CN206051362U - Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device - Google Patents

Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device Download PDF

Info

Publication number
CN206051362U
CN206051362U CN201621089105.XU CN201621089105U CN206051362U CN 206051362 U CN206051362 U CN 206051362U CN 201621089105 U CN201621089105 U CN 201621089105U CN 206051362 U CN206051362 U CN 206051362U
Authority
CN
China
Prior art keywords
connecting plate
steel wire
wire rope
tower crane
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621089105.XU
Other languages
Chinese (zh)
Inventor
钟晓沧
刘政伟
李鹏
赫鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING PANGYUAN MACHINERY ENGINEERING CO LTD
Original Assignee
BEIJING PANGYUAN MACHINERY ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING PANGYUAN MACHINERY ENGINEERING CO LTD filed Critical BEIJING PANGYUAN MACHINERY ENGINEERING CO LTD
Priority to CN201621089105.XU priority Critical patent/CN206051362U/en
Application granted granted Critical
Publication of CN206051362U publication Critical patent/CN206051362U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

This utility model discloses a kind of tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, including first, second connecting plate, screw rod, union joint and several pulleys, first connecting plate is threadedly connected to each screw rod one end, second connecting plate is threadedly connected to the other end of each screw rod, described first on each screw rod, nut is respectively arranged with the outside of second connecting plate, the union joint includes the upper junction plate being parallel to each other, lower connecting plate and it is fixed on, two gussets between lower connecting plate, two gusset is rotationally connected with the outside of first connecting plate, the second connecting plate lateral wall is fixed with second installing plate perpendicular with second connecting plate, the pulley is arranged on second installing plate.This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, tower crane Upon Flexible Adhesion can be realized, for attachment point is away from tower body building farther out and variable cross-section building, site operation requirement had both been met, meet the safety work of derrick crane again, smoothly install, smoothly remove.

Description

Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
Technical field
This utility model is related to a kind of building machinery, more particularly to a kind of tower crane Upon Flexible Adhesion steel wire rope pre-tightening device.
Background technology
Jobs that requires special skills industry specifies that the attachment pull bar length of the rigid attachment of derrick crane is not to be exceeded 8m, for change Section building structure such as Hyperbolic cooling tower and attachment point are ensureing tower for the construction operation of more than tower body 30m Crane construction operation is met after terminating in the case that normal drop section removes, at least together the length of attachment pull bar considerably beyond 8m, and the own wt of the attachment pull bar of overlength will necessarily cause attachment Tiebar structure to be deformed, this deformation does not often have Method is corrected it, and this will necessarily cause serious potential safety hazard to the daily construction of derrick crane;So rigid attachment is not Attachment suitable for overlength distance is constructed.
Utility model content
The purpose of this utility model is to provide a kind of tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, to solve above-mentioned existing skill The problem that art is present, realizes tower crane Upon Flexible Adhesion, for attachment point is away from tower body building farther out and variable cross-section building, both meets existing Field construction requirement, meets the safety work of derrick crane again, smoothly installs, smoothly removes.
For achieving the above object, this utility model provides following scheme:A kind of tower crane Upon Flexible Adhesion steel wire rope pretension dress Put, including the first connecting plate, the second connecting plate, at least three screw rods being parallel to each other, union joint and several pulleys, described One connecting plate is threadedly connected to described each screw rod one end, and second connecting plate is threadedly connected to the other end of each screw rod, Nut is respectively arranged with the outside of first, second connecting plate on each screw rod, the union joint includes what is be parallel to each other Upper junction plate, lower connecting plate and two gussets being fixed between upper and lower connecting plate, two gusset are rotationally connected with described On the outside of one connecting plate, the second connecting plate lateral wall is fixed with second installing plate perpendicular with second connecting plate, institute State pulley to be arranged on second installing plate.
This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, wherein, the screw rod is four.
This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, wherein, it is fixed on the first connecting plate lateral wall There are two the first installing plates being parallel to each other, the first installing plate described in two is perpendicular with first connecting plate, the upper and lower connection Plate and two gussets are respectively positioned on described in two between first installing plate, and two gusset is connected to the first installing plate described in two by bearing pin On.
This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, wherein, the pulley is four, and described second installs Plate is three, per being provided with two pulleys described in two between the second installing plate.
This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, wherein, the first installing plate described in two and described first Gusset is respectively and fixedly provided between connecting plate.
This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, wherein, the second installing plate described in two and described second Gusset is respectively and fixedly provided between connecting plate.
This utility model achieves following technique effect relative to prior art:Due to this utility model tower crane Upon Flexible Adhesion Steel wire rope pre-tightening device includes first, second connecting plate, screw rod, union joint and several pulleys, and first, second connecting plate can be Move left and right on screw rod, make the distance between union joint and pulley change, as union joint is articulated with building, therefore The distance between pulley and building can change, so as to can adjust the pulley of the pulley being wound on building and pre-tightening apparatus Between steel wire rope pretightning force, realize the Upon Flexible Adhesion of tower crane, for attachment point is built away from tower body building farther out and variable cross-section Build, both met site operation requirement, meet the safety work of derrick crane, the needs smoothly installed, smoothly remove again.
Description of the drawings
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will be to embodiment Needed for accompanying drawing to be used be briefly described, it should be apparent that, drawings in the following description are only of the present utility model Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can be with according to this A little accompanying drawings obtain other accompanying drawings.
Front view structure figures of the Fig. 1 for this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device;
Overlooking structure figures of the Fig. 2 for this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device.
Description of reference numerals:First connecting plate 11, the second connecting plate 12, screw rod 13, union joint 14, pulley 15, nut 16, 17th, upper junction plate 141, lower connecting plate 142, gusset 143, the first installing plate 19, the second installing plate 18, gusset 21,22.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only this utility model a part of embodiment, rather than whole Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment for being obtained, belongs to the scope of this utility model protection.
It is understandable to enable above-mentioned purpose of the present utility model, feature and advantage to become apparent from, below in conjunction with the accompanying drawings and tool Body embodiment is described in further detail to this utility model.
This utility model provides a kind of tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, as shown in Figure 1, 2, including the first connection Plate 11,12, four screw rods being parallel to each other 13 of the second connecting plate, union joint 14 and several pulleys 15, first, second connecting plate Steel plate, the first connecting plate 11 is adopted to be threadedly connected to four 13 one end of screw rod, the second connecting plate 12 is threadedly connected to four spiral shells The other end of bar 13, is respectively arranged with nut 16,17 on each screw rod 13 on the outside of first, second connecting plate, and union joint 14 includes Upper junction plate 141, lower connecting plate 142 and two gussets 143 being fixedly welded between upper and lower connecting plate being parallel to each other, two muscle Plate 143 is rotationally connected with the outside of the first connecting plate 11, and 12 lateral wall of the second connecting plate is welded with and the second connecting plate 12 The second perpendicular installing plate 18, pulley 15 are arranged on the second installing plate 18.
As shown in Figure 1, 2, it is welded with two the first installing plates 19 being parallel to each other on 11 lateral wall of the first connecting plate, two First installing plate 19 is perpendicular with the first connecting plate 11, and 141,142 and two gusset 143 of upper and lower connecting plate is respectively positioned on two first peaces Between dress plate 19, and upper and lower connecting plate 141,142 is welded on two first installing plates 19, and two gussets 143 are connected by bearing pin On two first installing plates 19.
Pulley 15 arranges four, and the second installing plate 18 arranges three, and three the second installing plates 18 are parallel to each other, per two second Two pulleys 15 are installed between installing plate 18.
Screw rod 13 may also be configured to three, five etc..
For further increase this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device intensity, in two first installing plates 19 and first are welded with gusset 21 between connecting plate 11, weld between two second installing plates 18 and the second connecting plate 12 It is fixed with gusset 22.
The installation process of this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device comprises the steps:
Attachment frame is installed first, then this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device is installed,
Steel wire rope pre-tightening device is mainly used in steel wire rope to be fixed at tower body and applies pretightning force, Ke Yi to steel wire rope Pretightning force of the steel wire rope to tower crane is adjusted at any time in whole work progress.
The union joint 14 of this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device is connected by bearing pin with attachment frame, 4 pulleys 15 of the other end are used to pass around steel wire rope, and its operation principle is:By the pulley on building masonry wall and installation Pulley Jing steel wire ropes on tower crane Upon Flexible Adhesion steel wire rope pre-tightening device are passed around, and the two ends of steel wire rope are fixed, and use spanner The nut on pre-tightening apparatus bolt is tightened, makes the first connecting plate 11 of pre-tightening apparatus, the second connecting plate 12 constantly close, and finally Reach the purpose to steel wire rope pretension.This utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device is mainly used in steel wire rope in tower It is in fixed and pretightning force is applied to steel wire rope, pretension of the steel wire rope to tower crane can be adjusted in whole work progress at any time Power.
When this utility model tower crane Upon Flexible Adhesion steel wire rope pre-tightening device is used for cooling tower tower crane attachment, first on cooling tower Built-in fitting is set, then erection support and pulley on built-in fitting:
The projection line of attachment steel wire rope is released on cooling tower base plate by the position and angle of conceptual scheme, according to projection line and Absolute altitude theodolite in scheme determines position of each anchor point on Cooling Tower Wall, in anchor point both sides and upper and lower colligation The reinforcement of annular and meridian to barrel, the specification of reinforcement, quantity, length, position must not must be put accurately and less, leak and put and mistake Put.
During tower crane attachment, per layer of uniform 5 built-in fitting on each direction, the level interval of built-in fitting are 3 meters, between the upper and lower away from Pre-buried point on 2.6 meters of each directions is divided into upper and lower two-layer arrangement again, wherein, in 5 built-in fittings, middle installation of embedded parts exists The point of intersection of 45 ° of extension lines of standard section of tower crane and body of wall.The elevation of pre-buried point is as shown in the table:
Attachment Attachment frame institute Attachment collimation mark Upper strata is pre-buried Lower floor is pre-buried
Passage 1 Put 9 sections in place position the High 23.49m Point 3 high 2.5m of mark Point 2 high 9.5m of mark
Pulley is arranged on bearing in advance on ground, and confirms installation site of the different pulleys in wall body built-in fitting Afterwards, bearing is connected with the corrugated tubing of built-in fitting by 6 M24 high-strength bolts.
Pass around steel wire rope:
Steel wire rope is fixed on tower crane attachment frame:Fill by steel wire rope pretension is installed at tower crane facade layout drawing attachment position Put, steel wire rope bypassed into steel wire rope pre-tightening device, it is fixed after diagonally opposed use pulling force jack applies pretension, while two with Theodolite verifies tower crane perpendicularity, fixes steel wire rope when strain gauge reading is identical, fixes remaining steel wire with same method Rope.The single pretension of steel wire rope is controlled in 5600kg.
Pass around steel wire rope detailed process:
1) pull rope of 200 meters of long Φ 12, steel wire rope is needed to receive construction technology when mounted when steel wire rope is installed Impact needs to increase by 1000 meters.
2) by pull rope one end with attachment steel wire rope using snapping connection, other end is connected with crane hook, using tower Hang to carry out auxiliary installation.
3) other end that attachment steel wire rope is connected with pull rope is fixed on attachment frame, pull rope is hung using crane hook To structure built-in fitting position, and built-in fitting pulley is passed through, fag end is hung to into tower crane direction again afterwards, it is pre- through attachment frame steel wire rope Pulley on tight device, same mode complete ten multiplying power wire rope handlings.
4) finally the attachment steel wire rope end head being connected with pull rope is connected with jack, completes pretension work is installed.
Note:Diagonal steel wire rope must be while pretension.
This installation procedure is only applicable to the attachment of JCD260 derrick cranes and installs.
Points for attention
1) it is unloaded, in the state of wind speed is not more than 3m/s, free height tower body side more than attachment state highest attachment point To perpendicularity franchise to control within 4/1000, the tower body axial line perpendicularity franchise below highest attachment point is 2/ 1000。
2) at the top of tower body swing-scanning control in the range of 1/100, the such as amplitude of oscillation is excessive, reason to be analyzed, solve in time.
3) observe the amount of deflection of steel cable in use at any time, such as find that amount of deflection is excessive, steel cable should be tensioned in time.
4) forbid to hang other articles on steel wire rope.
Apply specific case to be set forth principle of the present utility model and embodiment in this utility model, the above The explanation of embodiment is only intended to help and understands method of the present utility model and its core concept;Simultaneously for the one of this area As technical staff, according to thought of the present utility model, will change in specific embodiments and applications.To sum up Described, this specification content is should not be construed as to restriction of the present utility model.

Claims (6)

1. a kind of tower crane Upon Flexible Adhesion steel wire rope pre-tightening device, it is characterised in that:Including the first connecting plate (11), the second connecting plate (12), at least three screw rods being parallel to each other (13), union joint (14) and several pulleys (15), first connecting plate (11) Described each screw rod (13) one end is threadedly connected to, second connecting plate (12) is threadedly connected to the another of each screw rod (13) End, is respectively arranged with nut (16,17), the union joint on the outside of first, second connecting plate on each screw rod (13) (14) including the upper junction plate (141), lower connecting plate (142) and two gussets being fixed between upper and lower connecting plate being parallel to each other (143), two gusset (143) is rotationally connected with the outside of first connecting plate (11), and second connecting plate (12) is outward Side wall is fixed with second installing plate (18) perpendicular with second connecting plate (12), and the pulley (15) is arranged at described On two installing plates (18).
2. tower crane Upon Flexible Adhesion steel wire rope pre-tightening device according to claim 1, it is characterised in that:The screw rod (13) is Four.
3. tower crane Upon Flexible Adhesion steel wire rope pre-tightening device according to claim 1, it is characterised in that:First connecting plate (11) two the first installing plates (19) being parallel to each other are fixed with lateral wall, the first installing plate (19) described in two connects with described first Fishplate bar (11) is perpendicular, and the upper and lower connecting plate and two gussets (143) are respectively positioned on described in two between first installing plate (19), institute State two gussets (143) to be connected on the first installing plate (19) described in two by bearing pin.
4. tower crane Upon Flexible Adhesion steel wire rope pre-tightening device according to claim 1, it is characterised in that:The pulley (15) is Four, second installing plate (18) is three, per being provided with two pulleys described in two between the second installing plate (18).
5. tower crane Upon Flexible Adhesion steel wire rope pre-tightening device according to claim 3, it is characterised in that:Described in two, first installs Gusset (21) is respectively and fixedly provided between plate (19) and first connecting plate (11).
6. tower crane Upon Flexible Adhesion steel wire rope pre-tightening device according to claim 1, it is characterised in that:Described in two, second installs Gusset (22) is respectively and fixedly provided between plate (18) and second connecting plate (12).
CN201621089105.XU 2016-09-28 2016-09-28 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device Withdrawn - After Issue CN206051362U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621089105.XU CN206051362U (en) 2016-09-28 2016-09-28 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621089105.XU CN206051362U (en) 2016-09-28 2016-09-28 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device

Publications (1)

Publication Number Publication Date
CN206051362U true CN206051362U (en) 2017-03-29

Family

ID=58367742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621089105.XU Withdrawn - After Issue CN206051362U (en) 2016-09-28 2016-09-28 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device

Country Status (1)

Country Link
CN (1) CN206051362U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106185642A (en) * 2016-09-28 2016-12-07 北京庞源机械工程有限公司 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
CN109928307A (en) * 2017-12-19 2019-06-25 广东庞源工程机械有限公司 A kind of novel tower airfoil type attached wall structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106185642A (en) * 2016-09-28 2016-12-07 北京庞源机械工程有限公司 Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
CN109928307A (en) * 2017-12-19 2019-06-25 广东庞源工程机械有限公司 A kind of novel tower airfoil type attached wall structure
CN109928307B (en) * 2017-12-19 2023-11-10 广东庞源工程机械有限公司 Novel tower wing type wall-attached structure

Similar Documents

Publication Publication Date Title
CN106185642B (en) Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
CN206521197U (en) A kind of adjustable balance hoisting beam
CN101126279A (en) Silo slipform construction technique
CN107575652A (en) A kind of support frame set up for petroleum pipeline
CN102888991B (en) Large-scale profile steel beam and concrete combined house roof constructing method
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN105692470A (en) Internal climbing tower crane and operating method thereof
CN104018656A (en) Scaffold construction method for prefabricated outer wall
CN206051362U (en) Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
CN108331429A (en) A kind of tubulose highrise steel structure installation method
CN108002255A (en) Movable arm tower crane climbing beam support system and its application method
CN106505484A (en) Piping lane cable laying method
CN104627849A (en) Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
CN108190808B (en) Color steel plate anti-suspended ceiling high-altitude sliding device and anti-suspended ceiling construction method
CN107816209A (en) The large-scale Roof Truss construction technology of installation is lifted across outer both sides
CN204059904U (en) A kind of hoistway operation platform being applied to multi-platform operation
CN106760558A (en) A kind of suspension type boiler-steam dome aerial aligning method after installing
CN206720680U (en) A kind of roofing color corrugated sheet steel lifting device
CN206693630U (en) A kind of concreting servicing unit
CN108756197A (en) A kind of construction method of hoistway operation platform
CN205975613U (en) Steel trestle steel -pipe pile construction leading truck
CN212956944U (en) Special fixing device for hoisting pipe truss structure system equipment
CN110424808B (en) Skin construction method of steel structure indirect cooling tower
CN203655151U (en) Core drilling machine
CN103015323B (en) Beam body hoisting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20170329

Effective date of abandoning: 20170815

AV01 Patent right actively abandoned