepared by raw material
CN202785635U (en) Adsorptive hydrogen purifying device
CN202216490U (en) Extraction device for high-purity liquid neon
CN103589550A (en) Carbon dioxide balanced system for beer brewing technology
CN106440661A (en) Energy-saving type device for preparing high-purity liquid carbon dioxide and method
CN204057968U (en) A kind of helium recovery purifying plant
CN107677045B (en) Internal purifier research system
CN102706101B (en) Air separating device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 215152 Anmin Road, Panyang Industrial Park, Huangdai Town, Xiangcheng District, Suzhou City, Jiangsu Province

Patentee after: Jinhong Gas Co.,Ltd.

Address before: 215152 No. 6 Anmin Road, Panyang Industrial Park, Huangdi Town, Xiangcheng District, Suzhou City, Jiangsu Province

Patentee before: SUZHOU JINHONG GAS Co.,Ltd.