CN205938514U CN201620916400.1U CN201620916400U CN205938514U CN 205938514 U CN205938514 U CN 205938514U CN 201620916400 U CN201620916400 U CN 201620916400U CN 205938514 U CN205938514 U CN 205938514U
Authority
CN
China
Prior art keywords
gas
natural gas
pipeline
pressure regulator
smelly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620916400.1U
Other languages
Chinese (zh)
Inventor
袁亮
谭利军
张伟
苏润
范龙
董元龙
苟娜娜
姚明辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi First Tiancheng Engineering Technology Co Ltd
Original Assignee
Shaanxi First Tiancheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi First Tiancheng Engineering Technology Co Ltd filed Critical Shaanxi First Tiancheng Engineering Technology Co Ltd
Priority to CN201620916400.1U priority Critical patent/CN205938514U/en
Application granted granted Critical
Publication of CN205938514U publication Critical patent/CN205938514U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a novel CNG stores up and joins in marriage station relates to natural gas storage and joins in marriage technical field. The natural gas in the natural gas tanks car lets in the trunk line through unloading the gas well, and the voltage regulator in the trunk line is done the pressure of the natural gas and is let in the gas storage pipeline after the decompression is handled, and the natural gas of emitting from the gas storage pipeline is once more through the voltage regulator decompression after overflow the gauge and add and lead to the city gas supply line after smelly, and the atmospheric pressure in the natural gas tanks car diminishes the back and continues to take the remaining natural gas out through the residual air pipe simultaneously, improves conveying efficiency, equipment among the chu peizhan all sets up at the below ground, and area is little, and maintenance cost is low, and in the relatively poor or anti -terrorism region that the situation is tense of the great social security of personnel flow, the chupeizhan of this structure is more hidden, and the gas storage pipeline the lies in underground that keep clear -High voltage, difficult by the discovery with suffer destruction, consequently have apparent safe advantage.

Description

A kind of new type of compression natural gas distribution station
Technical field
This utility model is related to natural gas storage and joins technical field, more particularly to a kind of new type of compression natural gas distribution station.
Background technology
City " rate of gasification " is also the important indicator weighing urban modernization degree.Promote Integration of Urban-rural Areas, be area The key factor of the domain level of economic development, just in time, compressed natural gas is as cleaning energy for iterative method " village leads to combustion gas " engineering Source, is difficult the area radiating, is to solve the problems, such as one of supply important means using CNG gas holder station in pipeline network construction.But such station The operation of point, natural gas belongs to Class A gas hazard medium, and process tool pressure height, pipeline system pressure are high, safe spacing Have high demands, each side code requirement such as security against fire is strict.
CNG, after CNG tank car reaches gas holder station, is discharged into gas cylinder, height by unloading gas sledge by existing CNG gas holder station scheme Pressure gas storage well, if without compressor boost, can store in 20MPa, and band booster compressor pressure store is up to 25MPa highest. Or after reducing pressure by pressure regulator valve, adopt high pressure buried pipeline storing mode to store.Operational phase, by storage CNG through pressure regulation/ Be depressurized to the pressure of user's needs, in mostly generally being pressure 0.4MPa about outbound.Metering before outbound, plus smelly, then pass through pipeline Fed downstream user.
Because CNG belongs to the inflammable medium of high pressure, danger is higher, and such gas holder station major defect on building has:
First, conventional gas storage means include gas cylinder and high-pressure gas storage well, and the former problem is:1. storage facilities is thrown Costly, 2. safe spacing requirement is higher, and ground floor space is big for money, and 3. pressure vessel detection maintenance cost is high, 4. necessary It is arranged on ground.Latter issues are:1. it is mainly pressure vessel detection, maintenance cost height, 2. long construction period, construction quality Have high demands.3. investment cost is high.
2nd, the arrangement such as pressure regulation metering facility, instrument cubicle, discharge column arranges, safe spacing has high demands on the ground, takes up an area face Long-pending big, exhaust stack is higher apart from the requirement of aforementioned station equipment mutual safe spacing, and floor space is also larger.
3rd, because more than process facility and high pressure equipment all ground arranging, line service amount is big, there is operational error Risk;Project area in the public security risk that stability maintenance situation is severeer or population mobility is big, easily cause saboteur to pay close attention to And destruction, flammability hazard medium, after wrecking, power, impact are larger, and social harm is huge.
Utility model content
This utility model embodiment provides a kind of new type of compression natural gas distribution station, can solve presence in prior art Problem.
A kind of new type of compression natural gas distribution station, including unload gas well, main pipeline, gas storage pipeline, metering plus smelly room, residual air pipe And heater, described unload gas well mouth be located at ground, be internally provided with unloading trachea, described unload trachea one end pass through high-pressure ball valve with First unloads soft pipe connection, and the described trachea other end that unloads is connected with described main pipeline, and described main pipeline is sequentially installed with first Quick action emergency valve, the first pressure regulator, the second quick action emergency valve and the second pressure regulator;Described heater is also mounted at described main pipeline On, and be located between described first quick action emergency valve and the first pressure regulator, described main pipeline and described gas storage pipeline communication, connection Point is located between described first pressure regulator and the second quick action emergency valve;Basset in described metering plus smelly ceiling portion, described supervisor Road is located in described metering plus smelly room away from described one end unloading trachea, and described main pipeline is located in described metering plus smelly room Part is provided with effusion meter, and described main pipeline is connected with outside network by outlet pipe in described metering plus smelly room;Described Be additionally provided with the smelly tank of storage in metering plus smelly room, the smelly tank of described storage connects with described outlet pipe by pipeline, and connection described store up smelly On the pipeline of tank and outlet pipe, air pump is installed;Described residual air pipe one end and described gas storage pipeline communication, the other end is installed Have second to unload flexible pipe, described residual air pipe is sequentially provided with the 3rd pressure regulator, surge tank and compressor;Described main pipeline, gas storage Pipeline and residual air pipe are respectively positioned on below ground.
It is preferred that also including backup line, described backup line one end is connected with the described trachea that unloads, the other end with described go out Feed channel connect, described backup line is sequentially installed with the 3rd quick action emergency valve, the 4th pressure regulator, the 4th quick action emergency valve and 5th pressure regulator.
It is preferred that described heater is also mounted on described backup line, and it is located at described 3rd quick action emergency valve and the Between four pressure regulators, described backup line also with described gas storage pipeline communication, and connectivity points are located at described 4th pressure regulator and the Between four quick action emergency valves.
It is preferred that described heater is electric heating water-bath heater.
It is preferred that the described length and width unloading gas well is 1 meter, depth is 0.6 meter, and its inwall and bottom all adopt C25 concrete is made, and inner wall surface scribbles the waterproof mortar of 20 millimeters thick;The described gas well mouth that unloads also has well lid, described Well lid is the matchboard of 15 millimeters thick, is surrounded by the aluminium sheet of 1 millimeters thick thereon.
It is preferred that described flow is calculated as Roots type flowmeter.
It is preferred that described metering plus smelly room are reinforced concrete shear wall structure, its side wall and base plate are all using impervious mixed Solidifying soil, seepage-resistant grade P6, the part basseted is made using chromatic steel sandwich plate, and core is rock wool, and the height basseting is 300 millimeters.
It is preferred that having deposited Tetramethylene sulfide in the smelly tank of described storage.
It is preferred that described air pump according to 20 milligrams of every cubic metre of natural gas ratio by the described tetrahydrochysene thiophene storing up in smelly tank Fen is evacuated in described outlet pipe.
A kind of new type of compression natural gas distribution station in this utility model embodiment, the natural gas in natural gas tank car passes through to unload Gas well is passed through main pipeline, and the pressure regulator in main pipeline does to the pressure of natural gas and is passed through gas storage pipeline after reduced pressure treatment, from gas storage In pipeline release natural gas again pass by pressure regulator decompression after through excessively stream gauge and plus smelly after lead to city steam line, simultaneously Pass through residual air pipe to continue to extract remaining natural gas out after the air pressure in natural gas tank car diminishes, improve conevying efficiency, described Equipment in gas holder station is arranged at below ground, and floor space is little, and maintenance cost is low, in the larger social security of flow of personnel relatively Difference or the anti-terrorism region that the situation is tense, the gas holder station of this structure is more hidden, and Keep Clear-High Voltage, and gas storage pipeline is located underground, is difficult It is found and is destroyed, therefore there are significant security advantages.
Brief description
A kind of structure chart of new type of compression natural gas distribution station that Fig. 1 provides for this utility model embodiment.
Description of reference numerals:
100- unloads gas well, and 110- unloads trachea, 120- high-pressure ball valve, and 130- first unloads flexible pipe, 210- main pipeline, 211- One quick action emergency valve, 212- first pressure regulator, 213- second quick action emergency valve, 214- second pressure regulator, 220- backup line, 221- the 3rd quick action emergency valve, 222- the 4th pressure regulator, 223- the 4th quick action emergency valve, 224- the 5th pressure regulator, 300- gas storage Pipeline, 400- metering plus smelly room, 410- effusion meter, 420- outlet pipe, the 430- smelly tank of storage, 440- air pump, 500- residual air pipe, 510- second unloads flexible pipe, 520- the 3rd pressure regulator, 530- surge tank, 540- compressor, 600- heater.
Specific embodiment
Below in conjunction with the accompanying drawings, a specific embodiment of the present utility model is described in detail, it is to be understood that this The protection domain of utility model is not limited by specific embodiment.
With reference to Fig. 1, this utility model embodiment provides a kind of new type of compression natural gas distribution station, including unload gas well 100, Main pipeline 210, backup line 220, gas storage pipeline 300, metering plus smelly room 400, residual air pipe 500 and heater 600.
Described gas well 100 well head that unloads is located at ground, and in the present embodiment, the described length and width unloading gas well 100 is 1 Rice, depth is 0.6 meter, and its inwall and bottom are all made using C25 concrete, and inner wall surface scribbles the Waterproof sand of 20 millimeters thick Slurry;Described gas well 100 well head that unloads also has well lid (not shown), and described well lid is the matchboard of 15 millimeters thick, is surrounded by 1 milli thereon The thick aluminium sheet of rice.Described unload to be provided with inside gas well 100 unload trachea 110, described unload trachea 110 one end pass through high-pressure ball valve 120 with First flexible pipe 130 of unloading connects, and described trachea 110 other end that unloads is connected with described main pipeline 210, on described main pipeline 210 according to Secondary first quick action emergency valve 211, the first pressure regulator 212, the second quick action emergency valve 213 and the second pressure regulator 214 are installed.
Described heater 600 is arranged on described main pipeline 210, and is located at described first quick action emergency valve 211 and first Between pressure regulator 212, described main pipeline 210 is connected with described gas storage pipeline 300, and connectivity points are located at described first pressure regulator 212 With second between quick action emergency valve 213.Basset in described metering plus smelly room 400 top, described main pipeline 210 unloads away from described One end of trachea 110 is located in described metering plus smelly room 400, and described main pipeline 210 is located in described metering plus smelly room 400 Part is provided with effusion meter 410, and described main pipeline 210 passes through outlet pipe 420 and exterior tube in described metering plus smelly room 400 Net connection.
In the present embodiment, described metering plus smelly room 400 are reinforced concrete shear wall structure, and its side wall and base plate are all adopted With water-tight concrete, seepage-resistant grade P6, the part basseted is made using chromatic steel sandwich plate, and core is rock wool, bassets Height be 300 millimeters.Described effusion meter 410 is Roots type flowmeter, and it has, and measuring accuracy is high, range ratio is big, convection cell is disturbed The low feature of dynamic sensitivity.
It is additionally provided with the smelly tank 430 of storage, the smelly tank 430 of described storage passes through pipeline and described escape pipe in described metering plus smelly room 400 Road 420 connects, and is provided with air pump 440 on the pipeline of the connection smelly tank 430 of described storage and outlet pipe 420.Described residual air pipe 500 one end are connected with described gas storage pipeline 300, and the other end is provided with second and unloads flexible pipe 510, on described residual air pipe 500 successively It is provided with the 3rd pressure regulator 520, surge tank 530 and compressor 540.Described main pipeline 210, backup line 220, gas storage pipeline 300 It is respectively positioned on below ground with residual air pipe 500.
In the present embodiment, deposited Tetramethylene sulfide in the smelly tank 430 of described storage.Described air pump 440 is according to described flow The flows of meter 410 detection store up described the Tetramethylene sulfide in smelly tank 430 and are evacuated to according to the ratio of 20 milligrams of every cubic metre of natural gas In described outlet pipe 420.
Described backup line 220 one end is connected with the described trachea 110 that unloads, and the other end is connected with described outlet pipe 420, institute State and the 3rd quick action emergency valve 221, the 4th pressure regulator 222, the 4th quick action emergency valve 223 and are sequentially installed with backup line 220 5th pressure regulator 224.
Described heater 600 is also mounted on described backup line 220, and is located at described 3rd quick action emergency valve 221 He Between 4th pressure regulator 222, described backup line 220 is also connected with described gas storage pipeline 300, and connectivity points are located at the described 4th Between pressure regulator 222 and the 4th quick action emergency valve 223.In the present embodiment, described heater 600 is electric heating heating in water bath Device, so that being higher than 0 degree from the described natural gas temperature discharged trachea 110 of unloading, prevents from freezing valve body.
In sum, a kind of new type of compression natural gas distribution station, the sky in natural gas tank car in this utility model embodiment So gas is passed through main pipeline by unloading gas well, and the pressure regulator in main pipeline does to the pressure of natural gas and is passed through cylinder after reduced pressure treatment Road, from gas storage pipeline release natural gas again pass by pressure regulator decompression after through excessively stream gauge and plus smelly after lead to city supply Pipeline, passes through residual air pipe simultaneously after the air pressure in natural gas tank car diminishes and continues to extract remaining natural gas out, improve transport Efficiency, the equipment in described gas holder station is arranged at below ground, and floor space is little, and maintenance cost is low, larger in flow of personnel Social security is poor or the anti-terrorism region that the situation is tense, and the gas holder station of this structure is more hidden, and Keep Clear-High Voltage gas storage pipeline position In underground, it is difficult to be found and is destroyed, therefore there are significant security advantages.
Only several specific embodiments of the present utility model disclosed above, but, this utility model embodiment not office It is limited to this, the changes that any person skilled in the art can think of all should fall into protection domain of the present utility model.

Claims (9)

1. a kind of new type of compression natural gas distribution station is it is characterised in that include unloading gas well (100), main pipeline (210), cylinder Road (300), metering plus smelly room (400), residual air pipe (500) and heater (600), described gas well (100) well head that unloads is located at ground, Be internally provided with unloading trachea (110), described unload trachea (110) one end and pass through high-pressure ball valve (120) unload flexible pipe (130) with first Connection, described trachea (110) other end that unloads connected with described main pipeline (210), and described main pipeline (210) is sequentially installed with the One quick action emergency valve (211), the first pressure regulator (212), the second quick action emergency valve (213) and the second pressure regulator (214);Described plus Hot device (600) is also mounted on described main pipeline (210), and is located at described first quick action emergency valve (211) and the first pressure regulator (212) between, described main pipeline (210) is connected with described gas storage pipeline (300), and connectivity points are located at described first pressure regulator (212) between and the second quick action emergency valve (213);Basset in described metering plus smelly room (400) top, described main pipeline (210) it is located in described metering plus smelly room (400) away from described one end unloading trachea (110), and described main pipeline (210) is located at Part in described metering plus smelly room (400) is provided with effusion meter (410), and described main pipeline (210) is in described metering plus smelly room (400) connected with outside network by outlet pipe (420) in;It is additionally provided with the smelly tank of storage in described metering plus smelly room (400) (430), described storage smelly tank (430) connect with described outlet pipe (420) by pipeline, and connection described store up smelly tank (430) and Air pump (440) is provided with the pipeline of outlet pipe (420);Described residual air pipe (500) one end and described gas storage pipeline (300) Connection, the other end is provided with second and unloads flexible pipe (510), described residual air pipe (500) is sequentially provided with the 3rd pressure regulator (520), Surge tank (530) and compressor (540);Described main pipeline (210), gas storage pipeline (300) and residual air pipe (500) are respectively positioned on ground Below.
2. compressed natural gas gas holder station as claimed in claim 1 is it is characterised in that also including backup line (220), described standby Connected with the described trachea (110) that unloads with pipeline (220) one end, the other end is connected with described outlet pipe (420), described standby pipe Be sequentially installed with road (220) the 3rd quick action emergency valve (221), the 4th pressure regulator (222), the 4th quick action emergency valve (223) and 5th pressure regulator (224).
3. compressed natural gas gas holder station as claimed in claim 2 is it is characterised in that described heater (600) is also mounted at institute State on backup line (220), and be located between described 3rd quick action emergency valve (221) and the 4th pressure regulator (222), described standby Pipeline (220) is also connected with described gas storage pipeline (300), and connectivity points are urgent positioned at described 4th pressure regulator (222) and the 4th Between stop valve (223).
4. compressed natural gas gas holder station as claimed in claim 3 is it is characterised in that described heater (600) is electric heating water Bath heater.
5. compressed natural gas gas holder station as claimed in claim 1 is it is characterised in that the described length unloading gas well (100) and width Degree is 1 meter, and depth is 0.6 meter, and its inwall and bottom are all made using C25 concrete, and inner wall surface scribbles 20 millimeters thick Waterproof mortar;Described gas well (100) well head that unloads also has well lid, and described well lid is the matchboard of 15 millimeters thick, is surrounded by 1 thereon The aluminium sheet of millimeters thick.
6. compressed natural gas gas holder station as claimed in claim 1 is it is characterised in that described effusion meter (410) is Roots's flow Meter.
7. compressed natural gas gas holder station as claimed in claim 1 is it is characterised in that it is reinforcing bar that described metering adds smelly room (400) , all using water-tight concrete, seepage-resistant grade P6, the part basseted is using color for concrete shear wall structure, its side wall and base plate Steel sandwich board is made, and core is rock wool, and the height basseting is 300 millimeters.
8. compressed natural gas gas holder station as claimed in claim 1 is it is characterised in that deposited four in the smelly tank of described storage (430) Hydrogen thiophene.
9. compressed natural gas gas holder station as claimed in claim 8 is it is characterised in that described air pump (440) is according to every cube Tetramethylene sulfide in the smelly tank of described storage (430) is evacuated in described outlet pipe (420) ratio of 20 milligrams of natural gas of rice.
CN201620916400.1U 2016-08-22 2016-08-22 Novel CNG stores up and joins in marriage station Active CN205938514U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620916400.1U CN205938514U (en) 2016-08-22 2016-08-22 Novel CNG stores up and joins in marriage station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620916400.1U CN205938514U (en) 2016-08-22 2016-08-22 Novel CNG stores up and joins in marriage station

Publications (1)

Publication Number Publication Date
CN205938514U true CN205938514U (en) 2017-02-08

Family

ID=57947936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620916400.1U Active CN205938514U (en) 2016-08-22 2016-08-22 Novel CNG stores up and joins in marriage station

Country Status (1)

Country Link
CN (1) CN205938514U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108799834A (en) * 2018-06-21 2018-11-13 南京国电南自新能源工程技术有限公司 A kind of natural gas tube line control system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108799834A (en) * 2018-06-21 2018-11-13 南京国电南自新能源工程技术有限公司 A kind of natural gas tube line control system

Similar Documents

Publication Publication Date Title
US20020124567A1 (en) Storage of energy producing fluids and process thereof
CN206496185U (en) A kind of removable bank base formula loading system filled for LNG ship oceangoing ship
CN104964159B (en) The method of replacing of ammonia in a kind of liquid ammonia storage tank
CN205938514U (en) Novel CNG stores up and joins in marriage station
CN102705693A (en) High pressure gas storage device of deeply-embedded steel lining structure
CN109316698A (en) A kind of double-hole tunnel two-way subregion relay moisturizing pipeline dry type water fire fighting system
CN109335366B (en) Oversized flexible gas storage and method
CN105889746B (en) A kind of method based on Anhydrite Ore goaf natural gas-storing
CN103423583A (en) High-pressure gas preservation method
CN105927846B (en) LNG field station loading and unloading integrated system and loading and unloading method using same
CN206754793U (en) A kind of double film gas holder caissons
CN210687759U (en) Skid-mounted natural gas hydrate decomposition and aeration device
CN210739957U (en) Hydropower station construction branch tunnel hydrogen storage system
CN204729911U (en) A kind of buried spherical tank group
CN2416338Y (en) Natural gas small-district supplying & storing gas apparatus
CN205742273U (en) A kind of fiberglass pipe gallery
CN201485902U (en) Full-automatic water filling supercharger
CN115467710A (en) System and method for storing energy by utilizing compressed air in scrapped coal mine
CN101429774A (en) Secondary water supply preposition equipment and its control method
CN202546248U (en) Liquefied natural gas box-type filling station
CN209540491U (en) Underground LNG storage tank with thin cushion cap
US6826911B2 (en) Storage of energy producing fluids and process thereof
CN207094180U (en) A kind of LNG filling ships BOG reutilization system
CN213202939U (en) Device for preparing CNG from natural gas hydrate
CN203173949U (en) Explosion-proof septic-tank

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant