CN205888059U - Hot metal bottle is built by laying bricks or stones to blast furnace - Google Patents

Hot metal bottle is built by laying bricks or stones to blast furnace Download PDF

Info

Publication number
CN205888059U
CN205888059U CN201620902781.8U CN201620902781U CN205888059U CN 205888059 U CN205888059 U CN 205888059U CN 201620902781 U CN201620902781 U CN 201620902781U CN 205888059 U CN205888059 U CN 205888059U
Authority
CN
China
Prior art keywords
lining
stones
tank
laying bricks
tank bottoms
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620902781.8U
Other languages
Chinese (zh)
Inventor
丁丰收
宋永辉
蒲李刚
晁尚奎
尚路易
校闯
张新伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Ruiwo New Material Co ltd
Original Assignee
REWELL REFRACTORY (ZHENGZHOU) CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by REWELL REFRACTORY (ZHENGZHOU) CO Ltd filed Critical REWELL REFRACTORY (ZHENGZHOU) CO Ltd
Priority to CN201620902781.8U priority Critical patent/CN205888059U/en
Application granted granted Critical
Publication of CN205888059U publication Critical patent/CN205888059U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a hot metal bottle is built by laying bricks or stones to blast furnace, include molten iron tank shell, set up the operational layer inside lining and straightening jar side lining of cylindric can body internal surface including the tank bottoms lining of building by laying bricks or stones at hemisphere tank bottoms internal surface with building by laying bricks or stones on molten iron tank shell inner wall, tank bottoms lining is including hugging closely the permanent chamotte brick layer that hemisphere tank bottoms internal surface was built by laying bricks or stones, and the tank bottoms central point department of putting on permanent chamotte brick layer is provided with the prefabricated brick that shocks resistance of frustum of a cone shape, has built aluminium carborundum carbon brick layer by laying bricks or stones on the anti permanent lining chamotte brick layer that dashes prefabricated brick periphery, is the upper surface on aluminium carborundum carbon brick layer less than the prefabricated brick upper surface 20 that shocks resistance 50mm, jar side lining is including setting gradually the permanent pouring bed of material and the work brick layer at straight cylindric can body internal surface, is the thickness of tank bottoms lining higher by 30 than jar thickness of side lining 50mm. The utility model discloses design the inside lining thickness of hot metal bottle to the destruction degree of different positions impact erosion according to the molten iron, prolonged the life of hot metal bottle, practiced thrift lining material.

Description

Hot-metal bottle built by laying bricks or stones by blast furnace
Technical field
This utility model is related to collection and the vehicle of molten iron, especially relates to a kind of blast furnace and builds hot-metal bottle by laying bricks or stones.
Background technology
Hot-metal bottle is to collect during blast furnace process product and transport molten iron device.The top of general hot-metal bottle is straight tube shape, Tank bottoms hemispherical in order to be incubated and make bottom molten iron overturn evacuation as far as possible.The shell of hot-metal bottle is welded into by steel plate, work Make to be lined with layer based on brick and integrated poured two methods, also have the building method that two ways is combined.But these methods All there is working lining consistency of thickness, because molten iron is different to the destructiveness of ladle lining each position impact erosion, make liner Can not synchronously deteriorate, corroding thickness is uneven when hot-metal bottle is offline, make ladle lining that potential safety hazard to occur, frequently repair Or replacing can cause the significant wastage of inner lining material.
Content of the invention
The purpose of this utility model is to provide a kind of blast furnace making each position of liner synchronously deteriorate to build hot-metal bottle by laying bricks or stones.
For achieving the above object, this utility model can take following technical proposals:
Hot-metal bottle built by laying bricks or stones by blast furnace described in the utility model, including the molten iron tank shell being welded by steel plate, described ferrum The upper can of water pot housing as straight tubular construction, bottom tank bottoms for hemispherical dome structure, on the inwall of described molten iron tank shell It is provided with working lining liner, described working lining liner includes building by laying bricks or stones in the tank bottoms lining of the tank bottoms inner surface of described hemispherical and builds by laying bricks or stones The tank side lining of straight tube shape can body inner surface;
Described tank bottoms lining bag includes the permanent undercloak being close to that the tank bottoms inner surface of hemispherical is built by laying bricks or stones, in described permanent clay brick The tank bottoms center position of layer is provided with the shock resistance preformed bricks of truncated cone, the permanent liner clay of described anti-impact preformed bricks periphery Aluminum silicon carbide carbon brick layer is built on brick layer by laying bricks or stones, the upper surface of described aluminum silicon carbide carbon brick layer is less than described shock resistance preformed bricks upper table Face 20-50mm;
Described tank side lining bag includes the permanent cast bed of material being successively set on straight tube shape can body inner surface and work brick layer;
The thickness 30-50mm higher than the thickness that tank side serves as a contrast of described tank bottoms lining.
The described thickness being close to the permanent undercloak that the tank bottoms inner surface of hemispherical is built by laying bricks or stones is 25-50mm, by the two-layer fissure of displacement The clay brick of wet block is constituted;The permanent cast thickness of feed layer of described tank side lining is 50-80mm.
The top pouring of described straight tube shape can body has tank mouth castable.
The utility model has the advantage of hot-metal bottle is designed to the destructiveness of different parts impact erosion according to molten iron Thickness of inner lining, the impact of tank bottoms center position molten steel is maximum, and remaining position is smaller, and the impulse ratio of can body is tank bottoms less, institute With the thickness of inner lining of the thickness of inner lining > can body of the tank bottoms surrounding of the thickness of inner lining > of tank bottoms center it is achieved that hot-metal bottle is offline When tank in the synchronization of each position working lining deteriorate, extend the service life of hot-metal bottle, saved inner lining material.
Brief description
Fig. 1 is structural representation of the present utility model.
Specific embodiment
As shown in figure 1, hot-metal bottle built by laying bricks or stones by blast furnace described in the utility model, including the molten iron ladle bowl being welded by steel plate Body, the top can body 1 of molten iron tank shell is straight tubular construction, and bottom tank bottoms 2 is hemispherical dome structure, in the inwall of molten iron tank shell On be provided with working lining liner, this working lining liner includes building by laying bricks or stones in the tank bottoms lining of tank bottoms 2 inner surfacies of hemispherical and builds by laying bricks or stones straight The tank side lining of tubular can body 1 inner surface;
Tank bottoms lining bag of the present utility model includes is close to thickness 25-50mm that tank bottoms 2 inner surfacies of hemispherical build by laying bricks or stones by two faults Stitch the permanent undercloak 3 of wet block, the tank bottoms center position of permanent undercloak 3 is provided with up-small and down-big truncated cone This preformed bricks of shock resistance preformed bricks 4(select corundum-silicon carbide-carbon material, and form through 300-450 DEG C of baking, have stronger Opposing molten iron impact property;During placement, tank bottoms center can be found out by crossing method, by shock resistance preformed bricks 4 center and tank The para-position of bottom center, will be tank bottoms levelling and consolidate with inserts 8, then preformed bricks 4 are put well), the permanent liner of anti-impact preformed bricks 4 periphery Aluminum silicon carbide carbon brick layer 5 is built on undercloak by laying bricks or stones, the upper surface of aluminum silicon carbide carbon brick layer 5 is less than shock resistance preformed bricks 4 upper table Face 20-50mm;
Tank side of the present utility model lining bag includes and is successively set on straight tube shape can body 1 inner surface thickness is the permanent of 50-80mm The cast bed of material 6 and work brick layer 7;Build tank side lining again by laying bricks or stones after tank bottoms lining cutting is good: reserved between work brick layer 7 and can body housing The gap of 50-80mm, builds work brick layer 7 by laying bricks or stones above tank bottoms permanent undercloak 3 and aluminum silicon carbide carbon brick layer 5, often builds three by laying bricks or stones After layer, toward in the gap between work brick layer 7 and can body housing, pour into a mould permanent castable, and the pulp that vibrates makes itself and work brick layer 7 combine closely, and so on, complete to build by laying bricks or stones.
The molten iron being born by reply tank base directly impacts, the thickness 30- higher than the thickness that tank side serves as a contrast of tank bottoms lining 50mm.
After the work brick layer 7 of straight tube shape can body 1 is built to the duckbilled of tank mouth, tank mouth top pouring tank mouth castable 8 is filled out Real.

Claims (3)

1. hot-metal bottle built by laying bricks or stones by a kind of blast furnace, including the molten iron tank shell being welded by steel plate, the top of described molten iron tank shell Can body (1) is straight tubular construction, and bottom tank bottoms (2) are hemispherical dome structure, are provided with work on the inwall of described molten iron tank shell Make layer liner it is characterised in that: described working lining liner include building by laying bricks or stones described hemispherical tank bottoms (2) inner surface tank bottoms lining and Build by laying bricks or stones in the tank side of straight tube shape can body (1) inner surface lining;
Described tank bottoms lining bag includes the permanent undercloak (3) being close to that hemispherical tank bottoms (2) inner surface is built by laying bricks or stones, in described permanent clay The tank bottoms center position of brick layer (3) is provided with the shock resistance preformed bricks (4) of truncated cone, described anti-impact preformed bricks (4) periphery Permanent liner undercloak on built aluminum silicon carbide carbon brick layer (5) by laying bricks or stones, the upper surface of described aluminum silicon carbide carbon brick layer (5) is less than institute State shock resistance preformed bricks (4) upper surface 20-50mm;
Described tank side lining bag includes the permanent cast bed of material (6) being successively set on straight tube shape can body (1) inner surface and work brick layer (7);
The thickness 30-50mm higher than the thickness that tank side serves as a contrast of described tank bottoms lining.
2. blast furnace according to claim 1 build hot-metal bottle by laying bricks or stones it is characterised in that: described be close to the tank bottoms inner surface of hemispherical build The thickness of the permanent undercloak (3) built is 25-50mm, is made up of the clay brick of the wet block of the two-layer fissure of displacement;Described tank side serves as a contrast forever The cast bed of material (6) thickness is 50-80mm long.
3. blast furnace according to claim 1 and 2 build hot-metal bottle by laying bricks or stones it is characterised in that: the top of described straight tube shape can body (1) It is cast with tank mouth castable (8).
CN201620902781.8U 2016-08-19 2016-08-19 Hot metal bottle is built by laying bricks or stones to blast furnace Active CN205888059U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620902781.8U CN205888059U (en) 2016-08-19 2016-08-19 Hot metal bottle is built by laying bricks or stones to blast furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620902781.8U CN205888059U (en) 2016-08-19 2016-08-19 Hot metal bottle is built by laying bricks or stones to blast furnace

Publications (1)

Publication Number Publication Date
CN205888059U true CN205888059U (en) 2017-01-18

Family

ID=57779721

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620902781.8U Active CN205888059U (en) 2016-08-19 2016-08-19 Hot metal bottle is built by laying bricks or stones to blast furnace

Country Status (1)

Country Link
CN (1) CN205888059U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108500249A (en) * 2018-04-04 2018-09-07 武汉精鼎科技股份有限公司 A kind of the packet bottom inner lining structure and building method of Spherical Bottom ladle
CN109990747A (en) * 2019-04-01 2019-07-09 山东钢铁集团日照有限公司 A kind of hot-metal bottle tank bottom height detection method and its implement system
CN110877100A (en) * 2019-12-11 2020-03-13 湖南湘钢瑞泰科技有限公司 Method for building bottom of spherical hot metal ladle of blast furnace
CN114905033A (en) * 2022-05-20 2022-08-16 武汉钢铁有限公司 Hot metal ladle structure with heating function

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108500249A (en) * 2018-04-04 2018-09-07 武汉精鼎科技股份有限公司 A kind of the packet bottom inner lining structure and building method of Spherical Bottom ladle
CN108500249B (en) * 2018-04-04 2024-01-12 武汉精鼎科技股份有限公司 Ladle bottom lining structure of spherical bottom ladle and masonry method
CN109990747A (en) * 2019-04-01 2019-07-09 山东钢铁集团日照有限公司 A kind of hot-metal bottle tank bottom height detection method and its implement system
CN110877100A (en) * 2019-12-11 2020-03-13 湖南湘钢瑞泰科技有限公司 Method for building bottom of spherical hot metal ladle of blast furnace
CN114905033A (en) * 2022-05-20 2022-08-16 武汉钢铁有限公司 Hot metal ladle structure with heating function

Similar Documents

Publication Publication Date Title
CN205888059U (en) Hot metal bottle is built by laying bricks or stones to blast furnace
CN108097941B (en) A kind of ladle and its building method
CN101683690B (en) Method for constructing bottom of ladle
CN105436495B (en) Tundish and middle water containing opening steel impermeable installation method
CN106475523A (en) Feed system
CN211248304U (en) Improved tundish for aluminum deoxidized steel
CN207076962U (en) A kind of ladle masonry construction
CN105081296A (en) Tundish manufacturing technology
CN111659870A (en) Centrifugal roller die casting tool and casting process thereof
CN103302280A (en) Construction method of steel ladle bottom for ultra-low carbon steel
CN107282917B (en) A kind of novel ladle and its packet are along building by laying method
CN206425545U (en) A kind of ladle wall working lining
CN205888058U (en) Compound masonry construction of steel ladle lining
CN203791613U (en) Casting ladle with open type spout-shaped lining
CN104057077A (en) High-pulling-speed sheet billet immersion-type water opening
CN209272454U (en) A kind of new-type ladle
CN103658552A (en) Mono-block casting mould system for large-scale cast steel supporting roller and casting method thereof
CN203751324U (en) Steel ladle with improved ladle port structure
CN110877100B (en) Method for building bottom of spherical hot metal ladle of blast furnace
CN205183761U (en) Ladle package end pouring structure
CN108543940A (en) A kind of molten steel pot of non-bonnet (NB) plate is along masonry construction and construction method
US2025336A (en) Method of forming large hollow castings
CN104985144B (en) A kind of new rolling ingot mould and its method for designing
CN201381330Y (en) Working lining of hot-metal swinging stem bar
CN202655591U (en) Multifunctional tundish current regulator with long service life

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 450041 No. 42, Jinping Road, Shangjie District, Zhengzhou City, Henan Province

Patentee after: Zhengzhou Ruiwo New Material Co.,Ltd.

Address before: 450041 north section of Xiushan Road, Shangjie District, Zhengzhou City, Henan Province

Patentee before: REWELL REFRACTORY (ZHENGZHOU) Co.,Ltd.

CP03 Change of name, title or address