CN206034909U - Pin -connected panel concrete group mould - Google Patents

Pin -connected panel concrete group mould Download PDF

Info

Publication number
CN206034909U
CN206034909U CN201620741566.4U CN201620741566U CN206034909U CN 206034909 U CN206034909 U CN 206034909U CN 201620741566 U CN201620741566 U CN 201620741566U CN 206034909 U CN206034909 U CN 206034909U
Authority
CN
China
Prior art keywords
template
group mould
concrete group
hole
assembling concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620741566.4U
Other languages
Chinese (zh)
Inventor
刘深思
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620741566.4U priority Critical patent/CN206034909U/en
Application granted granted Critical
Publication of CN206034909U publication Critical patent/CN206034909U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a pin -connected panel concrete group mould, including first template and second template, its characterized in that, the concatenation of first template and second template form the concrete placement chamber, the second template is fixed through the connecting piece with concatenation department of first template. Pin -connected panel concrete group mould assembly and disassembly convenient efficient, practice thrift man -hour, operation labour saving and time saving can not lead to the fact destruction to first template and second template, lengthens the life of first template and second template, first template and second template can a lot of used repeatedly, material saving, reduction construction cost, improvement economic benefits, the concrete member surfacing nature of building is good to the negative and positive angle that has the good linearity.

Description

A kind of assembling concrete group mould
Technical field
This utility model is related to concreting technical field, more particularly to a kind of assembling concrete group mould.
Background technology
With economic fast development, heavy construction is sharply increased, and most for reinforced concrete structure, coagulation , generally using building falsework to implement to pour, then mounting bracket first lays first on support for Tu Liang, the cast of plate Template, then will be reinforcing bar colligation in place, then installs side form around reinforcing bar, then formed cavity in casting concrete, most Health preserving form removal afterwards falls frame.
Traditional assembling concrete group mould is generally made using timber, in assembly jig with spike by each template It is nailed together, packaging efficiency is low, wastes time and energy, and needs the mode for extracting spike after the completion of pouring to take mould apart, Dismounting is difficult, high labor intensive, and during taking apart template can be damaged, and template can only be made using once needing twice to change Into the waste of timber resources, construction cost is high.And the mode of conventionally employed spike connection, assembly precision are poor, it is difficult to which guarantee is poured Build up the linearity at the negative and positive angle of the concrete component of type, negative and positive angle is generally all not straight situation of distorting, and concrete structure The perpendicularity on part surface is also difficult to be protected, while needing to mix and stir to being discharged into the concrete poured in storehouse in casting concrete Thing carries out mechanical pudding, and vibration can cause spike connection to loosen, and the assembly precision for further resulting in mould is deteriorated, after pouring molding Concrete component scale error it is big, structure can not meet design requirement, and outward appearance is coarse, it is difficult to meet high-quality demand, need Floating repairing carried out using the technique such as plaster subsequently, consume more manpower and materials, construction cost is high, efficiency is low.
Utility model content
Technical problem to be solved in the utility model and the technical assignment for proposing are that prior art is improved, there is provided A kind of assembling concrete group mould, in the current technology of solution, traditional assembling concrete group mould efficiency of loading and unloading is low, wastes time and energy, Template, service life short problem can be destroyed during dismounting.
For solving above technical problem, the technical solution of the utility model is:
A kind of assembling concrete group mould, including the first template and the second template, it is characterised in that the first described template Concreting chamber is formed with the second template splicing, the stitching portion of the second template and the first template is fixed by connector.This reality It is simple with new described assembling concrete group mode structure, assemble and facilitate efficiency high, save man-hour, connector is by second It is connected between template and the first template, while convenient disassembly, will not damage to the first template and the second template, extends The service life of the first template and the second template, the first template and the second template can be repeatedly used, and save material, reduce applying Work cost, increases economic efficiency.
Further, described connector is bolt fastening structure or hasp, and simple structure is convenient to operation, carries High efficiency of construction, will not damage to the first template and the second template during dismounting, so that it is guaranteed that the first template and the second template Can repeatedly use, save material, reduce construction cost.
Further, location structure, the second template and during the first template splicing second is provided with the first described template The bottom of template is positioned by location structure, improves the assembly precision of assembling concrete group mould, so as to improve concrete component Dimensional accuracy, improves pouring quality.
Further, described location structure is positioning retaining strip or detent, and the Basolateral of the second template is resisted against On positioning retaining strip, or the bottom of the second template is inserted in detent.Spacing between two offside positioning retaining strips is deducted The thickness of the second template is the size of concrete component, and while raising pours dimensional accuracy, positioning retaining strip plays good adding Gu effect, prevents the pressure that the concrete that pours into is produced from the second template is shifted, it is ensured that when mechanical pudding operation is carried out the Two templates will not also be shifted over, and improve the structural strength and dimensional accuracy of assembling concrete group mould;Detent equally may be used To improve the attachment structure intensity of assembling concrete group mould, ensure that assembling concrete group mould possesses long-acting dimensionally stable Property.
Further, second template of two sides splicing of the first described template forms trench structure and pours chamber, the second mould The middle and upper part of plate is provided with take-up device and the second template of two offsides is connected, and the top of the second template is connected by take-up device Fixation is connect, structural strength is high, can bear concrete and pour fashionable pressure, prevent the second template from turning up, so that it is guaranteed that pouring size Precisely, improve pouring quality.
Further, through hole has been opened up in the second described template, and take-up device includes screw rod, and screw rod is through two offsides Second template tightening is being fixed, structure letter by the through hole in the second template positioned at device nut on the screw rod on the outside of the second template Single, convenient to operation, bonding strength is high, it is ensured that the second template can bear the pressure of concrete, it is to avoid the second template is turned up, and protects Hold structural stability.
Further, through hole has been opened up in the second described template, and take-up device includes stock, and stock is through two offsides Through hole in second template, on the stock on the outside of the second template is opening up pin-and-hole, is filling latch on pin-and-hole, and latch is close to Second template tightening is fixed by the second template outer wall, and same structure is simple, is convenient to mount and dismount fast, the second template will not be caused brokenly It is bad, extend the service life of the second template, it is reusable, material is saved, construction cost is reduced.
Further, sleeve pipe is provided between the through hole of the second template of two described offsides, take-up device is through sleeve pipe It is interior that second template tightening is fixed.The screw rod or stock of take-up device can be then needed to naked with concrete setting inside which The part being exposed at outside concrete is cut, and can so increase the consumption of screw rod or stock, improves construction cost, while also increasing The labor intensity of workmen is added, has extended the engineering time, reduced efficiency of construction, therefore this utility model is provided with set Pipe, sleeve pipe with concrete setting inside which, and screw rod or stock can the directly extraction from sleeve pipe, reduce screw rod or stock Consumption, reduces construction cost, reduces the labor intensity of workmen, shortens the engineering time, improves efficiency of construction, while avoiding Second template inwardly rolls oblique, the dimensional accuracy of guarantee concrete component, improves pouring quality.
Further, the first described template, the second template-setup have several, are spliced to form circumferentially from one another and pour Chamber, can be used to pour the concrete components such as column.
Further, each wall of the bathtub construction that the first described template and the second template splicing are formed all is smooth table Face, ensures pouring quality so that the concrete component for pouring molding has even curface, ensures the negative and positive angle of concrete component With the good linearity, it is to avoid diastrophic situation occurs in concrete component, so as to without the need for subsequently being carried out using plastering etc. The technique of floating repairing, reduces construction cost, improves efficiency of construction.The bottom surface of the first template is provided with some buttress braces, institute State and on the outside of the second template, be provided with some reinforcement ribs, improve structural strength, the pressure that concrete is produced is prevented to first Template and the second template are damaged, and are increased the service life.
Compared with prior art, this utility model advantage is:
Assembling concrete group mould assembly and disassembly described in the utility model facilitates efficiency high, saves man-hour, and operation saves time It is laborsaving, the first template and the second template will not be damaged, extend the service life of the first template and the second template, the first mould Plate and the second template can be repeatedly used, and save material, reduce construction cost, increase economic efficiency;It is described in the utility model Assembling concrete group mode structure intensity it is high, concrete can be born and pour fashionable pressure, dimensional accuracy stability is high, so as to true It is accurate that guarantor pours size, it is adaptable to beam, column, the pouring construction of shear wall, pour molding concrete component have it is smooth Surface, and the negative and positive angle with good linearity, improve pouring quality, without the need for the follow-up floating repair procedure such as plaster, enter One step improves efficiency of construction, reduces construction cost.
Description of the drawings
Structural representations of the Fig. 1 for this utility model embodiment one;
Structural representations of the Fig. 2 for this utility model embodiment two;
Structural representations of the Fig. 3 for this utility model embodiment three;
Structural representations of the Fig. 4 for this utility model example IV;
Structural representations of the Fig. 5 for take-up device embodiment one;
Structural representations of the Fig. 6 for take-up device embodiment two.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only this utility model a part of embodiment, rather than whole Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment for being obtained, belongs to the scope of this utility model protection.
A kind of assembling concrete group mould disclosed in this utility model embodiment, the efficiency of loading and unloading are high, and time saving and energy saving, structure is strong Degree is high, ensures concrete pouring quality, makes concrete component have the negative and positive angle of good linearity, template will not be made during dismounting Into destruction, use is can be repeated several times, construction cost is low, efficiency high.
As shown in Figures 1 to 6, a kind of assembling concrete group mould, including the first template 1 and the second template 2, the first template 1 and second template 2 be spliced to form concreting chamber, the stitching portion of the second template 2 and the first template 1 is fixed by connector 3, Connector 3 is bolt fastening structure or hasp.As shown in Fig. 2 the bonding strength of bolt fastening structure is high, good stability has Effect avoids the situation for occurring to loosen in operation of vibrating due to vibration, ensures the mould structure of stable strong;As shown in figure 1, Hasp structure is simpler, and assembly and disassembly operations is more quick, and raising group imitates rate, shortens the engineering time, will not be to the first template 1 and the Two templates 2 are damaged, so as to the first template 1 and the second template 2 can multiple Reusability, increase the service life, reduce material Consumption, reduces construction cost.
Dimensional accuracy is poured in order to ensure, location structure, the second template 2 and the first template 1 is provided with the first template 1 During splicing, the bottom of the second template 2 is positioned by location structure, improves packaging efficiency and assembly precision, and location structure can be using positioning Blend stop 5 or detent 6, as shown in figure 1, positioning retaining strip 5 is arranged on the edge of the first template 1, outside the bottom of the second template 2 Side is resisted against on positioning retaining strip 5, so that it is guaranteed that having accurate size between the second template 2 of two offsides;As shown in Fig. 2 fixed Position groove 6 is also disposed at the edge of the first template 1, and the bottom of the second template 2 is completed by being directly inserted in detent 6 Positioning, it is convenient to operation, it is ensured that there is between the second template 2 of two offsides accurate size, pouring for concrete component is improved Build quality.
As shown in Figure 1, 2, second template of two sides splicing 2 of the first template 1 forms trench structure and pours chamber, it is adaptable to beam Pour;As shown in figure 3, two the first templates 1 and two the second templates 2 interval be spliced to form ring-type pour chamber, it is adaptable to Column is poured;As shown in figure 4, several first templates 1 are mutually spliced to form pouring for shear wall with several second templates 2 Chamber.
When concrete is poured into into bathtub construction, concrete can produce outside pressure to the second template, therefore the The middle and upper part of two templates 2 is provided with take-up device 4 and second template 2 of two offsides is strained and fixed, and improves structural strength, prevents the Two templates are turned up, and ensure concreting dimensional accuracy.
Take-up device 4 can adopt various structures, in the present embodiment, as shown in figure 5, through hole has been opened up in the second template 2, Take-up device 4 includes screw rod 41, and screw rod 41 is being exposed on the outside of the second template 2 through the through hole in the second template 2 of two offsides Screw rod 41 on device nut 42, the second template 2 is strained and fixed by tightening nut 42, and simple structure is easy to assembly, will not be to Two templates are damaged, with good structural stability, it is ensured that concreting dimensional accuracy;As shown in fig. 6, the second template Through hole has been opened up on 2, and take-up device 4 includes stock 43, and stock 43 is being located at through the through hole in the second template 2 of two offsides Pin-and-hole is opened up on stock 43 on the outside of second template 2, latch 44 on pin-and-hole, has been filled, latch 44 is close to 2 outer wall of the second template will Second template 2 is strained and fixed, same simple operation, and the second template will not be damaged, it is ensured that the second template can Reusability, Reduce construction cost.
After having poured into concrete, screw rod or stock can be then needed to exposed mixed with concrete setting inside which Part outside solidifying soil is cut, and can so increase the consumption of screw rod or stock, improve construction cost, while also increase applying Work operation, extends the engineering time, reduces efficiency of construction, therefore the application is between the through hole of the second template 2 of two offsides Sleeve pipe 7 is provided with, the screw rod or stock of take-up device 4 are through in sleeve pipe 7 and second template 2 is strained and fixed, using this kind of mode So that sleeve pipe 7 with concrete setting inside which, and screw rod or stock directly can be extracted out from sleeve pipe 7, and screw rod or stock can Reuse, reduce construction cost, sleeve pipe 7 need not be taken out in being set in concrete, can be using lower-cost materials such as sebific ducts Make, effectively reduce working procedure, so as to shorten the construction period, improve efficiency of construction.The end of sleeve pipe 7 is resisted against the second template On 2 medial surface, the length of sleeve pipe 7 is the design pitch between the second template 2 of two offsides, and sleeve pipe 7 plays what positioning was supported Effect, improves the group mould precision of assembling concrete group mould, it is to avoid the second template slopes inwardly, and pours the mixed of molding so as to improve The dimensional accuracy of solidifying soil component.
The each wall for pouring chamber that first template 1 and the second template 2 are spliced to form all is smooth surface so that pour molding Concrete component there is even curface, ensure that the negative and positive angle of concrete component has the good linearity, without the need for subsequently adopt The technique for carrying out floating repairing with plastering etc., improves pouring quality, improves efficiency of construction;Meanwhile, set in the bottom surface of the first template 1 It is equipped with some buttress braces 8, the outside of second template 2 is provided with some reinforcement ribs 9, improves the first template 1 and the The structural strength of two templates 2, it is to avoid the pressure that not solidified concrete is produced cause the first template 1 and the second template 2 rupture and The scale error that pours of concrete component is caused to become, it is ensured that pouring quality meets design requirement.
The above is only preferred implementation of the present utility model, it is noted that above-mentioned preferred implementation should not be regarded It is that, to restriction of the present utility model, protection domain of the present utility model should be defined by claim limited range.For For those skilled in the art, in without departing from spirit and scope of the present utility model, can also make some Improvements and modifications, these improvements and modifications also should be regarded as protection domain of the present utility model.

Claims (10)

1. a kind of assembling concrete group mould, including the first template (1) and the second template (2), it is characterised in that described first Template (1) is spliced to form concreting chamber with the second template (2), and the second template (2) is passed through with the stitching portion of the first template (1) Connector (3) is fixed.
2. assembling concrete group mould according to claim 1, it is characterised in that described connector (3) is that bolt connects Binding structure or hasp.
3. assembling concrete group mould according to claim 1, it is characterised in that arrange in described the first template (1) Location structure, when the second template (2) is spliced with the first template (1), the bottom of the second template (2) is positioned by location structure.
4. assembling concrete group mould according to claim 3, it is characterised in that described location structure is positioning retaining strip (5) or detent (6), the Basolateral of the second template (2) is resisted against on positioning retaining strip (5), or the second template (2) Bottom is inserted in detent (6).
5. assembling concrete group mould according to claim 1, it is characterised in that the both sides of described the first template (1) Splice the second template (2) formation trench structure pours chamber, and the middle and upper part of the second template (2) is provided with take-up device (4) by two Second template (2) of offside is connected.
6. assembling concrete group mould according to claim 5, it is characterised in that open up in described the second template (2) Through hole, take-up device (4) include screw rod (41), and screw rod (41) is being located at through the through hole in second template (2) of two offsides On screw rod (41) on the outside of second template (2), the second template (2) is strained and fixed by device nut (42).
7. assembling concrete group mould according to claim 5, it is characterised in that open up in described the second template (2) Through hole, take-up device (4) include stock (43), and stock (43) is being located at through the through hole in second template (2) of two offsides Pin-and-hole is opened up on stock (43) on the outside of second template (2), latch (44) on pin-and-hole, has been filled, latch (44) has been close to the second template (2) the second template (2) is strained and fixed by outer wall.
8. the assembling concrete group mould according to claim 6 or 7, it is characterised in that the second mould of two described offsides Sleeve pipe (7) is provided between the through hole of plate (2), and take-up device (4) is through in sleeve pipe (7) and the second template (2) is strained and fixed.
9. assembling concrete group mould according to claim 1, it is characterised in that described the first template (1), the second mould Plate (2) is provided with several, is spliced to form circumferentially from one another and pours chamber.
10. assembling concrete group mould according to claim 1, it is characterised in that described the first template (1) and second It is all smooth surface that what template (2) was spliced to form pours each wall in chamber, and the bottom surface of described the first template (1) is provided with some Buttress brace (8), be provided with some reinforcement ribs (9) on the outside of the second template (2).
CN201620741566.4U 2016-07-14 2016-07-14 Pin -connected panel concrete group mould Expired - Fee Related CN206034909U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620741566.4U CN206034909U (en) 2016-07-14 2016-07-14 Pin -connected panel concrete group mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620741566.4U CN206034909U (en) 2016-07-14 2016-07-14 Pin -connected panel concrete group mould

Publications (1)

Publication Number Publication Date
CN206034909U true CN206034909U (en) 2017-03-22

Family

ID=58311017

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620741566.4U Expired - Fee Related CN206034909U (en) 2016-07-14 2016-07-14 Pin -connected panel concrete group mould

Country Status (1)

Country Link
CN (1) CN206034909U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013794A (en) * 2016-07-14 2016-10-12 刘深思 Assembling-type concrete combined mold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013794A (en) * 2016-07-14 2016-10-12 刘深思 Assembling-type concrete combined mold

Similar Documents

Publication Publication Date Title
CN110509396B (en) Laminated slab, laminated slab production equipment and laminated slab production method
US8844224B2 (en) Utility dowel bracket
CN209568705U (en) A kind of constructional column regularization template formwork erecting structure
CN209585294U (en) A kind of tower crane attachment pre-embedded device based on aluminum dipping form construction
CN205875734U (en) Concrete placement splices template
CN113738145B (en) Building reinforcement engineering structure and construction method thereof
CN105952154B (en) A kind of concrete-pouring template stent
CN106193588A (en) A kind of method pouring building post-cast strip and pour mould
CN106013794A (en) Assembling-type concrete combined mold
CN206220489U (en) Concrete post formwork for placing tightening device
CN204983649U (en) Big inclination cylinder steel form
CN206034909U (en) Pin -connected panel concrete group mould
CN201756793U (en) Building templates capable of being assembled and combined through injection moulding
CN109868923B (en) Construction method of bare concrete of loose-spliced wood formwork
CN202831624U (en) Template for deformation joint of shear wall
CN210289132U (en) Cross-shaped constructional column combined type aluminum alloy template assembly
CN105804396B (en) A kind of non-type, template system precast stair bench and construction can be had enough to meet the need
CN204898612U (en) Mould with adjustable be used for pouring ditch
CN208152107U (en) A kind of rubber watertight strip mounting device
CN205976472U (en) Pour mould of building post -cast strip
CN110439257A (en) A kind of high turnover rate fashioned iron of sectional-film coating plywood light-type template system construction method
CN206477581U (en) Formwork reinforcement corner key
CN206722138U (en) A kind of vertical splice bar slurry anchor connection node of fabricated shear wall exterior wall
CN204826626U (en) But reuse's concatenation formula typical forms
CN204826618U (en) After water board template structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170322

Termination date: 20210714