CN206080166U - Instant -heating water drinking machine - Google Patents

Instant -heating water drinking machine Download PDF

Info

Publication number
CN206080166U
CN206080166U CN201620397568.6U CN201620397568U CN206080166U CN 206080166 U CN206080166 U CN 206080166U CN 201620397568 U CN201620397568 U CN 201620397568U CN 206080166 U CN206080166 U CN 206080166U
Authority
CN
China
Prior art keywords
water
heating chamber
heating
outlet box
water outlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620397568.6U
Other languages
Chinese (zh)
Inventor
王旭宁
马明阳
刘宗印
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Joyoung Co Ltd
Original Assignee
Joyoung Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Joyoung Co Ltd filed Critical Joyoung Co Ltd
Priority to CN201620397568.6U priority Critical patent/CN206080166U/en
Application granted granted Critical
Publication of CN206080166U publication Critical patent/CN206080166U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Apparatus For Making Beverages (AREA)

Abstract

The utility model provides an instant -heating water drinking machine, including water tank, heating chamber and play water box, go out the water box and be equipped with the hot water export, its characterized in that, the water tank is located the top in heating chamber, the bottom of water tank is equipped with the lower water hole in intercommunication heating chamber, the heating intracavity is equipped with the buoyancy of water of by heating intracavity and the pressure variation of heating intracavity reciprocates the switch spare with water hole under the switching, go out the top that the water box is located the heating chamber, be equipped with the intercommunication pipeline between heating chamber and the play water box, the water of heating intracavity gets into out the water box through the intercommunication pipeline under heating cavity pressure's effect. The utility model discloses in, the water of heating intracavity flows into out the water box under steam pressure's effect, and automatic discharge in the water boiling back short time need not the manual work to topple over, avoids heating the intracavity and forms chen shui. In addition, water dispenser overall structure is simple, the stable performance, and low cost need not to set up outlet water pump, pressure controller, micro -gap switch etc..

Description

A kind of instant-heating water drinking machine
Technical field
The utility model is related to a kind of water dispenser, especially a kind of instant-heating water drinking machine.
Background technology
Existing water dispenser is conveniently designed with a water tank for people's water intaking, store a certain amount of boiling water in case drink and Domestic water, these water Jing long-time heat preservations storage oxygen content is greatly lowered the health for being unfavorable for people.With health of people The continuous enhancing of consciousness, the remaining water in many water dispensers will be let go every morning, waste the water resource of preciousness.In addition, Existing water dispenser volume is larger, and inside arranges the portions such as a large amount of magnetic valves, pressure controller, microswitch, electrode, tongue tube Part, on the one hand, improve cost, on the other hand, structural complexity but also reduces overall reliability while raising.
Utility model content
For the problem of existing water dispenser, the utility model provides a kind of instant-heating water drinking machine, by the following technical programs Realize:A kind of instant-heating water drinking machine, including water tank, heating chamber and water outlet box, the water outlet box is provided with hot water outlet, and its feature exists In the water tank is located at the top of heating chamber, and the bottom of the water tank is communicated with the drainage hole of heating chamber, in the heating chamber It is provided with and is moved up and down to be opened and closed the switch member of drainage hole by the pressure change in the buoyancy of water and heating chamber in heating chamber, The water outlet box is located at the top of heating chamber, pipeline is communicated between the heating chamber and water outlet box, in the heating chamber Water enters water outlet box in the presence of heating cavity pressure by connecting pipeline.
Further, relief tube is additionally provided between the heating chamber and water outlet box, the relief tube is located at one in water outlet box Higher than the highest liquid level of water outlet box, the relief tube is positioned at the highest liquid level that one end in heating chamber is higher than heating chamber at end.
Further, the passage being connected with relief tube, the outer phase of the passage are provided with the top of the heating chamber Top indent to heating chamber.
Further, the switch member is provided with the sucker of opening and closing drainage hole, and at least three are provided with the top of the heating chamber The lead column of limit switch part lateral displacement, the lower end of the lead column is provided with locating part of the limit switch part to bottom offset, institute State switch member to move up and down between locating part and drainage hole;Or, the switch member is provided with the sucker of opening and closing drainage hole and sets Guide post below sucker, is provided with the pilot hole for the mobilizable plug of guide post in the heating chamber.
Further, the area of the drainage hole is S1, and the area of the sucker is S2, wherein, 2 square centimeters≤S1≤ 5 square centimeters, 0.4≤S1/S2≤0.7.
Further, the bottom of the water tank also includes collect cavity, and the drainage hole is located at the diapire of collect cavity, the collection The roof of water cavity is provided with multiple through holes, under the water above the collect cavity is further passed through after being come together in collect cavity by through hole Water hole is entered in heating chamber.
Further, the through hole of the collect cavity roof includes being located at the main through hole of central area and outside main through hole The auxiliary through hole for enclosing.
Further, the bottom of the water outlet box is provided with the refluxing opening connected with water tank, arranges at the refluxing opening and passes through Rotation adjusts the shutter member of refluxing opening size, is provided with the top of the water outlet box and be connected with shutter member by connecting rod and control opening and closing The knob of part rotation.
Further, the sidewall upper of the water tank is provided with water outlet box installation cavity, and the water outlet box installation cavity includes horizontal The base plate of extension, the base plate is provided with the installing port fixed for connecting pipeline and the through hole connected with refluxing opening.
Further, raw water chamber is provided with above the water tank, the lower end in the raw water chamber is provided with purifier.
In the utility model, the water in heating chamber flows into water outlet box in the presence of steam pressure, the short time after boiling water Inside it is automatically drained out, without the need for manually toppling over, it is to avoid remaining water is formed in heating chamber.In addition, water dispenser overall structure is simple, performance is steady It is fixed, it is with low cost, without the need for arranging out water pump, pressure controller, microswitch etc..Further, backflow is also set up at water outlet box Mouthful, each water withdrawal is controlled by controlling the size of refluxing opening, i.e., hot to drink, simple operation.
Description of the drawings
With reference to the accompanying drawings and detailed description the utility model is described in further detail:
Fig. 1 is exploded view of the present utility model;
Fig. 2 is section view Fig. 1 of the present utility model;
Fig. 3 is section view Fig. 2 of the present utility model;
Fig. 4 is the enlarged drawing of a-quadrant in Fig. 3;
Fig. 5 is top view of the present utility model;
Fig. 6 is the schematic diagram of the another embodiment of the utility model breaker in middle part;
Fig. 7 is the schematic diagram that the utility model has purifier.
Specific embodiment
As Figure 1-Figure 5, a kind of instant-heating water drinking machine, including water tank 1, heating chamber 2 and water outlet box 3, water outlet box 3 is provided with heat Water out 31, water tank 1 is located at the top of heating chamber 2, and the bottom of water tank 1 is communicated with the drainage hole 11 of heating chamber 2, heating chamber 2 Inside it is provided with and moves up and down to be opened and closed drainage hole 11 by the pressure change in the buoyancy of water in heating chamber 2 and heating chamber 2 Switch member 4, water outlet box 3 is located at the top of heating chamber 2, pipeline 21 is communicated between heating chamber 2 and water outlet box 3, in heating chamber 2 Water in the presence of pressure in heating chamber 2 by connecting pipeline 21 enter water outlet box 3.Water in water tank 1 is made in self gravitation Enter in heating chamber 2 from drainage hole 11 with.With the rising of the water level of heating chamber 2, switch member 4 floats to drainage hole 11 nearby very To sealing drainage hole 11.Meanwhile, the heater in heating chamber 2 is heated to the water in it, wherein, heater can be Electric heating plate, or Electromagnetic Heating or other mode of heatings, this partial content emphasis that not the utility model is paid close attention to, Here is omitted.A large amount of steam are produced in heating process, in this section in the presence of steam, pressure is continuous in heating chamber 2 Increase, further such that the tightening seal of switch member 4 is stayed water hole 11, it is to avoid pressure release from this, meanwhile, the water in heating chamber 2 exists Entered by connecting pipeline 21 in the presence of steam pressure in the water outlet box 3 of top, immediately the heater in heating chamber 2 passes through Time control stops heating situations such as detect water level decreasing.It is right when discharge reduction in heating chamber 2 and then reduced pressure For switch member 4, in the case that the pressure of lower section steam is less than the pressure of top water, come off from apopore 11, heating chamber 2 Connect with water tank 1, in heating chamber 2 while pressure release, cold water is again introduced into.User can pass through the water receiving of hot water outlet 31.
In the present embodiment, relief tube 22 is additionally provided between heating chamber 2 and water outlet box 1, relief tube 22 is located at one in water outlet box 1 Higher than the highest liquid level of water outlet box 1, relief tube 22 is positioned at the highest liquid level that one end in heating chamber 2 is higher than heating chamber 2 at end.Heating chamber High pressure in 2 may form certain risk, in order to avoid due to connecting pipeline 21 occur blocking water outlet pressure release it is not smooth, or Hypertonia in the heating chamber 2 that other unexpected factors are caused and the danger that brings, by relief tube 22 by the pressure in heating chamber 2 It is adjusted to suitable size.Wherein, in order to avoid the hot water return in water outlet box 1, it is high that relief tube 22 is located at one end in water outlet box 1 In the highest liquid level of water outlet box 1, in addition, in order to avoid the water in heating chamber 2 results in blockage in relief tube 22, relief tube 22 Highest liquid level of the one end higher than heating chamber 2 in heating chamber 2.Further, the top of heating chamber 2 is provided with solid with relief tube 22 Passage 23 even, with respect to the top indent of heating chamber 2, i.e., the top of heating chamber 2 is in passage 23 for the outer of passage 23 The place of putting forms cavity, even if the water level in heating chamber 2 touches its top, the lower end of relief tube 22 will still be located at water surface top. In addition, it is necessary to, it is noted that the lower end of connecting pipeline 21 should be lower than the lower end of relief tube 22, and less than the highest of heating chamber 2 Liquid level, and each water yield should be less than or equal to the liquid that the lower end of the highest liquid level to connecting pipeline 21 of heating chamber 2 is located The water yield between face.
Further illustrate, switch member 4 is provided with the sucker 41 of opening and closing drainage hole 11, and the top of heating chamber 2 is provided with least three The lead column 24 of the lateral displacement of limit switch part 4, the lower end of lead column 24 is provided with locating part 25 of the limit switch part to bottom offset, Switch member 4 is moved up and down between locating part 25 and drainage hole 11.Specifically, locating part 25 is extended transversely, plate-like, is passed through Screw is connected with lead column 24, and certainly, locating part and lead column can also be integrally formed.As the another of switch member Embodiment is planted, as shown in fig. 6, switch member 4a is provided with the sucker 41a and the guide post below sucker 41a of opening and closing drainage hole 42a, is provided with the pilot hole 24a for the mobilizable plugs of guide post 42a in heating chamber, wherein, pilot hole 24a passes through support 25a It is fixed in heating chamber.
Preferably, the area of drainage hole 11 is S1, and the area of sucker 41 is S2, wherein, 2 square centimeters≤S1≤5 square Centimetre, 0.4≤S1/S2≤0.7.In the case of in view of user's everyday water-drinking amount, 2 square centimeters≤S1≤5 square centimeter, Time Of Launching is taken into account and switch member 4 has closed the reliability of drainage hole 11.On the other hand, as 0.7 < S1/S2 < 1, due under The area S1 in water hole 11 is larger with respect to the area S2 of sucker 41, causes the pressure of the top water of switch member 4 larger, the envelope of switch member 4 Closing drainage hole 11 will become unreliable;As S1/S2 < 0.4, due to drainage hole 11 area S1 meet 2 square centimeters≤S1≤ On the premise of 5 square centimeters, the area S2 of sucker 41 will become larger, on the one hand, switch member 4 is overall to become big quality change greatly, separately On the one hand, the suction that sucker 41 adsorbs at the top of heating chamber 2 also becomes big, and the on-off action in turn resulting in switch member 4 is insensitive.
In the present embodiment, the bottom of water tank 1 also includes collect cavity 12, and drainage hole 11 is located at the diapire of collect cavity 12, catchments The roof in chamber 12 is provided with multiple through holes 13, and the water of the top of collect cavity 12 is further led to after being come together in collect cavity 12 by through hole 13 Cross drainage hole 11 to enter in heating chamber 2.On the one hand so that the water above the roof of collect cavity 12 can be flowed by multiple through holes 13 Enter in collect cavity, improve lower water efficiency, on the other hand, it is to avoid the roof of heating chamber 2 is directly contacted with the water in water tank 1 and made Into heat losses, in addition, in product is embodied as, because the roof of heating chamber 2 needs setting through hole, cavity, pipeline to fix End, screw pole etc., and the roof of collect cavity 12 directly exposes, therefore, the former is adapted to adopt plastic material, and the latter is adapted to adopt Metal material, the present embodiment arranges collect cavity 12 and then causes both to be separated into two faces, is easy to arrange different materials.Further , the through hole 13 of the roof of collect cavity 12 includes that being located at the main through hole 131 of central area and the auxiliary positioned at main through hole periphery leads to Hole 132, is conducive to improving lower water efficiency.In addition, the diapire in collect cavity 12 is additionally provided with the through hole 122 that sealed by silica gel part 121, The setting of silica gel part 121 causes the water in collect cavity 12 from passing through through hole 122, and when the hypertonia in heating chamber 2, silicon Glue part 121 will open pressure release, further protect machine.
Water withdrawal is adjusted for the ease of user, the bottom of water outlet box 3 is provided with the refluxing opening 32 connected with water tank 1, refluxing opening The shutter member 33 that the size of refluxing opening 32 is adjusted by rotation is set at 32, and the top of water outlet box 3 is provided with by connecting rod 34 and opening and closing Part 33 connects and controls the knob 35 of the rotation of shutter member 33.User controls the size of refluxing opening 32 by manipulation knob 35, goes out A water part in water box 3 is by the way that in the reflux tank 1 of refluxing opening 32, other part is then flowed out by hot water outlet 31.Specifically, The sidewall upper of water tank 1 is provided with water outlet box installation cavity, and water outlet box installation cavity includes the base plate for extending laterally, and base plate is provided with for connecting The installing port of siphunculus road fixation and the through hole connected with refluxing opening, in addition in the case where relief tube is provided with, also need to arrange The through hole connected with relief tube.The setting of said structure, is conducive to the reliable installation of water outlet box, while reducing water outlet box evagination Partial size, it is to avoid take excessive space.
Further, in order to meet demand of the user to water purification, as shown in fig. 7, also setting up raw water chamber in the top of water tank 1 5, the lower end in raw water chamber 5 is provided with purifier 51.Purifier in the present embodiment is filter core, and the water in raw water chamber 5 is at itself Entered in water tank 1 after filter core purification in the presence of gravity.
Certainly, those skilled in the art be appreciated that above content be only preferred embodiment of the present utility model and , not it is all for limiting practical range of the present utility model, i.e., all impartial changes made according to the utility model and modification The utility model right is covered, and no longer illustrates one by one here.

Claims (10)

1. a kind of instant-heating water drinking machine, including water tank, heating chamber and water outlet box, the water outlet box is provided with hot water outlet, and its feature exists In the water tank is located at the top of heating chamber, and the bottom of the water tank is communicated with the drainage hole of heating chamber, in the heating chamber It is provided with and is moved up and down to be opened and closed the switch member of drainage hole by the pressure change in the buoyancy of water and heating chamber in heating chamber, The water outlet box is located at the top of heating chamber, pipeline is communicated between the heating chamber and water outlet box, in the heating chamber Water enters water outlet box in the presence of heating cavity pressure by connecting pipeline.
2. instant-heating water drinking machine according to claim 1, it is characterised in that be additionally provided between the heating chamber and water outlet box and let out Pressure pipe, the relief tube is located at one end in water outlet box, and, higher than the highest liquid level of water outlet box, the relief tube is positioned in heating chamber one Highest liquid level of the end higher than heating chamber.
3. instant-heating water drinking machine according to claim 2, it is characterised in that be provided with solid with relief tube at the top of the heating chamber Passage even, the top indent of the outer of the passage with respect to heating chamber.
4. instant-heating water drinking machine according to claim 1, it is characterised in that the switch member is provided with the suction of opening and closing drainage hole Disk, is provided with the lead column of at least three limit switch part lateral displacements at the top of the heating chamber, the lower end of the lead column sets To the locating part of bottom offset, the switch member moves up and down restricted switch member between locating part and drainage hole;Or, it is described Switch member is provided with the sucker and the guide post below sucker of opening and closing drainage hole, and being provided with the heating chamber can live for guide post The pilot hole of dynamic plug.
5. instant-heating water drinking machine according to claim 4, it is characterised in that the area of the drainage hole is S1, the sucker Area be S2, wherein, 2 square centimeters≤S1≤5 square centimeter, 0.4≤S1/S2≤0.7.
6. instant-heating water drinking machine according to claim 1, it is characterised in that the bottom of the water tank also includes collect cavity, institute Diapire of the drainage hole positioned at collect cavity is stated, the roof of the collect cavity is provided with multiple through holes, and the water above the collect cavity passes through Through hole is further entered in heating chamber after coming together in collect cavity by drainage hole.
7. instant-heating water drinking machine according to claim 6, it is characterised in that during the through hole of the collect cavity roof includes being located at The main through hole in heart district domain and the auxiliary through hole positioned at main through hole periphery.
8. instant-heating water drinking machine according to claim 1, it is characterised in that the bottom of the water outlet box is provided with and is connected with water tank Refluxing opening, at the refluxing opening arrange by rotation adjust refluxing opening size shutter member, be provided with the top of the water outlet box It is connected and controls the knob of shutter member rotation with shutter member by connecting rod.
9. instant-heating water drinking machine according to claim 8, it is characterised in that the sidewall upper of the water tank is provided with water outlet box peace It behave affectedly, the water outlet box installation cavity includes the base plate for extending laterally, the base plate is provided with the installing port fixed for connecting pipeline And the through hole connected with refluxing opening.
10. instant-heating water drinking machine according to claim 1, it is characterised in that raw water chamber is provided with above the water tank, it is described The lower end in raw water chamber is provided with purifier.
CN201620397568.6U 2016-05-05 2016-05-05 Instant -heating water drinking machine Active CN206080166U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620397568.6U CN206080166U (en) 2016-05-05 2016-05-05 Instant -heating water drinking machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620397568.6U CN206080166U (en) 2016-05-05 2016-05-05 Instant -heating water drinking machine

Publications (1)

Publication Number Publication Date
CN206080166U true CN206080166U (en) 2017-04-12

Family

ID=58472318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620397568.6U Active CN206080166U (en) 2016-05-05 2016-05-05 Instant -heating water drinking machine

Country Status (1)

Country Link
CN (1) CN206080166U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112675601A (en) * 2019-10-18 2021-04-20 佛山市顺德区美的饮水机制造有限公司 Water tank assembly and water purifying equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112675601A (en) * 2019-10-18 2021-04-20 佛山市顺德区美的饮水机制造有限公司 Water tank assembly and water purifying equipment
CN112675601B (en) * 2019-10-18 2022-06-07 佛山市顺德区美的饮水机制造有限公司 Water tank assembly and water purifying equipment

Similar Documents

Publication Publication Date Title
CN104061682B (en) Vertical heat-preservation water tank and air energy water heater
CN202692400U (en) Novel variable volume electric water heater
CN101956970B (en) Steam generation device, control method thereof and household electric steam box
CN206080166U (en) Instant -heating water drinking machine
CN208635325U (en) A kind of stepping water boiler
CN201237340Y (en) Energy-saving instant water boiling equipment
CN207017345U (en) A kind of energy-conserving and environment-protective public transport stop board awning
CN201935152U (en) Steam generator and household electric steamer
CN110145862B (en) Double-throttling accurate instant-heating type pure water boiler and heating method
CN201624535U (en) Sanitary energy-saving water dispenser
CN213984008U (en) Green intelligent house water saving fixtures
CN206771768U (en) All-in-one formula domestic type solar water heater with two bearing insulated water boxes
CN210374033U (en) Double-throttling accurate instant heating type pure water boiler
CN204394248U (en) Multifunctional drinking machine
CN206771782U (en) The safe solar water heater of pressure-bearing all-in-one formula
CN202589279U (en) Bottle with heat preservation and water boiling functions
CN206166649U (en) Domestic watering device of instant heating type
CN206784520U (en) A kind of kitchen cabinet with energy-saving drainage arrangement
CN101049212A (en) Electrothermal drinking trough double bags
CN205444294U (en) Simple and easy two ball -cock assembly water saving fixtures
CN202813738U (en) Water boiler
CN2788080Y (en) Electric water heater
CN203190598U (en) Instant-heating type drinking water heating device
CN205306738U (en) Steamed rice case of pallet separating steamed rice
CN104344545A (en) Intelligent electrical water boiler

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant