CN206128114U - Assembled prefabricated comprehensive pipe rack - Google Patents

Assembled prefabricated comprehensive pipe rack Download PDF

Info

Publication number
CN206128114U
CN206128114U CN201620959214.6U CN201620959214U CN206128114U CN 206128114 U CN206128114 U CN 206128114U CN 201620959214 U CN201620959214 U CN 201620959214U CN 206128114 U CN206128114 U CN 206128114U
Authority
CN
China
Prior art keywords
prefabricated
skeleton
plate
top board
web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620959214.6U
Other languages
Chinese (zh)
Inventor
杨卓舒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuoda Real Estate Group Co Ltd
Original Assignee
Zhuoda Real Estate Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuoda Real Estate Group Co Ltd filed Critical Zhuoda Real Estate Group Co Ltd
Priority to CN201620959214.6U priority Critical patent/CN206128114U/en
Application granted granted Critical
Publication of CN206128114U publication Critical patent/CN206128114U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses an assembled prefabricated comprehensive pipe rack is assembled in proper order by a plurality of prefabricated unit and forms, and wherein every prefabricated unit is mainly formed by roof, two webs and bottom plate assembly, and above -mentioned each board is the prefabricated plate, and the key lies in: including the skeleton that mainly forms by channel -section steel end to end in the structure of prefabricated plate, set up at the wire net of skeleton one side or both sides and fill the aerated concrete in the skeleton. The utility model discloses an useful technological effect is: it all is prefabs that roof, web and bottom plate all are the prefab, and its simple structure, intensity are good, and the construction preparation is convenient quick, prefabricated the connecting piece in the skeleton, the site operation is quick, can guarantee construction cycle.

Description

Prefabricated pipe gallery
Technical field
This utility model is related to a kind of prefabricated piping lane, and in particular to a kind of prefabricated pipe gallery.
Background technology
Urban Underground city planting ductwork is the important component part of urban public utilities.Public utility belongs to the public clothes in city Business facility, with the double properties for servicing for social production and social life simultaneously.As can be seen here, urban public utilities are to maintain City produces and lives the basis of normal operation, and is also therefore referred to as city as the Municipal pipe network of its important component part " life line " in city.Municipal Infrastructure includes the transmission & distribution pipelines such as feedwater, sewage, rainwater, electric power, communication, combustion gas, heating power With the facility such as plant stand.
For lifting construction speed, the way of various prefabricated piping lanes is there has been, wherein conventional is integrated precast With it is prefabricated.Because pipe gallery size, than larger, integrated precast piping lane is often very heavy, to prefabrication, transport, existing Field lifting brings many inconvenience;Also a kind of assembled pipe gallery way is that bearing, side plate, top board are separately pre- in factory System, to on-site consolidation combination;But the structure of its each component is complex, cause the prolongation of construction period.
The content of the invention
Problem to be solved in the utility model is to provide a kind of prefabricated pipe gallery for being capable of rapid construction, top Plate, web and base plate are precoated plate, and skeleton, steel wire and the air entrained concrete that precoated plate is made up of channel-section steel is constituted, Neng Gou Factory is quick prefabricated, live rapid construction.
To solve above-mentioned technical problem, the technical solution adopted in the utility model is:A kind of prefabricated pipe gallery, It is assembled successively by some prefabricated units, wherein each prefabricated unit is mainly assembled by top board, two webs and base plate, Above-mentioned each plate is precoated plate, it is critical only that:The structure of the precoated plate includes main by the end to end bone for being formed of channel-section steel Frame, the steel wire for being arranged on skeleton one or both sides and it is poured in intraskeletal air entrained concrete.
Further, the top board connecting bolt and web fixed with its skeleton respectively is provided with the inside of top board and base plate Connecting bolt, the upper and lower ends on the inside of web be provided with position with top board connecting bolt and web connecting bolt respectively and by The connecting plate that nut is fixed, the connecting plate is mutually fixed with the skeleton of web.
Further, I-steel is further fixed in skeleton.
Further, in piping lane, the I-shaped that upper and lower ends are fixed respectively with top board and base plate is provided between two webs Type prefabricated component.
Further, the connecting bolt fixed with its skeleton respectively is provided with the inside of top board and base plate, in I shape Prefabricated component upper and lower ends are provided with the prefabricated component connecting plate fixed with connecting bolt positioning and by nut.
Advantageous Effects of the present utility model are:Top board, web and base plate are prefabricated components, and simple structure, intensity are good, Construction is easy to make quick;The prefabricated connector in skeleton, site operation is quick, ensure that construction period.
This utility model is described in detail below in conjunction with the accompanying drawings.
Description of the drawings
Fig. 1 is the structural representation of the prefabricated pipe gallery of this utility model;
Fig. 2 is the sectional view of precoated plate in Fig. 1;
Fig. 3 is the skeleton schematic diagram of precoated plate in Fig. 1.
In the accompanying drawings:1 is top board, and 2 is web, and 3 is base plate, and 4 is channel-section steel, and 5 is steel wire, and 6 is air entrained concrete, and 7 are Top board connecting bolt, 8 is web connecting bolt, and 9 is connecting plate, and 10 is I-steel, and 11 is I shape prefabricated component, and 12 is connection spiral shell Bolt, 13 is prefabricated component connecting plate.
Specific embodiment
Referring to accompanying drawing 1-3, this utility model provides a kind of prefabricated pipe gallery, by some prefabricated units successively It is assembled, wherein each prefabricated unit is mainly assembled by 1, two webs 2 of top board and base plate 3, and above-mentioned each plate is pre- Making sheet, it is critical only that:The structure of the precoated plate includes mainly forming enclosed skeleton, setting by channel-section steel 4 is end to end Skeleton one or both sides steel wire 5 and be poured in intraskeletal air entrained concrete 6.
To make live rapid construction, it is provided with the inner side of top board 1 and base plate 3 and is connected with the top board of its skeleton fixation respectively Bolt 7 and web connecting bolt 8, the upper and lower ends in the inner side of web 2 are provided with and are connected with top board connecting bolt 7 and web respectively The connecting plate 9 that bolt 8 is positioned and fixed by nut, connecting plate 9 is mutually fixed with the skeleton of web 2.Web 2 in the specific implementation It is connected with top board connecting bolt 7 and web connecting bolt 8 by clamp nut between top board 1 and base plate 3 and realizes web 2 and top board Fixation between 1 and base plate 3.
To ensure frame strength, I-steel 10 is further fixed in skeleton.The groove of channel-section steel 4 and I-steel 10 can be easy to add The cast of gas concrete 6.
To ensure the stability of whole piping lane, be provided with piping lane, between two webs 2 upper and lower ends respectively with top board 1 The I shape prefabricated component 11 fixed with base plate 3.I shape prefabricated component 11 can be the steel skeleton knot as above-mentioned precoated plate The structure such as structure, or concrete.
To realize the connection of I shape prefabricated component 11 and top board 1 and base plate 3, it is provided with point in the inner side of top board 1 and base plate 3 The connecting bolt 12 do not fixed with its skeleton, is provided with prefabricated with what connecting bolt 12 was fixed in the upper and lower ends of I shape prefabricated component 11 Part connecting plate 13.In the specific implementation by clamp nut and connecting bolt 12 between I shape prefabricated component 11 and top board 1 and base plate 3 The fixation between I shape prefabricated component 11 and top board 1 and base plate 3 is realized in connection.
Finally it should be noted that:Above example is only to illustrate the technical solution of the utility model rather than it is limited System;Although being described in detail to this utility model with reference to preferred embodiment, those of ordinary skill in the art should Understand:Still specific embodiment of the present utility model can be modified or equivalent is carried out to some technical characteristics and be replaced Change;Without deviating from the spirit of technical solutions of the utility model, it all should cover the technical scheme being claimed in this utility model In the middle of scope.

Claims (4)

1. a kind of prefabricated pipe gallery, is assembled successively by some prefabricated units, and wherein each prefabricated unit is main By top board(1), two webs(2)And base plate(3)It is assembled, above-mentioned each plate is precoated plate, it is characterised in that:It is described prefabricated The structure of plate includes main by channel-section steel(4)The skeleton of end to end formation, the steel wire for being arranged on skeleton one or both sides(5) And it is poured in intraskeletal air entrained concrete(6);
In piping lane, two webs(2)Between be provided with upper and lower ends respectively with top board(1)And base plate(3)Fixed I shape is pre- Product(11), I shape prefabricated component(11)It is and described precoated plate identical steel skeleton construction or xoncrete structure.
2. prefabricated pipe gallery according to claim 1, it is characterised in that:In top board(1)And base plate(3)It is interior Side is provided with the top board connecting bolt fixed with its skeleton respectively(7)With web connecting bolt(8), in web(2)Inner side it is upper Lower two ends be provided with respectively with top board connecting bolt(7)With web connecting bolt(8)Positioning and the connecting plate fixed by nut (9), the connecting plate(9)With web(2)Skeleton mutually fix.
3. prefabricated pipe gallery according to claim 1, it is characterised in that:I-steel is further fixed in skeleton (10).
4. prefabricated pipe gallery according to claim 1, it is characterised in that:In top board(1)And base plate(3)It is interior Side is provided with the connecting bolt fixed with its skeleton respectively(12), in I shape prefabricated component(11)Upper and lower ends are provided with and are connected spiral shell Bolt(12)Positioning and the prefabricated component connecting plate fixed by nut(13).
CN201620959214.6U 2016-08-29 2016-08-29 Assembled prefabricated comprehensive pipe rack Expired - Fee Related CN206128114U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620959214.6U CN206128114U (en) 2016-08-29 2016-08-29 Assembled prefabricated comprehensive pipe rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620959214.6U CN206128114U (en) 2016-08-29 2016-08-29 Assembled prefabricated comprehensive pipe rack

Publications (1)

Publication Number Publication Date
CN206128114U true CN206128114U (en) 2017-04-26

Family

ID=58566159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620959214.6U Expired - Fee Related CN206128114U (en) 2016-08-29 2016-08-29 Assembled prefabricated comprehensive pipe rack

Country Status (1)

Country Link
CN (1) CN206128114U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236314A (en) * 2020-03-26 2020-06-05 张延年 Assembled rectangle concrete slab for utility tunnel
CN113047338A (en) * 2021-03-26 2021-06-29 上海浦东混凝土制品有限公司 Comparatively firm prefabricated utility tunnel of concatenation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236314A (en) * 2020-03-26 2020-06-05 张延年 Assembled rectangle concrete slab for utility tunnel
CN113047338A (en) * 2021-03-26 2021-06-29 上海浦东混凝土制品有限公司 Comparatively firm prefabricated utility tunnel of concatenation
CN113047338B (en) * 2021-03-26 2024-04-26 上海浦东混凝土制品有限公司 Comparatively firm prefabricated utility tunnel of concatenation

Similar Documents

Publication Publication Date Title
CN207348091U (en) A kind of assembled pipe gallery
CN206128114U (en) Assembled prefabricated comprehensive pipe rack
CN103161174A (en) Offshore wind turbine generator set installation fundamental assembly
CN103669336A (en) Geothermal air conditioner preformed pile
CN201121768Y (en) Manufactory pipe network arrangement structure
CN208605197U (en) A kind of building structure that subway driving section is built together with Urban Underground pipe gallery
CN204151824U (en) A kind of glass reinforced plastic underground comprehensive pipe network common trench
CN206428721U (en) Assembled underground pipe gallery
CN206233688U (en) A kind of urban construction guardrail
CN202787240U (en) Precast pile of geothermal air-conditioner
CN202247941U (en) Foundation of steam turbogenerator
CN206128115U (en) Utility tunnel prefabricated plate
CN209703554U (en) Pipe gallery with comprehensive support
CN203174882U (en) Shock resistant composite beam for housing building
CN202324155U (en) Adjustable corrugated prestress anti-pollution drainage culvert
CN205934965U (en) Utility tunnel
CN202059082U (en) Special embedded type transformer for wind power tower barrel transformer substation
CN201560437U (en) Manhole
CN202218418U (en) Self-bringing counterweight type base station with integrated body of tower and cabinet
CN206090609U (en) City utility tunnel pedestrian protection device
CN205296221U (en) Many function synthesis piping lane
CN204326105U (en) A kind of plastic inspection well
CN204225062U (en) The inner gallery structure of bulb turbine hydropower station factory building
CN206438537U (en) underground pipe gallery structure
CN204080859U (en) High-strength resistance to compression centripetal-stress Urban Underground pipe gallery

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170426

Termination date: 20170829

CF01 Termination of patent right due to non-payment of annual fee