CN205934733U - Whole bundle of tensioning device subassembly that clear hole was used is changed to jib - Google Patents

Whole bundle of tensioning device subassembly that clear hole was used is changed to jib Download PDF

Info

Publication number
CN205934733U
CN205934733U CN201620866146.9U CN201620866146U CN205934733U CN 205934733 U CN205934733 U CN 205934733U CN 201620866146 U CN201620866146 U CN 201620866146U CN 205934733 U CN205934733 U CN 205934733U
Authority
CN
China
Prior art keywords
jack
connector
spike
draw
instrument nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620866146.9U
Other languages
Chinese (zh)
Inventor
窦勇芝
韦福堂
曾俊志
黎祖金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIUZHOU OVM ENGINEERING Co Ltd
Original Assignee
LIUZHOU OVM ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIUZHOU OVM ENGINEERING Co Ltd filed Critical LIUZHOU OVM ENGINEERING Co Ltd
Priority to CN201620866146.9U priority Critical patent/CN205934733U/en
Application granted granted Critical
Publication of CN205934733U publication Critical patent/CN205934733U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a whole bundle of tensioning device subassembly that clear hole was used is changed to jib, includes connector, instrument nut I, the screw rod that excels in, spike, stressing jack and instrument nut II, connector both ends head has a round hole respectively, and stressing jack is center hole jack, under the user state, round hole cover in connector upper end is through welding mode fixed connection with it on waiting to draw the anchor slab of steel wire anchor head, and connector lower extreme round hole entangles the screw rod one end of excelling in to be passed through instrument nut I and adopt screw thread connection fixed connection with it, and the spike is installed in underbridge crossbeam bottom surface as stressing jack's counter -force support frame, and stressing jack installs under the spike in the upper end, the screw rod that excels in is locked through backing plate and instrument nut II to the stressing jack lower extreme. When being used for demolising steel wire and the clear hole of the old jib of arched bridge with the the device subassembly, earlier with concrete core drill machine in bridge floor top -down drilling old jib anchor head section extremely, again with the the device unit mount under the bridge floor, its construction operation time is shorter relatively, and is with low costs, safe and reliable.

Description

The whole bundle draw-off gear assembly of suspender replacement borehole cleaning
Technical field
The utility model is related to a kind of bridge construction device, particularly a kind of withdrawing for changing the old suspension rod of arched bridge pre-stressed boom Steel wire and hole cleaning device.
Background technology
Due to past most of suspension rod anticorrosion process using perfusion high-strength cement slurry outsourcing anti-corrosion so that suspender replacement engineering In old suspension rod demolishing process need to carry out cable guide pipe borehole cleaning process.At present, borehole cleaning processes and mainly takes the method for cutting, bore extracting core process. Cut method, using pneumatic pick or air drill, high-strength cement slurry in cable guide pipe is cut, remove old suspension rod steel wire and reach borehole cleaning purpose, it lacks Putting is:Manual work intensity is big, and airborne dust is big, and pneumatic pick or air drill are easily stuck in steel wire with cable guide pipe gap it is impossible to extract, thus affecting Job scheduling;Bore extracting core process, using core drill to high-strength cement slurry in cable guide pipe and steel wire or steel strand wires boring and coring, reaches Borehole cleaning purpose;Shortcoming is:Core drill is easily stuck in steel wire with cable guide pipe gap it is impossible to extract, and affects job scheduling;Core drill simultaneously Head needs grinding, causes the rig proportion of goods damageds big, work efficiency is relatively low, high cost.
Patent publication No. is the application for a patent for invention of CN104746442A, discloses one kind and is used for changing that arched bridge pre-stressed boom is old to be hung The withdrawing steel wire of bar and hole cleaning device assembly and its method removed for old suspension rod, although this application for a patent for invention has manually Operation intensity is little, safe and reliable, the advantage being easy to standardized construction, but the withdrawing steel wire of this application for a patent for invention and hole cleaning device Assembly is single withdrawing device, and the method for employing is by root withdrawing steel wire, finally carries out borehole cleaning, manual work intensity is relatively Height, the construction operation time is relatively long, and construction cost is of a relatively high.
Content of the invention
The purpose of this utility model is:A kind of whole bundle draw-off gear assembly of suspender replacement borehole cleaning is provided, this is filled Put and remove and borehole cleaning for the old suspension rod of arch bridge, its mechanization degree is higher than the application for a patent for invention of CN104746442A, construction Activity duration is relatively short, and construction cost is lower, both economical, safe and reliable, is easy to standardized construction again.
The technical scheme solving the above problems is:A kind of whole bundle draw-off gear assembly of suspender replacement borehole cleaning, its feature It is:This device assembly includes connector, instrument nut I, high-strength bolt, spike, stretch-draw jack and instrument nut II;
Described connector two ends have a circular hole respectively, and described stretch-draw jack is centre-hole jack;
Under use state:Connector upper end circular hole is enclosed within the anchor slab treating drawn steel wire anchor head and passes through welding manner therewith admittedly Fixed connection, connector lower end circular hole entangles high-strength bolt one end and adopts thread connecting mode company fixed thereto by instrument nut I Connect, spike is arranged on bridge sill bottom surface as the counter-force bracing frame of stretch-draw jack, and stretch-draw jack upper end is arranged on support Backing plate is passed through in underfooting, stretch-draw jack lower end and instrument nut II locks high-strength bolt.
Due to taking said structure, the whole bundle draw-off gear assembly of the suspender replacement borehole cleaning of the utility model has following Beneficial effect:
1. process with existing borehole cleaning compared with mainly taking the method for cutting, bore extracting core process, manual work intensity is little, safely may be used Lean on, be easy to standardized construction.
2. the application for a patent for invention with Publication No. CN104746442A《For changing the withdrawing steel of the old suspension rod of arched bridge pre-stressed boom Silk and hole cleaning device assembly and its method removed for old suspension rod》Single withdrawing steel wire device compare, the utility model fill Put assembly to hole from top to bottom to old Hanger Anchor head section in bridge floor first with concrete core drilling rig, recycle hydraulic tensioning very heavy Top tensioning high-strength bolt, the steel wire of the old suspension rod of whole bundle drawing arch bridge or stranded wire anchor head, mechanization degree is higher, during construction operation Between relatively short, construction cost is lower, not only economical but also safe and reliable.
3. the whole bundle draw-off gear assembly of the suspender replacement borehole cleaning of the utility model is used for removing the old suspension rod of arch bridge Steel wire and borehole cleaning method are to be arranged under bridge floor, provide driving force with hydraulic tensioning jack whole bundle draw-off gear assembly, with High-strength bolt is jack tension part;High-strength bolt and the old suspension rod of arch bridge are treated to connect by connector is fixing between withdrawing steel wire anchor head Connect;Therefore, on bridge deck traffic impact less, practicality and the security of construction are more increased.
With reference to the accompanying drawings and examples to the whole bundle draw-off gear assembly of the suspender replacement borehole cleaning of the utility model Technical characteristic is described further.
Brief description
Fig. 1:The structural representation of the whole bundle draw-off gear assembly of the suspender replacement borehole cleaning of the utility model(Front view);
Fig. 2:The stereoscopic-state figure of Fig. 1;
Fig. 3:The whole bundle draw-off gear assembly of the suspender replacement borehole cleaning of the utility model is used for the installation of old suspension rod dismounting Use state reference view(Front view);
Fig. 4:The stereoscopic-state figure of Fig. 3.
In figure:
The suspension rod steel wire of 1- bar to be changed, 2- cable guide pipe, the suspension rod anchor head of 3- bar to be changed, 4- spike, 5- connector,
6- instrument nut I, 7- stretch-draw jack, 8- backing plate, 9- instrument nut II, 10- high-strength bolt,
11- concrete core drilling rig, 12- bridge sill.
Specific embodiment
A kind of whole bundle draw-off gear assembly of suspender replacement borehole cleaning, as shown in Figure 1 and Figure 2, this device assembly includes connecting Device 5, instrument nut I 6, high-strength bolt 10, spike 4, stretch-draw jack 7 and instrument nut II 9;
Described connector 5 two ends have a circular hole respectively, and described stretch-draw jack 7 is centre-hole jack;
Under use state:Connector 5 upper end circular hole is enclosed within and passes through welding manner therewith on the anchor slab treating drawn steel wire anchor head It is fixedly connected, connector 5 lower end circular hole entangles high-strength bolt 10 one end and adopts thread connecting mode therewith by instrument nut I 6 It is fixedly connected, spike 4 is arranged on bridge sill bottom surface as the counter-force bracing frame of stretch-draw jack 7, and stretch-draw jack 7 upper end is pacified It is contained under spike 4, backing plate 8 is passed through in stretch-draw jack 7 lower end and instrument nut II 9 locks high-strength bolt 10(Referring to Fig. 3, Fig. 4).
The whole bundle draw-off gear components of the utility model suspender replacement borehole cleaning are used for removing the old suspension rod of arch bridge Steel wire and borehole cleaning method are:Hole from top to bottom to old Hanger Anchor head section in bridge floor first with concrete core drilling rig, then will be whole Bundle draw-off gear assembly is arranged under bridge floor, provides driving force with hydraulic tensioning jack, with high-strength bolt as jack tension Part, the steel wire of the old suspension rod of whole bundle drawing arch bridge or stranded wire anchor head.

Claims (1)

1. a kind of suspender replacement borehole cleaning whole bundle draw-off gear assembly it is characterised in that:This device assembly includes connector (5), instrument nut I(6), high-strength bolt(10), spike(4), stretch-draw jack(7)With instrument nut II(9);
Described connector(5)Two ends have a circular hole respectively, described stretch-draw jack(7)For centre-hole jack;
Under use state:Connector(5)Upper end circular hole is enclosed within the anchor slab treating drawn steel wire anchor head and passes through welding manner therewith admittedly Fixed connection, connector(5)Lower end circular hole entangles high-strength bolt(10)Instrument nut I is passed through in one end(6)Using thread connecting mode Connection fixed thereto, spike(4)As stretch-draw jack(7)Counter-force bracing frame be arranged on bridge(12)Sill bottom surface, Draw jack(7)Upper end is arranged on spike(4)Under, stretch-draw jack(7)Backing plate is passed through in lower end(8)With instrument nut II(9)Lock Tight high-strength bolt(10).
CN201620866146.9U 2016-08-11 2016-08-11 Whole bundle of tensioning device subassembly that clear hole was used is changed to jib Withdrawn - After Issue CN205934733U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620866146.9U CN205934733U (en) 2016-08-11 2016-08-11 Whole bundle of tensioning device subassembly that clear hole was used is changed to jib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620866146.9U CN205934733U (en) 2016-08-11 2016-08-11 Whole bundle of tensioning device subassembly that clear hole was used is changed to jib

Publications (1)

Publication Number Publication Date
CN205934733U true CN205934733U (en) 2017-02-08

Family

ID=57919675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620866146.9U Withdrawn - After Issue CN205934733U (en) 2016-08-11 2016-08-11 Whole bundle of tensioning device subassembly that clear hole was used is changed to jib

Country Status (1)

Country Link
CN (1) CN205934733U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087767A (en) * 2016-08-11 2016-11-09 柳州欧维姆工程有限公司 The whole bundle draw-off gear assembly in the clear hole of suspender replacement and remove steel wire and the clear hole method of the old suspension rod of arch bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087767A (en) * 2016-08-11 2016-11-09 柳州欧维姆工程有限公司 The whole bundle draw-off gear assembly in the clear hole of suspender replacement and remove steel wire and the clear hole method of the old suspension rod of arch bridge

Similar Documents

Publication Publication Date Title
CN106087767B (en) The whole beam draw-off gear component of suspender replacement borehole cleaning and its steel wire and borehole cleaning method for removing the old suspension rod of arch bridge
CN104746442B (en) For changing the withdrawing steel wire of the old suspension rod of arched bridge pre-stressed boom and hole cleaning device assembly and the method removed for old suspension rod thereof
CN203270577U (en) Underground pile foundation pulling device with door plate clamp
CN1963044A (en) Construction method for withdrawal of waste pile
CN102182150B (en) Installation method of externally hung steel template for anti-collision guardrail construction outside viaduct
CN205934733U (en) Whole bundle of tensioning device subassembly that clear hole was used is changed to jib
CN209873584U (en) Hang basket template and demolish device
CN211922619U (en) Pile head breaking device
CN204662284U (en) For changing withdrawing steel wire and the hole cleaning device assembly of the old suspension rod of arched bridge pre-stressed boom
CN106498860B (en) A method of pulling out steel wire and borehole cleaning in the whole bunchy top removed for the old sunpender of arch bridge
CN206408541U (en) A kind of whole bunchy top pulling device component of suspender replacement borehole cleaning
CN105275389A (en) Double-rod well drilling machine
CN210768682U (en) Can repeatedly salvage formula rope and get core fishing device
CN211872644U (en) Steel strand prestress tension construction device
CN102061883B (en) Eccentric wheel clamp and method for running casing in drill hole of mine
CN210564597U (en) Anchor cable lockset convenient to disassemble
CN203285367U (en) Pulling fork frame for anchor cables and anchor rods
CN208534513U (en) A kind of Anchor Agent sleeve
CN107059872A (en) Oblique cord pile extracting method and oblique cord pile pulling system
CN203174507U (en) Steel pipe arch suspender installation device
CN216194753U (en) Anti-seepage grouting equipment for earth dam
CN203905983U (en) Bolting and grouting anchor cable for reinforcing base plate of soft rock roadway
CN220450869U (en) Deep foundation pit anchor rope supporting structure
CN217651639U (en) Road and bridge with crack reinforcing structure
CN210033345U (en) Totally-enclosed shallow coring tool

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170208

Effective date of abandoning: 20171031