- CN206052679U CN206052679U CN201620784544.6U CN201620784544U CN206052679U CN 206052679 U CN206052679 U CN 206052679U CN 201620784544 U CN201620784544 U CN 201620784544U CN 206052679 U CN206052679 U CN 206052679U
- Authority
- CN
- China
- Prior art keywords
- soil layer
- basement rock
- foundation structure
- layer
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
A kind of foundation structure, is related to foundation technical field, including soil layer and basement rock, and soil layer is located above basement rock, and some steel pipes are vertically provided with soil layer, and steel pipe is extend in horizon d from the top of soil layer, and slurry is marked with steel pipe.This programme reduces phenomenon of caving in by providing a kind of foundation structure with solid and reliable structural strength.
Description
Technical field
This utility model is related to foundation treatment technology field, more particularly to a kind of foundation structure.
Background technology
In construction, it is inevitable working link to excavate and reinforce and be rudimentary, with a varied topography in some constructions
In environment, boulder or solution cavity and Soft Clay often occurs.In some construction sites, basement rock is very large, and interior hollow, this
Be exactly the situation of the mutual fit of solution cavity basement rock often said, if consolidation process is not carried out to whole basement rock, base is directly done on basement rock
Plinth, the solution cavity inside basement rock can cause the inequality of earth's surface because long-time avalanche is occurred by the extruding of upper building gravity
Even sedimentation, destroys the stability in the large of building;If digging positive basement rock, solution cavity is punched, cement is carried out in solution cavity internal drainage and mixed
Solidifying earth foundation construction, then construction cost is again sufficiently expensive, and schedule delays.Therefore, apply carrying out engineering to these complicated geologicals
In man-hour, the progress of whole engineering be to not only consider, the reliability of foundation stabilization and the economy of construction guaranteed again.
The Chinese utility model of Application No. CN201120005549 discloses a kind of composite foundation structure, including soft subgrade soil
Body layer, is provided with supporting course below soft subgrade soil body layer, be provided with the mixing bed of material, be provided with least one in the mixing bed of material above soft subgrade soil body layer
Individual drill hole, drill bottom hole end are extended in soft subgrade soil body, and drill is provided with mixture in hole.The composite foundation structure construction method
Simply, but just because of excessively simply causing its bearing capacity to need further to be improved.
Utility model content
The purpose of this utility model is to provide a kind of foundation structure, and with solid and reliable structural strength, reduction is caved in
Phenomenon.
Above-mentioned purpose of the present utility model technical scheme is that:A kind of foundation structure, including soil
Layer and basement rock, soil layer are located above basement rock, and some steel pipes are vertically provided with soil layer, and steel pipe extend into horizon d from the top of soil layer
It is interior, and in steel pipe, it is marked with slurry.
By adopting above-mentioned technical proposal, soil layer is set above basement rock, due to softer for the relative basement rock of soil layer,
Therefore the pressure that buffering superstructure is applied to basement rock can be played, plays a part of to protect basement rock to prevent its breakage;In soil layer
Interior to arrange after the steel pipe in soil layer to basement rock, detached soil layer and basement rock originally are coupled together by steel pipe, improve ground
The globality of structure;The slip casting in the steel pipe is conducive to the intensity for strengthening steel pipe, makes foundation structure more stable.
Preferably, some GSZs are provided with soil layer.
All kinds of ambient soils are adapted to by adopting above-mentioned technical proposal, GSZ, is had compared with conventional grates strong
Many advantages, such as spending big, strong, anticorrosive bearing capacity, anti-aging, easy construction, long service life, arranges geotechnological lattice in soil layer
The bearing capacity of the enhancing ground of grid energy high degree, effectively constrains the lateral displacement of the soil body, strengthens the firm performance of ground, reduces
Cave in phenomenon.
Preferably, GSZ is set in parallel in the horizontal plane of differing heights.
By adopting above-mentioned technical proposal, GSZ is set in parallel in the different level in soil layer, by soil layer
It is separated into multiple modules to be protected, the soil layer in each module can obtain effective reinforcement effect, so that soil layer entirety
It is more solid firm.
Preferably, the first spontaneous recovery concrete layer is provided with above soil layer.
There is the effect for voluntarily mending a split by adopting above-mentioned technical proposal, spontaneous recovery concrete, the inside contains can give birth to
The nutrient needed the bacterial spore and bacterial growth for producing the dormancy of limestone, after corrosivity rainwater penetrates into spontaneous recovery concrete layer more
Bacterial spore can be just activated, concrete cracking part is locally filled with so as to produce limestone, Efficient software patching crack, be protected
The soil layer and basement rock of shield lower section.
Preferably, the second spontaneous recovery concrete layer is provided between basement rock and soil layer.
By adopting above-mentioned technical proposal, spontaneous recovery concrete layer is covered above basement rock protection work can be played to basement rock
With, the phenomenon that basement rock suffers breakage because of the pressure that top is built is reduced, the steadiness of protection ground increases the service life.
Preferably, the top of soil layer is provided with some filling baggy fabrics in the horizontal direction.
By adopting above-mentioned technical proposal, as soil layer is in the overall top position of ground, when current stream enters in ground
When, it is exactly more soft soil layer by water impact effect at first, after the top of soil layer arranges filling baggy fabric, filling baggy fabric can
To absorb to the current for flowing down, reduce the water content into underground layer bottom and basement rock so that soil layer can keep compared with
For solid soil property state, it is ensured that the overall construction intensity of ground.
Preferably, fine sand is filled with filling baggy fabric.
By adopting above-mentioned technical proposal, the granule of fine sand is less, forms tiny space, work as water between fine sand and fine sand
After stream is flowed into, fine sand has preferable Absorption to current, thus reduces into the water yield in underground layer.
Preferably, the top and bottom of soil layer is coated with geotextiles.
The overall structure and function of soil layer can be kept, the carrying of ground is made by adopting above-mentioned technical proposal, geotextiles
Ability is strengthened, and strengthens the structural stability of ground;Geotextiles are covered at the top of soil layer and bottom, soil layer can be made integrally more to tie
It is real firm.
Preferably, rubble is evenly equipped with soil layer.
By adopting above-mentioned technical proposal, soil layer is more soft, easily caves in, and can be made after mixing rubble in soil layer
Soil layer is overall firmer, plays a part of to tamp soil ground, reduces by caving in that soft soil causes.
Preferably, the outer ring of soil layer is with baffle plate.
By adopting above-mentioned technical proposal, the baffle plate for enclosing is set in the outer ring of soil layer, by soil layer lock ring in baffle plate, is risen
To the effect for preventing soil layer from caving in.
To sum up, soil layer and basement rock effectively can be combined into by a kind of foundation structure described in the utility model, slip casting in steel pipe
It is overall, improve globality;Soil layer compacting is fastened by geotextiles, GSZ, rubble, makes soil layer be difficult loosely, to improve overall knot
Structure intensity.
Description of the drawings
Schematic diagrams of the Fig. 1 for embodiment 1;
Schematic diagrams of the Fig. 2 for embodiment 2.
Reference:1st, soil layer;2nd, basement rock;3rd, steel pipe;4th, GSZ;5th, the first spontaneous recovery concrete layer;6th, second certainly
More concrete layer;7th, filling baggy fabric;8th, geotextiles;9th, rubble;10th, baffle plate.
Specific embodiment
This utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1
As shown in figure 1, a kind of foundation structure, including soil layer 1, the outer ring of soil layer 1 is enclosed with baffle plate 10, the top of soil layer 1
Geotextiles 8 are coated with bottom, in soil layer 1, rubble 9 is evenly equipped with.The top of soil layer 1 is horizontally disposed some filling baggy fabrics
7, filling fine sand in filling baggy fabric 7.
Basement rock 2 is provided with below soil layer 1, in soil layer 1, steel pipe 3 is provided with, steel pipe 3 is extend in basement rock 2 from the top of soil layer 1,
And slurry is marked with steel pipe 3.
When ground is built, first steel pipe 3 is inserted in basement rock 2, and toward slip casting in steel pipe 3;Then keep off in 2 outer ring of basement rock
Plate 10 encloses the scope of soil layer 1;Geotextiles 8 are covered above basement rock 2, toward 10 inner ring of baffle plate filling soil and the batch mixing of rubble 9;
During to 1 the top of soil layer, being spaced a distance prevents the filling baggy fabric 7 for being filled with fine sand;Soil layer 1 is continued to fill up, finally in soil layer 1
Surface covers geotextiles 8.
Embodiment 2
As shown in Fig. 2 a kind of foundation structure, the present embodiment is that soil layer 1 is interior with the difference of embodiment 1 is provided with some parallel
GSZ 4, and these GSZs 4 be located at different level in.
The first spontaneous recovery concrete layer 5 is provided with above soil layer 1, the second spontaneous recovery concrete layer 6 between basement rock 2 and soil layer 1, is provided with.
When ground is built, first steel pipe 3 is inserted in basement rock 2, and toward slip casting in steel pipe 3;Then keep off in 2 outer ring of basement rock
Plate 10 encloses the scope of soil layer 1;The second spontaneous recovery concrete layer 6 is laid above basement rock 2 first, then in the second spontaneous recovery concrete
Filling soil above layer 6, then covers one layer of geotextiles 8;Toward 10 inner ring of baffle plate filling soil and the batch mixing of rubble 9, filling is certain thick
Degree just lays one layer of GSZ 4, is further continued for filling and laying GSZ 4;When 1 the top of soil layer, interval one section away from
From preventing from being filled with the filling baggy fabric 7 of fine sand;Soil layer 1 is continued to fill up, and then geotextiles 8 is covered on 1 surface of soil layer;Finally in geotechnique
After certain thickness soil is filled above cloth 8, the first spontaneous recovery concrete layer 5 is laid.
This specific embodiment is only which is not to restriction of the present utility model, ability to explanation of the present utility model
Field technique personnel can make the modification for not having creative contribution after this specification is read as needed to the present embodiment, but
As long as all being protected by Patent Law in right of the present utility model.
Claims (7)
1. a kind of foundation structure, including soil layer(1)And basement rock(2), soil layer(1)Positioned at basement rock(2)Top, it is characterised in that:Soil
Layer(1)Some steel pipes are vertically provided with inside(3), steel pipe(3)From soil layer(1)Top extend into basement rock(2)In layer, and steel pipe(3)
Slurry, soil layer are marked with inside(1)Some GSZs are provided with inside(4), GSZ(4)It is set in parallel in the horizontal plane of differing heights
It is interior, soil layer(1)Outer ring be with baffle plate(10).
2. a kind of foundation structure according to claim 1, it is characterised in that:The soil layer(1)Top is provided with the first spontaneous recovery
Concrete layer(5).
3. a kind of foundation structure according to claim 1, it is characterised in that:The basement rock(2)And soil layer(1)Between be provided with
Second spontaneous recovery concrete layer(6).
4. a kind of foundation structure according to claim 1, it is characterised in that:The soil layer(1)Top in the horizontal direction
It is provided with some filling baggy fabrics(7).
5. a kind of foundation structure according to claim 4, it is characterised in that:The filling baggy fabric(7)It is interior filled with fine sand.
6. a kind of foundation structure according to claim 1, it is characterised in that:The soil layer(1)Top and bottom cover
There are geotextiles(8).
7. a kind of foundation structure according to claim 1, it is characterised in that:The soil layer(1)Rubble is evenly equipped with inside(9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620784544.6U CN206052679U (en) | 2016-07-23 | 2016-07-23 | A kind of foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620784544.6U CN206052679U (en) | 2016-07-23 | 2016-07-23 | A kind of foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206052679U true CN206052679U (en) | 2017-03-29 |
Family
ID=58376329
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620784544.6U Expired - Fee Related CN206052679U (en) | 2016-07-23 | 2016-07-23 | A kind of foundation structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206052679U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318757A (en) * | 2019-05-17 | 2019-10-11 | 昌鑫生态科技(陕西)有限公司 | Pit stemming operation technology |
-
2016
- 2016-07-23 CN CN201620784544.6U patent/CN206052679U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318757A (en) * | 2019-05-17 | 2019-10-11 | 昌鑫生态科技(陕西)有限公司 | Pit stemming operation technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759473B (en) | The constructing structure and its construction method of underground pipe gallery and road | |
CN105887898B (en) | A kind of method and structure of protection swell-shrink characteristic ground cut slope | |
CN104153304B (en) | A kind of corrugated steel culvert fills structure and dam filling construction thereof | |
CN104612143A (en) | Bored composite pile structure under karst cave/soil cave geological condition | |
CN205387720U (en) | Tertiary light -duty retaining structure of double circular pile pile foundation of superelevation embankment | |
CN101598028A (en) | Lining structure for super large section water-rich loess tunnel of high-speed railroad | |
CN203808088U (en) | Gabion gully detention structure for top of hydropower station slag yard | |
CN103643689B (en) | A kind of pipe type underground water drainage blind ditch and construction technology thereof and application | |
CN211200426U (en) | Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall | |
CN201436323U (en) | Drainage structure of dynamic compaction foundation | |
CN112983461B (en) | Construction method for biasing tunnel portal in slope integrated | |
CN102518136A (en) | Flexible reinforced combined protection structure for preventing and treating humidifying damage of soft rock strongly weathered zone | |
CN206052679U (en) | A kind of foundation structure | |
CN105821902B (en) | The light-duty armored concrete Ecological Retaining Wall construction method of vertical lattice | |
CN216920384U (en) | Highway tunnel entrance to a cave section landslide body side slope protection additional strengthening that collapses | |
CN206667263U (en) | A kind of foundation pit supporting construction | |
RU121275U1 (en) | REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED | |
CN205530218U (en) | Slip casting composite foundation suitable for high -rise building structural strengthening is rectified | |
CN107882062A (en) | Massif hillside fields is based on gravity type and the compound Retaining wall method of Fill Reinforced With Geogrids | |
KR101525942B1 (en) | Method for slope reinforcement construction using the ground improvement product | |
CN209482302U (en) | Sanitary filling field laying assembled anchor structure | |
CN208152061U (en) | Method steel pipe pile cofferdam structure is unidirectionally attacked and occupied suitable for Soft Clay | |
CN109403356B (en) | Side slope supporting structure | |
CN207228130U (en) | A kind of city integrated piping lane foundation pit backfill processing combined system | |
KR102146783B1 (en) | Construction method for embankmet ground structured using high water content dredged cohesive soil |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170329 Termination date: 20200723 |