CN206004840U - Unmanned plane inspection command system after a kind of reservoir dam calamity - Google Patents

Unmanned plane inspection command system after a kind of reservoir dam calamity Download PDF

Info

Publication number
CN206004840U
CN206004840U CN201621076487.2U CN201621076487U CN206004840U CN 206004840 U CN206004840 U CN 206004840U CN 201621076487 U CN201621076487 U CN 201621076487U CN 206004840 U CN206004840 U CN 206004840U
Authority
CN
China
Prior art keywords
conference
consultation
unmanned plane
decision
making
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621076487.2U
Other languages
Chinese (zh)
Inventor
杨阳
何勇军
范光亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority to CN201621076487.2U priority Critical patent/CN206004840U/en
Application granted granted Critical
Publication of CN206004840U publication Critical patent/CN206004840U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Alarm Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This utility model is related to unmanned plane inspection command system after a kind of reservoir dam calamity, holds a conference or consultation central station, client of remotely holding a conference or consultation including unmanned plane, wireless transport module, ground signal relay station, decision-making;Unmanned plane connects ground signal relay station by wireless transport module;Ground signal relay station connects decision-making by GPRS mobile network and holds a conference or consultation central station;Client of remotely holding a conference or consultation is held a conference or consultation central station by Internet connection decision-making;Unmanned plane is used for gathering disaster area the condition of a disaster information after reservoir dam calamity, by wireless transport module by the condition of a disaster information transfer to ground signal relay station;The condition of a disaster information transfer is aggregated into decision-making by GPRS mobile network and holds a conference or consultation central station by ground signal relay station;Disaster decision-making and research worker by remotely hold a conference or consultation client and decision-making hold a conference or consultation central station disaster assistance personnel carry out calamity after emergency management and rescue decision-making hold a conference or consultation, realize inspection commander after reservoir dam calamity.

Description

Unmanned plane inspection command system after a kind of reservoir dam calamity
Technical field
This utility model is related to mitigation rescue field after reservoir dam calamity, and unmanned plane inspection particularly after reservoir dam calamity refers to Wave system.
Background technology
China's water storage and conservation enriches, but region distribution is uneven.In order to solve the demand to water resource, domestic built big Amount reservoir dam engineering.But reservoir dam is while playing benefit, also to constituting potential risk in the neighbourhood.From 1954 So far, China has more than 3500 seat reservoir dam break accidents, and many dam-break accidents cause serious human loss.Due to reservoir dam Often result in large area region after calamity to flood, traffic damage, power communication etc. are interrupted, existing emergency management and rescue mode is difficult to timely depth Enter disaster area, also the condition of a disaster information cannot be reported in time simultaneously, the development of impact rescue works.
In order to be able to the timely loss controlling reservoir dam accident to cause, effectively organize and speedily carry out rescue work and the disaster relief, prevent Only disaster expands and stretches.Using unmanned plane, is patrolled in the air in devastated, and by power autonomous by the condition of a disaster information and When report and collect, to assist Post disaster relief decision-making, form unmanned plane after the strong reservoir dam calamity of a set of high degree of automation, performance Inspection command system, accelerates the efficiency of Post disaster relief work, it is to avoid bigger consequential loss.
Content of the invention
The purpose of this utility model is to provide unmanned plane inspection command system after a kind of reservoir dam calamity, realizes reservoir big The quick purpose patrolled and assist rescue command decision-making after dam calamity.
For solving above-mentioned technical problem, this utility model be employed technical scheme comprise that:Unmanned after a kind of reservoir dam calamity Machine is patrolled command system, holds a conference or consultation central station, client of remotely holding a conference or consultation including unmanned plane, ground signal relay station, decision-making;Described Unmanned plane connects ground signal relay station by wireless network;Described ground signal relay station is connected by GPRS mobile network Decision-making is held a conference or consultation central station;Described client of remotely holding a conference or consultation is held a conference or consultation central station by Internet connection decision-making;Described unmanned plane For gathering the condition of a disaster information in disaster area after reservoir dam calamity, by wireless transport module, the condition of a disaster information transfer to ground signal is relayed Stand;The condition of a disaster information transfer is aggregated into decision-making by GPRS mobile network and holds a conference or consultation central station by described ground signal relay station;Calamity Evil decision-making and research worker are passed through described remotely to hold a conference or consultation client and the hold a conference or consultation disaster assistance personnel of central station of decision-making carry out calamity Emergency management and rescue decision-making afterwards is held a conference or consultation, and realizes inspection commander after reservoir dam calamity.
Wherein, unmanned plane includes the body of unmanned plane, video capture device, wireless network module, power supply.Unmanned plane carries It is capable of the video capture device of 360 degree of shootings, and video information is sent to terrestrial relay station by wireless network module.Unmanned Electromechanical source is high-capacity lithium battery, provides unmanned plane during flying, the energy of video acquisition transmission.
Ground signal relay station includes data management module, GPRS mobile network's module, wireless network module, power supply, sends out Motor.Data management module is used for unmanned plane is controlled;Wireless network module is used for receiving the video letter that unmanned plane is beamed back Breath;GPRS mobile network's module is used for sending video information and holds a conference or consultation central station to decision-making;Electromotor is used for ground signal relaying Stand and unmanned plane power source charges.
Decision-making central station of holding a conference or consultation includes data sink, data storage device, data presentation device, communication device.Number Receive, according to reception device, the information that ground signal relay station and client of remotely holding a conference or consultation send, and store information in data storage In device;Data presentation device is used for showing the condition of a disaster information and decision-making exchange of information of holding a conference or consultation;Communication device is used for and remotely holds a conference or consultation Client carries out communication of holding a conference or consultation.
Client of remotely holding a conference or consultation comprises mobile phone, notebook computer, desktop computer, mobile terminal, has shooting and call function, And the Internet can be linked, for the communication for information of disaster relief expert, disaster management department.
The beneficial effects of the utility model are:
Using unmanned plane, is patrolled in the air in devastated, do not caused to be affected by disaster area traffic damage, can be timely The disaster area of acquisition on a large scale the condition of a disaster;Provide Large Copacity portable power source and electromotor for oneself, do not interrupted etc. causing by disaster area power communication Impact;By multiple wireless transmission the condition of a disaster information it is achieved that quickly the collecting of the condition of a disaster information.Set up during decision-making holds a conference or consultation Center station and client of remotely holding a conference or consultation, improve the communication for information efficiency of disaster relief expert, disaster management department, accelerate Post disaster relief The efficiency of work, it is to avoid bigger consequential loss.
Brief description
Fig. 1 is this utility model system structure relation schematic diagram.
Fig. 2 is this utility model one example structure relation schematic diagram.
Specific embodiment
Below in conjunction with accompanying drawing, principle of the present utility model and feature are further described.
As shown in figure 1, this utility model includes some set unmanned planes and ground signal relay station, a decision-making are held a conference or consultation center Stand, some sets are remotely held a conference or consultation client.Some set unmanned planes and ground signal relay station collection disaster area diverse location the condition of a disaster information, Transmission is aggregated into decision-making and holds a conference or consultation central station;Some sets client of remotely holding a conference or consultation helps some disaster relief experts, disaster management department Carry out communication for information with decision-making central station of holding a conference or consultation, realize decision-making and hold a conference or consultation, to command rescue and relief work.
As shown in Fig. 2 arranging demand according to disaster surveillance, realize prison using some set unmanned planes and ground signal relay station Survey, including being arranged in reservoir dam upper river, 2 sets of unmanned planes of near reservoir and a set of ground signal relay station;On dam The a set of unmanned plane of empty arrangement and a set of ground signal relay station;A set of unmanned plane and a set of ground letter are arranged in dam downstream flooding area Number relay station.Upper river, the reservoir unmanned plane collection the condition of a disaster information such as rainfall and reservoir level, share a set of ground signal relaying Stand;Dam overhead unmanned plane collection Dam Crack and dam break the condition of a disaster information;Downstream flooding area unmanned plane collection submergence ratio, flood The condition of a disaster information such as process.
The condition of a disaster information transfer to decision-making is held a conference or consultation central station by unmanned plane by ground signal relay station;Mobile phone and removable computer Connect decision-making as client of remotely holding a conference or consultation to hold a conference or consultation central station, be implemented in meeting after the long-range calamity of disaster relief expert, disaster management department Business's Disaster relief countermeasure function.
Wherein, unmanned plane lithium battery is not less than the high-performance lithium battery of 40000mAh it is ensured that being used for multiple times for capacity(It is more than 300 charge and discharge cycles)Afterwards, active volume is not less than 85%.
Consider the portability of electromotor and fuel oil can availability, electromotor adopts 10kw double cylinder diesel electromotor(Single Phase 220V), often 2 electromotors of set ground signal relay station outfit, wherein one is standby.
Data storage device adopts Large Copacity 10T high speed hard-disk, for the real-time the condition of a disaster letter preserving and reading multiple places Breath.
The Internet uplink and downlink network speed is not less than 4M/s, to guarantee the fluency of real-time video and call.
Above-described embodiment be this utility model preferably embodiment, but embodiment of the present utility model be not subject to above-mentioned The restriction of embodiment, other any without departing from the change made under spirit of the present utility model and principle, modify, replace Generation, combination, simplification, all should be equivalent substitute mode, are included within protection domain of the present utility model.

Claims (6)

1. after a kind of reservoir dam calamity unmanned plane inspection command system it is characterised in that:Including unmanned plane, ground signal relaying Stand, decision-making is held a conference or consultation central station, client of remotely holding a conference or consultation;Described unmanned plane connects ground signal relay station by wireless network; Described ground signal relay station connects decision-making by GPRS mobile network and holds a conference or consultation central station;Described client of remotely holding a conference or consultation is led to Cross Internet connection decision-making to hold a conference or consultation central station;Described unmanned plane is used for gathering disaster area the condition of a disaster information after reservoir dam calamity, passes through Wireless transport module is by the condition of a disaster information transfer to ground signal relay station;Described ground signal relay station passes through GPRS mobile network The condition of a disaster information transfer is aggregated into decision-making and holds a conference or consultation central station by network;Disaster decision-making and research worker pass through the described client that remotely holds a conference or consultation The hold a conference or consultation disaster assistance personnel of central station carry out emergency management and rescue decision-making after calamity and hold a conference or consultation for end and decision-making, realize inspection after reservoir dam calamity Commander.
2. after a kind of reservoir dam calamity according to claim 1 unmanned plane inspection command system it is characterised in that described Unmanned plane includes the body of unmanned plane, video capture device, wireless network module, power supply.
3. after a kind of reservoir dam calamity according to claim 2 unmanned plane inspection command system it is characterised in that described Power supply is high-capacity lithium battery.
4. after a kind of reservoir dam calamity according to claim 1 unmanned plane inspection command system it is characterised in that described Ground signal relay station includes data management module, GPRS mobile network's module, wireless network module, power supply, electromotor.
5. after a kind of reservoir dam calamity according to claim 1 unmanned plane inspection command system it is characterised in that described Decision-making central station of holding a conference or consultation includes data sink, data storage device, data presentation device, communication device.
6. after a kind of reservoir dam calamity according to claim 1 unmanned plane inspection command system it is characterised in that described Client of remotely holding a conference or consultation comprises mobile phone, notebook computer, desktop computer, mobile terminal, has shooting and call function, and can link The Internet.
CN201621076487.2U 2016-09-26 2016-09-26 Unmanned plane inspection command system after a kind of reservoir dam calamity Active CN206004840U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621076487.2U CN206004840U (en) 2016-09-26 2016-09-26 Unmanned plane inspection command system after a kind of reservoir dam calamity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621076487.2U CN206004840U (en) 2016-09-26 2016-09-26 Unmanned plane inspection command system after a kind of reservoir dam calamity

Publications (1)

Publication Number Publication Date
CN206004840U true CN206004840U (en) 2017-03-08

Family

ID=58193743

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621076487.2U Active CN206004840U (en) 2016-09-26 2016-09-26 Unmanned plane inspection command system after a kind of reservoir dam calamity

Country Status (1)

Country Link
CN (1) CN206004840U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107727239A (en) * 2017-10-20 2018-02-23 江苏筑升土木工程科技有限公司 A kind of the dam leakage method of telemetering and system based on unmanned plane
WO2019047502A1 (en) * 2017-09-08 2019-03-14 深圳市道通智能航空技术有限公司 Unmanned aerial vehicle control system and realization method, ground control device and relay station
CN112556782A (en) * 2020-12-04 2021-03-26 四川华能太平驿水电有限责任公司 Water diversion type power station reservoir water level measuring device, water level calculating method and system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019047502A1 (en) * 2017-09-08 2019-03-14 深圳市道通智能航空技术有限公司 Unmanned aerial vehicle control system and realization method, ground control device and relay station
US11454989B2 (en) 2017-09-08 2022-09-27 Autel Robotics Co., Ltd. Unmanned aerial vehicle control system and implementation method therefor, ground control device and relay station
CN107727239A (en) * 2017-10-20 2018-02-23 江苏筑升土木工程科技有限公司 A kind of the dam leakage method of telemetering and system based on unmanned plane
CN112556782A (en) * 2020-12-04 2021-03-26 四川华能太平驿水电有限责任公司 Water diversion type power station reservoir water level measuring device, water level calculating method and system

Similar Documents

Publication Publication Date Title
CN206004840U (en) Unmanned plane inspection command system after a kind of reservoir dam calamity
CN108011948A (en) A kind of industrial equipment integrated monitoring system based on edge calculations
CN204859417U (en) Unmanned aerial vehicle ground satellite station
CN101753743A (en) Major accident mobile monitoring and commanding platform system and working method thereof
CN107727239A (en) A kind of the dam leakage method of telemetering and system based on unmanned plane
CN105083520A (en) Method for bringing mobile base station into stratosphere by using hot-air balloon to restore communication
CN103347176A (en) Production field real-time video and audio remote monitoring system
CN208782840U (en) A kind of safe and reliable shaft tower data information transfer system
CN206629279U (en) A kind of mobile cruising inspection system applied to pipe gallery
CN203289576U (en) Portable 3g wireless solar energy monitoring system
CN105592305A (en) Three-dimensional video emergency communication system based on multi-rotor unmanned plane
CN212258961U (en) Super-fusion satellite communication command system
CN105049484A (en) Emergency disaster rescue intelligent individual soldier system
CN203554591U (en) Real-time audio-video remote monitoring system for production site
CN106802580A (en) A kind of colleges and universities' intelligent management system
CN210014802U (en) Well lid monitoring system
CN205861128U (en) A kind of energy mix system integrated-type machine room fuel tank volume read-out measuring equipment
CN105654751A (en) Charging pile and intelligent traffic system
CN203535463U (en) Mine emergency command communication and management system
CN205384717U (en) Earthquake forecasting of school circuit
CN203457243U (en) Portable remote video conference command system
CN203562085U (en) Agriculture outdoor acquirer
CN202304930U (en) Water level monitoring device
CN207460371U (en) Field image monitoring device
CN219834393U (en) Wind farm Mesh ad hoc network mobile communication device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant