CN205990755U - A kind of masonry panel no scaffold eye constructing device - Google Patents

A kind of masonry panel no scaffold eye constructing device Download PDF

Info

Publication number
CN205990755U
CN205990755U CN201621015215.1U CN201621015215U CN205990755U CN 205990755 U CN205990755 U CN 205990755U CN 201621015215 U CN201621015215 U CN 201621015215U CN 205990755 U CN205990755 U CN 205990755U
Authority
CN
China
Prior art keywords
scaffold
eye
constructing device
masonry panel
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621015215.1U
Other languages
Chinese (zh)
Inventor
范磊
井吉成
王守民
郭金伦
刘桂华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO1 Electric Power Construction Co Ltd filed Critical SEPCO1 Electric Power Construction Co Ltd
Priority to CN201621015215.1U priority Critical patent/CN205990755U/en
Application granted granted Critical
Publication of CN205990755U publication Critical patent/CN205990755U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of masonry panel no scaffold eye constructing device, it is characterized in that, it includes scaffold tubes and support, described support is T-shaped structure the end being fixed on scaffold tubes, described is placed between the vertical mortar joint of body of wall and horizontal mortar joint, and described scaffold tubes ride upon the both sides of body of wall.Described support includes vertically disposed transverse slat and riser, and transverse slat is welded and fixed with riser.Described support is welded and fixed with scaffold tubes and is connected.The end face of described scaffold tubes is provided with slot, described is placed in slot, and is provided with bolt between described support and scaffold tubes.Some grooves are respectively equipped with the upper and lower surface of described transverse slat.Some grooves are respectively equipped with the left and right surface of described riser.A kind of masonry panel no scaffold eye constructing device that this utility model provides, T-shaped propping up is placed on the appearance on the one hand avoiding foot trick between vertical mortar joint and horizontal mortar joint, on the other hand avoids secondary benefit eye.

Description

A kind of masonry panel no scaffold eye constructing device
Technical field
This utility model is related to building wall technical field, specifically a kind of masonry panel no scaffold eye construction dress Put.
Background technology
During building wall, need to set up non-bearing scaffold, generally for double-pole scaffold, erection scheme is usually Vertical pole's span 1500mm × 1500mm, step pitch 1800mm, add the connecting elements with body of wall under 2~3 step pitches, referred to as connect wall Part, reinforces scaffold stability in the large, and existing wall-connecting piece technology is that frame pipe is passed through body of wall, in body of wall other side, uses little horizontal stroke Bar or fastener pin frame pipe, double frame and body of wall are linked to be entirety, stablize double frame.Under this mode, existing wall-connecting piece skill Art makes body of wall leave scaffold eye, finally also needs to carry out scaffold eye closure, secondary construction, increased workload, and for staying The scaffold eye closure put on body of wall is very loaded down with trivial details, in the case of such as meeting water, holds at scaffold eye after wall plastering molding Easily occur dry and cracked.
Utility model content
The purpose of this utility model is to provide a kind of masonry panel no scaffold eye constructing device, for solving to use frame Pipe carries out easily leaving the problem of putlog hole during building wall.
The technical scheme in the invention for solving the technical problem is:A kind of no scaffold eye construction of masonry panel Device, is characterized in that, it includes scaffold tubes and support, and described support is T-shaped structure the end being fixed on scaffold tubes, described Prop up and be placed between the vertical mortar joint of body of wall and horizontal mortar joint, described scaffold tubes ride upon the both sides of body of wall.
Further, described support includes vertically disposed transverse slat and riser, and transverse slat is welded and fixed with riser.
Further, described support is welded and fixed with scaffold tubes and is connected.
Further, the end face of described scaffold tubes is provided with slot, described is placed in slot, and in described support It is provided with bolt and scaffold tubes between.
Further, some grooves are respectively equipped with the upper and lower surface of described transverse slat.
Further, some grooves are respectively equipped with the left and right surface of described riser.
Further, described groove is arc-shaped slot.
The beneficial effects of the utility model are:A kind of masonry panel that this utility model provides no scaffold eye construction dress Put, T-shaped propping up is placed on the appearance on the one hand avoiding foot trick between vertical mortar joint and horizontal mortar joint, on the other hand Avoid secondary benefit eye.
Brief description
Fig. 1 is existing schematic diagram of building a wall;
The schematic diagram that Fig. 2 builds a wall for this utility model;
Fig. 3 is the front schematic view of support;
Fig. 4 is the leftschematic diagram of support;
Fig. 5 is the schematic diagram arranging groove on support;
Fig. 6 is one of connection diagram of support and scaffold tubes;
Fig. 7 is the two of support and the connection diagram of scaffold tubes;
Fig. 8 is the side view of Fig. 7;
In figure:1 body of wall, 2 scaffold tubes, 3 supports, 31 risers, 32 transverse slats, 4 grooves, 5 bolts.
Specific embodiment
As shown in figure 1, being the schematic diagram built a wall in prior art, it is respectively provided with scaffold tubes 2 in the both sides of body of wall 1, vertically Scaffold tubes and horizontal scaffold tubes constitute netted and horizontal scaffold tubes and be through in body of wall.
As shown in Fig. 2 to Fig. 8, it is schematic diagram of the present utility model, mainly include scaffold tubes 2 and support 3, such as Fig. 3, Fig. 4 Shown, support 3 is " T " character form structure, is mainly made up of riser 31 and transverse slat 32, and riser and transverse slat are the metallic plate of rectangle, Riser is vertically arranged with transverse slat and is welded and fixed.As shown in fig. 6, scaffold tubes are welded and fixed with support being connected, and scaffold tubes with The welding position of frame is located at the intersection of riser and transverse slat.In addition, can also be solid by bolt between support and scaffold tubes Fixed connection.Now, the end in scaffold tubes be provided with hold support insertion slot, as shown in Figure 7, Figure 8, then scaffold tubes with Installation bolt 5 between frame.Three slots are set in scaffold tubes end, the transverse slat of support and riser are respectively placed in three slots In, when support extend into the bottommost of slot, between scaffold tubes and transverse slat, installation bolt can achieve support and scaffold tubes Be relatively fixed.
As shown in Fig. 2 when using, scaffold tubes being built in the side of body of wall 1, now placing a stent into adjacent vertical ash Seam and horizontal mortar joint intersection, can not put mortar in support lay down location, reach the convenient purpose of dismounting, and this scheme can avoid building Foot trick is left on walling body, in turn ensure that scaffold tubes form wall-connecting piece with body of wall, stablize double frame, avoid secondary benefit simultaneously Foot trick hole.
For avoiding the frictional force between scaffold tubes and body of wall excessive, support is caused to be difficult to extract from body of wall, as Fig. 5 institute Show, groove 4 be provided with support, groove is arranged on the left and right two sides of riser, the upper and lower surface of transverse slat, groove is arc-shaped slot, The setting of groove makes support and the contact area of body of wall reduce, and now the frictional force between support and body of wall is less, can be light Loose extracts out support from body of wall.The groove of the left and right sides on riser mutually staggers.

Claims (7)

1. a kind of masonry panel no scaffold eye constructing device, is characterized in that, it includes scaffold tubes and support, and described support is T Character form structure is simultaneously fixed on the end of scaffold tubes, and described is placed between the vertical mortar joint of body of wall and horizontal mortar joint, described foot Handss pipe rides upon the both sides of body of wall.
2. a kind of masonry panel according to claim 1 no scaffold eye constructing device, is characterized in that, described support includes Vertically disposed transverse slat and riser, and transverse slat is welded and fixed with riser.
3. a kind of masonry panel according to claim 1 no scaffold eye constructing device, is characterized in that, described support and foot Handss sealing of tube is fixedly connected.
4. a kind of masonry panel according to claim 1 no scaffold eye constructing device, is characterized in that, in described scaffold tubes End face be provided with slot, described is placed in slot, and is provided with bolt between described support and scaffold tubes.
5. a kind of masonry panel according to claim 2 no scaffold eye constructing device, is characterized in that, in described transverse slat Some grooves are respectively equipped with upper and lower surface.
6. a kind of masonry panel according to claim 2 no scaffold eye constructing device, is characterized in that, in described riser Some grooves are respectively equipped with the surface of left and right.
7. a kind of no scaffold eye constructing device of the masonry panel according to claim 5 or 6, is characterized in that, described groove For arc-shaped slot.
CN201621015215.1U 2016-08-31 2016-08-31 A kind of masonry panel no scaffold eye constructing device Active CN205990755U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621015215.1U CN205990755U (en) 2016-08-31 2016-08-31 A kind of masonry panel no scaffold eye constructing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621015215.1U CN205990755U (en) 2016-08-31 2016-08-31 A kind of masonry panel no scaffold eye constructing device

Publications (1)

Publication Number Publication Date
CN205990755U true CN205990755U (en) 2017-03-01

Family

ID=58105359

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621015215.1U Active CN205990755U (en) 2016-08-31 2016-08-31 A kind of masonry panel no scaffold eye constructing device

Country Status (1)

Country Link
CN (1) CN205990755U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457465A (en) * 2018-03-18 2018-08-28 内蒙古华立建设工程有限公司 It builds by laying bricks or stones and uses inner wall scaffold and its method of administration

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457465A (en) * 2018-03-18 2018-08-28 内蒙古华立建设工程有限公司 It builds by laying bricks or stones and uses inner wall scaffold and its method of administration

Similar Documents

Publication Publication Date Title
CN109629810B (en) Closed type overhanging scaffold and construction method
CN205875537U (en) Metal containment system roofing expansion joint resistance to deformation waterproof construction
CN205617420U (en) Building block formula panel reinforced earth retaining wall
CN207419870U (en) A kind of roof boarding deformation joint node apparatus
CN205990755U (en) A kind of masonry panel no scaffold eye constructing device
CN205063032U (en) Wall connection node structure
CN104328875B (en) Guard bar
CN204098219U (en) Bracket steel bar concrete frame connecting pin contact assembled architecture
CN104533092B (en) The construction method of rack roofing furred ceiling
CN204001702U (en) A kind of J-shaped wall plastic formwork
CN205954935U (en) No stand glass curtain wall system
CN207846855U (en) A kind of assembly wallboard
CN203856182U (en) Novel cantilever scaffold structure
CN103334520B (en) A kind of three-dimensional adjustable connecting components device
CN103726575B (en) A kind of prefabricated balcony slab and balcony support and connection structure
CN205829097U (en) A kind of temporary cable hanging hook assembly
CN207392438U (en) A kind of detachable modular small building
CN207633583U (en) A kind of connection structure of prefabricated post and prefabricated partition wall
CN204960118U (en) Big wallboard for building
CN205689897U (en) A kind of detachable cable support
CN205276852U (en) Coupling assembling of expanded metals and scaffold and connect fastener and connect frame thereof
CN104405091B (en) Vertical column for connecting foot plate frame and vertical column and transverse rod connecting piece
CN217353086U (en) Assembled building curtain
CN205894350U (en) Prefabricated formula wall connection structure and utilize this connection structure's prefabricated formula housing construction
CN215331121U (en) Assembled steel construction side fascia system

Legal Events

Date Code Title Description
GR01 Patent grant