CN206008367U - Absorber filler automates filling system - Google Patents

Absorber filler automates filling system Download PDF

Info

Publication number
CN206008367U
CN206008367U CN201620515609.7U CN201620515609U CN206008367U CN 206008367 U CN206008367 U CN 206008367U CN 201620515609 U CN201620515609 U CN 201620515609U CN 206008367 U CN206008367 U CN 206008367U
Authority
CN
China
Prior art keywords
filler
flexible pipe
filling
mouth
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620515609.7U
Other languages
Chinese (zh)
Inventor
楼旭铼
孙旭阳
彭荣梅
韦霆
杨荣
郑召华
俞活龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhihai Chemical Equipment Engineering Co Ltd
Original Assignee
Zhejiang Zhihai Chemical Equipment Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhihai Chemical Equipment Engineering Co Ltd filed Critical Zhejiang Zhihai Chemical Equipment Engineering Co Ltd
Priority to CN201620515609.7U priority Critical patent/CN206008367U/en
Application granted granted Critical
Publication of CN206008367U publication Critical patent/CN206008367U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices And Processes Conducted In The Presence Of Fluids And Solid Particles (AREA)

Abstract

A kind of absorber filler automates filling system, it mainly includes the connection flexible pipe that a lift suction pump and two sections are connected in lift suction pump inlet and outlet, and constitute filler filling passage, the filler entrance point configuration of the first connection flexible pipe for drawing pump inlet connection in sizing vat to be loaded or filler storing place, the second connection flexible pipe of the absorption pump discharge connection be a leading portion can length adjustment, the filler port of export can load the Telescopic flexible pipe that mouth is stretched into from above tower body equipment;Mouth is loaded above described tower body equipment at least provided with symmetrical four, the second connection flexible pipe is sequentially inserted into filling mouth according to the filling of right-angled intersection respectively, and during filling, the second connection flexible pipe gradually tapers up filling from the bottom up;It has simple structure, safe and reliable, rationally efficiently, can effectively prevent filler abrasion, fragmentation, it is to avoid filler loads inequality the features such as cause absorber internals to be damaged.

Description

Absorber filler automates filling system
Technical field
The utility model relates to a kind of absorber filler automates filling system, it is adaptable in including air separation plant Absorber etc. all need granular pattern filler load tankage, belong to the filling technical field of absorber filler.
Background technology
Absorber is equipped with the equipment that absorber filler realizes gas-solid absorption and desorption, is used for cold in space division system But air absorbs the excessive gas such as water and carbon dioxide;Absorber is made up of tower body equipment and filler, is filled out as a kind of packed tower Material needs to be loaded after factory's installation again in tower body equipment, and the filling speed that frequently can lead to filler this when is delayed Slowly, there is situations such as loading uneven.
Generally, tower body device height is higher, and the filling mouth platform of filler is less, and conventional filler can go out when loading Existing filler filling efficiency is low, time-consuming, takes the phenomenon such as artificial.Filler wherein in tower body equipment loads speed height can direct shadow Ring the economy to the operation of tower body equipment.In the prior art, the filling of filler needs numerous workmans, needs crane, forklift, The equipment such as transport vehicle, can also load speed because of inside even from weather sometimes;The filler of one tower body equipment is loaded and is often needed Take two weeks, one month even more long.This when, the filling speed of filler can lowly cause the driving of new plant items to be entered Degree, and then affect its economy.
In addition, in prior art, the filler of tower body equipment loads harmony and is also required to artificial assurance, the filler of tower body equipment Load the unbalanced destruction that can cause tower body internals even to fail.Absorber higher, inequality of the filler during filling of height Weighing apparatus can cause pressure differential occur, and the internals of tower body equipment are when subject pressure differential, it may appear that damaged even damage completely Possibility.Such case forbids appearance in the design, operation of tower body equipment.
Content of the invention
The purpose of this utility model is to overcome the shortcomings of that prior art is present, and a kind of simple structure is provided, safety can Lean on, time saving and energy saving, rationally efficiently, can effectively prevent filler from when loading, producing lack of uniformity, and because of tower caused by lack of uniformity Part is damaged in vivo, can effectively improve the speed of filler filling so as to the absorber filler for lifting tower body equipment performance driving economy is automatic Change filling system.
The purpose of this utility model is by following technical solution completing:A kind of absorber filler automation loads system System, it mainly includes the connection flexible pipe that a lift suction pump and two sections are connected in lift suction pump inlet and outlet, and constitutes filler Passage is loaded, the filler entrance point configuration of the first connection flexible pipe of the absorption pump inlet connection in sizing vat to be loaded or is filled out Material storing place, the second connection flexible pipe of absorption pump discharge connection be a leading portion can length adjustment, the filler port of export can be from tower The Telescopic flexible pipe that mouth is stretched into is loaded above body equipment.
As preferred:Mouth is loaded above described tower body equipment at least provided with symmetrical four, and second connection is soft Pipe is sequentially inserted into filling mouth according to the filling of right-angled intersection respectively, and during filling, and the second connection flexible pipe is from lower past On gradually taper up filling.
Adjustable flexible pipe described in the utility model can be determined according to absorber height or bed stuffing height, reaching Packing layer bottom is defined;The adjustable purpose of hose length is to prevent filler from running down into the meeting of packing layer bottom in certain altitude Damage filler physical characteristic;Prevent flexible pipe buried after filler filling simultaneously;It has simple structure, safe and reliable, reasonable Efficiently, filler abrasion, fragmentation effectively can be prevented, it is to avoid the features such as filler filling inequality causes absorber internals to be damaged.
Description of the drawings
Fig. 1 is the structural representation that absorber filler described in the utility model automates filling system.
Fig. 2 is the filling mouth position view that absorber described in the utility model loads automated system.
Specific embodiment
Detailed introduction is done to the utility model below in conjunction with accompanying drawing:Shown in Fig. 1, a kind of absorber filler automation is filled out Dress system, it mainly include the connection flexible pipe 2,3 that a lift suction pump 1 and two sections are connected in lift suction pump inlet and outlet, and Constitute filler and load passage, the filler entrance point of the first connection flexible pipe 2 of the absorption pump inlet connection is configured to be loaded Sizing vat 4 or filler storing place, the second connection flexible pipe 3 of the absorption pump discharge connection can length adjustment, filler for a leading portion The port of export can load the Telescopic flexible pipe that mouth 5 is stretched into from above tower body equipment.
In conjunction with mouth 5 shown in Fig. 2, is loaded above described tower body equipment at least provided with symmetrical four, described second connects Connect flexible pipe 3 filling mouth 5 is sequentially inserted into according to the filling of right-angled intersection respectively, and during filling, the second connection flexible pipe Filling is gradually tapered up from the bottom up.
Filling flexible pipe described in the utility model is corresponding respectively to load mouth accordingly, and filler flexible pipe is at the top of tankage Position arranges switch, is also provided with switching in ground location;When loading beginning, the filler flexible pipe in adsorber vessels keeps reaching filling out The length of bed of material bottom, slowly extracts flexible pipe out then as the operation of the progress of filling, keeps the outlet for loading flexible pipe in filler Near surface.
In conjunction with shown in Fig. 2, filling order will be loaded according to uniform requirement is installed, and load the principle of mouth right-angled intersection.Fill out During dress, D1 mouths are loaded first, then keep the closing of remaining filling mouth switch, after loading quantitative filler, close opening for D1 mouths Close, then open D3 mouths switch, quantitative filler is loaded to D3 mouths then.D1 mouths, D2 have been loaded according to the order of right-angled intersection Mouth, D3 mouths, D4 mouths.At this moment a partial circulating is completed.Filling is continued cycling through with this partial circulating.
Shown in figure, loading mouth has 4.Also load according to right-angled intersection order when loading when mouth is not 4.Even A filling mouth needs to load two kinds, multiple different fillers sometimes, also will load according to right-angled intersection order.

Claims (2)

1. a kind of absorber filler automates filling system, it mainly include a lift suction pump and two sections be connected to lift suction pump and enter Connection flexible pipe on mouth and outlet, and constitute filler filling passage, it is characterised in that the first of the absorption pump inlet connection connects The filler entrance point configuration of flexible pipe is connect in sizing vat to be loaded or filler storing place, the second company of the absorption pump discharge connection Connect flexible pipe be a leading portion can length adjustment, the filler port of export can load the Telescopic flexible pipe that mouth is stretched into from above tower body equipment.
2. absorber filler according to claim 1 automates filling system, it is characterised in that on described tower body equipment Face loads mouth at least provided with symmetrical four, and the second connection flexible pipe is sequentially inserted into and fills out according to the filling of right-angled intersection respectively Dress mouth, and during filling, the second connection flexible pipe gradually tapers up filling from the bottom up.
CN201620515609.7U 2016-05-31 2016-05-31 Absorber filler automates filling system Expired - Fee Related CN206008367U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620515609.7U CN206008367U (en) 2016-05-31 2016-05-31 Absorber filler automates filling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620515609.7U CN206008367U (en) 2016-05-31 2016-05-31 Absorber filler automates filling system

Publications (1)

Publication Number Publication Date
CN206008367U true CN206008367U (en) 2017-03-15

Family

ID=58241360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620515609.7U Expired - Fee Related CN206008367U (en) 2016-05-31 2016-05-31 Absorber filler automates filling system

Country Status (1)

Country Link
CN (1) CN206008367U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105920971A (en) * 2016-05-31 2016-09-07 浙江智海化工设备工程有限公司 Automatic filling system for adsorber packing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105920971A (en) * 2016-05-31 2016-09-07 浙江智海化工设备工程有限公司 Automatic filling system for adsorber packing

Similar Documents

Publication Publication Date Title
CN205383430U (en) Aerating device is transported to vertical gas cylinder
CN203743819U (en) Underground storage tank for LNG (Liquefied Natural Gas) filling station
CN206008367U (en) Absorber filler automates filling system
CN206290281U (en) A kind of mine gas extraction pipe negative pressure automatic drainage device
CN103668868B (en) A kind of gimbal salt solution filling apparatus
CN103448598A (en) Powder tanker using compressed gas to assist in gravitational closed unloading
CN206969402U (en) Hydrochloric acid tank exhaust, anti-negative pressure and entrucking acid gas absorb control system
CN103738905B (en) Ultralow temperature loading arm structure with anti-overflowing pipeline
CN103086095A (en) System and method for powder transportation
CN209185591U (en) A kind of grain depot nitrogen intelligently fills ring Air-conditioning system
CN205916783U (en) Pressure release dust absorption powder jar that concrete mixing plant used
CN210977585U (en) Mine drop shaft mouth safety device
CN205991210U (en) A kind of deadweight safety valve
CN206028085U (en) Bucket is glued to injecting glue machine
CN104303725A (en) Flow equalization and transverse penetration type ventilated drying granary
CN204944762U (en) PCCP steel cylinder sealing hydrostatic test machine
CN107950210A (en) A kind of gas deinsectization grain storage device
CN105920971A (en) Automatic filling system for adsorber packing
CN203767995U (en) Caprolactam tank lorry unloading device
CN206886767U (en) A kind of silicon chip processes EDI water circulation systems
CN208650062U (en) A kind of automation pile dusting machine feeding device
CN105775793A (en) Bulk grain container loading machine
CN206723811U (en) A kind of liquid nitrogen container
CN206358687U (en) A kind of liquid tank insurance system
CN210564421U (en) Positive pressure pneumatic rock debris closed transmission device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315

Termination date: 20210531

CF01 Termination of patent right due to non-payment of annual fee