CN206104547U - Cut deal production line - Google Patents

Cut deal production line Download PDF

Info

Publication number
CN206104547U
CN206104547U CN201621176660.6U CN201621176660U CN206104547U CN 206104547 U CN206104547 U CN 206104547U CN 201621176660 U CN201621176660 U CN 201621176660U CN 206104547 U CN206104547 U CN 206104547U
Authority
CN
China
Prior art keywords
line
cold bed
way
roller
shearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621176660.6U
Other languages
Chinese (zh)
Inventor
曹建宁
韩文
熊明鲜
苏洸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Capital Engineering and Research Incorporation Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
CERI Technology Co Ltd
Original Assignee
Zhongye Jingcheng Engineering Technology Co Ltd
CERI Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Jingcheng Engineering Technology Co Ltd, CERI Technology Co Ltd filed Critical Zhongye Jingcheng Engineering Technology Co Ltd
Priority to CN201621176660.6U priority Critical patent/CN206104547U/en
Application granted granted Critical
Publication of CN206104547U publication Critical patent/CN206104547U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a cut deal production line, cut deal production line includes: the main line that rolls is including the main line export roller way that rolls, the shear line is including the shear line approach table, the delay table is located main rolling between line and the shear line, and the delay table is respectively with mainly roll line export roller way and the shear line approach table is sharp the connection. Roll line and shear line with the owner and pass through delay table lug connection, can directly enter into the shear line through the delay table through the main mother board that rolls line production and cut, can improve the lumber recovery, the quantity that can reduce to get into the mother board of cold bed subassembly simultaneously to improve the availability factor of cold bed, and then improved cut deal production line's production efficiency.

Description

Heavy Plate Production line
Technical field
This utility model is related to metallurgical technical field of steel rolling, specifically a kind of Heavy Plate Production line.
Background technology
Cut deal mill is typically made up of Ban Jiaqu, Zhu Zha area, cold bed area, shearing line and Runout area etc..Steel plate Jing Ban Jia areas heat, and after Zhu Zha areas complete the operations such as rolling, cool down into cold bed area as needed, shearing line are entered back into afterwards complete Into cutting operation.As shown in figure 1, cut deal mill of the prior art typically has with lower component:Milling train 1, roller-way 2, Pre-straightening machine 3, quickly cooling device 4, thermal straightening machine 5, main rolling line runout table 6 (thermal straightening machine runout table), cold bed area is defeated Enter roller-way 7, cold bed 8, cold bed 9 checks reconditioning stand 10, and panel turnover machine 11, cold bed area runout table 12 (checks that reconditioning stand 10 is defeated Go out roller-way), shearing line inlet roller way 13 (crop cuts approach table), crop cuts 14, bilateral scissors 15, fixed size scissors 16.Prior art In technology arrangement mode be main rolling line with shearing line in the entering of cold bed area, Way out staggers and is arranged in parallel.I.e. main rolling line Runout table 6 is connected with cold bed area approach table 7, and shearing line inlet roller way 13 is then connected with cold bed area runout table 12, cold bed Area's approach table 7 is separated by a distance along vertical rolling direction (i.e. vertical roller-way centerline direction) with cold bed area runout table 12 It is arranged in parallel.Under this arrangement, all steel plates from main rolling line into shearing line all have to pass through cold bed area, are brought Subject matter be:The length of rolled piece is affected by cold bed width, and (expansion of cold bed width is limited by plant designing and investment etc. System), it is unfavorable for that flexible organization is produced, it is unfavorable for improving lumber recovery;In addition, cold bed is typically to affect production on Heavy Plate Production line The important bottleneck of efficiency, in the case where main rolling line and shearing line are arranged in parallel, also necessary Jing is cold for the relatively low steel plate of some temperature Bed enters shearing line, have impact on the service efficiency of cold bed.
Thus, this utility model people proposes a kind of Heavy Plate Production by the experience and practice of being engaged in relevant industries for many years Line and production method, to overcome the defect of prior art.
Utility model content
The purpose of this utility model is to provide a kind of Heavy Plate Production line, to improve the production efficiency of cut deal and become a useful person Rate.
Another object of the present utility model is to provide a kind of Heavy Plate Production line, to improve cold bed service efficiency.
This utility model solves the technical scheme that its technical problem adopted:A kind of Heavy Plate Production line, cut deal life Producing line includes:Main rolling line, including main rolling line runout table;Shearing line, including shearing line approach table;Delay table, positioned at master Between rolling line and shearing line, delay table is linearly connected respectively with main rolling line runout table and shearing line approach table.
Further, Heavy Plate Production line also includes cold bed component, and cold bed component is arranged between main rolling line and shearing line, Cold bed component and delay table at least side lateral connection.
Further, Heavy Plate Production line also includes detection components, and detection components are arranged at main rolling line runout table.
Further, cold bed component includes the first cold bed and the second cold bed, and delay table includes:Inlet roller way, is arranged on At first cold bed, inlet roller way is connected with main rolling line runout table, and inlet roller way is the approach table of the first cold bed;Connection roll Road, is arranged at the second cold bed, and connection roller-way is connected with inlet roller way, connects the approach table that roller-way is the second cold bed.
Further, cold bed component also includes checking the defeated of reconditioning stand, the runout table of the first cold bed and the second cold bed Go out roller-way to be connected with the approach table for checking reconditioning stand, delay table also includes outlet roller-way, outlet roller-way is arranged on inspection Look at reconditioning stand, outlet roller-way two ends respectively be connected roller-way and the connection of shearing line approach table, export roller-way and repair for inspection The runout table of mill stand.
Further, main rolling line includes milling train, pre-straightening machine, quickly cooling device and the thermal straightening machine being sequentially connected, heat Straightener rear end connects main rolling line runout table.
Further, shearing line include the crop that is sequentially connected cut, bilateral scissors and fixed size scissors, crop cuts front end connection shearing Line approach table.
The beneficial effects of the utility model are:
1st, the production of milling train can not consider cold bed width, and length of rolled piece can consider blank and roll according to order The flexible organization production of situations such as function power, realizes many multiple length rollings of overlength.In the case that this steel plate length exceeds cold bed width, Steel plate thickness is generally relatively thin, and temperature is generally relatively low, therefore steel plate is out not required to afterwards directly pass through roller through cold bed from main rolling line Road enters shearing line shearing.The largest benefit of overlength many multiple lengths rolling is to make the average shear amount of waste of monolithic finished steel plate significantly Reduce, so as to be conducive to improving lumber recovery.
2nd, the thinner thickness of main rolling line production or through the relatively low steel plate of the temperature of fast cooling device water-cooled, goes out from main rolling line Directly subsequent handling can be completed into shearing line by roller transport without cold bed after coming, therefore be reduced into cold bed cooling Steel plate number, it is to avoid a large amount of satisfactions are waited in line on cold bed, take cold bed into the relatively low steel plate of the temperature that shearing line is required Area, the cooling capacity of waste cold bed, therefore the service efficiency of cold bed is also just improve, cold bed has been extenuated as production line bottleneck Restricted influence to production capacity, optimizes the logistics in cold bed region.
Description of the drawings
The Figure of description for constituting the part of the application is used for providing further understanding to of the present utility model, this practicality New schematic description and description is used to explain this utility model, does not constitute to improper restriction of the present utility model. In the accompanying drawings:
Fig. 1 is the structural representation of prior art Heavy Plate Production line;
Fig. 2 is the structural representation of this utility model Heavy Plate Production line embodiment;
Fig. 3 is the schematic flow sheet of this utility model Heavy Plate Production method.
Reference in figure:1st, milling train;2nd, the first roller-way;3rd, pre-straightening machine;4th, quickly cooling device;5th, thermal straightening machine; 6th, main rolling line runout table;7th, cold bed area approach table;8th, the first cold bed;9th, the second cold bed;10th, reconditioning stand is checked;11st, turn over Trigger;12nd, cold bed area outlet roller-way;13rd, shearing line approach table;14th, crop is cut;15th, bilateral scissors;16th, fixed size scissors;17th, in Between roller-way;171st, inlet roller way;172nd, roller-way is connected;173rd, roller-way is exported;18th, the second roller-way;19th, the 3rd roller-way.
Specific embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Below with reference to the accompanying drawings and in conjunction with the embodiments describing this utility model in detail.
As shown in Fig. 2 this utility model embodiment provides a kind of Heavy Plate Production line, Heavy Plate Production line includes that master rolls Line, shearing line, cold bed component and the delay table between main rolling line and shearing line 17.Main rolling line includes main rolling line outlet roller Road 6.Shearing line includes shearing line approach table 13.Delay table 17 respectively with main rolling line runout table 6 and shearing line input roller Road 13 linearly connects, i.e.,:The centrage of main rolling line runout table 6, the centrage of delay table 17 and shearing line approach table 13 centrage is respectively positioned on same straight line.Cold bed component is arranged between main rolling line and shearing line, cold bed component and intermediate calender rolls At least side lateral connection of road 17, above-mentioned is laterally perpendicular to the direction of the centrage of delay table 17 in Fig. 2.
Main rolling line is directly connected to shearing line by delay table 17, can directly be led to through the motherboard of main rolling line production Cross delay table 17 and enter in shearing line and sheared, the quantity of the motherboard into cold bed component can be reduced, so as to improve The service efficiency of cold bed, and then improve the production efficiency of Heavy Plate Production line.
Needs say that the cold bed component in this utility model embodiment is cold bed area commonly used in the prior art.
As shown in Fig. 2 main rolling line includes milling train 1, pre-straightening machine 3, quickly cooling device 4 and the thermal straightening machine being sequentially connected The first roller-way 2 between 5 and the above-mentioned each part of connection, the rear end of thermal straightening machine 5 reconnects main rolling line runout table 6.Shearing line 14, bilateral scissors 15 and fixed size scissors 16 are cut including the crop being sequentially connected and for connecting the second roller-way between above-mentioned each part 18, crop cuts 14 front ends and reconnects shearing line approach table 13.
Delay table 17 in this utility model embodiment includes the first connection status and the second connection status, connects first When connecing state, main rolling line is directly connected to shearing line by delay table 17.In the second connection status, main rolling line, cold bed group Part and shearing line are sequentially connected by delay table 17.
Specifically, one end of delay table 17 is connected with main rolling line runout table 6, the other end and the shearing of delay table 17 Line approach table 13 connects.It is direct by one end of delay table 17 through the motherboard of main rolling line production in the first connection status It is delivered to the other end of delay table 17 (i.e. being delivered directly to the right side of delay table 17 in Fig. 2 from the left side of delay table 17) And enter in shearing line and carry out shearing manipulation.In first connection status, motherboard need not move through cold bed component carry out it is cold But.In the second connection status, through main rolling line production motherboard by delay table 17 one end (left end in Fig. 2) along perpendicular to The direction of delay table centrage is moved horizontally to cold bed component (i.e. downwardly direction is moved horizontally along Fig. 2), and motherboard is cold Export again after cooling to the other end of delay table 17 (right-hand member in Fig. 2) in bed component, and enter in shearing line and carry out Shearing.
Heavy Plate Production line in this utility model embodiment also includes detection components (not shown), and detection components are arranged on At main rolling line runout table 6 or delay table 17 end, detection components can be according to tested on main rolling line runout table 6 The state-driven delay table 17 of object (i.e. above-mentioned motherboard) switches between the first connection status and the second connection status.If Put detection components, it is therefore an objective to need to select the transportation route of motherboard according to the condition and technique of motherboard.The detection components Installation site does not produce restriction, installation that can be according to different environment and job demand to detection components to this utility model Position is changed, but all should be within the protection domain of the application.
Detection components in this utility model embodiment are the pyrometer being arranged on main rolling line runout table 6, the high temperature Meter can measure the temperature of motherboard.Each roller-way equipment on Heavy Plate Production line in the present embodiment is provided with the detection such as grating Element, to determine the run location of motherboard.
As shown in Fig. 2 cold bed component includes the first cold bed 8 and the second cold bed 9.First cold bed 8 is parallel with the second cold bed 9 simultaneously Row arrange, and the length of the first cold bed 8 and the second cold bed 9 (above-below direction is the length of the first cold bed 8 and the second cold bed 9 in Fig. 2 Degree direction) it is equal.Delay table 17 includes inlet roller way 171 and connection roller-way 172.Inlet roller way 171 is arranged on the first cold bed 8 Place, one end of inlet roller way 171 is connected with main rolling line runout table 6, and one end of the inlet roller way 171 is the one of delay table 17 End, and the inlet roller way 171 is the approach table of the first cold bed 8.Connection roller-way 172 is arranged at the second cold bed 9, connection roll Road 172 is connected with inlet roller way 171, connects approach table of the roller-way 172 for the second cold bed 9.
It should be noted that the inlet roller way 171 and connection roller-way 172 in this utility model embodiment can make motherboard Move or can make motherboard direction movement along Fig. 2 from top to bottom in direction along Fig. 2 from left to right.
Cold bed component also includes inspection reconditioning stand 10, and on the inspection reconditioning stand 10 panel turnover machine 11 is provided with.First is cold 8 runout table of bed and the runout table of the second cold bed 9 are respectively positioned on lower section, the i.e. runout table and second of the first cold bed 8 in Fig. 2 The runout table of cold bed 9 is sequentially connected and (the 3rd roller-way 19 below cold bed is located in Fig. 2, is the outlet roller of above-mentioned first cold bed 8 The runout table in road and the second cold bed 9).The runout table of the second cold bed 9 is connected with the approach table for checking reconditioning stand 10, the The motherboard being cooled in one cold bed 8 and the second cold bed 9 can be delivered in inspection reconditioning stand 10 to carry out checking the operation such as reconditioning. Delay table 17 in this utility model embodiment also includes outlet roller-way 173, and outlet roller-way 173 is arranged on inspection reconditioning stand At 10, outlet one end of roller-way 173 connects with roller-way 172 is connected, and the other end for exporting roller-way 173 connects with shearing line approach table 13 Connect, the other end of the outlet roller-way 173 in this utility model embodiment is the other end of delay table 17.Exporting roller-way 173 is Check the runout table of reconditioning stand 10.
It should be noted that the concrete composition of main rolling line, shearing line and cold bed component is not in this utility model embodiment It is limited to the above, to increase corresponding assembly according to different working environments or corresponding assembly can be reduced.Deformation above Mode all should belong within protection domain of the present utility model.
As shown in figure 3, this utility model additionally provides a kind of Heavy Plate Production method, using above-mentioned Heavy Plate Production line Produced, Heavy Plate Production method is comprised the following steps:Step 1, the main rolling lines of blank Jing are rolled into into motherboard.Step 2, basis The length and/or temperature of motherboard, by main rolling line is fed directly to motherboard shearing line or is delivered to motherboard by main rolling line cold Bed component, then motherboard is delivered to into shearing line by cold bed component.Step 3, motherboard is sheared in shearing line.
Specifically, step 1 is comprised the following steps:Blank come out of the stove after Jing high-pressure water descalings, subsequently into roller-way 2 and be delivered to Milling train 1, blank Jing milling trains 1 are rolled into motherboard.The motherboard pre-straightening of Jing pre-straightenings machine 3, the water-cooled of Jing quickly cooling devices 4, again successively Jing thermal straightening machines 5 are aligned, and finally transfer out Zhu Zha areas by main rolling line runout table 6 (i.e. thermal straightening machine runout table).
Less than the width of the second cold bed 9, the width of the second cold bed 9 is a to the width of above-mentioned first cold bed 8, and step 2 includes:
When the length of motherboard is more than a, motherboard is fed directly to into shearing line approach table by main rolling line runout table 6 13.When the length of motherboard is less than a and the motherboard temperature is more than 400 DEG C, motherboard is delivered to by main rolling line runout table 6 cold Bed component, then motherboard is delivered to into shearing line approach table 13 by cold bed component.When the length of motherboard is less than less than a and temperature When 400 DEG C, motherboard is fed directly to into shearing line approach table 13 by main rolling line runout table 6, or by motherboard by main rolling line Runout table 6 is delivered to cold bed component and is cooled down, then motherboard is delivered to into shearing line approach table 13 by cold bed component, i.e., when When the length of motherboard is less than 400 DEG C less than a and temperature, motherboard can select to be fed directly to shearing line approach table 13, also may be used To select first to be delivered to after cold bed component to be delivered to shearing line approach table 13 again.
It should be noted that in this utility model embodiment, it is female when the length of motherboard is more than the width a of the second cold bed The thickness of plate is generally less than 20mm, under this kind of situation, motherboard temperature drop speed, and when it runs to delay table 17, temperature Less than 400 DEG C.And the motherboard of normal thickness, during into cold bed component, the temperature of motherboard is at 600 DEG C~700 DEG C or so.
Because the motherboard cooled down without the need for cold bed component transports directly to enter by delay table 17 in this utility model embodiment Enter shearing line, it is to avoid Route Dependence unnecessary occupancy cold bed, it also avoid that crane handling motherboard is offline and reach the standard grade again caused by The logistics of cold bed component complicate, make the utilization ratio of cold bed component higher.
When motherboard is transported to cold bed component, the motherboard is cooled down through the air cooling of the first cold bed 8 and/or the second cold bed 9, (temperature can need to be changed according to unlike material, be not changeless after motherboard is cooled to less than 400 DEG C Numerical value) inspection reconditioning stand 10 is transferred to, through checking and being delivered at the outlet roller-way 173 of delay table 17 after reconditioning, And it is delivered to shearing line through outlet roller-way 173.
As shown in figure 3, above-mentioned steps 3 include, motherboard enters into crop cuts 14 carries out crop end, then goes through bilateral scissors 15 carry out trimming, enter finally into and carry out in fixed size scissors 16 scale or sampling.
Heavy Plate Production line and Heavy Plate Production method and cut deal of the prior art in this utility model embodiment The application example contrast of production line and Heavy Plate Production method is specific as follows:
Assume that cold bed Breadth Maximum is designed as 52m (the maximum cold bedside degree of current Domestic Plate factory is 52m), in figure In the case that 1 main rolling line is arranged with shearing line interleaved parallel, the fertile motherboard greatest length of the institute of milling train 1 is less than 52m.It is false If steel grade Q235, finished steel plate length 10m, width 2500mm, steel plate thickness 12mm, it is considered to which 5 multiple length mill lengths select base, motherboard Of length no more than 52m.Under the technology arrangement that the main rolling line of this utility model shown in Fig. 2 is directly connected with shearing line, to same Finished steel plate specification, it is considered to the rolling of overlength many multiple lengths, under the conditions of current rolling technique, it is possible to achieve 10 multiple lengths are rolled, That is motherboard length is more than 100m.Therefore, the finished steel plate of 10 pieces of above-mentioned specifications is produced, under the deployment scenarios of Fig. 1,2 pieces is needed Blank, under Fig. 2 technology arrangements of the present utility model, 1 block of blank can meet requirement.
In shear history, end to end shearing displacement considers that respectively edge is per side shearing displacement to motherboard according to 500mm for every piece of motherboard 50mm.Motherboard sampling requirement is pressed, every motherboard samples the width 200mm (examinations that specimen width is sheared i.e. along motherboard length direction Sample ruler cun);Additionally, during cutting to length, every motherboard all must be reserved in plate tail~the pressing plate function space of 150mm, this part Finally become shearing waste material.
To sum up, it is length 10m, width 2500mm, the steel plate of thickness 12mm to produce 10 block specifications, under Fig. 1 deployment scenarios, Waste material (the contain sample) total length sheared on steel plate length direction is:500mm × 2 × 2+200mm × 2+150mm × 2= 2700mm;Under the conditions of Fig. 2 technology arrangements of the present utility model, waste material (the containing sample) overall length sheared on steel plate length direction Spend and be:500mm × 2+200mm+150mm=1350mm.Motherboard edge shearing displacement is considered further that per side 50mm, calculating shows, at this Under the technology arrangement that the main rolling line of utility model is directly connected with shearing line, can reduce by more than 20% shearing amount of waste.Hypothesis is cut The waste material gross weight cut is about 5.5% with respect to the ratio of blank, that is, shear impact of the waste material ratio to lumber recovery percentage ratio and account for To~5.5%, then by above-mentioned analysing content, same finished steel plate amount is produced, it is straight with shearing line in the main rolling line of this utility model In succession under logical technology arrangement, can reduce by 20% shearing waste material, lumber recovery improves~1.1%.For yield reaches million For tonne other Heavy Plate Production workshop, lumber recovery often improves 1 percentage ratio and can all bring huge economic benefit.
Certainly, for the steel plate of different steel grade different sizes, the current rolling technique maximum mill length to be reached It is not quite similar, additionally, also have the restriction of blank substance and specification to different factories, and the difference of order requirements, therefore it is right In the impact of lumber recovery, concrete condition is needed to make a concrete analysis of.Embodiment of the present utility model is done calculating analysis above, purport In concrete impact content of the explanation this utility model embodiment on this utility model embodiment application workshop lumber recovery.More than In description, it can be seen that this utility model the above embodiments realize following technique effect:
1st, the production of milling train can not consider cold bed width, and length of rolled piece can consider blank and roll according to order The flexible organization production of situations such as function power, realizes many multiple length rollings of overlength.In the case that this steel plate length exceeds cold bed width, Steel plate thickness is generally relatively thin, and temperature is generally relatively low, therefore steel plate is out not required to afterwards directly pass through roller through cold bed from main rolling line Road enters shearing line shearing.The largest benefit of overlength many multiple lengths rolling is to make the average shear amount of waste of monolithic finished steel plate significantly Reduce, so as to be conducive to improving lumber recovery.
2nd, the thinner thickness of main rolling line production or through the relatively low steel plate of the temperature of fast cooling device water-cooled, goes out from main rolling line Directly subsequent handling can be completed into shearing line by roller transport without cold bed after coming, therefore be reduced into cold bed cooling Steel plate number, it is to avoid a large amount of satisfactions are waited in line on cold bed, take cold bed into the relatively low steel plate of the temperature that shearing line is required Area, the cooling capacity of waste cold bed, therefore the service efficiency of cold bed is also just improve, cold bed has been extenuated as production line bottleneck Restricted influence to production capacity, optimizes the logistics in cold bed region.
The above, only specific embodiment of the utility model, it is impossible to which the scope that utility model is implemented, institute are limited with it With the displacement of its equivalent assemblies, or the equivalent variations made according to this utility model scope of patent protection and modification, all should still fall within The category that this patent is covered.In addition, between the technical characteristic and technical characteristic in this utility model, technical characteristic and technical scheme Between, can be used with independent assortment between technical scheme and technical scheme.

Claims (7)

1. a kind of Heavy Plate Production line, it is characterised in that the Heavy Plate Production line includes:
Main rolling line, including main rolling line runout table (6);
Shearing line, including shearing line approach table (13);
Delay table (17), between the main rolling line and the shearing line, delay table (17) is exported respectively with main rolling line Roller-way (6) and shearing line approach table (13) linearly connect.
2. Heavy Plate Production line according to claim 1, it is characterised in that the Heavy Plate Production line also includes cold bed group Part, the cold bed component is arranged between the main rolling line and the shearing line, and the cold bed component is with delay table (17) extremely Few side lateral connection.
3. Heavy Plate Production line according to claim 1, it is characterised in that the Heavy Plate Production line also includes detection group Part, the detection components are arranged on main rolling line runout table (6) place.
4. Heavy Plate Production line according to claim 2, it is characterised in that the cold bed component includes the first cold bed (8) With the second cold bed (9), delay table (17) includes:
Inlet roller way (171), is arranged on the first cold bed (8) place, and inlet roller way (171) is connected with main rolling line runout table (6), enters Mouthful roller-way (171) for the first cold bed (8) approach table;
Connection roller-way (172), is arranged on the second cold bed (9) place, and connection roller-way (172) is connected with inlet roller way (171), connection roll Road (172) for the second cold bed (9) approach table.
5. Heavy Plate Production line according to claim 4, it is characterised in that the cold bed component also includes checking reconditioning platform Frame (10), the runout table of the first cold bed (8) and the runout table of the second cold bed (9) with check reconditioning stand (10) input Roller-way connects, and delay table (17) also includes outlet roller-way (173), and outlet roller-way (173) is arranged on inspection reconditioning stand (10) Place, outlet roller-way (173) two ends respectively be connected roller-way (172) and shearing line approach table (13) and connects, export roller-way (173) To check the runout table of reconditioning stand (10).
6. Heavy Plate Production line according to claim 1, it is characterised in that the main rolling line includes the milling train being sequentially connected (1), pre-straightening machine (3), quickly cooling device (4) and thermal straightening machine (5), thermal straightening machine (5) rear end connects main rolling line outlet roller Road (6).
7. Heavy Plate Production line according to claim 1, it is characterised in that the shearing line includes the crop being sequentially connected (14), bilateral scissors (15) and fixed size scissors (16) are cut, crop cuts (14) front end connection shearing line approach table (13).
CN201621176660.6U 2016-11-02 2016-11-02 Cut deal production line Active CN206104547U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621176660.6U CN206104547U (en) 2016-11-02 2016-11-02 Cut deal production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621176660.6U CN206104547U (en) 2016-11-02 2016-11-02 Cut deal production line

Publications (1)

Publication Number Publication Date
CN206104547U true CN206104547U (en) 2017-04-19

Family

ID=58525095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621176660.6U Active CN206104547U (en) 2016-11-02 2016-11-02 Cut deal production line

Country Status (1)

Country Link
CN (1) CN206104547U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106345807A (en) * 2016-11-02 2017-01-25 北京京诚之星科技开发有限公司 Middle thick plate production line and production method
CN112570450A (en) * 2019-09-30 2021-03-30 宝钢湛江钢铁有限公司 Thick plate rolling line and production method thereof
WO2021063363A1 (en) * 2019-09-30 2021-04-08 宝钢湛江钢铁有限公司 Steel plate double-pre-stacking system for single shear line, and stacking method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106345807A (en) * 2016-11-02 2017-01-25 北京京诚之星科技开发有限公司 Middle thick plate production line and production method
CN112570450A (en) * 2019-09-30 2021-03-30 宝钢湛江钢铁有限公司 Thick plate rolling line and production method thereof
WO2021063363A1 (en) * 2019-09-30 2021-04-08 宝钢湛江钢铁有限公司 Steel plate double-pre-stacking system for single shear line, and stacking method thereof
CN112570450B (en) * 2019-09-30 2022-03-01 宝钢湛江钢铁有限公司 Thick plate rolling line and production method thereof

Similar Documents

Publication Publication Date Title
CN106345807A (en) Middle thick plate production line and production method
CN206104547U (en) Cut deal production line
WO2021063364A1 (en) High-efficiency double-frame double-cutting line feed-through intermediate thickness slab production line and production method
CN108213086B (en) A method of realizing hot-strip slight center wave rolling
CN101596546B (en) Steel rolling production process used in steel production
CN101607262A (en) A kind of production technology procedures for steel rolling
CN201470675U (en) Producing device for composite steel plate
CN102688896B (en) Mechanism model-based virtual crown gauge setting method for four-roll cold continuous rolling machine set
CN109663809A (en) Large-scale and ultra-large H-beam rolling mill practice
CN108941196A (en) A method of with 200 big cross section square billet continuous rolling small-sized bars
CN108620434A (en) A kind of X-shaped steel hot rolling molding process method
CN201744485U (en) System for producing wide and heavy plate products
CN103706634A (en) Compact wire and bar rolling production line
CN112387780A (en) Novel steel rolling production process
CN111872114A (en) High-yield high-precision slitting bar production method and production line
CN203853375U (en) Long-length rolling production line for T-shaped guide rails of elevators
CN210614644U (en) Rolling device suitable for lengthened medium plate
WO2021063363A1 (en) Steel plate double-pre-stacking system for single shear line, and stacking method thereof
CN203635617U (en) Compact wire and rod rolling production line
CN102648059B (en) Compact reversible universal mill for producing medium-large sections
CN220717231U (en) Board production system
CN202621535U (en) Profile steel straightening ferric oxide skin chip collection device
CN102672415A (en) Steel coil opening and leveling method for reducing warping of steel plate after cutting
CN218395319U (en) Three-roller/two-roller integrated oblique tube rolling unit for hot rolling seamless steel tube
CN218925720U (en) Production process line for rod and wire

Legal Events

Date Code Title Description
GR01 Patent grant