CN205914936U - Utensil is assisted to branches such as welding rebar cage - Google Patents

Utensil is assisted to branches such as welding rebar cage Download PDF

Info

Publication number
CN205914936U
CN205914936U CN201620946161.4U CN201620946161U CN205914936U CN 205914936 U CN205914936 U CN 205914936U CN 201620946161 U CN201620946161 U CN 201620946161U CN 205914936 U CN205914936 U CN 205914936U
Authority
CN
China
Prior art keywords
steel reinforcement
bar
reinforcement cage
clamping block
chi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620946161.4U
Other languages
Chinese (zh)
Inventor
冯志华
赵辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Bozhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Bozhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Bozhou Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201620946161.4U priority Critical patent/CN205914936U/en
Application granted granted Critical
Publication of CN205914936U publication Critical patent/CN205914936U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model relates to an utensil is assisted to branches such as welding rebar cage, including the chi pole that is provided with the scale, be provided with on the chi pole and be used for the first of support steel reinforcement cage owner muscle, second joint piece, first joint piece is fixed to be set up on the chi pole, first joint piece constitutes the hook with steel reinforcement cage owner muscle and establishes the cooperation, second joint piece constitutes adjustable sliding fit with the chi pole, the one end setting of chi pole is used for the couple of fixed ruler pole, utilize firstly, the support location to double -phase neighbour's steel reinforcement cage owner muscle is implemented to second joint piece, it is adjustable that the length direction of chi pole can be followed to second joint piece, thereby can ensure the degree of accuracy of the position between the double -phase adjacent steel reinforcement cage owner muscle, after the location finishes, utilize the couple to be fixed up the whole utensil of assisting, the completion is to the welding operation of two adjacent steel reinforcement cage owner muscle with internal support ring, weld steel reinforcement cage owner muscle one by one, accomplish the welding of whole steel reinforcement cage, this assists the utensil, and not only welding operation is convenient, and the steel reinforcement cage precision that the welding was come out is high, and the material has broad application prospects.

Description

Point accessories such as steel reinforcement cage welding
Technical field
This utility model is related to Construction Technology field and in particular to a kind of steel reinforcement cage welding etc. divides accessory.
Background technology
For strengthening the steadiness of building, bored concrete pile widely uses in construction, bored concrete pile during construction, Firstly the need of pre-production steel reinforcement cage, then on the building basal plane needing construction, dig bored concrete pile well, by cylindric reinforcing bar Cage is placed in bored concrete pile well, injects concrete, be the formation of structural strength very high after concrete setting into bored concrete pile well Bored concrete pile;In conjunction with shown in Fig. 1, the steel reinforcement cage of above-mentioned bored concrete pile includes inside support ring, the outer wall circumferential direction of inside support ring Multiple cage bars are equidistantly welded at interval, and the length direction of cage bar is parallel to each other, and the length of cage bar is the length of steel reinforcement cage, in cage bar Outer wall set multiple tracks stirrup in hoop, material is thus formed whole reinforcement cage structure.
Because the length of general steel reinforcement cage is all in 8~20m, can only keep flat in steel reinforcement cage welding processing and be processed, Uniformly arrange the position of cage bar and inside support ring according to the drawing requirement of design, then can be welded, steel reinforcement cage is in system During work, rely primarily on manpower and measure welding position one by one, because support ring and stirrup are along between the length direction of cage bar Much individual every arranging, therefore during actual welding operation, not only welding efficiency is extremely inefficient, but also exists in measurement Error, while wasting time and energy, the precision of the steel reinforcement cage processing is very poor.
Utility model content
The purpose of this utility model is to provide a kind of point accessories such as steel reinforcement cage welding, facilitates the same of reinforcement welding positioning When it is ensured that steel reinforcement cage processing precision.
This utility model solves technical problem and adopts the following technical scheme that
Point accessories such as steel reinforcement cage welding, including arranging graduated chi bar, chi bar are provided with for support support steel reinforcement cage master First, second clamping block of muscle, described first clamping block is fixedly installed on chi bar, and the first clamping block is constituted with steel reinforcement cage cage bar Hook establishing is closed, and the second clamping block and chi bar constitute adjustable sliding cooperation, and one end of chi bar is provided for the hook of fixed ruler bar.
Also there is following technical characteristic in this utility model:
One end of described chi bar is provided with spring, and described hook is fixed on one end of spring.
Described first clamping block at right angles rolls over rod-like structure, and one end pole section of the first clamping block passes through chi bar, the first card Connecing block passes through the pole section rod end of chi bar to be arranged to screw thread bar segment, and this screw thread bar segment is provided with adjusting nut, the first clamping block Other end pole section is parallel with the length direction of chi bar, and the other end pole section of the first clamping block constitutes clamping steel reinforcement cage with chi bar The card interface of cage bar.
Described second clamping block includes the sleeve pipe being set on chi bar, and described sleeve pipe tube wall is provided with fastening bolt, institute The tube wall stating fastening bolt and sleeve pipe constitutes threaded cooperation and rod end is constituted against with chi bar or separates cooperation.
Compared with the prior art, the beneficial effects of the utility model are embodied in: implementing steel reinforcement cage cage bar and inside support ring During welding operation, implement the support positioning of the steel reinforcement cage cage bar adjacent to two using first, second clamping block, the second clamping block can Adjustable along the length direction of chi bar, thus can ensure that the accuracy of the position between two adjacent steel reinforcement cage cage bars, positioning finishes Afterwards, using hook, whole accessory is fixed up, thus completing the welding behaviour to two adjacent steel reinforcement cage cage bars and inside support ring Make, after welding finishes, repeat aforesaid operations, one by one steel reinforcement cage cage bar is welded, thus completing the welding of whole steel reinforcement cage, Not only welding operation is convenient for point accessories such as this steel reinforcement cage welding, and welds steel reinforcement cage high precision out, has wide answering Use prospect.
Brief description
Fig. 1 is the end view of steel reinforcement cage;
Fig. 2 is point accessory floor map such as steel reinforcement cage welding;
Fig. 3 is the end view of second clamping blocks of point accessory such as steel reinforcement cage welding;
Fig. 4 is the view that point accessories such as steel reinforcement cage welding are in use.
Specific embodiment
Referring to figs. 1 to Fig. 4, to the feature of point accessories such as steel reinforcement cage welding, details are as follows:
Point accessories such as steel reinforcement cage welding, including arranging graduated chi bar 10, chi bar 10 are provided with for support support reinforcing bar First, second clamping block 20,30 of cage cage bar 40, described first clamping block 20 is fixedly installed on chi bar 10, the first clamping block 20 constitute hook establishing with steel reinforcement cage cage bar 40 closes, and the second clamping block 30 and chi bar 10 constitute adjustable sliding cooperation, chi bar 10 One end is provided for the hook 50 of fixed ruler bar 10.
When implementing steel reinforcement cage cage bar 40 with inside support ring 70 welding operation, implemented using first, second clamping block 20,30 The support positioning of the steel reinforcement cage cage bar 40 adjacent to two, the second clamping block 30 can be adjustable along the length direction of chi bar 10, thus can Guarantee the accuracy of the position between two adjacent steel reinforcement cage cage bars 40, after positioning finishes, using hook 50, whole accessory is solid Decide, thus completing the welding operation to two adjacent steel reinforcement cage cage bars 40 and inside support ring 70, after welding finishes, repeat on State operation, one by one steel reinforcement cage cage bar 40 is welded, thus completing the welding of whole steel reinforcement cage, this steel reinforcement cage welding decile is auxiliary Not only welding operation is convenient for tool, and welds steel reinforcement cage high precision out, has broad application prospects.
For convenience of the fixation to whole accessory, one end of described chi bar 10 is provided with spring 60, and described hook 50 is fixed on One end of spring 60, the spring 60 at this is extension spring, it is possible to increase the fixing strong degree of accessory, in conjunction with shown in Fig. 4, links up with 50 Hang position to fix with inside support ring.
Described first clamping block 20 at right angles rolls over rod-like structure, and one end pole section of the first clamping block 20 passes through chi bar 10, First clamping block 20 passes through the pole section rod end of chi bar 10 to be arranged to screw thread bar segment, and this screw thread bar segment is provided with adjusting nut 21, The other end pole section of the first clamping block 20 is parallel with the length direction of chi bar 10, the other end pole section of the first clamping block 20 with Chi bar 10 constitutes the card interface of clamping steel reinforcement cage cage bar 40, by screwing adjusting nut 21, can adjust the first clamping block 20 and stretch Go out the length of chi bar 10, and then adjust the size of card interface, thus can be with the connecting and fixing of the steel reinforcement cage cage bar 40 of different-diameter.
Described second clamping block 30 includes the sleeve pipe 31 being set on chi bar 10, and described sleeve pipe 31 tube wall is provided with fastening Bolt 32, the tube wall of described fastening bolt 32 and sleeve pipe 31 constitute threaded cooperation and rod end and chi bar 10 constitute against or point From cooperation, in conjunction with shown in Fig. 2, the distance between two adjacent steel reinforcement cage cage bars 40 size is outside first, second clamping block 20,30 Side apart from size, by adjusting the position of the second clamping block 30 and chi bar 10, and then demarcate adjacent steel reinforcement cage cage bar 40 and have Body position it is ensured that welding accuracy.
It is obvious to a person skilled in the art that this utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of without departing substantially from spirit or essential attributes of the present utility model, this practicality can be realized in other specific forms new Type.Therefore, no matter from the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, this practicality is new The scope of type is limited by claims rather than described above, it is intended that the containing of equivalency that will fall in claim All changes in justice and scope are included in this utility model.Any reference in claim should not be considered as limiting Involved claim.
Moreover, it will be appreciated that although this specification is been described by according to embodiment, not each embodiment only wraps Containing an independent technical scheme, only for clarity, those skilled in the art should for this narrating mode of description Using description as an entirety, the technical scheme in each embodiment can also form those skilled in the art through appropriately combined Understandable other embodiment.

Claims (4)

1. point accessory such as steel reinforcement cage welding it is characterised in that: include arranging graduated chi bar (10), chi bar is provided with (10) For first, second clamping block (20,30) of support support steel reinforcement cage cage bar (40), described first clamping block (20) is fixedly installed on chi On bar (10), the first clamping block (20) and steel reinforcement cage cage bar (40) constitute hook establishing conjunction, the second clamping block (30) and chi bar (10) Constitute adjustable sliding cooperation, one end of chi bar (10) is provided for the hook (50) of fixed ruler bar (10).
2. point accessory such as steel reinforcement cage according to claim 1 welding it is characterised in that: one end setting of described chi bar (10) There is spring (60), described hook (50) is fixed on one end of spring (60).
3. point accessory such as steel reinforcement cage according to claim 1 and 2 welding it is characterised in that: described first clamping block (20) At right angles folding rod-like structure, one end pole section of the first clamping block (20) passes through chi bar (10), and the first clamping block (20) passes through chi The pole section rod end of bar (10) is arranged to screw thread bar segment, and this screw thread bar segment is provided with adjusting nut (21), the first clamping block (20) Other end pole section parallel with the length direction of chi bar (10), the other end pole section of the first clamping block (20) and chi bar (10) Constitute the card interface of clamping steel reinforcement cage cage bar (40).
4. point accessory such as steel reinforcement cage according to claim 1 welding it is characterised in that: described second clamping block (30) includes It is set in the sleeve pipe (31) on chi bar (10), described sleeve pipe (31) tube wall is provided with fastening bolt (32), described fastening bolt (32) constitute threaded cooperation with the tube wall of sleeve pipe (31) and rod end is constituted against with chi bar (10) or separates cooperation.
CN201620946161.4U 2016-08-25 2016-08-25 Utensil is assisted to branches such as welding rebar cage Expired - Fee Related CN205914936U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620946161.4U CN205914936U (en) 2016-08-25 2016-08-25 Utensil is assisted to branches such as welding rebar cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620946161.4U CN205914936U (en) 2016-08-25 2016-08-25 Utensil is assisted to branches such as welding rebar cage

Publications (1)

Publication Number Publication Date
CN205914936U true CN205914936U (en) 2017-02-01

Family

ID=57869626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620946161.4U Expired - Fee Related CN205914936U (en) 2016-08-25 2016-08-25 Utensil is assisted to branches such as welding rebar cage

Country Status (1)

Country Link
CN (1) CN205914936U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442361A (en) * 2018-04-28 2018-08-24 山西建筑工程有限公司 A kind of anti-levitating device of filling concrete pile cages fluking type and application method
CN110340508A (en) * 2019-08-07 2019-10-18 刘亚军 A kind of steel reinforcement cage construction technology of the semi-automatic seam welder of steel reinforcement cage and the application equipment
CN114888210A (en) * 2022-07-14 2022-08-12 中建八局第二建设有限公司 Steel reinforcement cage main reinforcement positioning tool and use method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442361A (en) * 2018-04-28 2018-08-24 山西建筑工程有限公司 A kind of anti-levitating device of filling concrete pile cages fluking type and application method
CN108442361B (en) * 2018-04-28 2024-05-10 山西建筑工程集团有限公司 Reinforced cage barb type anti-floating device for bored concrete pile and use method
CN110340508A (en) * 2019-08-07 2019-10-18 刘亚军 A kind of steel reinforcement cage construction technology of the semi-automatic seam welder of steel reinforcement cage and the application equipment
CN110340508B (en) * 2019-08-07 2023-09-01 刘亚军 Semi-automatic seam welder for reinforcement cage and reinforcement cage construction process using same
CN114888210A (en) * 2022-07-14 2022-08-12 中建八局第二建设有限公司 Steel reinforcement cage main reinforcement positioning tool and use method thereof

Similar Documents

Publication Publication Date Title
CN205914936U (en) Utensil is assisted to branches such as welding rebar cage
CN107060352B (en) Movable anchor bolt locating rack
CN206512927U (en) The attachment structure of grout sleeve and reinforcing bar
CN205777597U (en) The hydraulic regulation bar of self adaptation diagonal brace vertical adjustment
CN209025468U (en) The device of accurate control multi-thickness wall mortar joint
CN211312500U (en) Adjustable large-diameter reinforcement cage main reinforcement binding device
CN205660343U (en) Be used for welding rebar cage with fan -shaped utensil of assisting
CN206218799U (en) A kind of tong
CN103822026A (en) Mine self-rooting cable hook device
CN106948339B (en) Steel reinforcement cage pipe penetrating guide and steel reinforcement cage pipe penetrating method
CN204174902U (en) Scaffold
CN207479958U (en) Structural tube girth joint group is to tooling
CN205660318U (en) Be used for ribbon assistance utensil for welding rebar cage
CN206091273U (en) Scaffold connecting device for civil engineering
CN205063338U (en) Be used for stupefied device of reinforced (rfd) adjustable back of body of post template
CN210766426U (en) Reinforcing steel bar laying tool
CN207724877U (en) Heavy caliber solid wall pipe tube head supporting rack
CN205580498U (en) Foldable alfalfa determination of yield sample prescription frame
CN204080799U (en) A kind of prestress steel pile tube
CN107956485B (en) Tunnel secondary lining reinforcing steel bar binding and positioning device
CN208830168U (en) The wet seam reinforcing bar penetrating device of T-type beam
CN202031315U (en) A vertical rod of a fastener type steel pipe scaffold
CN204475862U (en) Length-adjustable construction formwork is to drawing device
CN205217876U (en) Wire spiral fixture
CN205217849U (en) Steel bar bending tool

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170201

CF01 Termination of patent right due to non-payment of annual fee