CN206094895U - Continuous tunnel furnace operation monitored control system - Google Patents

Continuous tunnel furnace operation monitored control system Download PDF

Info

Publication number
CN206094895U
CN206094895U CN201620961492.5U CN201620961492U CN206094895U CN 206094895 U CN206094895 U CN 206094895U CN 201620961492 U CN201620961492 U CN 201620961492U CN 206094895 U CN206094895 U CN 206094895U
Authority
CN
China
Prior art keywords
tunnel furnace
continuous tunnel
gear
motor
monitoring system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620961492.5U
Other languages
Chinese (zh)
Inventor
郝建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Yongchang Welding Wire Co Ltd
Original Assignee
Tianjin Yongchang Welding Wire Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Yongchang Welding Wire Co Ltd filed Critical Tianjin Yongchang Welding Wire Co Ltd
Priority to CN201620961492.5U priority Critical patent/CN206094895U/en
Application granted granted Critical
Publication of CN206094895U publication Critical patent/CN206094895U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tunnel Furnaces (AREA)

Abstract

The utility model provides a continuous tunnel furnace operation monitored control system, including converter, programmable controller, touch -sensitive screen, potentiometre, motor, roller, speed sensing element and alarm, last a plurality of converters, touch -sensitive screen, a plurality of speed sensing element and the alarm connected of programmable controller, be equipped with corresponding opening and stopping switch between programmable controller and every converter, every be connected with a potentiometre and a plurality of motor on the converter, every the motor passes through a set of roller of chain conveying, the chain operates through the multiunit gear, the gear drives through the motor, every driven gear one side that speed sensing element installed at last a set of gear. The utility model has the advantages of: realize automated inspection equipment running state's function through real -time supervision chain functioning speed, the security of improve equipment reliability and production is avoided causing destructive shut down to equipment.

Description

A kind of continuous tunnel furnace operating monitoring system
Technical field
The utility model belongs to automation field, more particularly, to a kind of continuous tunnel furnace operating monitoring system.
Background technology
Carrying out toasting the process of welding rod in continuous tunnel furnace can be divided into low-temperature zone, baking section, four ranks of high temperature section and cooling section Section, the speed of service in each stage is, by multiple Frequency Converter Controls, to carry multiple motors, each motor on each frequency converter again By one group of roller of chain belt, every group of roller includes multiple rollers again, and every group of roller-way Operating match speed is different.Once by The factors such as chain-loose, certain roller operation are blocked or paused, certain frequency converter cancel closedown cause speed chain to change, from And it is abnormal certain roller-way operating condition occur, the dolly of arrangement operating all will be extruded into together in whole stove, and by below Easily there is inconsistent phenomenon in the effect of running force, chain, very big to damage of facilities, and has a strong impact on production.Therefore ensure whole It is necessary that individual mechanical system running status operationally is intact.
Utility model content
In view of this, the utility model is directed to a kind of continuous tunnel furnace operating monitoring system, and shape is run to equipment to reach State carries out the purpose of real time automatic detection.
To reach above-mentioned purpose, what the technical solution of the utility model was realized in:
A kind of continuous tunnel furnace operating monitoring system, including frequency converter, Programmable Logic Controller, touch-screen, potentiometer, motor, roller Cylinder, velocity response element and alarm, connect multiple frequency converters, touch-screen, a multiple speed on the Programmable Logic Controller Sensing element and alarm, are provided with corresponding unlatching and halt switch, often between the Programmable Logic Controller and each frequency converter A potentiometer and multiple motors are connected with the individual frequency converter, each described motor transmits one group of roller, institute by chain State chain to be operated by multigroup gear, the gear is driven by motor, each described velocity response element is installed In the driven gear side of last group of gear.
Further, the velocity response element is positive-negative-positive proximity switch.
Further, the Programmable Logic Controller is Siemens S 7-200 PLC.
Further, the frequency converter is ABB frequency converter As CS510.
Further, the potentiometer is 5.6K potentiometers.
Further, tell that touch-screen is OP73 touch screens.
Relative to prior art, a kind of continuous tunnel furnace operating monitoring system described in the utility model has the advantage that:
A kind of continuous tunnel furnace operating monitoring system described in the utility model is realized by the real-time monitoring chain speed of service The function of automatic checkout equipment running status, when certain group motor institute band roller-way operation occur it is abnormal, equipment can hard stop report to the police, And relevant position is shown, improve the security of equipment dependability and production, it is to avoid the shutdown to damaging property of equipment.
Description of the drawings
The accompanying drawing for constituting a part of the present utility model is used for providing further understanding to of the present utility model, and this practicality is new The schematic description and description of type is used to explain the utility model, does not constitute to improper restriction of the present utility model. In accompanying drawing:
Fig. 1 is the Programmable Logic Controller schematic diagram described in the utility model embodiment;
Fig. 2 is the circuit theory schematic diagram of the control continuous tunnel furnace operation described in the utility model embodiment;
Fig. 3 is the monitoring device structural representation described in the utility model embodiment.
Description of reference numerals:
1- velocity response elements;2- driven gears.
Specific embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the utility model can To be mutually combined.
Below with reference to the accompanying drawings and in conjunction with the embodiments describing the utility model in detail.
As shown in Figures 1 to 3, a kind of continuous tunnel furnace operating monitoring system, including frequency converter, Programmable Logic Controller, touch-screen, electricity Position device, motor, roller, velocity response element 1 and alarm, connect on the Programmable Logic Controller multiple frequency converters, one touch Screen, multiple velocity response elements 1 and alarm are touched, corresponding unlatching is provided between the Programmable Logic Controller and each frequency converter And halt switch, a potentiometer and multiple motors are connected with each described frequency converter, each described motor is passed by chain One group of roller, the chain is sent to be operated by multigroup gear, the gear is driven by motor, each described speed Sensing element is arranged on the side of driven gear 2 of last group of gear.
The velocity response element 1 is positive-negative-positive proximity switch, and the Programmable Logic Controller is programmable for siemens PLC Controller, the frequency converter is ABB frequency converter As CS510, and the potentiometer is 5.6K potentiometers, tells touch-screen and touches for OP73 Mould screen.
The course of work of the present embodiment is as follows:
The given potentiometer voltage signal of system master is collected PLC technology by frequency converter by MOULDBUS communications protocol In device, Programmable Logic Controller is received through signal transacting after main Setting signal, using each motor operation speed arranged on touch-screen The radiometer of degree calculates the speed preset signal of corresponding frequency converter, and by DP communications protocol be sent to each frequency converter be used as to Each frequency converter speed preset signal, drives each group roller to connect by gear with given speed respectively by each motor of transducer drive The mode of connecing operates, and velocity response element calculates the speed of service of gear by the presence or absence of sensing teeth, such as sense in 1 second Teeth number be n, have 10 teeth on each gear, then system-computed gear operation speed be n/10 revolutions per second.When each motor System sends stopping signal and reports to the police when given speed is mismatched with the speed that velocity response element is collected, and from touch-screen Show abort situation.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc. should be included in the utility model Protection domain within.

Claims (6)

1. a kind of continuous tunnel furnace operates monitoring system, it is characterised in that:Including frequency converter, Programmable Logic Controller, touch-screen, current potential Device, motor, roller, velocity response element and alarm, connect multiple frequency converters, a touch on the Programmable Logic Controller Screen, multiple velocity response elements and alarm, be provided between the Programmable Logic Controller and each frequency converter corresponding unlatching and Halt switch, is connected with a potentiometer and multiple motors on each described frequency converter, each described motor is transmitted by chain One group of roller, the chain is operated by multigroup gear, and the gear is driven by motor, each described speed sense Element is answered to be arranged on the driven gear side of last group of gear.
2. a kind of continuous tunnel furnace according to claim 1 operates monitoring system, it is characterised in that:The velocity response element is Positive-negative-positive proximity switch.
3. a kind of continuous tunnel furnace according to claim 1 operates monitoring system, it is characterised in that:The Programmable Logic Controller is Siemens S 7-200 PLC.
4. a kind of continuous tunnel furnace according to claim 1 operates monitoring system, it is characterised in that:The frequency converter is ABB changes Frequency device ACS510.
5. a kind of continuous tunnel furnace according to claim 1 operates monitoring system, it is characterised in that:The potentiometer is that 5.6K is electric Position device.
6. a kind of continuous tunnel furnace according to claim 1 operates monitoring system, it is characterised in that:Told touch-screen is touched for OP73 Mould screen.
CN201620961492.5U 2016-08-26 2016-08-26 Continuous tunnel furnace operation monitored control system Active CN206094895U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620961492.5U CN206094895U (en) 2016-08-26 2016-08-26 Continuous tunnel furnace operation monitored control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620961492.5U CN206094895U (en) 2016-08-26 2016-08-26 Continuous tunnel furnace operation monitored control system

Publications (1)

Publication Number Publication Date
CN206094895U true CN206094895U (en) 2017-04-12

Family

ID=58473181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620961492.5U Active CN206094895U (en) 2016-08-26 2016-08-26 Continuous tunnel furnace operation monitored control system

Country Status (1)

Country Link
CN (1) CN206094895U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109877218A (en) * 2019-02-27 2019-06-14 东莞行特电子有限公司 Punching press iron-clad manufacturing method thereof free of cleaning
CN109985907A (en) * 2019-04-24 2019-07-09 芜湖新兴铸管有限责任公司 Steel billet roller-way automatic control system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109877218A (en) * 2019-02-27 2019-06-14 东莞行特电子有限公司 Punching press iron-clad manufacturing method thereof free of cleaning
CN109985907A (en) * 2019-04-24 2019-07-09 芜湖新兴铸管有限责任公司 Steel billet roller-way automatic control system

Similar Documents

Publication Publication Date Title
CN201658910U (en) Electric integrated control system of dust-cleaning apparatus
CN104535221B (en) One kind is based on distributed optical fiber temperature measurement intelligent analysis method
CN206094895U (en) Continuous tunnel furnace operation monitored control system
CN205616153U (en) Concentrate intelligent conveyor system of unmanned on duty belt under interlocking control system
CN104049566B (en) A kind of Electrified Transmission control method of converter inclining safety
CN103575560A (en) Intelligent early warning system for electromechanical equipment
CN204011163U (en) A kind of line switching automatic assembling machine
CN202013212U (en) Air quantity calculating system of variable speed or constant speed fan
CN109592343A (en) A kind of bucket elevator slip detector and its detection method
CN206515682U (en) The big motor temperature centralized management system of toilet paper machine based on PLC system
CN203240921U (en) Safety cooling tower based on PLC (Programmable Logic Controller) intelligent control
CN204058523U (en) There is the thermal treatment cooling equipment of temperature control and warning device
CN205910558U (en) Thing networking ammeter case
CN204458660U (en) Petroleum logging winch
CN204438762U (en) A kind of roller kilns roller rod rotating speed and roll breakage monitoring device
CN204162023U (en) Belt anti-skidding control device
AU2016102336A4 (en) An equipment isolation system
CN201203783Y (en) Intelligent detection device for transmission fault of ring cold machine
CN104670840B (en) Bulk-material conveying belt running monitoring device
CN205445277U (en) Hangar gate of all -round image control
CN207076542U (en) The against pressure of two-stage stationary disintegrating machine stops warning device
CN203807496U (en) Concentrated on-line monitoring system for environment coal gas of multiple blast furnaces
CN103587922B (en) Annealing furnace main gear abends alarm control system and control method
CN203199603U (en) Belt anti-fracture monitoring device
CN104651600A (en) Anchor chain thermal treatment furnace monitoring system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant